Vulcan Gantt Scheduler : Contents Page 1 of 44

Vulcan Gantt Scheduler


Home > Vulcan Gantt Scheduler

Note This section contains information about the Vulcan Gantt Scheduler application. For more information about the Gantt options in Envisage, see the Gantt section of the
documentation.

Overview
This section provides an overview of the Vulcan Gantt Scheduler feature.

Opening Vulcan Gantt Scheduler


This section includes instructions for opening the Gantt Scheduler.

Gantt Scheduler Interface


The Gantt Scheduler interface is comprised of several sections, including the ribbon and tabs, the Gantt Chart area, the Summary Report area, and the Notification Center area.

Home Tab
The Home tab of the Gantt Scheduler interface includes options for creating, modifying, and aligning activities displayed in the Gantt chart.

Precedences Tab
The Precedences tab includes options for creating, modifying, and removing precedences, as well as creating, selecting, and managing precedence groups.

Resources Tab
The Resources tab includes options for allocating, applying, and leveling resources and modifying resource settings.

Setup Tab
The Setup tab includes options for modifying settings, periods, and summary reports.

View Tab
The View tab includes options for viewing activities in Envisage as well as filtering, grouping, and sorting activities.

Keyboard Shortcuts
This topic includes a list of keyboard shortcuts for the Vulcan Gantt Scheduler.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Overview

Vulcan Gantt Scheduler


The Vulcan Gantt Scheduler is a rate-based Gantt chart scheduler with a suite of tools for attributing, sequencing, animating, resource levelling, and reporting mine plans. Activity
durations can be calculated from inherent design properties such as length, volume, or area or from other attributes associated with the design such as mass or fixed time.

The main component of the Gantt Scheduler is the Gantt chart type display which includes a data side and a bar chart side. It allows users to define activities (tasks), which are in
general related to 3D graphical representation of mine entities. Activities are assigned start and end dates for completion as well as precedence information from other 3D activities
or types of activities for the same 3D representation. Those activities will have a series of associated fields with information that will be used in order to drive the schedule and for
reporting purposes. Users will be able to create new fields with derived information.

Requirements
n You must have Vulcan installed on your computer and Envisage must be open in order to use the Gantt Scheduler.
n You must have a valid Gantt Scheduler license for Vulcan. If the Gantt menu option is not displayed in Envisage, contact your local Maptek office to obtain a license for the
Gantt Scheduler.
n You must have Java installed on your computer to use the Gantt Scheduler. If you do not have Java installed already, you can download the latest version at www.java.com.

Gantt Scheduler Tutorials


Click to view Gantt Scheduler tutorials

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Opening the Gantt Scheduler

Opening the Gantt Scheduler

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 2 of 44

Following are instructions on how to open the Gantt Scheduler from within Envisage.

Instructions
In Envisage, on the Gantt menu, click Open to open the Gantt Scheduler application and display the Vulcan Gantt Scheduler interface.

For more information about the Gantt options in Envisage, see the Gantt section of the documentation.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Gantt Scheduler Interface


Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface

The Gantt Scheduler interface is comprised of several sections, including the ribbon and tabs, the Gantt Chart area, the Summary Report area, the Notification Center area, and the
Quick Access Toolbar.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 3 of 44

Maptek File Button, File Menu, and Application Options


The File menu includes options to create a new project, open an existing project, save a project, and exit the Gantt Scheduler. In addition, you can set application preferences such
as language, scheduler start date, and date and time formats.

Quick Access Toolbar


The Quick Access Toolbar provides shortcuts to commonly used commands and the ability to minimize the ribbon.

Ribbon and Tabs


The Gantt Scheduler interface includes a ribbon along the top of the interface. The ribbon includes tabs for creating and modifying activities, precedences, resources, setup, and
viewing.

Gantt Chart Window Area


The Gantt Chart window is the visual display of the scheduling information for the project. It includes an Activity Grid area with activity and setting information, a Gantt Chart area
which serves as a visual chart with timeline and precedence information, and an Overview area which includes a visual overview of all activity information over the entire timeline of
the project.

Summary Report Window


The Summary Report window displays report information that is generated from report specifications created in the Summary Report Manager (accessed via the Report Setup
option on the Setup tab). The Summary Report shows values for filtered activities in the grid.

Notification Center Window


The Notification Center window displays information and notifications regarding actions in the Gantt Scheduler. Notification types include logs, warnings, errors, and resolved
issues.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > File Menu and Application Options

Maptek File Button, File Menu, and Application Options


The Gantt Scheduler includes a Maptek File button in the top left corner of the interface. This button displays the File menu which includes options to create a new project,
open an existing project, save a project, and exit the Gantt Scheduler.

Click Options on the File menu to display the Options panel to set application preferences such as language, scheduler start date, and date and time formats.

Maptek File Button

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 4 of 44

Click the Maptek File button to display the File menu.

Menu Options
New

Click New to create a new project.

Open

Click Open to open an existing project. You can also open a project by clicking on the file name in the Recent Projects column.

Save

Click Save to save the project that is currently open.

Save As

Click Save As to save the project that is currently open with a different name.

Options

Click Options to display the Options panel.

General
Language

Select your preferred language from the list.

Scheduler
Start for new activities

Select Project Start Day or Current Day to specify what the default start day should be for new activities.

Date/Time Format
Format

Select your preferred date and time format.

Layout
Overwrite project layout

Select this check box to overwrite the default project layout with the current layout.

Save Layout

Click Save Layout to save the current layout as the default layout for the project.

Automatic Backup
Number of backups

Enter the number of backups you want to keep

Backup every

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 5 of 44

Enter the number of minutes you want between backups.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Quick Access Toolbar


Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Quick Access Toolbar

The Gantt Scheduler interface includes a Quick Access Toolbar along the top title bar of the interface. The Quick Access Toolbar includes shortcuts for the Copy and Paste options.
You can also customize the toolbar or use it to minimize the ribbon.

Customizing the Quick Access Toolbar

Click the drop-down arrow icon and click Show Below the Ribbon to move the Quick Access Toolbar below the ribbon. To move it back above the ribbon, click the drop-down
arrow icon and click Show Above the Ribbon.

Minimizing the Ribbon

Click the drop-down arrow icon and click Minimize the Ribbon to hide the icons and labels on the ribbon. When the ribbon is minimized, only the tab names will display. To
display the ribbon, click the drop-down arrow icon and click Minimize the Ribbon again.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Ribbon and Tabs

Ribbon and Tabs


The Gantt Scheduler interface includes a ribbon along the top of the interface. The ribbon includes tabs for creating and modifying activities, precedences, resources, setup, and
viewing.

Alternatively, you can right-click on an activity in the Gantt Chart window to view the options for that activity or use keyboard shortcuts for some options.

