Professional Documents
Culture Documents
Chapter 10
Chapter 10
2) Bennet Company employs 20 individuals. Eighteen employees are paid $18 per hour and the rest are
salaried employees paid $3,000 a month. Which of the following is the total cost function of personnel?
A) y = a + bX
B) y = b
C) y = bX
D) y = a
Answer: A
Diff: 2
Objective: 1
AACSB: Analytical thinking
3) Crimson Services, Inc., employs 8 individuals. They are all paid $16.50 per hour. How would total costs
of personnel be classified?
A) variable cost
B) mixed cost
C) irrelevant cost
D) fixed cost
Answer: A
Diff: 2
Objective: 1
AACSB: Analytical thinking
4) For February, the cost components of a picture frame include $0.40 for the glass, $0.67 for the wooden
frame, and $0.83 for assembly. The assembly desk and tools cost $570. Two hundred fifty frames are
expected to be produced in the coming year. What cost function best represents these costs?
A) y = 1.90 + 570X
B) y = 570 + 1.90X
C) y = 570 + 1.07X
D) y = 1.07 + 570X
Answer: B
Explanation: Per unit costs: 0.40 + 0.67 + 0.83 = 1.90
Diff: 2
Objective: 1
AACSB: Analytical thinking
5) The cost components of a heater include $35 for the compressor, $11 for the sheet molded compound
frame, and $74 per unit for assembly. The factory machines and tools cost is $55,000. The company
expects to produce 1,300 heaters in the coming year. What cost function best represents these costs?
A) y = 55,000 + 120X
B) y = 1,300 + 55,000X
C) y = 55,000 + 1,300X
D) y = 1,300 + 120X
Answer: A
Explanation: Per unit costs: 35 + 11 + 74 = 120
Diff: 2
Objective: 1
AACSB: Analytical thinking
7) A finance manager has to select one of the four different suppliers of raw materials. The total cost
functions under the four options are given below. Assume the quality of the raw material to be the same,
which of the following is preferred by the finance manager?
A) y = 600 + 4.96X
B) y = 600 + 5.49X
C) y = 600 + 4.41X
D) y = 600 + 4.67X
Answer: C
Diff: 3
Objective: 1
AACSB: Analytical thinking
8) If the total cost function is y = 6,500 + 9X, calculate the variable cost for 4,400 units.
A) $46,100
B) $39,600
C) $58,500
D) $6,500
Answer: B
Explanation: Explanation: Variable cost for 4,400 units = $9 × 4,400 units = $39,600
Diff: 2
Objective: 1
AACSB: Application of knowledge
14) One assumption frequently made in cost behavior estimation is that changes in total costs can be
explained by changes in the level of a single activity.
Answer: TRUE
Diff: 1
Objective: 1
AACSB: Analytical thinking
15) A cost function is a mathematical description of how a cost changes with changes in the level of an
activity relating to that cost.
Answer: TRUE
Diff: 1
Objective: 1
AACSB: Analytical thinking
19) If a cost item is fixed for one cost object, it will be fixed for all cost objects for which it is associated.
Answer: FALSE
Explanation: A particular cost item could be variable for one cost object and fixed for another cost object.
Diff: 1
Objective: 1
AACSB: Analytical thinking
20) All other things being equal, the longer the time horizon the more likely a cost will be fixed.
Answer: FALSE
Explanation: All other things being equal, the longer the time horizon, the more likely the cost will be
variable.
Diff: 1
Objective: 1
AACSB: Analytical thinking
21) Outside of the relevant range, variable and fixed cost-behavior patterns change, causing costs to
become nonlinear.
Answer: TRUE
Explanation:
Diff: 2
Objective: 1
AACSB: Analytical thinking
22) A particular cost item could be variable for one cost object and fixed for another cost object.
Answer: TRUE
Diff: 1
Objective: 1
AACSB: Analytical thinking
23) A linear cost function can only represent fixed cost behavior.
Answer: FALSE
Explanation: A linear cost function can represent fixed, mixed, or variable cost behavior.
Diff: 1
Objective: 2
AACSB: Analytical thinking
24) In a graphical display of a cost function, the steepness of a line represents the total amount of fixed
costs.
Answer: FALSE
Explanation: In a graphical display of a cost function, the constant or the y-intercept represents the
amount of fixed costs whereas the steepness of a line represents the variable cost.
Diff: 2
Objective: 2
AACSB: Analytical thinking
25) Write a linear cost function equation for each of the following conditions. Use y for estimated costs
and X for activity of the cost driver.
a. Direct manufacturing labor is $15 per hour.
b. Direct materials cost $25.60 per cubic yard.
c. Utilities have a minimum charge of $500, plus a charge of $0.25 per kilowatt-hour.
d. Machine operating costs include $250,000 of machine depreciation per year, plus $100 of utility
costs for each day the machinery is in operation.
Answer:
a. y = $15X
b. y = $25.60X
c. y = $500 + $0.25X
d. y = $250,000 + $100 X
Diff: 2
Objective: 1
AACSB: Analytical thinking
26) Write a linear cost function equation for each of the following conditions. Use y for estimated costs
and X for activity of the cost driver.
a. Direct materials cost is $2.70 per pound
b. Total cost is fixed at $800 per month regardless of the number of units produced.
c. Auto rental has a fixed fee of $90.00 per day plus $1.75 per mile driven.
d. Machine operating costs include $1,000 of maintenance per month, and $15.00 of coolant usage
costs for each day the machinery is in operation.
Answer:
a. y = $2.70X
b. y = $800
c. y = $90 + $1.75X
d. y = $1,000 + $15X
Diff: 2
Objective: 1
AACSB: Analytical thinking
10.2 Objective 10.2
1) Which of the following is not true about the cause-and-effect criterion when estimating a cost function?
A) Correlation of variables proves cause-and-effect
B) Managers must be careful not to equate high correlation between two variables to mean that either
variable causes the other
C) Knowledge of operations can help managers discover cause-and-effect relationships
D) Contractual arrangements may show a direct cause and effect between two variables
Answer: A
Diff: 2
Objective: 2
AACSB: Analytical thinking
2) It can be inferred that when there is a high correlation between two variables, one is the cause of the
other.
Answer: FALSE
Explanation: It cannot be inferred that a high correlation between two variables indicates that one is the
cause of the other. A high correlation simply indicates that the variables move together.
Diff: 2
Objective: 2
AACSB: Analytical thinking
4) Managers should use past data to create a cost function and then use the exact information provided
by that cost function to create the budgetary forecast for the next year.
Answer: FALSE
Explanation: Managers are interested in estimating past cost-behavior functions because the estimates
can help them make more accurate cost predictions, or forecasts, about future costs. But better
management decisions, cost predictions, and estimation of cost functions can be achieved only if
managers correctly identify the factors that affect costs.
Diff: 2
Objective: 2
AACSB: Analytical thinking
5) A contractual agreement that specifies a fee per mile driven, such as with a rental of a truck, is not
considered a cause-and-effect relationship between an activity and a cost.
Answer: FALSE
Explanation: A contractual agreement is a common example of a cause-and-effect relationship between
an activity and cost incurrence.
Diff: 2
Objective: 2
AACSB: Analytical thinking
6) What are the two assumptions behind a simple linear cost function? Briefly explain the three ways that
a linear cost function may behave?
