Ppe Exp.3 ROLLNO 1
Ppe Exp.3 ROLLNO 1
Experiment No.3
AIM- Experiments are conducted on Boiler to determine efficiency of boiler and generate heat balance
sheet
OBJECTIVES
1. To Determine Dryness fraction of Steam.
2. To determine boiler efficiency.
3. To conduct Heat Balance test.
I. INTRODUCTION:
Steam is one of the energy sources, by virtue of which thermal power plants are running. It finds its
application in process industry. It is very important to study thermodynamic properties of steam to
design all these plants. Basically steam is generated in a boiler by heating water above boiling
temperature. Combination of pressure and temperature along with rate of flow has to be decided for
all process.
Hence DEVALE’s Steam lab is a package with boiler, turbine, steam flow meter, steam calorimeter,
all instrumentation, steam line, insulation, all mounting, safety devises, heat exchanger, pumps,
etc,.which gives comprehensive training in steam lab also known as MINI POWER PLANT.
01. Steam boiler – fully automatic, oil fired,400 kg/hr, non IBR with all mountings
02. Diesel tank with accessories
03. Separating and Throttling calorimeter
04. Steam Flow meter
05. Steam Turbine coupled to Eddy current Dynamometer
06. Steam turbine control panel
07. Surface condenser
08. Pumps
09. Collection tanks
10. Chimney
11. Water pipelines, water softener
12. Steam line with insulation
13. All gauges, cables, thermocouples
14. Other instrumentation
This boiler is Non IBR, oil fired, fully automatic - 600 kg/ hr, four pass, vertical with following:
ACCESSORIES :
It is complete with separator and throttling unit, gauges, valves, pipes, etc, All the parts are insulated.
Sampling pipe is connected, to main steam pipe.
PROCEDURE :
EXPERIMENTAL PROCEDURE :
d. Put the controller rotary switch to WATER position( 1) .Now pump starts and water flows inside
coil and comes out of boiler through auxiliary valve.
e. Once water comes out freely(Observed Outside lab),set valve at about 4 bar
f. Now change control switch position to FIRE.(2)
g. Now boiler starts with all its sequence of operations and after 3-4 minutes steam comes out. Wait
until pressure raises to 10 bar and temperature to say 170 degree.
h. Boiler may stop as it would have triggered pressure switch, at this point open the valve completely.
Now boiler is ready for test.
i. Adjust pressure to say 6 bar, and see that boiler is running without stop.
j. Note down water meter reading with respect to time, note down fuel consumption with respect to
time. Note down all temperatures, pressure readings.
k. Repeat experiment for different valve openings and pressure
l. If difficulty is faced in maintaining low pressure, main steam valve may be opened, and open pipe
and valves fitted for calorimeter. Here close needle valve of calorimeter.
OBSERVATIONS :
A. BOILER:
CALCULATION
CONCLUSION- In this experiment we learnt about the boiler and calculated the efficiency of boiler and
generate heat balance sheet.