Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

CONSTRUCTION MANAGEMENT

LECTURE 15

PROJECT TIME-COST TRADE-OFF

1
CONSTRUCTION PROJECT COSTS (1)
 The principal components of a contractor's costs and expenses
result from the use of labors, materials, equipment, and
subcontractors.
 Additional general overhead cost components include taxes,
premiums on bonds and insurance, and interest on loans.

 Fixed cost: costs that spent once at specific point of time (e.g.,
the cost of purchasing equipment, etc.)

 Time-related cost: costs spent along the activity duration


(e.g., labor wages, equipment rental costs, etc.)

 Quantity-proportional cost: costs changes with the


quantities (e.g., material cost)
2
CONSTRUCTION PROJECT COSTS (2)
Total project costs = direct costs + indirect costs
Project direct costs
 The costs and expenses that are incurred for a specific
activity are termed direct costs.
 These costs are estimates based on detailed analysis of
contract activities, the site conditions, resources
productivity data, and the method of construction being
used for each activity.
 Includes labor costs, material costs, equipment costs, and
subcontractor costs.

Project indirect costs


 Other costs such as the overhead costs.
 Part of the company’s indirect costs is allocated to each of
the company's projects. The indirect costs always classified 3

to: Project (site) overhead; and General (head-office)


overhead.
CONSTRUCTION PROJECT COSTS (3)
Project overhead
 Site-related costs: cost of items that can not be directly
charged to a specific work element (fixed or time-related).
 Costs of site utilities, supervisors, housing and feeding of
project staff, parking facilities, offices, workshops, stores, and
first aid facility.
 A detailed analysis of the particular elements of site-related
costs is required to arrive at an accurate estimate.
 However, companies used to develop their own forms and
checklists for estimating these costs.

 Sit overhead costs are estimated to be between 5% - 15%


of project total direct cost.

4
CONSTRUCTION PROJECT COSTS (4)
General overhead
 Costs that cannot be directly attributed to a specific project
called general overhead.
 These are the costs that used to support the overall company
activities. (cost of the head-office expenses, mangers, directors,
design engineers, schedulers, etc.)

 Generally, the general overhead for a specific contract can be


estimated to be between 2% - 5% of the contract direct cost.

 The amount of the general overhead that should be allocated


to a specific project equals:
 Project direct cost x general overhead of the company in a
year/ expected sum of direct costs of all projects during the
5
year
CONSTRUCTION PROJECT COSTS (5)
 When studying cash flow, it is very important to determine the
actual dates when the expenditures (cost) will take place.
 At that time, the expenditures will renamed as the expenses.
 As shown in the figure, they are the same except the expenses
are shifted (delayed) than the costs.

6
EXAMPLE 1
 Consider the construction of 8-week foundation
activity with operation cost of PKR 8800.
 The operational cost is broken down into the following
elements:
 Labor PKR1600 paid weekly
 Plant PKR 4000 paid weekly after 4 weeks credit facility
 Materials PKR 800 paid weekly after 5 weeks credit
facility
 Subcontractors PKR 2400 paid weekly after 3 weeks credit
facility
 Determine the expenses (cash out) of this activity.
7
SOLUTION TO EXAMPLE 1
 A time-scaled plan is developed for this activity for the
payments for labor, plant, material, and subcontractors. The cot
will be plotted weekly with the delay specified

8
TIME-COST TRADE-OFF (1)
 Activity durations depends upon the type and amount of
resources.
 Assigning more workers to a particular activity will normally
result in a shorter duration.
 Greater speed may result in higher costs and lower quality
 Need to consider impacts of time and cost trade-offs.
 Reducing both projects’ cost and time is critical.