Answer: The two usual assumptions behind a simple linear cost function are:
1) Variations in the level of a single activity (the cost driver) explain the variations in the related total
costs; and
2) Cost behavior is approximated by a linear cost function within the relevant range. This means that total
cost versus the level of a single activity that is related to that cost is a straight line within the relevant
range.
4) Variable cost per labor-hour is $0.82 Fixed cost is $18,500. Machine hours during the period are 90.
Calculate the total cost for 360 labor hours.
A) $18,574
B) $18,795
C) $18,869
D) $369
Answer: B
Explanation: Total cost = $18,500 + ($0.82 × 360) = $18,795
Diff: 2
Objective: 3
AACSB: Application of knowledge
5) Which cost estimation method would involve analyzing direct labor subsidiary accounts and
classifying costs as as variable, fixed, or mixed to derive cost estimation formulas?
A) the account analysis method
B) the conference method
C) the marginal costing method
D) the incremental costing method
Answer: A
Diff: 1
Objective: 3
AACSB: Analytical thinking
6) Which cost estimation method uses a formal statistical method such as regression analysis to develop
cost functions based on past data?
A) the cash accounting method
B) the conference method
C) the accrual accounting method
D) the quantitative analysis method
Answer: D
Diff: 1
Objective: 3
AACSB: Analytical thinking
7) Which cost estimation method uses time-and-motion studies to reveal that to make a high quality
men's suit jacket , it takes of 3 hours of direct labor effort per jacket and 5 minutes of a salaried manager
to perform quality control?
A) the accrual accounting method
B) the high-low method
C) the industrial engineering method
D) the cash accounting method
Answer: C
Diff: 1
Objective: 3
AACSB: Analytical thinking
8) At the Spring Valley Company, the cost of the personnel department has always been charged to
production departments based upon number of employees. Recently, opinions gathered from the
department managers indicate that the number of new hires might be a better predictor of personnel
costs.
Department A B C
Number of employees 80 280 225
Number of new hires 15 17 16
If the number of employees is considered the cost driver, what amount of personnel costs will be
allocated to Department A? (Round any intermediary calculations to two decimal places and your final
answer to the nearest dollar.)
A) $41,860
B) $7,085
C) $143,111
D) $44,874
Answer: A
Explanation: 80 / (80 + 280 + 225) = 0.14
0.14 x $299,000 = $41,860
Diff: 2
Objective: 3
AACSB: Application of knowledge
9) At the Spring Valley Company Company, the cost of the personnel department has always been
charged to production departments based upon number of employees. Recently, opinions gathered from
the department managers indicate that the number of new hires might be a better predictor of personnel
costs.
Department A B C
Number of employees 90 280 210
Number of new hires 15 12 11
If the number of new hires is considered the cost driver, what amount of personnel costs will be allocated
to Department A? (Round any intermediary calculations to two decimal places and your final answer to
the nearest dollar.)
A) $43,759
B) $6,845
C) $109,980
D) $47,913
Answer: C
Explanation: Personnel costs of Department A = 15 / (15 + 12 + 11) = 0.39
0.39 x $282,000 = $109,980
Diff: 2
Objective: 3
AACSB: Application of knowledge
10) At the Spring Valley Company, the cost of the personnel department has always been charged to
production departments based upon number of employees. Recently, opinions gathered from the
department managers indicate that the number of new hires might be a better predictor of personnel
costs.
Department A B C
Number of employees 50 285 200
Number of new hires 30 13 12
Department A B C
Number of employees 175 525 140
Number of engineers 5 85 35
Which cost estimation method is being used by Wild Cat Group Company?
A) the regression analysis method
B) the marginal costing method
C) the conference method
D) the operating costing method
Answer: C
Diff: 3
Objective: 3
AACSB: Analytical thinking
12) At the Wild Cat Group Company, the cost of the library and information center has always been
charged to the various departments based upon number of employees. Recently, opinions gathered from
the department managers indicate that the number of engineers within a department might be a better
predictor of library and information center costs.
Department A B C
Number of employees 180 520 150
Number of engineers 10 60 35
If the number of employees is considered the cost driver, what amount of library and information center
costs will be allocated to Department A? (Round any intermediary calculations to two decimal places and
your final answer to the nearest dollar.)
A) $42,377
B) $44,730
C) $20,286
D) $130,306
Answer: B
Explanation: 180 / (180 + 520 + 150) = 0.21
0.21 x $213,000 = $44,730
Diff: 2
Objective: 3
AACSB: Application of knowledge
13) At the Wild Cat Group Company, the cost of the library and information center has always been
charged to the various departments based upon number of employees. Recently, opinions gathered from
the department managers indicate that the number of engineers within a department might be a better
predictor of library and information center costs.
Department A B C
Number of employees 175 505 150
Number of engineers 5 85 35
If the number of engineers is considered the cost driver, what amount of library and information center
costs will be allocated to Department A? (Round any intermediary calculations two decimal places and
your final answer to the nearest dollar.)
A) $40,524
B) $45,331
C) $8,600
D) $130,813
Answer: C
Explanation: 5 / (5 + 85 + 35) = 0.04
0.04 x $215,000 = $8,600
Diff: 2
Objective: 3
AACSB: Application of knowledge
14) M & G TV and Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
What was the variable cost per unit sold for 2017?
A) $30
B) $480
C) $770
D) $450
Answer: B
Explanation: Variable cost per unit = ($540,000 + $36,000) / 1,200 = $480 per unit
Diff: 2
Objective: 3
AACSB: Application of knowledge
15) M & G TV and Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
16) M & G TV and Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
What are the estimated total costs if the company expects to sell 3,300 units next year?
A) $1,458,400
B) $2,803,700
C) $2,361,700
D) $517,900
Answer: A
Explanation: Variable costs per unit = ($570,000 + $46,000) / 2,000 = $308 per unit
Total cost = fixed costs ($130,000 + $280,000 + $32,000) + variable costs (3,300 units × $308
variable costs per unit) = $1,016,400 = $1,458,400 total estimated costs.
Diff: 3
Objective: 3
AACSB: Application of knowledge
17) M & G TV and Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
Which cost estimation method is being used by M & G TV and Appliance Store?
A) the operating costing method
B) the marginal costing method
C) the account analysis method
D) the cost-volume-profit analysis method
Answer: C
Diff: 3
Objective: 3
AACSB: Analytical thinking
18) South Coast Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
Which cost estimation method is being used by South Coast Appliance Store?
A) the account analysis method
B) the operating costing method
C) the marginal costing method
D) the cost-volume-profit analysis method
Answer: A
Diff: 2
Objective: 3
AACSB: Analytical thinking
19) South Coast Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
What was the variable cost per unit sold for 2017?
A) $32.00
B) $175
C) $207.00
D) $277.72
Answer: C
Explanation: Variable cost per unit = ($962,500 + $176,000) / 5,500 = $207.00 per unit
Diff: 2
Objective: 3
AACSB: Application of knowledge
20) South Coast Appliance Store is a small company that has hired you to perform some management
advisory services. The following information pertains to 2017 operations.
What are the estimated total costs if South Coast's store expects to sell 8,900 units next year?
