PD 1096 (1977) – National Building Code

Section 207. Duties of a Building Official.

In his respective territorial jurisdiction, the Building Official shall be primarily responsible for the
enforcement of the provisions of this Code as well as of the implementing rules and regulations issued
therefor. He is the official charged with the duties of issuing building permits.

In the performance of his duties, a Building Official may enter any building or its premises at all
reasonable times to inspect and determine compliance with the requirements of this Code, and the
terms and conditions provided for in the building permit as issued.

When any building work is found to be contrary to the provisions of this Code, the Building Official may
order the work stopped and prescribe the terms and/or conditions when the work will be allowed to
resume.

Likewise, the Building Official is authorized to order the discontinuance of the occupancy or use of any
building or structure or portion thereof found to be occupied or used contrary to the provisions of this
Code.

xxx xxx xxx

Section 212. Administrative Fines.

For the violation of any of the provisions of this Code or any of the rules or regulations issued
thereunder the Secretary is hereby empowered to prescribe and impose fines not exceeding ten
thousand pesos.

Section 213. Penal Provisions.

It shall be unlawful for any person, firm or corporation, to erect, construct, enlarge, alter, repair, move,
improve, remove, convert, demolish, equip, use, occupy, or maintain any building or structure or cause
the same to be done contrary to or in violation of any provision of this Code.

Any person, firm or corporation who shall violate any of the provisions of this Code and/or commit any
act hereby declared to be unlawful shall upon conviction, be punished by a fine of not more than twenty
thousand pesos or by imprisonment of not more than two years or by both such fine and imprisonment:
Provided, that in the case of a corporation firm, partnership or association, the penalty shall be imposed
upon its officials responsible for such violation and in case the guilty party is an alien, he shall
immediately be deported after payment of the fine and/or service of his sentence.

xxx xxx xxx

Section 301. Building Permits.

No person, firm or corporation, including any agency or instrumentality of the government shall erect,
construct, alter, repair, move, convert or demolish any building or structure or cause the same to be
done without first obtaining a building permit therefor from the Building Official assigned in the place
where the subject building is located or the building work is to be done.

xxx xxx xxx

Section 309. Certificate of Occupancy.

No building or structure shall be used or occupied and no change in the existing use or occupancy
classification of a building or structure or portion thereof shall be made until the Building Official has
issued a Certificate of Occupancy therefor as provided in this Code.

A certificate of Occupancy shall be issued by the Building Official within thirty (30) days if after final
inspection and submittal of a Certificate of Completion referred to in the preceding section, it is found
that the building or structure complies with the provisions of this Code.

The Certificate of Occupancy shall be posted or displayed in a conspicuous place on the premises and
shall not be removed except upon order of the Building Official.

The non-issuance, suspension and revocation of Certificates of Occupancy and the procedure for appeal
therefrom shall be governed in so far as applicable, by the provisions of Section 306 and 307 of this
Code.

Pasig City Ordinance 25-92 dated 26 December 1992

ARTICLE IV

Building and Other Construction Permit Fees

SECTION 91. Administrative Provisions. — No person, firm or corporation, including government


agencies, is allowed to erect, construct, alter, move, convert or demolish any building or structure
without first obtaining a building permit issued by the Municipal Engineer/Building Official.

SECTION 92. Assessment. — Assessment of building permit fees shall be based on the following:
1. Type of Occupancy or Use of Building
2. Cost of Construction
3. Floor Area
4. Height

