Professional Documents
Culture Documents
Government of Andhra Pradesh Roads and Buildings Department: ST ND
Government of Andhra Pradesh Roads and Buildings Department: ST ND
From To
Sri A.S.S. Prakasa Rao, B.Tech., The Superintending Engineer,
Executive Engineer(R&B) (FAC), (R&B) Circle,
(R&B) Division : Peddapuram. Kakinada
Letter No. LWE Work/Y-J Road / ATO / PDP/ 2019-20, dt. . .2021
Sir,
Sub:- LWE - R&B Division, Peddapuram – Strengthening of Yeleswaram - Jaddangi
road from Km.0/0 to 4/420 in East Godavari District – Estimate Amount
Rs.279.00 Lakhs - 1st Working Estimate Amount Rs.279.00 Lakhs - 2nd Working
Estimate Amount Rs.279.00 Lakhs – Submitted – Approval – Requested –
Regarding.
The site handed over to the contractor on dated 13-07-2020 and date fixed for completion
of the work is 12-04-2021 (9 months). The work was completed in all aspects within the
agreement time.
The 1st working estimate was sanctioned with certain deviations vide Chief Engineer
(R&B), NABARD, LWE Memo No: 12084/EG/RCPLWE/ DCE (RR)/EE/DEE1/AEE2/2019 Dt: 06-
10-2020. The 1st working estimate is sanctioned with the provision of strengthening of existing
road to a length of 2.770kms of BT and 0.750kms CC (Total length : 3.520kms). But, during the
execution of work, the strengthening of length of BT road comes to 2.792kms and CC Road
comes to 0.728kms (Total length : 3.520kms). Due to increase in length of BT road of length
22m, the corresponding quantities of BT item of work are slightly increased and simultaneously
the quantities of CC pavement are slightly decreased.
Earth work for forming embankment with borrowed useful earth
There is “No Deviation” for Earth work for forming embankment with borrowed
useful earth.
Construction of CC pavement and strengthening of BT road:
st
The 1 working estimate is sanctioned with the provision of strengthening of
existing road to a length of 2.770kms of BT and 0.750kms of CC, but, during the
execution of work, the strengthening of length of BT road comes to 2.792m and
CC Road comes to 0.728kms.
Due to increase in length of BT road of length 22m, the corresponding quantities
of BT item of work are slightly increased and simultaneously the quantities of CC
pavement are slightly decreased.
Construction of Slab culvert 1 vent 2.0m span – 2nos :
The “Construction of slab Culverts” are since deleted in the 1st working estimate
and the deviations were approved vide Chief Engineer (R&B), NABARD, LWE
Memo No: 12084/ EG/ RCPLWE/ DCE (RR)/EE/DEE1/AEE2/2019 Dt: 06-10-
2020.
Construction of 2 Rows of 1000mm dia pipe Culverts – 3nos in km
1/6,
km.2/6 and km.3/4 :
As per site conditions the Construction of 2 Rows of 1000mm dia RCC Pipe
Culvert – 1No. at km 3/4 was only executed. Hence the quantities obtained after
execution are incorporated in the 2nd working estimate.
Construction of 1 Row of 1000mm dia RCC Pipe Culverts – 3 nos in km.2/4,
km.2/6 & km 3/6:
During the execution of 1 Row of 1000mm dia RCC Pipe Culverts the quantities
are slightly increased/ decreased as per site conditions. Hence the same are
incorporated in the 2nd working estimate.
L.S. Provisions :
In the sanctioned estimate, the L.S. Provision towards Price Adjustment is made
to an amount of Rs 5.00 Lakhs, but during the execution of work the cost of
materials used on the work are hike and the price adjustment was worked out to
an amount of Rs 7.15 Lakhs and accordingly the provision is made in the 2nd
working estimate.
1. The L.S. Provision towards seigniorage charges in the sanctioned estimate is
Rs.10,00,000/- But, in the 2nd working estimate Rs.9,47,000/- is provided as per
requirement.