A) $3,567,950
B) $2,192,400
C) $4,104,950
D) $901,900
Answer: B
Explanation: Total cost = fixed cost ($192,000 + $305,000 + $40,000) + variable costs (8,900 units × $186.00
variable costs per unit) = $1,655,400 = $2,192,400.
Diff: 3
Objective: 3
AACSB: Application of knowledge
22) High Tech Manufacturing Inc., incurred total indirect manufacturing labor costs of $490,000. The
company is labor intensive. Total labor hours during the period were 4,100. Using qualitative analysis,
the manager and the management accountant determine that over the period the indirect manufacturing
labor costs are mixed costs with only one cost driver–labor-hours. They separated the total indirect
manufacturing labor costs into costs that are fixed ($120,000 based on 8,600 hours of labor) and costs that
are variable ($370,000) based on the number of labor-hours used. The company has estimated 7,300 labor
hours during the next period.
24) High Tech Manufacturing Inc., incurred total indirect manufacturing labor costs of $550,000. The
company is labor intensive. Total labor hours during the period were 4,400. Using qualitative analysis,
the manager and the management accountant determine that over the period the indirect manufacturing
labor costs are mixed costs with only one cost driver–labor-hours. They separated the total indirect
manufacturing labor costs into costs that are fixed ($120,000 based on 8,700 hours of labor) and costs that
are variable ($430,000) based on the number of labor-hours used. The company has estimated 6,900 labor
hours during the next period.
What will be the total variable cost for the estimated 6,900 hours? (Round any intermediary calculations
to the nearest cent and your final answer to the nearest dollar.)
A) $341,034
B) $674,337
C) $862,500
D) $436,207
Answer: B
Explanation: $430,000 / 4,400 = $97.73
$97.73 x 6,900 = $674,337
Diff: 2
Objective: 3
AACSB: Application of knowledge
25) High Tech Manufacturing Inc., incurred total indirect manufacturing labor costs of $480,000. The
company is labor intensive. Total labor hours during the period were 4,400. Using qualitative analysis,
the manager and the management accountant determine that over the period the indirect manufacturing
labor costs are mixed costs with only one cost driver–labor-hours. They separated the total indirect
manufacturing labor costs into costs that are fixed ($130,000 based on 8,100 hours of labor) and costs that
are variable based on the number of labor-hours used. The company has estimated 7,700 labor
hours during the next period.
What will be the total cost for the estimated 7,700 hours? (Round any intermediary calculations to the
nearest cent and your final answer to the nearest dollar.)
A) $462,716
B) $586,296
C) $840,000
D) $742,535
Answer: D
Explanation: $350,000 / 4,400 = $79.55
$130,000 + ($79.55 x 7,700) = $742,535
Diff: 2
Objective: 3
AACSB: Application of knowledge
26) When management develops cost estimations, they must chose one method, such as industrial
engineering, conference, account analysis, or quantitative analysis, and stay consistently with that
method as each method is mutually exclusive of the others.
Answer: FALSE
Explanation: The methods are not mutually exclusive rather, many organizations use combination of
methods to estimate costs.
Diff: 1
Objective: 3
AACSB: Analytical thinking
27) The account analysis method of cost estimation classifies account costs as fixed, mixed, or variable
using qualitative judgments.
Answer: TRUE
Diff: 1
Objective: 3
AACSB: Analytical thinking
28) The account analysis method estimates cost functions by classifying various cost accounts as variable,
fixed, or mixed with respect to the identified level of activity.
Answer: TRUE
Diff: 1
Objective: 3
AACSB: Analytical thinking
29) The quantitative analysis method uses a formal mathematical method to identify cause-and-effect
relationships among past data observations.
Answer: TRUE
Diff: 1
Objective: 3
AACSB: Analytical thinking
30) The cost of the personnel department at the Speedy Process Company has always been charged to the
production departments based upon number of employees. Recently, opinions gathered from the
department managers indicated that the number of new hires might also be a predictor of personnel costs
to be assigned. Total personnel department costs are $200.000.
Required:
Using the above data, prepare a report that contrasts the different amounts of personnel department cost
that would be allocated to each of the production departments if the cost driver used is:
a. number of employees.
b. the number of new hires.
c. Which cost estimation method is being used by Speedy Company?
Answer: Department Department Department
Cost Driver A B C
a. Number of employees 390/780 × 200,000 325/780 × 200,000 65/780 × 200,000
$100,000 $83,333 $16,667
b. The number of new hires 30/95×180,000 40/95×200,000 25/95×200,000
$63,158 $84,211 $52,631
c. The Speedy Company is using the conference method for cost estimation.
Diff: 3
Objective: 3
AACSB: Application of knowledge
31) June Lockett, controller, gathered data on overhead costs and direct labor-hours over the past 12
months. List and discuss the different approaches June can use to estimate a cost function for overhead
costs using direct labor-hours as the cost driver.
Answer: The four approaches to cost estimation are:
The industrial engineering method, also called the work-measurement method, estimates cost functions by
analyzing the relationship between inputs and outputs in physical terms.
The conference method estimates cost functions on the basis of analysis and opinions about costs and their
drivers gathered from various departments of an organization (purchasing, process engineering,
manufacturing, employee relations, etc.).
The account analysis method estimates cost functions by classifying cost accounts in the ledger as variable,
fixed, or mixed with respect to the identified cost driver.
Quantitative analysis of cost relationships are formal methods, such as the high-low method or regression
analysis, to fit linear cost functions to past data observations.
Diff: 2
Objective: 3
AACSB: Analytical thinking
2) In the estimation of a cost function using quantitative analysis, the independent variable ________.
A) is the cost to be predicted
B) is the product of fixed costs and slope coefficient
C) is the factor used to predict the dependent variable
D) is the product of total costs and slope coefficient
Answer: C
Diff: 2
Objective: 4
AACSB: Analytical thinking
3) A cost driver should be measurable and have an economically plausible relationship with the
dependent variable which means:
A) that the cost driver can be identified in an economically feasible way
B) that the relationship is based on correlation
C) that the relationship is based on a cause -and-effect criterion and makes economic sense to
management
D) that the relationship must be based on a physical relationship
Answer: C
Diff: 2
Objective: 4
AACSB: Analytical thinking
4) Place the following steps in order for estimating a cost function using quantitative analysis.
A) D C E A B
B) C D B A E
C) A D C E B
D) E D C B A
Answer: B
Diff: 2
Objective: 4
AACSB: Analytical thinking
8) A plot of data that results in one extreme observation most likely indicates that ________.
A) more than one cost pool should be used
B) an unusual event such as a plant shutdown occurred during that month
C) the cost-allocation base has been incorrectly identified
D) individual cost items do not have the same cost driver
Answer: B
Diff: 2
Objective: 4
AACSB: Analytical thinking
12) When using the high-low method, the numerator of the equation that determines the slope is the
________.
A) difference between the positive and negative values of dependent and independent variables
B) difference between the fixed cost and variable cost associated with the cost driver
C) difference between the high and low observations of the cost driver
D) difference between the costs associated with highest and lowest observations of the cost driver
Answer: D
Diff: 2
Objective: 4
AACSB: Analytical thinking
A) D C A B
B) C D A B
C) A D C B
D) D C B A
Answer: C
Diff: 2
Objective: 4
AACSB: Analytical thinking
16) Which of the following statements shows a difference between simple regression and multiple
regression?
