Operations Management - - Unit 10 - Week 9 https://onlinecourses.nptel.ac.in/noc18_me26/un...

[email protected]

Courses » Operations Management

Announcements Course Ask a Question Progress Mentor

Unit 10 - Week 9

Course
outline
Assignment 9
The due date for submitting this assignment has passed. Due on 2018-03-28, 23:59 IST.
How to access
the portal Submitted assignment

Week 1 1) Which of the following is NOT a part of operations scheduling system? 1 point

Week 2 Sequencing

Scheduling
Week 3
Expediting
Week 4 None of the above

Week 5 No, the answer is incorrect.


Score: 0
Week 6 Accepted Answers:
None of the above
Week 7
2) Match the following: 1 point
Week 8 A Expediting 1 Assigning specific jobs to each work center for the
planning periods
Week 9 B Scheduling 2 Establishing start and finish times of all jobs at each
work center
Production
C Sequencing 3 Monitoring progress, taking corrective actions to
Control
minimize deviations
Sequencing D Loading 4 Determining the order of processing of all jobs at
Sequencing
each work center
Problems-I
A-3,B-4,C-1,D-2
Sequencing
Problems-II A-3,B-2,C-4,D-1

Master A-1,B-3,C-2,D-4
Production
Scheduling A-1,B-3,C-4,D-2
(MPS)
No, the answer is incorrect.
Quiz : Score: 0
Assignment 9
Accepted Answers:
Feedback A-3,B-2,C-4,D-1
week-9
3)©Gantt
2014chart
NPTEL
is a- tool
Privacy
used&for:
Terms - Honor Code - FAQs - 1 point
Solution
A project of for In association with
Assignment 9
Loading
Week 10 Scheduling
Funded by
Both A and B

1 of 3 Thursday 17 May 2018 05:42 PM


Operations Management - - Unit 10 - Week 9 https://onlinecourses.nptel.ac.in/noc18_me26/un...

Week 11 None Powered


of these by

No, the answer is incorrect.


Week 12
Score: 0

DOWNLOAD Accepted Answers:


VIDEOS Both A and B

4) Gantt chart consist of a simple triangular grid, divided by series of parallel horizontal and vertical 1 point
lines.

True

False

No, the answer is incorrect.


Score: 0
Accepted Answers:
False

5) Which of the following is not a part of Five M’s? 1 point

Material

Machine

Motion

Method

No, the answer is incorrect.


Score: 0
Accepted Answers:
Motion

6) The correct sequence of operations in production planning and control is; 1 point

Routing-Scheduling-Dispatching-Follow up

Scheduling-Routing- Dispatching-Follow up

Dispatching-Routing-Scheduling- Follow up

Routing-Scheduling-Follow up-Dispatching

No, the answer is incorrect.


Score: 0
Accepted Answers:
Routing-Scheduling-Dispatching-Follow up

7) Which of the following is (are) TRUE for ‘Routing’? 1 point

It is flow of work in the plant

Route sheets include list of machine tools that are to be followed

It depends upon material handling facilities

All of the above

No, the answer is incorrect.


Score: 0
Accepted Answers:
All of the above

8) Loading in context of Production Planning and Control may be defined as; 1 point

Sending the raw material to the machine

Sending the finished material to the store

2 of 3 Thursday 17 May 2018 05:42 PM


Operations Management - - Unit 10 - Week 9 https://onlinecourses.nptel.ac.in/noc18_me26/un...

Assign the work to the facilities

Uploading a software in machine control panel

No, the answer is incorrect.


Score: 0
Accepted Answers:
Assign the work to the facilities

9) The main function (s) of Master Production Scheduling (MPS) is (are); 1 point

Translate aggregate plans into specific end items

Generate material requirement

Generate capacity requirement

All of the above

No, the answer is incorrect.


Score: 0
Accepted Answers:
All of the above

10)Gantt chart is mostly used for; 1 point

Routing

Scheduling

Forecasting

Inspection and quality control

No, the answer is incorrect.


Score: 0
Accepted Answers:
Scheduling