Unops Meru-Site Status Report
Unops Meru-Site Status Report
&
Procedure Site Status Report Date:
03-12-2021
DATE: 03/12/2021
0 F. Zimbizi December
1. DOCUMENT BRIEF
2. LABOUR CAMP
We currently have 6 Cabin Houses (Double Roomed) on site out of the 16 required.
We have proceeded to erect 4 Cabin Houses (Double Roomed) to the roof level as is shown in
Appendix A.
The remaining 2 Cabin Houses shall be erected after the ground floor slabs have been cast on
06/12/2021.
Clearing and setting out the Toilet area has commenced together with trenching to the
proposed septic tank location.
Currently we have 7no. beds available on site for labour use.
3. STAFF CAMP
There hasn’t been any progress made on the Staff Camp due to lack of funds, lack of
materials, lack of adequate PPE and adequate labour.
However, we have located a source for the required bricks to start construction of the proposed
campsite.
03-12-2021
Appendix B details all Requisitions that have been made to date in regards to funds, materials,
plant, labour and all other necessities to successfully kick-off the aforementioned project.
APPENDIX A
03-12-2021
03-12-2021
APPENDIX B
Requisition Description Quantity Date Requested Date Required
Number
CASH
107226 Petty cash $800,000.00 18/11/2021 29/11/2021
107227 Labour feeding $300,000.00 18/11/2021 29/11/2021
PLANT
105248 Site Van 1 10/11/2021 15/11/2021
105248 2000 litre Fuel Bowser 1 10/11/2021 15/11/2021
105248 Water Bowser 1 10/11/2021 15/11/2021
105248 Grader 2 10/11/2021 15/11/2021
105248 Tipper 3 10/11/2021 15/11/2021
105248 FEL 1 10/11/2021 15/11/2021
105248 Dozer 1 10/11/2021 15/11/2021
105248 Excavator 1 10/11/2021 15/11/2021
105248 500R Concrete Mixer 1 10/11/2021 15/11/2021
105248 TLB 1 10/11/2021 15/11/2021