SPECIFICATIONS
w w w. c o b o d . c o m
CONTENT
1
3D CONSTRUCTION PRINTING OVERVIEW
3D Construction Printing (3DCP) was initiated in the late 1990s with the very first attempts to extrude
concrete from a computer controlled robot. Since then, a vast development has occurred and in 2014 the
world saw the first commercial 3D printed building.
Currently, the amount of interest and research has exploded around the world, with a wide range of
traditional construction industry putting efforts and investment into 3D printing for the construction.
Most of the major universities now have on-going research projects, challenging the boundaries and
expanding the global knowledge about this field. By 2020, a total of 29 houses are estimated to have
been built by 3D printing technology world-wide. And the number will likely increase fast in the next
years.
While there are many ways to use 3D printing technologies for construction, two specific methods are
currently dominating the industry:
• Gantry-type 3D printers mainly used for larger construction and on site
• Robotic arm 3D printers mainly used for smaller, more complex components
2
The gantry type printers can have 4 Z axis (as seen in the picture above) or 2 Z axis mounted on rails.
The gantry printer operates in 3 dimensions, with the print head moving back and forth on the X-axis
(from side to side on the picture), which is the first direction. The x-axis moves along the y-axis (in and
out of the picture), which is the second direction. The y-axis (holding the x-axis) moves up and down
on the Z-Axis columns, which is the third direction. The gantry principle allows the printer to access
any position within the print envelope and gives complete freedom of movement within the reach of
the printer, also known as the printable area. Within the printable area an entire building can be printed
with only one set up of the printer, and no need to move and calibrate the printer while constructing the
building.
The robotic arm printer works different than that, typically with additional movements. The downside is
that the robotic arm printer can only print in essence what is in front of it and with a width of the print of
1-1.5 meter. Also, small prints like that require fast curing of the concrete, typically leading to much higher
cost than that of normal concrete. Larger prints than the single elements require moving the robotic arm
and calibrating the system at the new location, which can be time consuming taking from hours to days
for each movement.
While there are some similarities between the two methods, they can best be used for different
applications, and with different strengths and weaknesses, outlined in the table below. The most
characteristic difference being, that a robotic arm typically has a very small reach, and thus will only print
smaller modules / parts/ elements of the whole building and will typically do it off-site, while the gantry
system can reach much larger distances, and print entire buildings on site.
Competitors in current market General contractors (low skill) Specialized contractors (high skill)
Both technologies extrude concrete or mortar in layers, and the entire structure is built from the bottom
and upwards, placing layer upon layer of concrete in a pattern decided by the 3D model input.
3
CONSTRUCTION WITH 3D CONSTRUCTION PRINTERS
Any technology has its optimal use and preferred shapes to build
from. Historically, buildings have been shaped from the availability
of its contemporary building methods. In ancient Rome, all
structures were “compression only” structures with large arches to
distribute the forces. This was the main method for many
years in concrete, until the reinforced concrete was invented. This
technology enabled concrete to have internal tensile strength, and
the building methods of today were developed, i.e. the slab
/ column structures that are commonly used today in most parts
of the world.
Roman architecture
3DCP geometry
4
Building permits and local building codes
When a 3D printed building project is initiated, the first thing to do is to investigate the local regulatory
environment. Normally any planned building above a certain minimum size requires a building permit and
such will only be given to the extent, that the local building code is followed in the planned 3D printed
project. Thus, the 3D printed building must follow local building code, but as this code varies between
regions and countries, in advance it cannot be stated how this should be done. Instead it is important
to discuss the building method as early as possible in the process with representatives from regulatory
parties and local structural engineers. Here you should remember that the printer is just a tool. The tool
can be used for different construction methods. In other words, the tool does not dictate that a certain
construction method should be used. COBOD is also always ready to advice you in the process of
determining how the printer should be used to live up to the building code.
The 3D printer and other equipment do not require obtaining a building permit
It is important to recognize that it is not the printer or any other equipment for that matter, that require
a building permit. It is the planned building when using the printer or any other equipment, that requires
a permission. The 3D printers are not different from any other construction equipment in this respect.
The printer is just a tool helping to construct a building, and like other tools require no building permit as
such.
Similar arguments can be used for determining the 3D printer’s ability to deliver buildings that are
earthquake and hurricane resistant. As the printer is just a tool, making a building that can be permitted
as earthquake and hurricane resistant is a matter of determining the requirements, and use the printer in
such a way, that this can be delivered.
It is possible to find methods for all regions be it earthquake, hurricane proof or the cold climate of
Scandinavia, the important thing is, to find a method that can be approved by the local authorities.
building in Europe
5
Load bearing walls or not
Load bearing walls/structures can be 3D printed, provided the specific material used for printing is
approved locally. In cases where the material is not yet locally approved, an often-used method is to
print hollow columns inside the printed walls, that are then cast with regular, approved, concrete with
reinforcement to satisfy the regulations.
