Davis Contractors LTD V Fareham UDC (1956) A

You might also like

Download as rtf, pdf, or txt
Download as rtf, pdf, or txt
You are on page 1of 4

Page 1

Davis Contractors Ltd v Fareham UDC


[1956] AC 696, [1956] 2 All ER 145, [1956] 3 WLR 37, 54 LGR 289, 100 Sol Jo 378

Court: HL

Judgment Date: 19/04/1956

Catchwords & Digest

BUILDING CONTRACTS, ARCHITECTS, ENGINEERS AND SURVEYORS - CERTIFICATION AND


REMUNERATION - REMUNERATION - METHOD OF PAYMENT - QUANTUM MERUIT -
CIRCUMSTANCES CONTEMPLATED ALTERED—LABOUR SHORTAGE
In March 1946, appellants tendered for a contract with respondents to build seventy-eight houses
within a period of eight months. The tender was accompanied by a letter which stated that the tender was
‘subject to adequate supplies of material and labour being available as and when required to carry out the
work within the time specified.’ In July 1946, after further negotiations, a formal contract was entered into
between the parties and this incorporated a number of preliminary documents; these were listed in a clause
of the contract and, although the tender was specified to be one of them, the letter was not so specified. The
contract was to build the houses at a fixed price subject to certain adjustments. For various reasons, the
chief of which was the lack of skilled labour, the work took twenty-two months to complete instead of eight
months. Appellants were paid the contract price together with stipulated increases and adjustments but they
claimed that they were entitled to a greater sum on the basis of a quantum meruit. They contended that the
contract price was not binding because either (a) the contract had been subject to an express overriding
condition (contained in the letter of March 1946) that there should be adequate supplies of material and
labour, or (b) that owing to the long delay due to the scarcity of labour the contract had been frustrated: Held
appellants were not entitled to be paid on the basis of a quantum meruit because (1) appellants’ letter of
March 1946, and the condition stated therein were not incorporated into the final contract of July 1946; (2)
the fact that both parties to the contract expected that it would be possible to complete the work within eight
months did not result in the contract being frustrated when, as events happened, these expectations were
not realised with the consequence that the contract became more onerous than the parties had
contemplated.

CONTRACT - IMPOSSIBILITY AND MISTAKE - SUBSEQUENT IMPOSSIBILITY AND FRUSTRATION -


IMPOSSIBILITY OF LEGAL PERFORMANCE — FRUSTRATION OF ADVENTURE - BUILDING
CONTRACTS - LABOUR SHORTAGE
In March 1946, appellants tendered for a contract with respondents to build seventy-eight houses
within a period of eight months. The tender was accompanied by a letter which stated that the tender was
‘subject to adequate supplies of material and labour being available as and when required to carry out the
work within the time specified’. In July 1946, after further negotiations, a formal contract was entered into
between the parties and this incorporated a number of preliminary documents; these were listed in a clause
of the contract and, although the tender was specified to be one of them, the letter was not so specified. The
contract was to build the houses at a fixed price subject to certain adjustments. For various reasons, the
chief of which was the lack of skilled labour, the work took twenty-two months to complete instead of eight
months. Appellants were paid the contract price together with stipulated increases and adjustments but they
claimed that they were entitled to a greater sum on the basis of a quantum meruit. They contended that the
contract price was not binding because either (a) the contract had been subject to an express over-riding
condition (contained in the letter of March 1946) that there should be adequate supplies of material and
labour, or (b) that owing to the long delay due to the scarcity of labour the contract had been frustrated: Held
Page 2

appellants were not entitled to be paid on the basis of a quantum meruit because (i) appellants' letter of
March 1946, and the condition stated therein were not incorporated into the final contract of July 1946; (ii) the
fact that both parties to the contract expected that it would be possible to complete the work within eight
months did not result in the contract being frustrated when, as events happened, these expectations were
not realised with the consequence that the contract became more onerous than the parties had
contemplated.

