Istanbul Bilgi University

Department of Industrial Engineering


IE 270 - Engineering Project Management
2020-2021 Spring - Case Study 01

Case: Creating a Methodology


Background

John Compton, the president of the company, expressed his feelings quite bluntly at the executive
staff meeting:

”We are no longer competitive in the marketplace. Almost all of the Requests for Proposal
(RFP) that we want to bid on have a requirement that we must identify in the proposal the project
management methodology we will use on the contract should we be awarded the contract. We have
no project management methodology. We have just a few templates we use based upon the PMBOK
Guide. All of our competitors have methodologies, but not us.

I have been asking for a methodology to be developed for more than a year now, and all I get
are excuses. some of you are obviously afraid that you might lose power and authority once the
methodology is up and running. That may be true, but losing some power and authority is obviously
better than losing your job. In six months, I want to see a methodology in use on all projects or I
will handle the situation myself. I simply cannot believe that my executive staff is afraid to develop
a project management methodology.”

Details of the Case

The executive staff knew this day was inevitable; they had to take the initiative in the implementation
of a project management methodology. Last year, a consultant was brought in to conduct a morning
three-hour session on the benefits of project management and the value of a project management
methodology (PM). As part of the session, the consultant explained that the time needed to develop
and implement an PM system can be shortened if the company has a project management office
(PMO) in place to take the lead role. The consultant also explained that whichever executive
gets control of the PMO may become more powerful than other executives because he or she now
controls all of the project management intellectual property. The executive staff fully understood
the implication of this and therefore became reluctant to visibly support project management until
they could see how their organization would be affected. In the meantime, project management
suffered.

Reluctantly, a PMO was formed reporting to the chief information officer. The PMO comprised
a handful of experienced project managers who could hopefully take the lead in the development
of a methodology. The PMO concluded that there were five steps that had to be done initially.
After the five steps were done, the executive committee would receive a final briefing on what had
IE 270 2020-2021 Spring Case Study 01 2/2

been accomplished. The final briefing would be in addition to the monthly updates and progress
reports. The PMO believed that getting executive support and sign-offs in a timely manner would
be difficult.

The first step that needed to be done was the establishment of the number of life-cycle phases.
some people interviewed wanted ten to twelve life-cycle phases. That meant that there would be
ten to twelve gate review meetings (a meeting that is organized for the phase-closure) and the
project managers would spend a great deal of time preparing paperwork for the gate review meetings
rather than managing the project. The decision was then made to have no more than six life-cycle
phases.

The second step was to decide whether the methodology should be designed around rigid policies
and procedures or go the more informal route of using forms, guidelines, checklists, and templates.
The PMO felt that project managers needed some degree of freedom in dealing with clients and
therefore the more informal approach would work best. Also, clients were asking to have the
methodology designed around the client’s business needs and the more informal approach would
provide the flexibility to do this.

The third step was to see what could be salvaged from the existing templates and checklists. The
company had a few templates and checklists but not all of the project managers used them. The
decision was made to develop a standardized set of documents in accordance with the information in
the PMBOK Guide. The project managers could then select whatever forms, guidelines, templates,
and checklists were appropriate for a particular project and client.

The fourth step would be to develop a means for capturing best practices using the PM system.
Clients were now requiring in their RFP that best practices on a project must be captured and shared
with the client prior to the closeout of the project. Most of the people in the PMO believed that
this could be done using forms or checklists at the final project debriefing meeting.

The fifth step involved education and training. The project managers and functional organizations
that would staff the projects would need to be trained in the use of the new methodology. The PMO
believed that a one-day training program would suffice and the functional organizations could easily
release their people for a one-day training session.

Answer the following questions:

1. What can you determine about the corporate culture from the fact that they waited this long to
consider the development of an PM system?

2. Can a PMO accelerate the implementation process? If so, how?

3. Is it acceptable for the PMO to report to the chief information officer or to someone else?

4. Why is it best to have six or fewer life-cycle phases in an PM system?

5. Should an PM system have the capability of capturing best practices?