A) Simple regression uses more than one dependent and independent variables, whereas multiple
regression uses only one dependent and independent variable.
B) Simple regression uses only the independent variables, whereas multiple regression uses only
dependent variables.
C) Simple regression uses only one dependent and one independent variable, whereas multiple
regression uses one dependent and more than one independent variable.
D) Simple regression uses only one dependent variable and more than one independent variables,
whereas multiple regression uses more than one dependent variable and only one independent variable.
Answer: C
Diff: 2
Objective: 4
AACSB: Analytical thinking
17) The slope of the line of regression is the ________.
A) rate at which the dependent variable varies
B) rate at which the independent variable varies
C) difference between the fixed cost and variable cost associated with the cost driver
D) difference between actual cost and estimated cost for each observation of the cost driver
Answer: A
Diff: 2
Objective: 4
AACSB: Analytical thinking
18) Quantum Company uses the high-low method to estimate the cost function. The information for 2017
is provided below:
Machine-hours Labor Costs
Highest observation of cost driver 400 $20,000
Lowest observation of cost driver 100 $8,000
19) Quantum Company uses the high-low method to estimate the cost function. The information for 2017
is provided below:
Machine-hours Labor Costs
Highest observation of cost driver 1,000 $32,000
Lowest observation of cost driver 200 $16,000
21) Quantum Company uses the high-low method to estimate the cost function. The information for 2017
is provided below:
Machine-hours Labor Costs
Highest observation of cost driver 900 $36,000
Lowest observation of cost driver 100 $14,000
What is the estimated total cost when 450 machine-hours are used?
A) $63,000
B) $32,000
C) $18,000
D) $23,625
Answer: D
Explanation: Slope = ($36,000 - $14,000) / (900 - 100) = $27.50
Constant (using highest observation): $36,000 - ($27.50 x 900) hours = $11,250
Constant (using lowest observation): $14,000- ($27.50 x 100) hours = $11,250
The total cost, y = $11,250 + ($27.50 × 450) = $23,625
Diff: 3
Objective: 4
AACSB: Application of knowledge
22) Taunton Company uses the high-low method to estimate its cost function. The information for 2017 is
provided below:
Machine-hours Costs
Highest observation of cost driver 3,000 $345,000
Lowest observation of cost driver 2,500 $315,000
23) Taunton Company uses the high-low method to estimate its cost function. The information for 2017 is
provided below:
Machine-hours Costs
Highest observation of cost driver 3,000 $300,000
Lowest observation of cost driver 2,500 $277,500
Machine-hours Costs
Highest observation of cost driver 4,000 $332,000
Lowest observation of cost driver 3,000 $312,000
25) Taunton Company uses the high-low method to estimate its cost function. The information for 2017 is
provided below:
Machine-hours Costs
Highest observation of cost driver 4,000 $332,000
Lowest observation of cost driver 3,000 $312,000
What is the estimated total cost when 1,900 machine-hours are used?
A) $509,600
B) $290,000
C) $489,700
D) $157,700
Answer: B
Explanation: Slope = ($332,000 - $312,000) / (4,000 - 3,000) = $20.00
Constant (using highest observation): $332,000 - ($20.00 x 4,000) hours = $252,000
Constant (using lowest observation): $312,000 - ($20.00 x 3,000) hours = $252,000
The total cost, y = $252,000 + ($20.00 × 1,900) = $290,000
Diff: 2
Objective: 4
AACSB: Application of knowledge
26) For Heavy Manufacturing Company, labor-hours are 40,000 and wages $144,000 at the high point of
the relevant range, and labor-hours are 24,000 and wages $96,000 at the low point of the relevant range.
27) For Heavy Manufacturing Company, labor-hours are 40,000 and wages $184,000 at the high point of
the relevant range, and labor-hours are 24,000 and wages $120,000 at the low point of the relevant range.
28) For Heavy Manufacturing Company, labor-hours are 48,000 and wages $156,000 at the high point of
the relevant range, and labor-hours are 32,000 and wages $112,000 at the low point of the relevant range.
What is the estimated total labor costs at Heavy Manufacturing Company when 11,400 labor-hours are
used?
A) $38,190
B) $55,350
C) $39,900
D) $37,050
Answer: B
Explanation: Slope = ($156,000 - $112,000) / (48,000 - 32,000) = $2.75
Constant (using highest observation): $156,000 − ($2.75 × 48,000) = $24,000
Constant (using lowest observation): $112,000 − ($2.75 × 32,000) = $24,000
Total labor costs, y = $24,000 + ($2.75 × 11,400) = $55,350
Diff: 3
Objective: 4
AACSB: Application of knowledge
29) The Connors Company has assembled the following data pertaining to certain costs that cannot be
easily identified as either fixed or variable. Connors Company has heard about a method of measuring
cost functions called the high-low method and has decided to use it in this situation.
Cost Hours
$24,000 5,000
$26,100 6,300
$34,700 7,900
$48,000 11,000
$38,300 9,250
Cost Hours
$23,000 5,000
$26,000 6,450
$34,600 7,650
$42,000 10,000
$38,000 9,350
35) Because the cost driver is the same for the fringe benefits of life insurance and pension benefits cost is
the same, those costs can be aggregated into one homogeneous cost pool.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
36) The first step in estimating a cost function using quantitative analysis is to plot the data.
Answer: FALSE
Explanation: The first step in estimating a cost function using quantitative analysis is to choose the
dependent variable.
Diff: 2
Objective: 4
AACSB: Analytical thinking
37) In estimating a cost function using quantitative analysis, the dependent variable is the factor used to
predict the independent variable.
Answer: FALSE
Explanation: In estimating a cost function using quantitative analysis, the independent variable is the
factor used to predict the dependent variable.
Diff: 2
Objective: 4
AACSB: Analytical thinking
38) Cross-sectional data pertain to the same entity (organization, plant, activity, and so on)
over successive past periods.
Answer: FALSE
Explanation: Time-series data pertain to the same entity (organization, plant, activity, and so on)
over successive past periods.
Diff: 1
Objective: 4
AACSB: Analytical thinking
39) Simple regression analysis estimates the relationship between the dependent variable
and one independent variable.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
40) Two common forms of quantitative analysis methods of cost estimation are the high-low method and
regression analysis.
Answer: TRUE
Diff: 1
Objective: 4
AACSB: Analytical thinking
41) The high-low method relies on only two observations, the highest and lowest, to estimate a linear cost
function.
Answer: TRUE
Diff: 1
Objective: 4
AACSB: Analytical thinking
42) The dependent variable is a cost to be predicted and managed, whereas an independent variable or
cost driver is the factor used to predict the dependent variable.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
43) The vertical difference, called the residual term, measures the distance between actual cost of one
period and estimated cost of the next period.
Answer: FALSE
Explanation: The vertical difference, called the residual term, measures the distance between actual cost
and estimated cost for each observation of the cost driver.
Diff: 2
Objective: 4
AACSB: Analytical thinking
44) Regression analysis is a statistical method that measures the average amount of change in the
dependent variable associated with a unit change in one or more independent variables.
