GOVERNMENT OF TELANGANA

HYDERABAD ROAD DEVELOPMENT CORPORATION LIMITED (HRDCL)

MISSING LINKS PROJECT

Government of Telangana State (GoTS) has decided to identify and develop the
Missing Link Corridors and Slip Roads which remain as backbone for the future areas of
developments and to improve the existing transport network to alleviate the existing and
growing traffic congestion issues. These road links will also act as shortest alternative
routes.
The Hon’ble Minister MA&UD and Principal Secretary to Govt. MA&UD after
reviewing with GHMC and HRDCL officials have finalized 133 links amounting to a total
length of 126.20 km.
These road links are termed as Missing/Slip roads because they are
intended to provide the missing connections in distributing the traffic more
effectively over the road network in Hyderabad City.
The proposed construction of missing links/slip roads are expected to achieve the
following objectives
 Improve the mobility of the residents of Hyderabad
 Improve traffic operations in major corridors
 Shorten the travel distances for commuters
 Improve road safety with improved features of safety
 Economic growth: to help enhancement of commercial establishment and
value of properties.
 Reduction of carbon emission levels and Journey time on main roads playing
vital role during peak hours Jams.
 Open up all dark areas to effectively control anti-social activities.
 Reduce risk of death of emergency patients by facilitating quick movement of
Ambulances.
ABSTRACT PHASE -I

1. Missing Links Completed 16 No 13.56 km 153.935 Cr


2. Missing Links in progress 6 No 10.74 km 121.601 Cr
Total 22 No 24.30 km 275.536 Cr

HRDCL
Missing Links Projects – Phase I
1) Phase I - Links roads Completed : 16 No; 13.56 km ; Rs. 153.935 Cr

Corridor Length Amount


Sl No Name of work
No. (in Km) ( in Cr)
1 2 3 4 5
Nizampet X roads to Hitex Jn.(via Vasanth nagar
1 1 0.75 6.410
and NAC) and Link road(2.20 km)
2 2 Link road from HT line to Miyapur road(1.00 km) 1.00 10.675

Miyapur Metro depot to Kondapur Masjid Jn. (via


3 3 IDPI Employees colony, Srila Park Pride road) 0.45 2.870
(length 1.80 km),
JV Hills park to Masjeed banda road via
4 12 Prabhupadha layout under HT line (length 1.0 1.00 7.573
km)
GHMC Serlingampally Zonal Office to NH 65 @
5 16 1.75 19.313
GSM mall (Via Manjeera pipe line road) (2.70 km)
Botanical Garden Road (Kondapur) to Hafeez
6 18 0.73 4.241
Railway track via JV Hills(0.73 km)

Old Mumbai Highway(leather park) to Road


7 23 1.20 21.695
No.45 under HT line (length 1.2 km)

Old Bombay Highway to Delhi Public School via


8 26 1.40 31.125
Engineering Staff College(2.30 km)

9 39 ISB Road to Lanco Hills jn(length 3.10km), 1.94 17.001

10 41 Bapu Ghat bridge to Attapur Bridge (0.75km), 0.75 6.610

11 42 Link road from NAC to KPHB Road 0.32 5.506


Link road from NOVATEL to RTA office (length
12 43 0.60 5.580
0.60 km)
Kukatpally Metro supermall to Jagdgirgutta via
13 75 0.20 0.888
HT lane (1.45km)
Akshaya Food court, Gokul Nagar to HMWS NH-9
14 134 Via IDPL Colony (length 0.20km) (Alignment 0.50 1.866
Changed as per RDP 0.45km)
Road no 70 Jubilee hills(Prashasan nagar) to
15 137 0.47 7.740
Narnie road no 78, Jubilee hills(0.47 km)

Neknampur road to Usman sgar road via Alkapur


16 138 0.50 4.842
Township (Approx. length 0.46 km)

Total 13.56 153.935

HRDCL
2) Phase I - Link roads in progress : 6 No; 10.74 km; Rs. 121.601 Cr

Sl Corridor Length Amount


Name of work Stage of work
No No. (in Km) (in Cr)

1 2 3 4 5 6

From Khajaguda Lake to ORR parallel to


Work in progress
1 27 Urdu University Compund Wall (length 1.7 1.00 47.666
( 60% Completed)
km),

Part of Old Bombay Highway to Khajaguda road Work in progress


2 1.39 15.070
29 & 32 via Malkam Cheruvu & Chitrapuri colony ( 50% Completed)

Radhika x roads - Balajinagar Dumping Work in progress


3 82 3.10 14.042
yard (3.10 km), ( 60% Completed)

Central ground water board to Pirzadiguda Work in progress


4 99 4.30 34.229
Road (length 4.74 km) ( 70% Completed)

Westin Hotel to Madhapur main road Work in progress


5 22 0.30 1.919
(length 0.30 km) ( 30% Completed)

New Allahpur to 100 ft road adjacent to Work in progress


6 66 0.65 8.675
Sunnam cheruvu (length 0.84 km) ( 30% Completed)