For information about the options on each tab of the Gantt Scheduler, see the following topics:

n Home tab
n Precedences tab
n Resources tab
n Setup tab
n View tab

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Gantt Chart Window

Gantt Chart Window


The Gantt Chart window is the visual display of the scheduling information for the project. It includes the following components:

n Activity Grid area with activity and setting information


n Gantt Chart area which serves as a visual chart with timeline and precedence information
n Overview area which includes a visual overview of all activity information over the entire timeline of the project

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 6 of 44

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Summary Report Window

Summary Report Window


The Summary Report window displays report information that is generated from report specifications created in the Summary Report Manager, which is accessed via the Report
Setup option on the Setup tab.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Notification Center Window

Notification Center Window


The Notification Center window displays information and notifications regarding actions in the Gantt Scheduler. Notification types include logs, warnings, errors, and resolved
issues.

n Select which notification types to display from the Show drop-down list.
n Click Clear to clear all notifications from the list.
n Click the Save icon to save all displayed notifications to a text file.
n Click the Expand and Collapse icons to view more or less information about a notification.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 7 of 44

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Home

Home Tab
The Home tab of the Gantt Scheduler interface includes options for creating, modifying, and aligning activities displayed in the Gantt chart.

Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.

Clipboard
The Clipboard group on the Home tab includes options for copying and pasting activities in the Gantt Chart window.

Activities
The Activities group on the Home tab includes options for creating, deleting, modifying, and updating activities in the Gantt Chart area.

Bars
The Bars group on the Home tab includes options for splitting bars and removing splits in the Gantt Chart area.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Clipboard
Home > Vulcan Gantt Scheduler > Home > Clipboard

The Clipboard section of the Home tab includes options for copying and pasting activities in the Gantt Chart window.

Copy activity
Click Copy activity or press Ctrl + C to copy the data values for the selected activity to the clipboard.

Copy with Headers

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 8 of 44

Click Copy with Headers to copy the data values and attribute name of the selected activity to the clipboard.

Paste activity
Click Paste activity or press Ctrl + V to paste the selected activity into the Gantt chart.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Activities
Home > Vulcan Gantt Scheduler > Home > Activities

The Activities group on the Home tab includes options for creating, deleting, modifying, and updating activities in the Gantt Chart window.

Note: You must set up attributes prior to creating activities. See the Attributes topic for more information.

New
Click New or press Shift+A to add a new activity. The Activity Information panel displays.

Delete activity
Click Delete activity or press Ctrl+D to delete an activity.

Properties
Click Properties or press F4 to view the activity properties on the Activity Information panel.

Update Activities
Click Update Activities or press Ctrl+U to update activities with Envisage data. The Updating activities progress bar displays in the bottom right corner of the Gantt Status Bar to
indicate the progress of the update.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Activity Information
Home > Vulcan Gantt Scheduler > Home > Activities > New

Use the Activity Information panel to add and modify activity information. This panel includes general activity information as well as information about precedences, scheduling
constraints, and resource allocation and rates.

Note You must set up attributes prior to creating activities. See the Attributes topic for more information.

Tutorials
Click to read the Creating Activities and Viewing and Interacting with Activities tutorials.

Instructions
On the Home tab, in the Activities group, click New to create a new activity, or Properties to view the properties of an existing activity.

This panel has two tabs: the General tab and the Resources tab.

General Tab

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 9 of 44

General

This section includes general information about the activity and its progress.

Name

Enter the name of the activity.

Is summary

Select this check box if the activity is a summary.

Start

Enter or select a start date for the activity.

End

Enter or select an end date for the activity.

Work

Enter the number of days the activity is expected to take to complete.

Percent Completed

Enter the percentage of work that has been completed for the activity.

Priority

Enter a number to indicate the priority of the activity.

Predecessors

This section displays information about any predecessors that are linked to the activity. For more information about precedences, see Precedence Information.

Predecessor

Displays the predecessor's name.

Type

Select whether the activity should be linked to the start or finish of the predecessor. You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start.

Lag

Enter the number of days that must separate the activity from the predecessor.

Successors

This section displays information about any successors that are linked to the activity. For more information about precedences, see Precedence Information.

Successor

Displays the successor's name.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 10 of 44

Type

Select whether the activity should be linked to the start or finish of the successor. You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start.

Lag

Enter the number of days that must separate the activity from the successor.

Scheduling Constraint

This section specifies any scheduling or time constraints for the activity.

Constraint type

Select a scheduling constraint type to indicate how early or late the activity can start or finish. You can specify whether the activity must start or finish on/before/after a specific
date, or you can specify that the activity should begin as soon or as late as possible.

Constraint date

Select a date to correspond with the Constraint type you selected. This box is disabled if you select As Soon As Possible or As Late As Possible as the Constraint type.

Click the Resources tab to continue.

Resources Tab

Resource Allocation

This section includes any resources that are allocated to the activity. For more information about resource settings and allocation, see Resources and Allocate Resources.

Resource

Select the name of the resource from the list. For more information about adding or modifying resources, see Resource Settings.

Rate

Displays the rate of the selected resource.

Rate

This section indicates the rate of the resources that are allocated to the activity.

Activity rate

Enter the activity rate.

Combined resource rate

Displays the sum of the rates from all resources that are allocated to the activity.

Resource manual rate

Enter the manual rate of the resources.

Source

Select a source from the list to display its current rate.

Current rate

Displays the current rate of the source selected from the Source list.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 11 of 44

Home > Vulcan Gantt Scheduler > Home > Bars

Bars
The Bars group on the Home tab includes options for splitting bars and removing splits in the Gantt Chart area.

Split
Use the Split option to split an activity by date, number of days, or percentage.

Remove Split
Use the Remove Split option to remove a split from an activity.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Home > Bars > Split

Split Activity
Use the Split Activity panel to split an activity by date, number of days, or percentage.

Instructions
In the Gantt Chart area, click on the bar that represent the activity that you want to split, then on the Home tab, in the Bars group, click Split to display the Split Activity panel.

You can split the activity in one of three ways: by date, number of days, or percentage. When you modify one number or date on the panel, the others will adjust according to you
value you entered.

To split the activity at a specific day, enter a date and time or click the arrow icon to select the date from the calendar.

To split the activity by number of days, enter the number of days into the activity that the split should occur.

To split the activity by percentage, enter the percentage of time into the activity that the split should occur.

Examples:

You have an activity that you want to split in half. The activity is scheduled for 30 days from July 1st to July 31st.

l To split the activity by date: Enter or select July 15th in the date format from your preferences (such as 07/15/2014 or 15/07/2014).
l To split the activity by number of days: Enter 15.
l To split the activity by percentage: Enter 50.00%.