Answer: TRUE
Diff: 1
Objective: 4
AACSB: Analytical thinking
45) In using high-low method, the slope coefficient is calculated by dividing the difference between
highest and lowest observations of the cost driver by the difference between costs associated with highest
and lowest observations of the cost driver.
Answer: FALSE
Explanation: In high-low method, slope coefficient is calculated by dividing the difference between costs
associated with highest and lowest observations of the cost driver by the difference between highest and
lowest observations of the cost driver.
Diff: 2
Objective: 4
AACSB: Analytical thinking
46) Simple regression analysis estimates the relationship between the dependent variable and one
independent variable.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
47) The advantages of the high-low method to estimate a cost function is that it is easy and accurate.
Answer: FALSE
Explanation: The method is easy to use but it produces an estimate , provides quick initial insight
however it is not necessarily accurate and is dangerous for managers to rely on only two observations to
estimate a cost function.
Diff: 2
Objective: 4
AACSB: Analytical thinking
48) Multiple regression analysis uses only independent variables and not dependent variables.
Answer: FALSE
Explanation: Multiple regression analysis estimates the relationship between the dependent variable and
two or more independent variables.
Diff: 2
Objective: 4
AACSB: Analytical thinking
49) In regression analysis, the term "goodness of fit" indicates the strength of the relationship between the
cost driver and the costs.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
50) Multiple regression analysis estimates the relationship between the dependent variable and two or
more independent variables.
Answer: TRUE
Diff: 2
Objective: 4
AACSB: Analytical thinking
51) The managers of the production department have decided to use the production levels of 2017 and
2018 as examples of the highest and lowest years of operating levels. Data for those years are as follows:
52) Mountain Manufacturing Inc. ran its machines in March, a slow month, for 410 hours for a total cost
of $63,000. In July, a peak month, the freezer ran for 756 hours for a total cost of $92,800.
Required:
a. What is the cost estimating equation for the department if hours of freezer use are used as the cost
driver?
b. What is the estimated total cost at an operating level of 600 hours?
Answer:
a. Slope (variable costs) = ($92,800 − $63,000) / (756 − 410) = $86.13
Constant (fixed cost) = $92,800 − (756 × $86.13) = $27,688
Estimating equation = $27,688 + ($86.13 per direct labor hour × number of direct labor hours)
b. Total costs of 600 hours = $27,688 + ($86.13 × 600) = $79,364
Diff: 2
Objective: 4
AACSB: Application of knowledge
53) The Michigan Manufacturing Company has provided the following information:
54) As part of his job as cost analyst, John Kelly collected the following information concerning the
operations of the Machining Department:
Required:
a. Use the high-low method to determine the estimating cost function with machine-hours as the cost
driver.
b. If June's estimated machine-hours are 4,300, calculate the total estimated costs of the Machining
Department?
Answer:
a. Slope coefficient = ($45,395 − $42,535) / (5,060 − 4,180) = $3.25 per machine-hour
Constant = $45,395 − ($3.25 × 5,060) = $28,950
Estimating equation = $28,950 + $3.25X
b. June's estimated costs = $28,950 + ($3.25 × 4,300) = $42,925
Diff: 2
Objective: 4
AACSB: Application of knowledge
55) Salter Manufacturing Company produces inventory in a highly automated assembly plant in Fall
River, Massachusetts. The automated system is in its first year of operation and management is still
unsure of the best way to estimate the overhead costs of operations for budgetary purposes. For the first
six months of operations, the following data were collected:
Required:
a. Use the high-low method to determine the estimating cost function with machine-hours as the cost
driver.
b. Use the high-low method to determine the estimating cost function with kilowatt-hours as the cost
driver.
c. For July, the company ran the machines for 4,000 hours and used 4,550,000 kilowatt-hours of
power. The overhead costs totaled $365,000. Which cost driver was the best predictor for July?
Answer:
a. Machine-hours:
Slope coefficient = ($407,040 − $384,000) / (4,680 − 3,720)
= $24.00 per machine-hour
Constant = $384,000 − ($24 × 3,720) = $294,720
Machine-hour estimating equation = $294,720 + $24X
b. Kilowatt-hours:
Slope coefficient = ($407,040 − $384,000) / (5,400,000 − 4,944,000) = $0.0505 per kilowatt-hour
Constant = $407,040 − ($0.0505 × 5,400,000) = $134,198
The best estimator for July was the kilowatt-hour cost driver.
Diff: 3
Objective: 4
AACSB: Application of knowledge
56) Patrick Ross, the president of M & M Materials Company, has asked for information about the cost
behavior of manufacturing overhead costs. Specifically, he wants to know how much overhead cost is
fixed and how much is variable. The following data are the only records available:
Required:
Using the high-low method, determine the overhead cost equation. Use machine-hours as your cost
driver.
Answer: High: June 3,850 $31,196
Low: April 1,100 24,321
Difference 2,750 $ 6,875
57) List and briefly describe the six steps in estimating a cost function under quantitative analysis.
Answer: The first step is to select the dependent variable. Selection of which dependent variable to use
will depend on the cost function being estimated. Once the dependent variable has been selected, it is
necessary to identify the independent variable or cost driver. The cost driver is the factor that is used to
predict the dependent variable costs. The cost driver should have an economically plausible relationship
with the dependent variable and be measurable. The third step involves collecting data on the dependent
variable and the cost driver. The data may be time-series data or they may be cross-sectional data. Once
the data are collected, they need to be plotted, which is step four. Plotting the data allows for the
relationship between the cost driver and the dependent variable to be more readily observed. This also
allows for the identification of extreme observations that should be further investigated. The fifth step is
to estimate the cost function, using some form of quantitative analysis. The last step is to evaluate the cost
driver of the estimated cost function to determine if the cost function provides a good estimation.
Diff: 2
Objective: 4
AACSB: Analytical thinking
10.5 Objective 10.5
1) If cost accountants decide to use production of prior periods as a cost driver for repair cost of the
current period they understand that
A) there is no correlation between repair costs and levels of production
B) repair costs tend to lag periods of high production
C) cost accountants do not need to understand operations
D) there is no cause-and-effect between production and repair costs
Answer: B
Diff: 2
Objective: 5
AACSB: Analytical thinking
2) Why is choosing the correct cost driver to estimate indirect manufacturing costs important?
A) Identifying the wrong driver can lead management to incorrect and costly decisions
B) Identifying the wrong driver can increase actual overhead costs
C) Identifying the wrong driver can increase the usage of the correct driver
D) Identifying the wrong driver can increase the direct costs of the cost object
Answer: A
Diff: 2
Objective: 5
AACSB: Analytical thinking
3) The trend in large corporations is a movement away from quantitative analysis of cost drivers to the
conference method.
Answer: FALSE
Explanation: Many companies are switching from the conference method to performing in-depth
quantitative analysis on their "bif-data" systems.
Diff: 2
Objective: 5
AACSB: Analytical thinking
4) What is a plausible explanation of a cost function has a slope coefficient of $30 for purchases of 1 to
1,000 units and $25 for production of 1,100 - 2,000 units, and $20 for production of 2,001 - 3,000 units
A) the fixed cost per unit has decreased because of efficiencies
B) economies of scale allowing for lower cost purchases with larger orders
C) their is a linear cost function in effect
D) contribution margins are decreasing
Answer: B
Diff: 2
Objective: 5
AACSB: Analytical thinking
5) If machine maintenance is scheduled at a time when production is at a low level, then ________.
