Professional Documents
Culture Documents
Davis Contractors LTD V Fareham UDC (1956) A
Davis Contractors LTD V Fareham UDC (1956) A
Davis Contractors LTD V Fareham UDC (1956) A
Court: HL
appellants were not entitled to be paid on the basis of a quantum meruit because (i) appellants' letter of
March 1946, and the condition stated therein were not incorporated into the final contract of July 1946; (ii) the
fact that both parties to the contract expected that it would be possible to complete the work within eight
months did not result in the contract being frustrated when, as events happened, these expectations were
not realised with the consequence that the contract became more onerous than the parties had
contemplated.
Document information
Page 4
Court
House of Lords
Judgment date
19/04/1956