You can remove a split in three different ways:

l Click on the bar in the Gantt Chart area, then on the Home tab, in the Bars group, click Remove Split.
l Click on the bar in the Gantt Chart area, then press Ctrl+J.
l Right-click on the activity's bar in the Gantt Chart area and click Remove Split.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Home > Bars > Remove Split

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 12 of 44

Remove Split
Use the Remove Split option to remove a split from an activity.

Instructions
You can remove a split in three different ways:

n Click on the bar in the Gantt Chart area, then on the Home tab, in the Bars group, click Remove Split.
n Click on the bar in the Gantt Chart area, then press Ctrl+J.
n Right-click on the activity's bar in the Gantt Chart area and click Remove Split.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences

Precedences Tab
The Precedences tab includes options for creating, modifying, and removing precedences, as well as creating, selecting, and managing precedence groups.

Alternatively, you can right-click on an activity in the Gantt Chart window to view the options for that activity or use keyboard shortcuts for some options.

Gantt Manual
The Gantt Manual group is located on the Precedences tab and includes options for creating and removing manual precedences, as well as viewing manual precedence properties.

Envisage Spatial
The Envisage Spatial group is located on the Precedences tab and includes options for creating, editing, and removing spatial precedence rules.

Precedence Group
The Precedence Group group is located on the Precedences tab and includes options for adding and managing precedence groups as well as selecting current precedence groups.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Gantt Manual
Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual

The Gantt Manual group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for creating and removing manual precedences, as well as
viewing manual precedence properties.

Create
Click Create to display the Allocate Precedence Group panel to create a new manual precedence.

Remove
Click Remove to remove a manual precedence.

Properties
Click Properties to view precedence properties. The Precedence Properties panel displays.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 13 of 44

Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual > Create

Create
Use the Create option to create a new manual precedence between activities.

Tutorial
Click to read the Creating Precedences tutorial.

Instructions
If you want to add the activities to an existing precedence group, select the group name from the Current Group list in the Precedence Group group of the Precedences tab. If a
group is selected, the new precedence will automatically be added to that group.

Select two or more activities in the Gantt Chart window.

On the Precedences tab, in the Gantt Manual group, click Create.

If you do not have a group selected in the Current Group list, the Allocate Precedence Group panel displays.

Group

Type or select a precedence group name in the box and click OK. If you enter a new group name, the new group will be displayed in the Current Group list and on the
Precedence Group Manager panel.

A precedence is then created between the activities you specified, and the precedence is added to the selected group.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual > Properties

Properties
Use the Precedence Information panel to display and modify information about a selected precedence.

Instructions
On the Precedences tab, in the Gantt Manual group, click Properties, or right-click on a precedence arrow in the Gantt Chart area and select Properties to display the
Precedence Information panel.

Precedence
Predecessor Activity

Displays the activity name of the predecessor.

Successor Activity

Displays the activity name of the successor.

Lag

Enter the number of days that must separate the activities in the precedence.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 14 of 44

Type

Select whether the precedence should be linked to the start or finish of the predecessor and successor activities. You may select Start to Start, Finish to Finish, Start to
Finish, or Finish to Start.

Example:

Activity A and Activity B are linked together with a precedence. Activity A must be completed before Activity B can begin. You want to wait three days after completing Activity A
before starting Activity B.

n Predecessor Activity : Activity A


n Successor Activity: Activity B
n Lag: 3 days
n Type: Finish - Start

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences > Envisage Spatial

Envisage Spatial
The Envisage Spatial group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for creating, editing, and removing spatial precedence rules.

Spatial Precedences
Use the Spatial Precedences option to create, edit, or remove precedence rules for spatial precedences.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences > Envisage Spatial > Spatial Precedences

Spatial Precedences
Use the Spatial Precedence Rules panel to create, edit, or remove precedence rules for spatial precedences.

Instructions
On the Precedences tab, in the Envisage Spatial group, click Spatial Precedences to display the Spatial Precedence Rules panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 15 of 44

Spatial Precedence Rules


Adding and Defining a New Precedence Group

Click Add to add a new entry, or press Insert.

Modifying a Precedence Group

Select an entry and modify the displayed information as needed.

Copying a Precedence Group

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Precedence Group

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Precedence Group

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General
Name

Enter a name for the report.

Description

Enter a brief description of the report.

General
Name

Enter the name of the rule.

Description

Enter a description of the rule.

Activities Filter
Predecessor Activities Filter

Select a filter for the predecessor activities.

Predecessor Activity Type

Select an activity type for the predecessor activities.

Successor Activities Filter

Select a filter for the successor activities.

Successor Activity Type

Select an activity type for the successor activities.

Search Criteria
Predecessor Point Selection

Select Start Point, End Point, or Closest Intersection to indicate the method of point selection of the predecessor.

Optional Offset

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 16 of 44

Enter a value for the offset and then select the unit of measure from the list. The closest intersection and optional offset allow the Gantt bars to be split and precedences
created between parts of activities. The optional offset only works for design data and is in reference to the nominated point (start, end, or closest intersection).

Successor Point Selection

Select Start Point or End Point to indicate the method of point selection of the predecessor.

Optional Offset

Enter a value for the offset and then select the unit of measure from the list. The closest intersection and optional offset allow the Gantt bars to be split and precedences
created between parts of activities. The optional offset only works for design data and is in reference to the nominated point (start, end, or closest intersection).

Precedence Creation
Closest (Single) or All (Multiple)

Select the method of precedence creation.

Gantt Precedence Type

Select the Gantt precedence type from the list.

Precedence Lag

If there is a lag between the predecessor and successor, enter the time and select the unit of measure from the list.

Apply Rule

Click Apply Rule to apply rule changes to precedences.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Precedence Group
Home > Vulcan Gantt Scheduler > Precedences > Precedence Group

The Precedence Group group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for adding and managing precedence groups as well as
selecting current precedence groups.

Group Manager
Click Group Manager to display the Precedence Group Manager panel to add, edit, and remove precedence groups.

Current Group
Select a precedence group from the drop-down list to set it as the current group.

New Group
Click New Group to display the Allocate Precedence Group panel to create a new precedence group.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences > Precedence Group > Group Manager

Group Manager
Use the Precedence Group Manager panel to add, edit, and remove precedence groups.

Instructions
On the Precedences tab, in the Precedence Group group, click Group Manager to display the Precedence Group Manager panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 17 of 44

Groups
Adding and Defining a New Precedence Group

Click Add to add a new entry, or press Insert.

Modifying a Precedence Group

Select an entry and modify the displayed information as needed.

Copying a Precedence Group

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Precedence Group

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Precedence Group

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General
Name

Enter a name for the group.

Description

Enter a brief description of the group.

Properties
Is Current

Select this check box to make this precedence group the current group.