Cases referring to this case


Annotations: All CasesCourt: ALL COURTS
Sort by: Judgment Date (Latest First)
Treatment Case Name Citations Court Date
[2015] EWCA Civ 18,
Blankley v Central
[2016] 3 All ER 382,
Manchester and
[2015] 1 WLR 4307, CaseSearch
Considered Manchester Children's CACivD 27/01/2015
165 NLJ 7639, [2015] 1 Entry
University Hospitals
Costs LR 119, [2015]
NHS Trust
All ER (D) 207 (Jan)
Planet Kids Ltd v [2013] NZSC 147, CaseSearch
Applied NZSC 17/12/2013
Auckland Council [2014] 3 LRC 222 Entry
[2013] EWHC 1506
Melli Bank Plc v Comml CaseSearch
Applied (Comm), [2013] All ER 13/05/2013
Holbug Ltd Ct Entry
(D) 165 (May)
Islamic Republic of [2010] EWHC 2661
Iran Shipping Lines v (Comm), [2011] 2 All
Steamship Mutual ER (Comm) 609, [2011] Comml CaseSearch
Applied 26/10/2010
Underwriting 1 Lloyd's Rep 195, Ct Entry
Association [2010] All ER (D) 261
(Bermuda) Ltd (Oct)
Gold Group Properties [2010] EWHC 323
Ltd v BDW Trading Ltd (TCC), [2010] BLR 235, CaseSearch
Applied TCC 03/03/2010
(formerly known as [2010] All ER (D) 216 Entry
Barratt Homes Ltd) (Mar)
[2008] EWCA Civ 856,
[2009] 2 All ER (Comm)
CTI Group Inc v
25, [2008] Bus LR CaseSearch
Applied Transclear SA, The CACivD 22/07/2008
1729, [2008] 2 Lloyd's Entry
Mary Nour
Rep 526, [2008] All ER
(D) 290 (Jul)
[2005] EWHC 2941
(QB), [2006] 3 All ER
173, 91 BMLR 1,
Badger v Ministry of CaseSearch
Considered [2006] NLJR 65, (2005) QBD 16/12/2005
Defence Entry
Times, 30 December,
[2005] All ER (D) 248
(Dec)
Globe Master [2002] EWCA Civ 313,
CaseSearch
Applied Management Ltd v [2002] All ER (D) 39 CACivD 05/03/2002
Entry
Boulus-Gad Ltd (Mar)
Wilson (Paal) & Co A/S [1983] 1 AC 854,
dicta Lord v Partenreederei [1982] 3 All ER 394,
CaseSearch
Radcliffe Hannah Blumenthal, [1982] 3 WLR 49, CACivD 26/03/1982
Entry
Applied The Hannah [1982] 1 Lloyd's Rep
Blumenthal 582, 126 Sol Jo 292
Applied Wilson (Paal) & Co A/S [1983] 1 AC 854, CACivD 26/03/1982 CaseSearch
Page 3

v Partenreederei [1982] 3 All ER 394,


Hannah Blumenthal, [1982] 3 WLR 49,
Entry
The Hannah [1982] 1 Lloyd's Rep
Blumenthal 582, 126 Sol Jo 292
[1980] QB 547, [1980]
3 All ER 117, [1980] 3
Pioneer Shipping Ltd CaseSearch
Considered WLR 326, [1980] 2 CACivD 22/05/1980
v BTP Tioxide Ltd Entry
Lloyd's Rep 339, 124
Sol Jo 428
[1979] 1 All ER 552, 38
Universal Corpn v
P & CR 687, 123 Sol CaseSearch
Applied Five Ways Properties CACivD 31/10/1978
Jo 33, 250 Estates Entry
Ltd
Gazette 447
Amalgamated [1976] 3 All ER 509,
Investment and [1977] 1 WLR 164, 120
CaseSearch
Applied Property Co Ltd v Sol Jo 252, [1976] 2 CACivD 03/03/1976
Entry
John Walker & Sons EGLR 153, 239 Estates
Ltd Gazette 277
[1974] 3 All ER 940,
[1974] IRLR 342,
Hare v Murphy Bros CaseSearch
Applied [1974] ICR 603, 17 KIR CACivD 06/06/1974
Ltd Entry
31, 10 ITR 1, 118 Sol
Jo 596
Hebden v Forsey & [1973] IRLR 344, CaseSearch
Followed NatIRC 03/10/1973
Son [1973] ICR 607 Entry
[1972] 2 All ER 715,
[1972] 1 WLR 899,
Marshall v Harland CaseSearch
Considered [1972] IRLR 90, [1972] NatIRC 13/03/1972
and Wolff Ltd Entry
ICR 101, 7 ITR 150,
116 Sol Jo 484
Société Franco [1961] 2 QB 278,
Tunisienne [1960] 2 All ER 529,
CaseSearch
Considered d'Armement v [1960] 3 WLR 701, QBD 18/05/1960
Entry
Sidermar SpA, The [1960] 1 Lloyd's Rep
Massalia 594, 104 Sol Jo 850
Emanuel (Lewis) & [1959] 2 Lloyd's Rep CaseSearch
Considered QBD circa 1959
Son Ltd v Sammut 629 Entry

Cases considered by this case


Annotations: All CasesCourt: ALL COURTS
Sort by: Judgment Date (Latest First)
Treatment Case Name Citations Court Date
Parkinson (Sir
Lindsay) & Co Ltd v [1949] 2 KB 632, [1950] CaseSearch
Considered CA 22/06/1949
Comrs of Works and 1 All ER 208 Entry
Public Buildings
(1888) 52 JP 392, 2
Bush v Whitehaven
Hudson's BC (4th Edn) CaseSearch
Explained Port and Town CA circa 1888
122, 130 (10th Edn) Entry
Trustees
357

Document information
Page 4

Court
House of Lords
Judgment date
19/04/1956

You might also like