xxx xxx xxx

SECTION 105. Certificates of Use of Occupancy — Schedule. —


a) Category I:
1) Building made of traditional indigenous
materials as defined under the Code P40.00
2) Building costing more than P15,000.00 up
to P50,000.00 125.00
3) Building costing more than P50,000.00 up
to P100,000.00 250.00
4) Building costing more than P100,000.00 up
to P150,000.00 375.00
5) Building costing more than P150,000.00 up
to P250,000.00 500.00
6) Building costing more than P250,000.00 up
to P500,000.00 1,000.00
7) Building costing more than P500,000.00 up
to P1,000,000.00 250.00
8) Building costing more than P1,000,000.00 2,500.00
b) Category II:
1) Building costing up to P50,000.00 P250.00
2) Building costing more than P50,000.00 up
to P100,000.00 500.00
3) Building costing more than P100,000.00 up
to P250,000.00 1,000.00
4) Building costing more than P250,000.00 up
to P500,000.00 2,000.00
5) Building costing more than P500,000.00 up 250.00 *
to P1,000,000.00 4,000.00
6) Building costing more than P1,000,000.00 6,000.00
c) Category III:
1) Building costing up to P50,000.00 P150.00
2) Building costing more than P50,000.00 up
to P150,000.00 375.00
3) Building costing more than P150,000.00 up
to P250,000.00 750.00
4) Building costing more than P250,000.00 up
to P500,000.00 1,500.00
5) Building costing more than P500,000.00 up
to P1,000,000.00 3,000.00
6) Building costing more than P1,000,000.00 5,000.00
d) Category IV:
1) Garages, carports, balconies, terraces, lanais and the like:
Fifty percent (50%) of the rate of the principal
building, according to Category
2) Aviaries, aquariums, zoo structures and the like:
a. With floor area up to 20 sq.m. P25.00
b. With floor area above 20 sq.m.
up to 500 sq.m. P50.00
c. With floor area above 500 sq.m.
up to 1,000 sq.m. P75.00
d. With floor area above 1,000 sq.m.
up to 5,000 sq.m. P100.00
e. With floor area above 5,000 sq.m.
up to 10,000 sq.m. P250.00
f. With floor area above 10,000 sq.m. P300/500.00
e) Ancillary Structures
1) Bank and Records Vaults,
per unit P50.00
2) Swimming Pools,
per unit:
2.1 Residential P25.00
2.2 Commercial/Industrial 75.00
2.3 Social/Institutional 50.00
2.4 Improvised swimming pools made of materials listed under this Rule:
3) Swimming pool shower rooms/locker rooms:
per unit
3.1 Residential P15.00
3.2 Commercial/Industrial 40.00
3.3 Social/Institutional 25.00
4) Towers, per unit
Self-Supporting Trilon
(guyed)
4.1 Residential P15.00 P15.00
4.2 Commercial/Industrial 300.00 30.00
4.3 Social/Institutional 25.00 25.00
5) Commercial/Industrial Storage Silos:
per unitP300.00
6) Smokestacks, per unit 50.00
7) Chimney, per unit 25.00
8) Commercial/Industrial Fixed Ovens,
per unitP25.00
9) Industrial Kiln/Furnace, per unit 50.00
10) Reinforced Concrete Tanks, per unit 20.00
10.1 Residential:
10.11 Up to 2 cu.m. P10.00
10.12 Above 2 cu.m. 30.00
10.2 Commercial/Industrial 60.00
10.3 Social/Institutional 40.00
11) Steel Tanks, per unit
11.1 Residential:
11.11 Up to 2 cu.m. P10.00
11.12 Above 2 cu.m. 30.00
11.2 Commercial/Industrial
11.21 Above ground P100.00
11.22 Underground 75.00
11.3 Social/Institutional 50.00
12) Booths, Kiosks, Platforms, Stages
and the like P25.00

SECTION 106. Change in Use/Occupancy. — The amount of Ten Pesos (P10.00) shall be charged for
every sq.m. or fraction thereof of area affected.
SECTION 107. Certificates of Occupancy for Buildings/Structures Completed Prior to Effectivity of the
NBC. — Schedule.
a) Category I:
1) Indigenous family dwellings and houses of
mixed materials having an area not
exceeding 40 sq.m. P50.00
2) Buildings with areas above 40 sq.m. up
to 100 sq.m. 100.00
3) Buildings with area above 100 sq.m. up
to 200 sq.m. 150.00
4) Buildings with area above 200 sq.m. up
to 300 sq.m. 200.00
5) Buildings with area above 300 sq.m. up
to 500 sq.m. 400.00
6) Buildings with area above 500 sq.m. 800.00
b) Category II:
1) Buildings with area up to 5,000 sq.m. P200.00
2) Buildings with area above 5,000 sq.m. up
to 10,000 sq.m. 400.00
3) Buildings with area above 10,000 sq.m. up
to 20,000 sq.m. 800.00
4) Buildings with area above 20,000 sq.m. up
to 30,000 sq.m. 1,600.00
5) Buildings with area above 30,000 sq.m. 3,200.00
c) Category III:
1) Buildings with area up to 5,000 sq.m. P90.00
2) Buildings with area above 5,000 sq.m. up
to 10,000 sq.m. 225.00
3) Buildings with area above 10,000 sq.m. up
to 20,000 sq.m. 450.00
4) Buildings with area above 20,000 sq.m. up
to 30,000 sq.m. 900.00
5) Buildings with area above 30,000 sq.m. 1,800.00

xxx xxx xxx

SECTION 111. Surcharge/Penalty. — Without prejudice to the provisions of the preceding sections,
the Municipal Engineer/Building Official is hereby authorized to impose a penalty or surcharge in the
following cases in such amount and in the manner as hereunder fixed and determined:
a) For constructing, installing, repairing, altering or causing any change in the use or occupancy of
any building or part thereof or appurtenances thereto without any permit, there shall be imposed a
surcharge of twenty five percent (25%) of the building permit fee. When the work in the building or
structure is started during the pendency of the final action or pending approval by the Municipal
Engineer/Building Official of the application for building permit, the amount of the surcharge shall be
according to the following:
1) Excavation for foundation 10%
2) Construction of foundation
(including pile driving and laying of
reinforcing bars) 15%
3) Construction of superstructure up to 2
meters above established grade 20%
4) Construction of superstructure above 2 meters 25%

Pasig City Ordinance 13-93 (Pasig Revenue Code of 1992, as amended) dated 3 March 1993

BUILDING AND OTHER CONSTRUCTION PERMIT FEES

SECTION 91. Administrative Provisions. — No person, firm or corporation, including government


agencies, is allowed to erect, construct, alter, move, convert or demolish any building or structure
without first obtaining a building permit issued by the Municipal Mayor.

SECTION 92. Time of Payment. — The fees imposed in Department Order No. 155 series of 1992 of
the Department of Public Works and Highways and its subsequent issuances pertaining to building,
occupancy and other construction permits and inspection fees shall be paid to the Municipal Treasurer
after securing the required permit from the Municipal Mayor.