Applied

Select this check box if you want the precedences from this group to be applied. Clear this check box if you do not want the precedences from this group to be applied.

Line Style

Select a line style for the precedence. This line style will be used for the precedence in the Gantt Chart area.

Line Color

Select a color for the precedence. This line color will be used for the precedence in the Gantt Chart area.

Precedences
Remove Selected

Highlight activities in the list and then click Remove Selected to remove the activities from the precedence group.

Predecessors

Displays the predecessor of the activity.

Successors

Displays the successor of the activity.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 18 of 44

Lag [Day]

Displays the lag time between the precedences.

Type

Displays the type of precedence, such as Finish-Start or Start-Finish.

Source

Displays the source of the precedence, such as whether the precedence was created in the Gantt Scheduler or in Envisage.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Precedences > Precedence Group > New Group

New Group
Use the Allocate Precedence Group panel to create a new precedence group.

Instructions
On the Precedences tab, in the Precedence Group group, click New Group to display the Allocate Precedence Group panel.

New Group

Enter a group name in the field and click OK. The new group will be displayed in the Current Group list and in the Group Manager.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Resources

Resources Tab
The Resources tab includes options for allocating, applying, and leveling resources and modifying resource settings.

Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.

Resources
The Resources group includes options for managing and allocating resources.

Resource Leveling
The Resource Leveling group includes options for managing leveling and resource rates.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited
Envisage Maptek

Home > Vulcan Gantt Scheduler > Resources > Resources

Resources
The Resources section of the Resources tab includes options for creating, modifying, deleting, and allocating resources.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 19 of 44

Settings
Click Settings to display the Resources panel. This panel has options to add, modify, or remove resource definitions.

Allocate resources
Click Allocate resources display the Allocate Resources panel. This panel includes options for allocating resources to selected activities.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Resources > Resources > Settings

Resource Settings
Use the Resources panel to add, modify, or remove resource definitions.

Instructions:
On the Resources tab, in the Resources group, click Settings to display the Resources panel.

Alternatively, you can press Ctrl+F10 to display the panel.

Resources
Adding and Defining a New Resource

Click Add to add a new entry, or press Insert.

Modifying a Resource

Select an entry and modify the displayed information as needed.

Copying a Resource

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Resource

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Resource

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 20 of 44

Name

Enter the name of the resource.

Description

Enter a description of the resource.

Calendar

Select a calendar to use for scheduling the resource.

Modify

Click Modify to modify the selected calendar.

Rate
Default Rate

Enter the default rate for the resource. This rate applies to all activity types for the resource. If you make changes to this value, click Apply rate to apply the rate change.

Use variable rate

Select this check box to use different rates for different activity types. If you select this option, you can specify a rate for different activity types by selecting the activity type
from the Activity Type list and entering a rate in the Rate box. If you do not specify a rate for an activity type, the default rate will be used for that activity type. The Unit box
displays the unit type for that activity type.

Capacity
Default capacity

Enter the default capacity for the resource. This capacity applies to all days for the resource.

Use variable capacity

Select this check box to use different capacities on different days. If you select this option, you can select a start date for the capacity in the Start column and enter the
capacity in the Capacity column. This capacity will apply until the next specified start date in the list. If you do not specify a rate for a date, the default capacity will be used for
that date.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Resources > Resources > Allocate Resources

Allocate Resources
Use the Allocate Resources panel to allocate resources to selected activities.

Tutorial
Click to read the Resource Allocation and Leveling tutorial.

Instructions
On the Resources tab, in the Resources group, click Allocate resources to display the Allocate Resources panel.

Alternatively, you can press Alt+F10 to display the panel.

Resources

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 21 of 44

Allocating a Resource

Click Add to allocate the selected resource to the activity.

Removing a Resource

Click Remove to remove the selected resource from the activity.

Activities
Activity

Displays the name of the activity.

Allocated Resources

Displays the resources that have been allocated to the activity.

Rate Source

Displays the rate source of the activity.

Rate

Displays the rate of the activity.

Rate Source

Select Activity Manual, Resource Default, or Resource Manual, Partial Series, or Partial Parallel as the rate source.

User defined rate

If you select Resource Manual in the Rate Source list, enter a rate for the activity.

Activity %

If you select Partial Series or Partial Parallel in the Rate Source list, enter the activity percentage.

Apply rate

Click Apply rate to save your changes and apply the updated rate source, user-defined rate, and activity percentage to the activities.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Resource Leveling
Home > Vulcan Gantt Scheduler > Resources > Resource Leveling

The Resource Leveling section of the Resources tab includes options for specifying and applying resource rates and leveling.

Apply Resource Rate


Click Apply Resource Rate or press Alt+F11 to apply the default resource rate to the selected activities.

Leveling Setup
Click Leveling Setup or press Alt+L to display the Resource Leveling Setup panel. This panel includes options for setting step, date range, priorities, and other options for
resource leveling.

Leveling by Capacity
Click Leveling by Capacity or press Alt+Y to resolve resource over-allocations based on the settings in the Resource Leveling Setup panel.

Leveling by Rate and Capacity


Click Leveling by Rate and Capacity or press Alt+R to resolve resource over-allocations based on the settings in the Resource Leveling Setup panel.

Clear Leveling Delays


Click Clear Leveling Delays or press Alt+C to clear the leveling delay from all activities.

Tutorial
Click to read the Resource Allocation and Leveling tutorial.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Resources > Resource Leveling > Leveling Setup

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 22 of 44

Leveling Setup
Use the Resource Leveling Setup panel to set step, date range, priorities, and other options for resource levelling.

Instructions
On the Resources tab, in the Resource Leveling group, click Leveling Setup to display the Resource Leveling Setup panel.

Alternatively, you can press Alt+L to display the panel.

Leveling Range
Entire Project

Select this option to apply resource levelling to the entire project.

Date Range

Select this option to apply resource levelling only to a specified date range. If you select this option, select the start and finish dates in the Start and Finish boxes.

Activity Prioritization
Type

Select the attribute type by which to prioritize activities from the list.

Ascending or Descending

Select Ascending or Descending to indicate whether the attributes should be sorted in ascending or descending order.

Add

Click Add to add the selected attribute to the list.

Up

Click the Up icon to move a selected entry up one row in the list.

Down

Click the Down icon to move a selected entry down one row in the list.

Attribute

Indicates the attribute name for the entry.

Mode

Indicates whether the selected attribute is sorted in ascending or descending order.

Remove

Click Remove to remove the entry from the list.

Clear last levelling values

Select this check box if you want to clear previous levelling values.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup

Setup Tab
The Setup tab includes options for modifying settings, periods, and summary reports.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 23 of 44

Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.

Settings
The Settings group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting general project options as well as creating, modifying, and
removing attributes, activity types, lookup tables, and calendars.

