Document No:

QUALITY MANAGEMENT SYSTEM FO/SQCL-1/QMS/10/01


Issue no: Issue Date:
FLOW CHART FOR GARMENTS PULL TEST 01 6-Jan-2020
Version: 001

Pull Test Machine

Pull Test Machine daily Send To Supplier


Calibration 15 LBS/6.8 kg M/C Replace/ Repair
FAIL

PASS

Goods / Mockup receive from required section

Keep separate in the


Garments/ Mock up pull test, as our rejected box & mark on
standard 90 N stand 10 sec, follow every the mock up with date,
02 hours time, machine no,
FAIL signsture and adjust
the machine properly.

PASS

Keep separate in the box


with written on goods/
Mock up, Buyer, Style, P.O
No, Color, Date, Time,
Machine No & Signature.

Keep record with mark- Order no,


Date,Time, M/c no, Color & Sign

Start the bulk production

END