A) low production is the cost driver of high repair costs
B) an understanding of operations is needed to determine an appropriate cost driver
C) low production should be avoided since it is the cause of machine maintenance
D) machine maintenance cannot be accurately predicted
Answer: B
Diff: 3
Objective: 5
AACSB: Analytical thinking
6) Goodness-of-fit measures how well the predicted values in a cost estimating equation ________.
A) match the cost driver
B) determine the level of activity
C) match the actual cost observations
D) rely on the independent variable
Answer: C
Diff: 2
Objective: 5
AACSB: Analytical thinking
10) Which of the following statements is true of choosing cost drivers under activity-based costing?
A) All the cost drivers should be unit-level cost drivers.
B) There should be a clear cause-and-effect relationship between cost drivers and cost pools.
C) Cost drivers are independent variables.
D) A single cost driver should be identified for all the activities.
Answer: C
Diff: 2
Objective: 5
AACSB: Analytical thinking
11) Machine-hours is a more economically plausible cost driver of machine maintenance than number of
direct manufacturing labor-hours.
Answer: TRUE
Diff: 2
Objective: 5
AACSB: Analytical thinking
12) The larger the vertical difference between actual costs and predicted costs the better the goodness of
fit.
Answer: FALSE
Explanation: The smaller the vertical difference between actual costs and predicted costs the better the
goodness of fit.
Diff: 2
Objective: 5
AACSB: Analytical thinking
13) The major advantages of quantitative methods are that they are objective, so managers can use them
to evaluate different cost drivers.
Answer: TRUE
Diff: 2
Objective: 5
AACSB: Analytical thinking
14) A flat or slightly sloped regression line indicates a strong relationship between the cost driver and
costs.
Answer: FALSE
Explanation: A flat or slightly sloped regression line indicates a weak relationship between the cost driver
and costs.
Diff: 2
Objective: 5
AACSB: Analytical thinking
15) When choosing among cost drivers, managers trade off level of detail, accuracy, feasibility, and costs
of estimating functions.
Answer: TRUE
Diff: 1
Objective: 5
AACSB: Analytical thinking
16) Activity-based costing systems use the quantitative analysis method exclusively for cost estimation
because of its accuracy.
Answer: FALSE
Explanation: Because ABC systems have a great number and variety of cost drivers and cost pools it
requires many cost relationships to be estimated. ABC systems use a variety of estimation methods -
industrial engineering, conference, and quantitative analysis. In making the choice of method to use,
managers trade off detail, accuracy, feasibility, and costs of estimating cost functions.
Diff: 2
Objective: 5
AACSB: Analytical thinking
17) When estimating the cost function for each cost pool, the manager must pay careful attention to the
cost hierarchy because the cost pool may have more than one cost driver from different levels of the cost
hierarchy.
Answer: TRUE
Diff: 3
Objective: 5
AACSB: Analytical thinking
18) What are the three criteria a company should use to evaluate and choose a cost driver? Briefly explain
each of the three criteria.
Answer: The three criteria a company should use to evaluate a cost driver are economic plausibility,
goodness of fit, and significance of the independent variable.
Economic plausibility involves the theoretical existence of a causal relationship between a driver and the
costs it is supposed to drive.
Goodness of fit involves the observed differences between predictions of costs based on the cost driver
and the actual costs that occurred.
Significance of the independent variable involves the steepness of the slope of the cost driver relative to
the slope of other possible cost drivers. The steeper the slope (given the same goodness of fit) the stronger
is the relationship between the cost driver and the related costs.
Diff: 2
Objective: 5
AACSB: Analytical thinking
10.6 Objective 10.6
7) To complete the first setup on a new machine took an employee 320 minutes. Using an 70% cumulative
average-time learning curve indicates that the second setup on the new machine is expected to take
________.
A) 112 minutes
B) 128 minutes
C) 272 minutes
D) 224 minutes
Answer: B
Explanation: The time taken for the second set up on machine = 320 × 0.7 = 224; (320 + X) / 2 = 224; X = 128
minutes
Diff: 3
Objective: 6
AACSB: Application of knowledge
8) To complete the first setup on a new machine took an employee 200 minutes. Using an 64%
incremental unit-time learning model indicates that the second setup on the new machine is expected to
take ________.
A) 128.0 minutes
B) 312.5 minutes
C) 328.0 minutes
D) 72.0 minutes
Answer: A
Explanation: The time taken for the second set up on machine = 200 × 0.64 = 128.0 minutes
Diff: 2
Objective: 6
AACSB: Application of knowledge
9) As a result of learning curve, ________.
A) unit costs increase as productivity increases and the unit-cost function behaves nonlinearly
B) unit costs decrease as productivity increases and the unit-cost function behaves nonlinearly
C) unit costs increase as productivity increases and the unit-cost function behaves linearly
D) unit costs decrease as productivity increases and the unit-cost function behaves linearly
Answer: B
Diff: 2
Objective: 6
AACSB: Analytical thinking
14) Step fixed-cost functions are variable over the long run.
Answer: TRUE
Diff: 2
Objective: 6
AACSB: Analytical thinking
15) An experience curve is a function that measures the decline in cost per unit in various business
functions of the value chain as the amount of these activities increases.
Answer: TRUE
Diff: 1
Objective: 6
AACSB: Analytical thinking
17) In the cumulative average-time learning model, cumulative average time per unit declines by a
constant percentage each time the cumulative quantity of units produced doubles.
Answer: TRUE
Diff: 2
Objective: 6
AACSB: Analytical thinking
18) When new products are introduced, learning-curve effects can have a major influence on production
scheduling.
Answer: TRUE
Diff: 2
Objective: 6
AACSB: Analytical thinking
20) The cumulative average-time learning model with a 85% learning curve indicates that if it takes 200
minutes to manufacture the first unit of a new model, then the second unit will take only 170 minutes to
manufacture.
Answer: FALSE
Explanation: Second unit set up time = 200 × .85 = 170; (200 + X)/2 = 170; X = 140 minutes
Diff: 2
Objective: 6
AACSB: Application of knowledge
21) The incremental unit-time learning model with a 80% learning curve indicates that if it takes 150
minutes to manufacture the first unit of a new model, then the second unit will take only 120 minutes to
manufacture.
Answer: TRUE
Explanation: Second unit set up time = 150 ×.80 = 120 minutes
Diff: 2
Objective: 6
AACSB: Application of knowledge
22) A learning curve is a function that measures how labor-hours per unit decrease, as units of
production decrease.
Answer: FALSE
Explanation: A learning curve is a function that measures how labor-hours per unit decrease, as units of
production increase.
Diff: 2
Objective: 6
AACSB: Analytical thinking
23) Harold's Picture manufactures various picture frames. Each new employee takes 6 hours to make the
first picture frame and 4.8 hours to make the second. The manufacturing overhead charge per hour is $25.