Period
The Period group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for selecting and modifying period definitions.

Summary Report
The Summary Report group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting up reports and exporting reports to CSV files.

Formula Editor
Use the Formula Editor panel to assist in creating formulas and expressions for activity attributes.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings

Settings
The Settings group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting general project options as well as creating, modifying, and
removing attributes, activity types, lookup tables, and calendars.

Project Options
Click Project Options to display the Project Options panel to define options for the current project.

Attributes
Click Setup to display the Attribute Manager panel to add, modify, and remove activity attributes.

Activity Types
Click Activity Types to display the Activity Types panel to add, edit, and delete activity types.

Lookup Tables
Click Lookup Tables to display the Lookup Tables panel to add, modify, or remove lookup table definitions.

Calendars
Click Calendars to display the Calendar Manager panel to define working and non-working times for the project.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings > Project Options

Project Options
Use the Project Options panel to define options for the current project.

Instructions
On the Setup tab, in the Settings group, click Project Options to display the Project Options panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 24 of 44

General
Name

Enter a name for the project.

Title

Enter a title for the project.

Subject

Enter a subject for the project.

Category

Enter a category for the project.

Company

Enter the company name.

Mine

Enter the mine name.

Site

Enter the site name.

Manager

Enter the manager name.

Author

Enter the author name.

Time and Date


Start date

Displays the date the project was created.

Finish date

Select or enter a finish date for the project. The finish date defaults to the last day of the last scheduled activity.

Schedule from

Select Project Start Date or Project Finish Date to specify how to schedule the project.

Calendar

Select the default project calendar from the list.

Project duration format

Select the format for the project duration. You can select Minute, Hour, Day, Week, or Month.

Work format

Select the format for work. You can select Minute, Hour, Day, Week, or Month.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings > Attributes

Attributes
Use the Attribute Manager panel to add, modify, and remove activity attributes.

Note Attributes must be set up before activities can be created.

For information about attribute default values, see the Default Values for Attributes topic.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 25 of 44

Instructions
On the Setup tab, in the Settings group, click Attributes to display the Attribute Manager panel.

Attributes
Adding and Defining a New Attribute

Click Add to add a new entry, or press Insert.

Modifying an Attribute

Select an entry and modify the displayed information as needed.

Copying an Attribute

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing an Attribute

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Note You cannot remove the Activity Name and Priority attributes, nor can you modify their names, descriptions, types, or units.

General
Name

Name of the attribute used in the whole project.

Description

A brief description of the attribute.

Type

Select the attribute type from the list.

Decimal Places

If you selected Double in as the attribute type, enter the number of decimal places to display for the number.

Units

Enter the unit type. If you select Inherent in the Calculation list in the Data Source section, this box will default to the information specified in the that section.

Data Source
Calculation

Select the type of calculation to use for the data source.

Select Manual to enter the information manually.

Select Expression to specify a formula for the data source. Enter the expression in the General box, or select the Separate for Design Data/Triangulation check box and enter
an expression for design data in the Design Data box and an expression for triangulations in the Triangulation box. If desired, you can use the Formula Editor panel to create
the formula by clicking the Formula icon.

Select Inherent to use a predefined property and unit of measurement. Select Length, Volume, or Area and then specify a unit of measurement from the list to the right of the
property.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 26 of 44

Home > Vulcan Gantt Scheduler > Setup > Settings > Default Values for Attributes

Default Values for Attributes


This topic lists the default values that are used when certain activities do not have a value defined. These values are only assigned for the expression evaluation process. The
default values cannot be changed.

Only user-defined attributes (the [ATT:] values in the expressions) have these default values because their type is known. Any other kind of metadata value ([DGD:], [TRI:] or
[MET:]) do not have a default value when the metadata value does not exist.

Attribute Type Default Value


Double 0.0
Integer 0
Boolean False
String (empty string)
Date 00:00:00.0000000, January 1, 0001. (More info: .NET 4.0, .NET 4.5)

The default values are used when any of the following conditions are met:

l The value of an attribute is #NULL! after evaluating the attribute expression.


l A manually assigned attribute of an activity type does not have a user-defined default value assigned.
l An activity type does not have an attribute.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings > Activity Types

Activity Types
Use the Activity Types panel to add, edit, and delete activity types. Activity types are a group of activities that share a common work calculation definition. An activity type is a
definition that converts an Envisage object (or triangulation) into a Vulcan Gantt activity. The activity type is defined by a quantity attribute and a default rate (to set an initial duration
to the activity) and also manages the discretisation of an Envisage object, creating a group of minimum mining units. An activity type has an auto-assigned expression that can be
used to assign automatically to an object. Activity groups consist of multiple activity types, sharing a common discretisation definition and operational precedence.

Instructions
On the Setup tab, in the Settings group, click Activity Types to display the Activity Types panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 27 of 44

Activity Types
Adding and Defining a New Activity Type

Click Add to add a new entry, or press Insert.

Modifying an Activity Type

Select an entry and modify the displayed information as needed.

Copying an Activity Type

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing an Activity Type

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving an Activity Type

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General
Name

Name of the activity type used in the whole project.

Description

A brief description of the activity type.

Work calculation

Select Calculate Work or Fixed Work to specify a method for calculating work.

Calculate Work

Select this option if you want to calculate work based upon a quantity attribute. If you select this option, you must select the attribute, default rate, and units.

Quantity attribute

Select the attribute upon which you want to calculate work. The list will contain all attributes that have an attribute type of Double on the Attribute Manager panel.

Default rate

Enter an expression to use for calculating work. To use the Formula Editor panel to enter or modify the expression, click the Formula Editor icon.

Units

Select the unit types for distance and time of the calculation, such as meters per day.

Fixed Work

Select this option if you want to calculate work using a specific amount of time.

Fixed time value

Enter the amount of time of the work.

Units

Select the unit type for the time value from the list.

Default auto assign expression


Condition

Enter a formula for the expression to be evaluated when Envisage objects and triangulations are selected for activity creation. To use the Formula Editor panel to enter or modify
the expression, click the Formula Editor icon. If the evaluated expression is true, then the activity type is assigned to the Envisage object.

Attributes

In the Selected column, select the check boxes next to the applicable attributes that are listed in the Attribute column.

Defining Attributes

There are three possible sources to populate attribute values in the activity grid: manual, expression, and inherent.

Manual

Manual attributes can be edited directly in the Gantt Chart window. They can be populated by an optional default value that is defined in the activity type setup, edited
individually in the Gantt Chart window, or edited in bulk with Copy and Paste in the Gantt Chart window.

Expression

Expression attributes are defined using the Formula Editor panel as described above.