 This relationship between construction projects’ time and cost


is called time cost trade-off decisions

 Time-cost trade-off decisions are complex and require selection


of appropriate construction method for each project task.
9
TIME-COST TRADE-OFF (2)
 The objective of the time-cost trade-off analysis is to reduce
the original project duration, determined from the critical path
analysis, and to meet a specific deadline, with the least cost.
 In addition to that it might be necessary to finish the project in
a specific time to:
 Recover early delays.
 Avoid liquidated damages.
 Free key resources early for other projects.
 Avoid adverse weather conditions that might affect
productivity
Liquidated damages:
 Receive an early completion-bonus.
Amount decided during the
 Improve project cash flow formation of contract for the
compensation of the late
performance for the injured
10
party. It is a fixed stipulated
sum of penalty by the
contractor
TIME-COST TRADE-OFF (3)
 Reducing project duration can be done by adjusting overlaps
between activities or by reducing activities’ duration.
 What is the reason for an increase in direct cost as the
activity duration is reduced?
 A simple case arises in the use of overtime work. By
scheduling weekend or evening work, the completion time for
an activity as measured in calendar days will be reduced.
However, extra wages must be paid for such overtime work, so
the cost will increase.
 Also, overtime work is more prone to accidents and quality
problems that must be corrected, so costs may increase.
 The activity duration can be reduced by one of the following
actions:
 Applying multiple-shifts work.
 Working extended hours (over time).
 Offering incentive payments to increase the productivity.
 Working on week ends and holidays.
 Using additional resources.
11
 Using materials with faster installation methods.
 Using alternate construction methods or sequence.
ACTIVITY TIME-COST RELATIONSHIP (1)
 In general, there is a trade-off between the time and the direct cost to
complete an activity; the less expensive the resources, the larger
duration they take to complete an activity.
 Shortening duration on an activity will normally increase its direct
cost which comprises: the cost of labor, equipment, and material.
 It should never be assumed that the quantity of resources deployed
and the task duration are inversely related. Thus one should never
automatically assume that the work that can be done by one man in
16 weeks can actually be done by 16 men in one week.
Normal duration: against minimum cost
Crash duration: against maximum cost
Intermediate point: ideal or optimal trade-
off between time and cost for this activity.
Cost slope of the activity: slope of line

12

linear time/cost trade-off for an activity


ACTIVITY TIME-COST RELATIONSHIP (2)
 The slope of this line can be calculated mathematically by
knowing the coordinates of the normal and crash points.
 Cost slope = crash cost – normal cost / normal duration – crash
duration

Illustration of non-linear 13
time/cost trade-off for an activity
EXAMPLE 2
 A subcontractor has the task of erecting 8400 square meter
of metal scaffolds. The contractor can use several crews
with various costs. It is expected that the production will
vary with the crew size as given below:

 Consider the following rates: Labor PKR 250/day;


carpenter PKR 350/day; foreman PKR 440/day and
scaffolding 160/day. Determine the direct cost of this
activity considering different crews formation. 14
SOLUTION TO EXAMPLE 2
 The duration for installing the metal scaffold can be
determined by dividing the total quantity by the estimated
daily production. The cost can be determined by summing
up the daily cost of each crew and then multiply it by the
duration of using that crew. The calculations are shown in
the following table.

Crew Duration Cost (PKR)


size (days)
5 50.6 (use 51) 51 x (1x160 + 2x250 + 2x350 + 1x440) = 91800
6 41.2 (use 42) 42 x (2x160 + 3x250 + 2x350 + 1x440) = 92820
7 36.5 (use 37) 37 x (2x160 + 3x250 + 3x350 + 1x440) = 94720

15
SOLUTION TO EXAMPLE 2
 This example illustrates the options which the planner
develops as he/she establishes the normal duration for an
activity by choosing the least cost alternative. The time-cost
relationship for this example is shown in Figure. The cost slop
for this activity can be calculates as follow:
 Cost slope 1 (between points 1 and 2) = (92820 – 91800) / (51 –
42) = 113.33 PKR/day
 Cost slope 2 (between points 2 and 3) = (94720 – 92820) / (42
– 37) = 380 PKR/day
95000
3
94000
93000
2
92000 1

91000
16
35 40 45 50 55
Time-cost relationship
PROJECT TIME-COST RELATIONSHIP (1)
 If each activity was scheduled for the duration that
resulted in the minimum direct cost, the time to complete
the entire project might be too long.
 Thus, planners perform what is called time-cost trade-off
analysis to shorten the project duration.
 This can be done by selecting some activities on the critical
path to shorten their duration.
 As the direct cost for the project equals the sum of the
direct costs of its activities, then the project direct cost will
increase by decreasing its duration.
 Indirect cost will decrease by decreasing the project
duration, as the indirect cost are almost a linear function
with the project duration.
 The optimum project duration can be determined as the
project duration that results in the least project total cost. 17
PROJECT TIME-COST RELATIONSHIP (2)

18
QUESTIONS?

19

You might also like