Reinforcement
6
BOD2 OVERVIEW
The BOD2 3D Construction Printer is a gantry type printer and is designed to enable the on-site printing
of a wide range of projects, including entire buildings with several floors. With its modular design, it can
be scaled up and down to everything from small concrete precast components, to on site printing of
houses, to larger office buildings, museums, schools, warehouses etc. in up to 3 stories (G+2).
The BOD2 modularity is a function of 2.5 meter modules, as shown in the picture below. Vertically, 4
modules are the maximum and 6 modules wide, while there are no limitations in the length.
The printer will be delivered with assembled and connected modules according to the ordered size.
7
Minimum and maximum size of printer
The BOD2 can be operated by a team of just two operators, one for the laptop controlling the printer and
one for assuring materials supply, and various smaller tasks during printing.
Besides from printing of the walls, the printer can also be used to mark locations on the building site.
For example, the printer can mark where installations should come out of the floor or walls, such that the
electricians and plumbers can be shown precisely, where they should put installations.
During printing the operators can assure that the walls have been prepared for the later insertion of
electrical sockets, plumbing, wires etc.
High speed and material output possible leading to minimal time to print the building
The BOD 2 printer is designed to be able to move the print head with a maximum speed of 1000mm/
second – 1m/s.
Presently (2020) the maximum realized speed for longer periods of printing is 400-500 mm/s.
Depending on the complexity of the print, the materials printed with and the mixer/pump used a larger
or smaller part of the speed can be utilized.
If a nozzle of 5 cm width and 2 cm layer height is used, at 400 mm/s speed, the printer will be extruding
up to 1.4 m3 of mortar/concrete per hour equivalent to 3 tons. 3 tons also corresponds to printing 14 m2
of a double wall section (inner and outer wall) per hour. A 100 m2 house has approximately 200 m2 of
wall sections, which the printer at that speed can do in 14-15 hours printing time, to which preparation
and cleaning time must be added.
8
Choice of print widths and heights; print nozzles and flaps
3D printed plastic nozzles can be used as print nozzles, while we recommend using metal nozzles for
larger prints.
Using 3D printed plastic nozzles allows for experimentation with nozzle designs to optimize the flow of
concrete and to change the size of the nozzle in minutes. The nozzles can be printed with plastic polymer
printers costing a maximum of 1,500 euro. COBOD is normally using PET-G plastic for the 3D printed
nozzles.
Because the nozzles are 3D printed, it is easy to try out new designs and produce nozzles for different
layer heights or widths. Nozzle are exchanged and fastened to the printhead using a triclamp.
very visible with a sharp edge between each layer, while the line nozzles
will be far less visible if the flaps are mounted straight down or a
tilted a bit away from the nozzle.
Tangential control – smooth walls
9
The tangential control facilitates the use of flaps, that removes excess material from the side of the walls
and provides a much smoother surface on the finished wall. This reduces the amount of work and materi-
al needed for plastering and painting, and greatly increases the aesthetics of the wall.
10
Automatic feeding of materials from the pump to the hopper
The material hopper is equipped with a material level sensor, and can be digitally connected to the pump
and mixer (both are extra options to be acquired, see the pricelist) if delivered by COBOD whereby
the whole feeding of materials to the printer is digital and automatically controlled. Hereby, the flow of
materials to the printhead can occur without the involvement of the operators.
Material is fed to the hopper on the print head via a concrete hose (typical size of ø50 mm), which is
connected to the pump and mixing system.
Software interface
COBOD Slice converts architect files to printable files
automatically
11
Follow the printing via 2 on board web cameras
The BOD2 printer is CE certified and built from an exceptionally durable steel truss framework, that
ensures the robustness to accommodate rough handling on and between sites, as well as guarantee
safety of the workers and operators during the construction process.
IP67 means that the printer safely can be operated in rainy and dusty conditions.
The BOD 2 printer comes with a manual, that explains how to operate the system and perform daily
tasks. The manual is plus 50 pages long and describes in detail how the printer is operated and
maintained.
COBOD provides on-site installation, training, and operation assistance as an extra option, see the
pricelist. When supplying such COBOD will instruct the customer in how to assemble, disassemble and
use the printer. We will also assist with doing test wall prints. The on-site training and installation usually
ends with printing of a test wall.
11
BOD2 SPECIFICATIONS
M-Tec Mixer/pump
12
When COBOD supplies the whole materials supply system next to the printer as turnkey supply, being
the silo and mixer/pump, the mixer/pump can be placed under the silo whereby dry material from the silo
are automatically send to the mixer as needed. The mixer/pump then adds water and mixes the concrete
to always keep the pump filled. The pump and flow of materials to the printer is controlled by the printer
itself.