Inherent

The Gantt Scheduler can inherently read the Length (design data only), Area (design data and/or triangulations), and Volume (triangulation and/or design data with assigned
primitive) attributes from Envisage.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings > Lookup Tables

Lookup Tables

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 28 of 44

Use the Lookup Tables panel to add, modify, or remove lookup table definitions.

Instructions
On the Setup tab, in the Settings group, click Lookup Tables to display the Lookup Tables panel.

Lookup Tables
Adding and Defining a New Lookup Table Definition

Click Add to add a new entry, or press Insert.

Modifying a Lookup Table

Select an entry and modify the displayed information as needed.

Copying a Lookup Table

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Lookup Table

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Lookup Table

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General
Name

Enter a name for the lookup table definition.

Description

Enter a brief description of the lookup table definition.

Details
Key

Enter text that will serve as the key for that entry in the lookup table definition.

Value 1, Value 2, Value 3...

Enter a value in each column.

Add

Click the Add icon below the table to add a new value column to the table.

Remove

Click the Remove icon below the table to remove the last value column from the table.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 29 of 44

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Calendars
Home > Vulcan Gantt Scheduler > Setup > Settings > Calendars

Use the Calendar Manager panel to define working and non-working times for the project. You can apply a calendar to an entire project, to resources in the resource definitions, or
to activities for future development.

Instructions
On the Setup tab, in the Settings group, click Calendars to display the Calendar Manager panel.

Calendars
Adding and Defining a New Calendar

Click Add to add a new entry, or press Insert.

Modifying a New Calendar

Select an entry and modify the displayed information as needed.

Copying a Calendar

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

The name of the new calendar will be the name of the copied calendar appended by the word copy. For example, if the original calendar name is Holiday, the new calendar
created from the Copy function will be Holiday copy.

Removing a Calendar

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Calendar Up or Down in the List

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

Calendar Specifications
Name

Enter a name for the calendar.

Description

Enter a description for the calendar.

Base calendar

Select this option if the calendar is not based on another calendar.

Base on

Select this option if the calendar is based on another calendar, and select the base calendar from the drop-down list. Any information from the chosen base calendar will be

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 30 of 44

included on the new calendar.

Calendar, Legend, and Information

These sections display the information for dates on the selected calendar. Days with a non-working time exception have a red background, days with modified (non-default)
working time have a green background, normal working days have a light grey background, and non-working days have a dark grey background. Information about the
selected day is displayed in the Information section.

Default Working Time

Use this section to set the default working days and times for the week. Select the check boxes next to each default working day. Clear the check boxes next to any default
non-working days. Enter the default start and end times in the From and To columns using a four-digit 24-hour notation. For example, enter 06:00 for 6:00 a.m. and 13:00 for
1:00 p.m.

Exceptions

Use this section to define any exceptions to the default working week. See Calendar Exceptions for more information.

Apply a Calendar to the Entire Project

You can apply a calendar to the entire project by selecting the name of the calendar from the Calendar drop-down list on the Project Options panel.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Settings > Calendars > Calendar Exceptions

Calendar Exceptions
Use the Exception panel to define any exceptions to standard working and non-working times for the project. You can specify exceptions for non-working time and for non-default
working time. Exceptions may be scheduled as single or recurring events. Any dates with exceptions are displayed in the Calendar and Exceptions sections of the Calendar
Manager panel.

Instructions
On the Calendar Manager panel, click Add to add a new exception, highlight an entry and click Remove to remove the exception from the list, or highlight an entry and click
Modify to modify an existing exception. If you click Remove, the exception will be removed from the list. If you click Add or Modify, the Exception panel displays.

General
Name

Enter a name for the exception.

Date

Enter the date of the exception in mm/dm/yyyy format or click the calendar icon to select a date.

Type

Select Nonworking for regular non-working time or select Non-default working time to specify that the exception is working time that is outside of the default schedule. If you
select Non-default working time, specify the time range in the Working Time section.

Working Time

Enter the time range in the From and To columns using a four-digit 24-hour notation if you selected Non-default working time in the Type section. For example, enter 06:00 for
6:00 a.m. and 13:00 for 1:00 p.m.

Repeat
Repetitive

Select the Repetitive check box if the exception is recurring. If selected, specify how often and when the event repeats.

To change a reoccurring exception to a one-time exception, clear the Repetitive check box.

Repeats

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 31 of 44

Select Daily, Weekly, Monthly, or Yearly from the drop-down list to specify how regularly the exception repeats.

Every ... days/weeks/months/years

Enter a number to indicate the frequency of the exception. For example, if the exception occurs every two weeks, in the Repeats drop-down list, select Weekly, and then in
the Every box, enter 2.

Starts on

Enter the date of the first occurrence of the exception in mm/dm/yyyy format or click the calendar icon to select a date.

Ends

Select After ... Occurrences to specify a finite number of occurrences or On to specify a date for the last occurrence of the exception. If you select After ... Occurrences, enter
the number of occurrences in the box. If you select On, enter the date of the last occurrence in mm/dd/yyyy format or click the calendar icon to select a date.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Period
Home > Vulcan Gantt Scheduler > Setup > Period

The Period group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for selecting and modifying period definitions.

Periods
Click Periods to display the Period Setup panel to create, modify, or remove period definitions.

Current Period
Select a period from the list to set it as the current period definition.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Period > Periods and Period Setup

Period Setup
Use the Period Setup panel to create, modify, or remove period definitions.

Instructions
On the Setup tab, in the Period group, click Periods to display the Period Setup panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 32 of 44

Periods
Adding and Defining a New Period

Click Add to add a new entry, or press Insert.

Modifying a Period

Select an entry and modify the displayed information as needed.

Copying a Period

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Period

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Period

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

Setting the Current Period

Select an entry and click Set Current to set it as the current selection in the tab group. Click Reset Current to reset the selection.

General
Name

Enter a name for the period.

Description

Enter a brief description of the period.

Generate Uniform Period List

Use this section to generate or modify a uniform period list by specifying a start date and time, increment of time, and number of periods. You can then modify individual periods in
the Details section.

Start date

Enter the start date of the period to be defined.

Start time

Enter the start time of the period to be defined.

Increment

Select the increment of time to use when generating the uniform period list. You can select Hour, Day, Week, Month, or Year.

Number of periods

Enter the number of periods to generate for the definition.

Details

Once you have generated a period list in the Generate Uniform Period List section, you can modify the time amounts and increments of individual periods. If you make a change to
a period, the subsequent periods will be automatically updated.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 33 of 44

Start date

Displays the start date and time of the period.

End date

Displays the end date and time of the period.

Time amount

Enter the amount of time per increment for the period.

Increment

Select the increment of time to use for that period. You can select Hour, Day, Week, Month, or Year.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Summary Report
Home > Vulcan Gantt Scheduler > Setup > Summary Report

The Summary Report group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options to set up reports and export report to CSV files.