Required:
a. What is the learning-curve percentage, assuming the cumulative average method?
b. What is the time needed to build 8 picture frames by a new employee using the cumulative average-
time method? You may use an index of −0.1520.
c. What is the time needed to produce the 16th frame by a new employee using the incremental unit-
time method? You may use an index of −0.3219.
d. How much manufacturing overhead would be charged to the 16 picture frames using the
average-time approach?
Answer:
a. Job Hours Cumulative Cumulative Average
1 6 6 6
2 4.8 10.8 5.4
Learning percentage = 4.8/6 = 0.90
b. Y = p × q
= 6 × 8− 0.1520
= 4.37 hours
or 1 unit = 6
2 units = 6 × 0.9 = 5.4
4 units = 5.4 × 0.9 = 4.86
8 units = 4.86 × 0.9 = 4.37 hours
Time to build 8 units: 8 × 4.37 = 35 hours
c. Y =p×q
= 6 × 16−.0.3219
= 2.458 hours
or 1 unit = 6
2 units = 6 × 0.8 = 4.8
4 units = 4.8 × 0.8 = 3.84
8 units = 3.84 × 0.8 = 3.072
16 units = 3.072 × .8 = 2.458 hours
d. Total time = 2.458 × 16 = 39.328 hours
Overhead charge = 39.328 × $25 = $983.20
Diff: 3
Objective: 6
AACSB: Application of knowledge
24) Each time Mayberry Nursery hires a new employee, it must wait for some period of time before the
employee can meet production standards. Management is unsure of the learning curve in its operations
but it knows the first job by a new employee averages 40 hours and the second job averages 32 hours.
Assume all jobs to be equal in size.
Required:
a. What is the learning-curve percentage, assuming the cumulative average-time method?
b. What is the time for a new employee to build 16 units with this learning curve using the
cumulative average-time method? You may use an index of −0.1520.
Answer:
a. Job Hours Cumulative Cumulative Average
1 40 40 40
2 32 72 36
Learning percentage = 36/40 = 0.90
b. Y = p × q
= 40 × 16−.1520
= 26.244 hours
or 1 unit = 40
2 units = 40 × 0.9 = 36
4 units = 36 × 0.9 = 32.4
8 units = 32.4 × 0.9 = 29.16
16 units = 29.16 × 0.9 = 26.244 hours
16 × 26.244 = 419.904 hours
Diff: 3
Objective: 6
AACSB: Application of knowledge
25) Jake's Copy Center hires a new employee. Jake knows he has to be patient with the employee until the
employee gains enough experience to meet production standards. Jake is unsure of the learning curve in
his operation, but he knows the first job by a new employee averages 50 minutes and the second job
averages 40 minutes. Assume all jobs to be equal in size.
Required:
a. What is the learning-curve percentage, assuming the cumulative average-time method?
b. What is the time for a new employee to do 32 jobs with this learning curve using the cumulative
average-time method? You may use an index of −0.1520.
Answer:
a. Job Minutes Cumulative Cumulative Average
1 50 50 50
2 40 90 45
Learning percentage = 45/50 = 0.90
b. Y = p × q
= 50 × 16−.1520
= 29.525 minutes
or 1 unit = 50
2 units = 50 × 0.9 = 45
4 units = 45 × 0.9 = 40.5
8 units = 40.5 × 0.9 = 36.45
16 units = 36.45 × 0.9 = 32.805
32 units = 32.805 × 0.9 = 29.525 minutes
32 × 29.525 = 944.784 minutes = Approximately 15 hours and 45 minutes
Diff: 3
Objective: 6
AACSB: Application of knowledge
26) Discuss the potential use of nonlinear curves in cost functions and cost analysis. Give some examples.
Answer: Cost functions are not always linear. A nonlinear cost function is a cost function for which the
graph of total costs is not a straight line within the relevant range of operations. One example is a series of
straight line segments that change their slopes at critical intersection points within the range of operation.
Another example would be a step function. A step function is a function where the cost remains the same
over various ranges of the level of activity, but the cost increases by discrete amounts (or steps) as the
level of activity advances from one range to another. In addition to the examples mentioned above, there
are situations where the cost or use of resources can be represented by a curve instead of a single straight
line or a group of segmented straight lines. One example of a curve is a learning curve. A learning curve
is a function that measures how labor-hours per unit decline as units of production increase because
workers are learning and becoming better at their jobs.
Diff: 2
Objective: 6
AACSB: Application of knowledge
27) Explain the difference between the cumulative average-time learning model and the incremental unit-
time learning model.
Answer: In the cumulative average-time learning model, cumulative average time per unit declines by a
constant percentage each time the cumulative quantity of units produced doubles.
In the incremental unit-time learning model, incremental time needed to produce the last unit declines by
a constant percentage each time the cumulative quantity of units produced doubles.
Diff: 2
Objective: 6
AACSB: Analytical thinking
3) Which of the following is a step to overcome problems related to data collection for estimating cost
function?
A) The analyst should remove the inflationary effects.
B) The analyst should consider fixed costs as variable.
C) The analyst should also use extreme values while calculating cost functions.
D) The analyst should not use accrual accounting.
Answer: A
Diff: 2
Objective: 7
AACSB: Analytical thinking
4) Which of the following is a step followed by an analyst to overcome problems related to data collection
for estimating cost function?
A) to use cash accounting
B) to consider fixed costs as variable costs and treat allocated fixed cost per unit as a variable cost
C) to eliminate unusual observations if extreme values of observations occur
D) to include the inflationary price effects in the data
Answer: C
Diff: 2
Objective: 7
AACSB: Analytical thinking
6) Data collection problems can arise when extreme values of observations occur.
Answer: TRUE
Diff: 1
Objective: 7
AACSB: Analytical thinking
7) Misinterpretation of data can arise when fixed costs are reported on a per unit basis.
Answer: TRUE
Diff: 2
Objective: 7
AACSB: Analytical thinking
8) Inflation can distort data that are compared over time so purely inflationary effects should be removed.
Answer: TRUE
Diff: 2
Objective: 7
AACSB: Analytical thinking
9) Fixed costs are sometimes allocated to individual products as part of the standard costing system.
When this is the case, they should be treated as variable costs for purposes of future cost estimation.
Answer: FALSE
Explanation: The danger is to regard these costs as variable rather than fixed. The analyst should
distinguish carefully fixed costs from variable costs and not treat allocated fixed cost per unit as a variable
cost.
Diff: 2
Objective: 7
AACSB: Analytical thinking
10) Jack Williams has just purchased the film studio of a movie company that specializes in comedies. He
found that the company did not try to estimate the cost of making a movie. Instead, it just gave the
producer a budget and told him/her to make a movie within budget. Mr. Williams does not like the
former movie-budget concept and desires to establish a formal cost estimation system.
Required:
What are some of the potential problems that may be encountered in changing from a budget to a cost
estimation movie making system?
Answer: One of the first problems will be the timing of matching the cost drivers with the actual movie
production process. Under the former budget system, the relationships with many of the cost drivers
were probably forced to meet budget, or else poorly kept because they were substantially under budget
and control over them was weak.
Next will be the problem of determining which costs are fixed and which are variable under the budget
system. It may be difficult to determine those that are truly variable.
Timing problems will also have to be reconciled. Some costs may be incurred monthly rather than by
movie, and some type of accrual will have to be made to keep the costs allocated to the proper cost driver.