Total 10.74 121.601

HRDCL
Missing Links Projects – Phase II:

1) Phase II - Missing links taken up : 4 No; 6.38 km ; Rs. 65.94 Cr

Length Cost
Sl.No Corridor No Name of work
(in Km) (in Cr)
1 2 3 4 5
Construction of Missing link for the corridor
1 140 Alkapuri Township to Radial road 5 Narsingi 0.75 3.00
Road from 0/0 to 0/750. ( Work in Progress)
Widening of Link from Dollar Hills to
2 153 Neknampur road from 0/500 to 2/240. 1.74 10.00
( Work in Progress)
Construction of Missing Link/Slip roads for
Corridor 39B from ORR to Lanco Hills Junction
of 2.35 km and Corridor 39C from 1+380 of
3 39 B & C 3.52 49.60
39B to Narsinghi- Puppalaguda Radial Road
no.5 of Length 1.170 km including construction
of retaining walls, CD works. ( Tender Stage)
Construction of missing links/slip roads for
4 39 D Corridor no. 39D from ISB to American 0.37 3.34
consulate of length 0.37km. ( Tender Stage)

Total 6.38 65.94

HRDCL
To Medak To Nagpur To Karimnagar
Missing Links
Phase 1
Phase - I & II Phase 2
To Bidar

COMPLETED : 16 NO. 13.56 KM


PROGRESS : 6 NO. 10.74 KM 2

82
134
18
Corridor 3
Name of Work Length (in km) 75
No. 43 1

Phase-I 16 12
1 Nizampet X Roads to Hitex Jn. (via Vasanth Nagar and NAC) and Link Road (2.20 km) 0.75 42 To Warangal
2 Link road from HT line to Miyapur road (1.00 km) 1 66
Miyapur Metro depot to Kondapur Masjid Jn. (via IDPI Employees Colony, Srila Park Pride road)
3 0.45 137
(length 1.80 km),
12 JV Hills Park to Masjeed Banda road via Prabhupadha layout under HT line (length 1.0 km) 1 26
16 GHMC Serilingampally Zonal Office to NH 65 @ GSM Mall (via Manjeera pipe line road) (2.70 km) 1.75 23
27 29 &32

18 Botanical Garden Road (Kondapur) to Hafeez Railway track via JV Hills (0.73 km) 0.73 39d
22
23 Old Mumbai Highway(leather park) to Road No.45 under HT line (length 1.2 km) 1.2 39BC
39a
26 Old Bombay Highway to Delhi Public School via Engineering Staff College (2.30 km) 1.4
140
39 ISB Road to Lanco Hills Jn. (length 3.10 km), 1.94 153

41 Bapu Ghat bridge to Attapur Bridge (0.75 km), 0.75

42 Link road from NAC to KPHB Road 0.32 138


43 Link road from NOVATEL to RTA office (length 0.60 km) 0.6 41
75 Kukatpally Metro supermall to Jagadgirigutta via HT lane (1.45 km) 0.2 99
Akshaya Food court, Gokul Nagar to HMWS NH-9 via IDPL Colony (length 0.20 km) (Alignment
134 0.5
Changed as per RDP 0.45 km)

137 Road no 70 Jubilee Hills (Prashasan Nagar) to Narnie Road No 78, Jubilee Hills (0.47 km) 0.47
To Vikarabad
138 Neknampur road to Usman Sagar road via Alkapur Township (Approx. length 0.46 km) 0.5

27 From Khajaguda Lake to ORR parallel to Urdu University Compound Wall (length 1.7 km), 1

Part of
Old Bombay Highway to Khajaguda road via Malkam Cheruvu & Chitrapuri Colony 1.39
29 & 32

82 Radhika X Roads – Balaji Nagar Dumping yard (3.10 km), 3.1


To
99 Central ground water board to Pirzadiguda Road (length 4.74 km) 4.3
Vijayawada
22 Westin Hotel to Madhapur main road (length 0.30 km) 0.3

66 New Allahpur to 100 ft. road adjacent to Sunnam cheruvu (length 0.84 km) 0.65

Total (Phase-I) 24.3

Phase-II
Construction of Missing link for the corridor Alkapur Township to Radial Road 5 Narsingi Road from
140 0.75
0/0 to 0/750.
153 Widening of Link from Dollar Hills to Neknampur road from 0/500 to 2/240 1.74

Construction of Missing Link/Slip roads for Corridor 39B from ORR to Lanco Hills Junction of 2.35 km
39 B & C and Corridor 39C from 1+380 of 39B to Narsingi- Puppalaguda Radial Road no.5 of Length 1.170 km 3.52 To Bangalore
including construction of retaining walls, CD works To Nagarjuna Sagar
Construction of missing links/slip roads for Corridor no. 39D from ISB to American consulate of
39 D 0.37
length 0.37 km.
Total (Phase-II) 6.38
To Srisailam