Report Setup
Click Report Setup to display the Summary Report Manager Export panel to create, modify, or remove reports and report setup information.

Current Report
Select a report from the drop-down list to set it as the current report.

Export to CSV
Click Export to CSV to display the Summary Report Export panel to export report information to a CSV file.

Tutorial
Click to read the Summary Report tutorial.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Summary Report > Report Setup

Report Setup
Use the Summary Report Manager panel to create, modify, or remove reports and report setup information.

Tutorial
Click to read the Summary Report tutorial.

Instructions
On the Setup tab, in the Summary Report group, click Report Setup to display the Summary Report Manager panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 34 of 44

Reports
Adding and Defining a New Report

Click Add to add a new entry, or press Insert.

Modifying a Report

Select an entry and modify the displayed information as needed.

Copying a Report

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Report

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Report

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

Setting the Current Report

Select an entry and click Set Current to set it as the current selection in the tab group. Click Reset Current to reset the selection.

Managing Report Details

Use the icons below the Details section to add, remove, copy, or move report items.

Add a new item to the report

Click the Add icon to add a new item to the report.

Remove an item from the report

Click the Remove icon to remove the selected item from the report.

Copy an item on the report

Click the Copy icon to create a copy the selected item.

Move an item to another report

Click the Move icon to move the item to another report.

Copy an item to another report

Click the Copy and Move icon to copy the selected item and move it to another report.

Move an item up or down in the list

Click the Up or Down icons to move the selected item up or down in the list.

Move an item to the top or bottom of the list

Click the Move to Top or Move to Bottom icons to move the selected item to the top or the bottom of the list.

General
Name

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 35 of 44

Enter a name for the report.

Description

Enter a brief description of the report.

Details
Title

Enter the title of the report item.

Unit

Enter the unit of measurement for the report item.

Attribute

Select the attribute of the report item from the list.

Weighted by

If the selected attribute is a custom expression, select the attribute by which it is weighted from the list.

Expression

If the selected attribute is a custom expression, select or enter the formula for the expression. To use the Formula Editor panel to enter or modify the expression, click the
Formula Editor icon.

Calculation

Select the calculation method of the report item from the list.

Activity Type

Select the activity type(s) of the report item. To select activity types, click the Browse icon to display a list of the available activity types. Click on an activity type in the left
column and then click the right arrow to add the activity type to the list, or click the double right arrow to add all activity types to the list. To remove selected activity
types, click on the activity in the right column and then click the left arrow to remove the activity type from the list, or click the double left arrow to remove all activity
types from the list. Click OK when finished to save selections and return to the Summary Report Manager panel.

Resource

Select a resource for the report item from the list.

Filter

Select a filter for the report item from the list.

Decimals

Enter or select the number of decimals to use for the report item on the report.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Summary Report > Export to CSV

Export to CSV
Use the Summary Report Export panel to export report information to a CSV file.

Tutorial
Click to read the Summary Report tutorial.

Instructions
On the Setup tab, in the Summary Report group, select the report you want to export from the Current report drop-down list, and then click Export to CSV to display the Summary
Report Export panel.

Summary Report Export


Start Date

Enter a start date for the report.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 36 of 44

Finish Date

Enter an ending date for the report.

Separator

Enter the character that separates the data fields in the CSV file.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Setup > Formula Editor

Formula Editor
Use the Formula Editor panel to assist in creating formulas and expressions for activity attributes.

Expression attributes are defined via the expression builder. The syntax for functions is similar to Microsoft Excel, with auto-complete while defining and helpful syntax prompts. The
available operands that can be used in expressions are Envisage Metadata, DGD Properties, Triangulation Attributes, and Templated Attributes.

Instructions
On the Attribute Manager panel, click the Formula icon to display the Formula Editor panel.

For additional information about using the expression builder, see: http://www.infragistics.com/help/wpf/xamFormulaEditor_ContextualHelp.html

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View

View Tab
The View tab includes options for viewing activities in Envisage as well as filtering, grouping, and sorting activities.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 37 of 44

Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.

Envisage
The Envisage group includes options for selecting and zooming on activities in Envisage based on selection in Gantt Scheduler as well as the ability to create animations of
selected activities.

Filter
The Filter group includes options for creating, modifying, and selecting filters for activity data.

Group
The Group group includes options for managing and selecting attribute groups.

Sorting
The Sorting group includes options for sorting data in ascending or descending order.

View
The View group includes an option for selecting all activities in the Gantt Chart area.

Column Format
The Column Format group includes options for formatting columns, including aligning, hiding, and displaying columns.

Layout
The Layout group includes options for saving, loading, and resetting the layout of the Gantt Scheduler.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Envisage
Home > Vulcan Gantt Scheduler > View > Envisage

The Envisage group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for selecting and zooming on activities in Envisage based on selection in
Gantt Scheduler as well as the ability to create animations of selected activities.

Envisage Selection
Click Envisage Selection to automatically select activities in Envisage when you select them in the Gantt Scheduler. This option will remain on until you click Envisage Selection
again.

Envisage Zoom
Click Envisage Zoom to automatically select and zoom in on activities in Envisage when you select them in the Gantt Scheduler. This option will remain on until you click
Envisage Zoom again.

Note In order to use the Envisage Zoom option, the Envisage Selection option must also be selected.

Envisage Hide
Click Envisage Hide to hide activities in Envisage when you select them in the Gantt Scheduler.

Envisage Shadow
Click Envisage Shadow to shadow activities in Envisage when you select them in the Gantt Scheduler.

Select in Envisage
Click Select in Envisage to select activities in Envisage when you select them in the Gantt Scheduler.

Zoom in Envisage
Click Zoom in Envisage to zoom in on activities in Envisage when you select them in the Gantt Scheduler.

Animation
Use the Animation option to display an animation of selected activities in Envisage.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 38 of 44

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View > Envisage > Animation

Animation
Use the Animation panel to display an animation of selected activities in Envisage.

Tutorial
Click to read the Animation tutorial.

On the View tab, in the Envisage group, click Animation to display the Animation panel.

Step increment

Select the increment of time for the animation. You can select Hour, Day, Week, Month, or Year.

Rate

Enter the number of steps per frame for the animation.

Show completed / Show remaining

Select whether to animate activities that have been completed or activities that are still remaining.

Icons
Previous

Click the Previous icon to jump back to the previous step of the animation.

Stop

Click the Stop icon to stop the animation.

Play

Click the Play icon to play the animation.

Pause

Click the Pause icon to pause the animation.

Next

Click the Next icon to jump to the next step of the animation.

Last

Click the Last icon to jump to the last step of the animation.