Finally, there may be gaps in the historical data because only total costs had to be maintained within the
budget. There was probably little attention paid to cost categories, thereby causing reliable cost data to be
scarce.
Diff: 2
Objective: 7
AACSB: Analytical thinking
3) Grandy's Beer was to manufacture 600 cases of ale next week. The accountant provided the following
analysis of total manufacturing costs.
Trainer's hours:
Variable Coefficient Standard Error t-Value
Constant $1,005.45 $217.52 4.61
Independent Variable $22.54 $3.23 7.40
r2 = 0.56
Number of horses:
Variable Coefficient Standard Error t-Value
Constant $5,240.20 $1,180.32 4.44
Independent Variable $951.73 $271.85 4.75
r2 = 0.63
What is the estimated total cost for the coming year if 14,700 trainer hours are incurred and the stable has
310 horses to be trained, based upon the best cost driver?
A) $7,992.85
B) $300,276.50
C) $332,343.45
D) $13,995,671.20
Answer: B
Explanation: y = $5,240.20 + ($951.73 × 310) = $300,276.50 based on highest r2, which uses # of horses as
the cost driver
Diff: 3
Objective: A
AACSB: Application of knowledge
5) A major concern that arises with multiple regression is multicollinearity, which exists when ________.
A) the dependent variable is not normally distributed
B) the standard errors of the coefficients of the individual variables decrease
C) the R2 statistic is low
D) two or more independent variables are highly correlated with one another
Answer: D
Diff: 2
Objective: A
AACSB: Analytical thinking
6) In multiple regression, when two or more independent variables are highly correlated with one
another, the situation is known as ________.
A) heteroscedasticity
B) homoscedasticity
C) multicollinearity
D) autocorrelation
Answer: C
Diff: 2
Objective: A
AACSB: Analytical thinking
7) Which of the following is the mathematical expression to calculate the coefficient of determination?
A) Coefficient of determination = 1 - (Unexplained variation / Total variation)
B) Coefficient of determination = (1 + Total variation ) / Unexplained variation)
C) Coefficient of determination = (1 - Unexplained variation ) / Total variation)
D) Coefficient of determination = 1 - Unexplained variation + Total variation)
Answer: A
Diff: 2
Objective: A
AACSB: Analytical thinking
8) The coefficient of determination (r2) measures the percentage of variation in X (the independent
variable) explained by Y (the dependent variable).
Answer: FALSE
Explanation: The coefficient of determination (r2) measures the percentage of variation in Y (the
dependent variable) explained by X (the independent variable).
Diff: 1
Objective: A
AACSB: Analytical thinking
9) Generally a coefficient of determination (r2) of 0.30 or higher passes a goodness of fit test.
Answer: TRUE
Diff: 2
Objective: A
AACSB: Analytical thinking
10) Goodness of fit has meaning only if the relationship between the cost drivers and costs is
economically plausible.
Answer: TRUE
Diff: 2
Objective: A
AACSB: Analytical thinking
11) Multicollinearity exists in multiple regression when two or more independent variables are highly
correlated with each other.
Answer: TRUE
Diff: 2
Objective: A
AACSB: Analytical thinking
12) The t-value of a coefficient measures how large the value of the estimated coefficient is relative to its
standard error.
Answer: TRUE
Diff: 2
Objective: A
AACSB: Analytical thinking
13) The standard error of the estimated coefficient indicates how much the estimated value, b, is likely to
be affected by random factors.
Answer: TRUE
Diff: 1
Objective: A
AACSB: Analytical thinking
14) The new cost analyst in your accounting department has just received a computer-generated report
that contains the results of a simple regression program for cost estimation. The summary results of the
report appear as follows:
Required:
a. What is the cost estimation equation according to the report?
b. What is the goodness of fit? What does it tell about the estimating equation?
Answer:
a. y = $74.79 + $1,081.76X
b. Goodness of fit is 0.75. It measures how well the predicted values match the actual observations. In
this case, the equation passes the goodness of fit test because it is substantially above 0.30, the threshold
of acceptance.
Diff: 1
Objective: A
AACSB: Application of knowledge
15) South by Southwest Company used least squares regression analysis to obtain the following output:
X coefficient(s) $2.473
Standard error of coefficient(s) 0.0966
Required:
a. What is the total fixed cost?
b. What is the variable cost per employee?
c. Prepare the linear cost function.
d. What is the coefficient of determination? Comment on the goodness of fit.
Answer:
a. The constant or intercept is the total fixed cost of $7,540.
b. The variable cost per employee is the X coefficient of $2.473.
c. y = $7,540 + $2.473X
d. The coefficient of determination is the r2 of 0.8924. This represents a very high goodness of fit. The
closer to 1.0, the better the cost driver explains the cost. Therefore, the conclusion can be drawn that there
is a significant relationship between the cost of the payroll department and the number of employees.
Diff: 2
Objective: A
AACSB: Analytical thinking
16) Dandy Manufacturing Company uses two different independent variables (machine-hours and
number of packages) in two different equations to evaluate costs of the packaging department. The most
recent results of the two regressions are as follows:
Machine-hours:
Variable Coefficient Standard Error t-Value
Constant $748.30 $341.20 2.19
Independent Variable $52.90 $35.20 1.50
r2 = 0.33
Number of packages:
Variable Coefficient Standard Error t-Value
Constant $242.90 $75.04 3.24
Independent Variable $5.60 $2.00 2.80
r2 = 0.73
Required:
a. What are the estimating equations for each cost driver?
b. Which cost driver is best and why?
Answer:
a. Machine-hours y = $748.30 + $52.90X
Number of packages y = $242.90 + $5.60X
b. Machine-hours has a low r2 which implies that a small proportion of the variance is explained by
machine-hours, thereby making it less attractive than number of packages as a cost predictor.
Also, for the independent variable, number of packages, the t-value of 2.80 indicates that a
relationship exists between the independent and dependent variables. For machine-hours, the t-value
(1.50) is below 2.00, indicating that the coefficient is not significantly different from zero and that there
may not be a relationship between the independent and dependent variables.
The t-values of the constant terms (g) for both drivers is greater than 2.00, therefore, there is no
distinguishing characteristic between the constants.
Given the above findings, it appears that number of packages is the best predictor of costs of the
packing department.
Diff: 2
Objective: A
AACSB: Analytical thinking
17) Yancy Company manufactures chairs. Because the efforts of manufacturing are approximately equal
between labor and machinery, management is considering other possible cost drivers. By considering
different cost drivers, it is anticipated that the estimating process can be improved. The following cost
estimating equations with their r2 values have been determined for 2017:
Required:
a. Which equation should be selected for the analysis?
b. What other factors should be included in the selection of the estimating equation?
Answer:
a. Equation 1 for cutting time is slightly better than the other two equations based on r2 values.
Generally, an r2 above 0.30 indicates a goodness of fit that is acceptable for most situations. Therefore, all
three equations are acceptable when considering only the coefficient of determination.
However, because the values are so close together, other factors should be considered.
b. Other factors to be considered are economic plausibility, the significance of independent variables,
and specification analysis. The best cost drivers of the dependent variables are those that meet all these
criteria plus that of best coefficient of determination.
Diff: 2
Objective: A
AACSB: Analytical thinking