The hopper of the printhead can contain a smaller amount of materials (20-30kg). The printer
continuously measures the content of the hopper and when the hopper is near empty, the printer
engages the pump. The system is monitoring the amount of material in the mixer and will automatically
open the valve on the silo to re-fill dry material into the mixer as needed.
3DCP MATERIALS
The materials for 3D printing, mortar, or concrete, are many and varied.
The BOD2 3D printer can work with any material that satisfies some basic requirements:
• Material can be pumped through a long hose (up to the length of the building to be printed + 10
meters) – materials are “pumpable”
• Material can be extruded, but are still stiff enough to support its own weight and has zero slump
when being printed – materials are “printable
• Setting time of the material is fast enough after a few minutes such that it can carry the subsequent
layers printed upon it – materials are “buildable”
One of the key factors, when deciding for a material for a project, is to know the so called “layer time” as
well as the build-up time.
13
The layer time refers to the exact time it takes to print 1 layer of the building. If the layer time is fast, you
need a fast setting material. If it is slow, you need a slower setting material.
The build-up time refers to the vertical build rate of the building in meter / hour. For faster build-up
times, you also need a faster setting material.
All three factors can be controlled in the software of the BOD2 printer and are key to getting a successful
and stable print.
Ready mix dry mix mortars or real concrete and consequences for the pump and mixer needed
More and more manufacturers like Heidelberg/Italcementi, Laticrete, Lafarge, Siam Cement etc. are
offering ready mix dry mix mortars for 3DCP in various parts of the world. Materials are typically supplied
in 25 kg bags, where all the necessary elements are in and water just has to be added to make the
3D printable concrete. The maximum particle size is normally below 4 mm (hence it is more correctly
described as a mortar not concrete).
As the cement is already mixed with the necessary sand and gravel aggregates all moisture has to be
driven out of the aggregates prior to that the materials are mixed together and put into the bags, as
if the moisture I still in there the process of making and curing of the concrete starts while in the bag.
Pre-drying is a costly process and as a consequence these dry mix materials are expensive on a per ton
or per m3 basis. For smaller prints, this will usually not be a big issue, but for larger prints and multiple
buildings this will be a challenge. On the other hand, the ready-mix dry mix mortars are very easy and
convenient to use.
The alternative is to make a 3D printable real concrete with a max particle size of 8-10 mm. The cement,
sand and gravel and other ingredients are mixed together on site (where the moisture in aggregates
has not been driven out first), which can be done with more manual equipment or via automatic mini
batching plants, which COBOD also offers. This process is more complex than relying on ready mix
dry mix mortars, but the cost is also a fraction of the cost of the alternative materials. We recommend
making real concrete for any larger prints.
When real concrete is used, the M-tec mixer/pump suitable for the mortars will generally not be suitable,
and a real concrete piston pump will be necessary. COBOD also supplies such. Other pumps, like pumps
from for instance Putzmeister can also be used, but the whole materials delivery process is then more
difficult to automate and make digital, than when COBOD is delivering all equipment as a turnkey supply.
14
Open source – locally sourced concrete
BOD2 is open source as for materials, which means that COBOD will not force you into using any mate-
rial supplied by COBOD.
The BOD2 can handle any mortar and concrete fulfilling the above-mentioned criteria.
Concrete is very versatile by nature and can be adjusted to fit almost any weather condition and specifi-
cation.
Due to cost of such, concrete is only very rarely shipped over longer distances, and thus in most places
in the world, it is significantly better and cheaper to develop local recipes based on materials that can
be supplied through the local infrastructure, then to use materials from far away.
This is why COBOD is constantly working alongside a long list of material suppliers around the world
to develop and test materials suitable for the local climate. If you are in an area where no one has been
3D printing in concrete, we will initiate a dialog with your local material suppliers in order for them to
supply materials for 3DCP, and we will work with you to help with finding the right recipe/mix of the
concrete based on the local available materials
15
Example of recipe
This recipe is a relatively slow setting material, as the printing speed in 2017 was less than 1/4 of what it
is today with the new BOD2. The layer time was 15 minutes during most of the printing process, and thus,
no accelerators or VMAs was needed. With smaller buildings, it might be necessary to add accelerators
and VMAs in the mixture to control the stiffness and setting time more precisely.
The compression strength of this specific recipe was tested at 52MPa (6,500 PSI), mainly due to the
relatively high cement content. In this specific project, 23% of the material was replaced with crushed,
recycled tiles, which added to the flow capabilities in the system and proved that recycled materials can
be used in 3DCP. However, this can easily be replaced with regular gravel of similar grain size.
As for reinforcements and fibers, both were used when the BOD building was printed in 2017.
So-called crackstop fibers were an integral part of our mixture and as part of the building 3D printed
columns were printed, where reinforcement rebars were added and then they were casted in normal
concrete.
16
REFERENCE PROJECTS
As this was our first project, we made many mistakes and have
improved our technology and skills considerably since this
print
17
3DPO building, Belgium
18