4. LS Provision for PMGSY Logo Board, Semi Reflective Cautionary, Mandatory &
Informatory Boards, Semi Reflective Sign Boards, KM Stones, HM Stones, 5th
Stone – No Deviation
5. LS Provision for 150 mm PVC pipes and 300 mm dia water pipe lines under CC
Road – No Deviation
In view of the above circumstances, the 2 nd working estimate is prepared for Rs.279.00
lakhs as against the sanctioned Estimate amount of Rs.279.00 Lakhs with all the above
deviations and the position of working estimate considering excess tender premium & Price
adjustment is as follows:
The necessity and provisions made are explained in the specification report
accompanying the working estimate, which is herewith submitted for favour of kind perusal and
request to approve the working estimate-II and communicate orders at an early date.
Yours faithfully,
Executive Engineer(R&B),
R&B Division : Peddapuram
I further submit that in the 1 st working estimate, there is a provision of Rs 3.00 Lakhs
towards price adjustment. But after the execution of work the price adjustment was worked out to
an amount of Rs 8.00 Lakhs.
In view of above, working estimate –II for an amount of Rs 275.00 Lakhs is here with
submitted by duly enhancing provision towards price adjustment amount to Rs 8.00 Lakhs.
In view of the above circumstances, the working estimate - II is prepared for Rs.275.00
lakhs as against the sanctioned Estimate amount of Rs.279.00 Lakhs by duly enhancing
provision towards price adjustment amount to Rs 8.00 Lakhs and the position of working
estimate considering excess tender premium & Price adjustment is as follows:
The necessity and provisions made are explained in the specification report
accompanying the working estimate, which is herewith submitted for favour of kind perusal and
request to approve the working estimate-II and communicate orders at an early date.
Yours faithfully,
Executive Engineer(R&B),
R&B Division : Peddapuram
GOVERNMENT OF ANDHRA PRADESH
ROADS AND BUILDINGS DEPARTMENT
From To
Sri A.S.S. Prakasa Rao, B.Tech., The Superintending Engineer,
Executive Engineer(R&B), (R&B) Circle,
(R&B) Division : Peddapuram. Kakinada
The site handed over to the contractor on dated 13-07-2020 and date fixed for
completion of the work is 12-04-2021 (9 months). At present the contractor has mobilized the
materials and takeup the work.
The estimate for the above work is sanctioned with the provision of strengthening the
existing road intermediate lane road (5.50m).
1) Construction of CC pavement with the provision of GSB 100mm thick + M10 concrete
100mm + M30 concrete 200mm thick of 5.50m width from Km.0/900 to 1/600 to a
length of 700mts
2) The estimate is sanctioned with the crust of WMM 150 mm + BM 50mm + SDBC
25mm thick from km.1/600 to 4/420 to a length of 2820m.
3) Construction of 1 vent of 2.0m span slab culverts – 2nos in Km. 0/2 and 1/6.
4) Construction of 1 Row of 1000mm dia pipe culverts – 2nos in Km. 1/2 and 1/8.
5) Construction of 2 Rows of 1000mm dia pipe culverts – 3nos in Km.2/6 – 2nos and
1/8.
During the execution of work the following deviations are found necessary as per the site
conditions and are explained as below:
L.S. Provisions :
8. The L.S. Provision towards Quality Control charges in the sanctioned estimate is
Rs.1,00,000/- But, in the working estimate Rs.50,000/- is provided as per
requirement.
10. LS Provision for PVC pipes and RCC Hume pipes to cross water in village limits
under CC pavement is not included in the original sanctioned estimate. But this
item is very much needed in village limits and CC Pavement stretches. Hence an
L.S provision for an amount of Rs 1,50,000/- is provided as per requirement.
The necessity and provisions made are explained in the specification report accompanying the
working estimate, which is herewith submitted for favour of kind perusal and request to approve the
working estimate and communicate variation orders at an early date.
Yours faithfully,
Executive Engineer(R&B),
R&B Division : Peddapuram