Loop

Click the Loop icon to continue playing the animation on a loop. When the animation reaches its end, it will return to the beginning and play again.

Refresh

Click the Refresh icon to refresh the animation to include any changes you have made to activities in the Gantt Scheduler.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Filter
Home > Vulcan Gantt Scheduler > View > Filter

The Filter group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for creating, modifying, and selecting filters for activity data.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 39 of 44

Filters
Click Filters to display the Filter Manager panel. This panel includes options to add, modify, or remove data filters.

Current Filter
Select the current filter from the list.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View > Filter > Filters

Filters
Use the Filter Manager panel to add, modify, or remove data filters.

Instructions
On the View tab, in the Filter group, click Filters to display the Filter Manager panel.

Reports
Adding and Defining a New Filter

Click Add to add a new entry, or press Insert.

Modifying a Filter

Select an entry and modify the displayed information as needed.

Copying a Filter

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Filter

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Filter

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 40 of 44

Setting the Current Filter

Select an entry and click Set Current to set it as the current selection in the tab group. Click Reset Current to reset the selection.

General
Name

Enter a name for the filter.

Description

Enter a brief description of the filter.

Filter
...

Select whether you want to include or exclude attributes based on the filter and whether or not to enclose the expression within parentheses. You can select _blank_, (, Not (,
or Not.

Attribute

Select the attribute name from the list. For more information about managing attributes, see Attributes.

Rule

Select a rule from the list. You can select = (is equal to the specified value), Starts with (attribute starts with the specified value), Ends with (ends with the specified value), or
Like (includes the specified value).

Value

Enter a value for the rule. Wildcards are allowed.

...

Select whether or not to include a closing parenthesis for the expression based on your selection in the first column.

Logical Operator

Select And or Or if you want to add another line to your expression to indicate whether the rules are inclusive or exclusive of each other.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Group
Home > Vulcan Gantt Scheduler > View > Group

The Group group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for managing and selecting attribute groups.

Groups
Click Groups to display the Group Setup panel. This panel includes options to add, modify, and remove attribute groups.

Current Group
Select the current group from the list.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View > Group > Groups

Group Setup
Use the Group Setup panel to add, modify, and remove attribute groups.

Instructions
On the View tab, in the Group group, click Groups to display the Group Setup panel.

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 41 of 44

Groups
Adding and Defining a New Group

Click Add to add a new entry, or press Insert.

Modifying a Group

Select an entry and modify the displayed information as needed.

Copying a Group

Select an entry and click Copy to create a copy of the selected entry or press Ctrl+C.

Removing a Group

Select an entry and click Remove to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.

Moving a Group

Select an entry and click Up or Down to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.

General
Name

Enter a name for the group.

Description

Enter a brief description of the group.

Details
Attribute

Select an attribute from the list. For more information about managing and modifying attributes, see Attributes.

From

Enter a value for the beginning of the group selection.

Length

Enter the length of the group.

Sort Order

Select whether to display the results in Ascending or Descending order.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View > Sorting

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 42 of 44

Sorting
The Sorting group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for sorting data in ascending or descending order.

Ascending
Select a column in the Gantt Chart area and then click Ascending to sort activities in ascending order by that column's values.

Descending
Select a column in the Gantt Chart area and then click Descending to sort activities in descending order by that column's values.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited
Envisage Maptek

View
Home > Vulcan Gantt Scheduler > View > View

The View group is located on the View tab of the ribbon in the Gantt Scheduler. It includes an option for selecting all activities in the Gantt Chart area.

Select all activities


Click Select all activities to select all activities displayed in the Gantt Chart area.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > View > Column Format

Column Format
The Column Format group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for formatting columns, including aligning, hiding, and displaying
columns.

Left
Select a column in the Gantt Chart area and then click Left to left-align the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align,
and then click Left.

Center
Select a column in the Gantt Chart area and then click Center to center the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align,
and then click Center.

Right
Select a column in the Gantt Chart area and then click Right to right-align the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align,
and then click Right.

Hide
Select a column in the Gantt Chart area and then click Hide to hide the column from view. Alternatively, you can right-click the column header and then click Hide. To display a
single hidden column, right-click on any column header, point to Show, and then click on the name of the column you want to show.

Show All
Click Show All to display all columns in the Gantt Chart area, including any columns that have previously been hidden. Alternatively, you can right-click any column header and click
Show All. To display a single hidden column, right-click on any column header, point to Show, and then click on the name of the column you want to show.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 43 of 44

Home > Vulcan Gantt Scheduler > View > Layout

Layout
The Layout group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for saving, loading, and resetting the layout of the Gantt Scheduler.

Save
Click Save to save the current Gantt Scheduler layout. If you make changes to the layout after you save it, you can return to the most recently saved layout using the Load option

Load
Click Load to return to the most recently saved layout.

Reset
Click Reset to return to the default layout.

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited

Home > Vulcan Gantt Scheduler > Keyboard Shortcuts

Keyboard Shortcuts
Following is a list of keyboard shortcuts for the Vulcan Gantt Scheduler. The keyboard shortcuts are grouped by the name of the tab on which they appear in the Gantt Scheduler
interface.

n Home tab
n Precedences tab
n Resources tab
n Setup tab
n View tab

Home Tab
Option Keyboard Shortcut
Copy activity Ctrl+C
Cut activity Ctrl+X
Paste activity Ctrl+V
Delete activity Ctrl+D
Undo Ctrl+Z
Redo Ctrl+Y
New Shift+A
Insert Ctrl+I
Properties F4
Update activities Ctrl+U
Increase indent Alt+Right Arrow
Decrease indent Alt+Left Arrow

Precedences Tab
Option Keyboard Shortcut
Create Ctrl+F12
Remove Shift+F12
Spatial precedences F9
Group manager Ctrl+G
New group Alt+G

Resources Tab
Option Keyboard Shortcut
Settings Ctrl+F10
Allocate resources Alt+F10
Apply resource rate Alt+F11
Leveling setup Alt+L
Leveling by capacity Alt+Y
Leveling by rate and capacity Alt+R
Clear leveling delays Alt+C

file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm 05-05-2016
Vulcan Gantt Scheduler : Contents Page 44 of 44

Setup Tab
Option Keyboard Shortcut
Project options F5
Attributes F6
Activity types F7
Lookup Tables None
Calendars F8
Periods Ctrl+F8
Report setup None
Export to CSV Alt+R

View Tab
Option Keyboard Shortcut
Automatic selection in Envisage (toggle
Ctrl+F3
on/off)
Zoom in Envisage (toggle on/off) None
Animation None
Filters F11
Groups None
Sorting None

Need more help?


Go to www.maptek.com/support to access the Maptek Client Support page.

Have feedback on this help topic? Share it with us at [email protected]. Copyright© 2015 Maptek Pty Limited