PROJECT LOGO

PROJECT NAME

INSPECTION TEST PLAN


MIVAN FORMWORK
(PROJ NUMBERING CODES) -ITP-MFW-R0

Rev # Date Prepared By Reviewed By Approved By Remarks

Revision Revision History

0 First Issue

Page 1 of 6
Project Logo (PROJECT NAME)

INSPECTION TEST PLAN


MIVAN FORMWORK
Prepared By ITP No: Rev: No:

LEGEND: XXX – ______________ / YYY – ___________________ R – REVIEW / S - SURVIELLANCE


ZZZ – __________________ W- WITNESS / H – HOLD POINT

Inspection XXX In Verifying


No Activity Frequency Acceptance Criteria
XXX YYY ZZZ Charge Documents

1 DOCUMENTATION REVIEW

On site drawing
In accordance with contract specs, Design requirement, check against
1a Check Formwork Detailed design Drawings
drawings Current GFC
drawing issue
Check for Material Approvals - Different parts of Procurement
1b As per details approved for the project
Mivan shuttering works Record
Approved Method
Check for Method statement / and method of As per contract specs/ drawings, and applicable
1c Statement Current
erection details guidelines & schedule
Revision

2 INSPECTION OF INCOMING MATERIALS.

All materials to be stored as per IS standard minimum


2a Storage of material including agreed by site team and detailed on the Visual Inspection
method statement. Material Deliveries
Formwork materials, panels, pins, wedges, and As per the standards, and items approved for the check sheet
2b
other accessories project

3 PRE-WORK INSPECTION

All materials (Panels/wedges and pins) shall be available


3a Availability of materials in the required quantity to ensure that fixing
arrangements are followed as per the details approved.
The numbering on the panels are to be verified and to
3b Check on numbering of panels be in order and to be stacked in such a way that
installation sequence are easily be followed

Page 2 of 6
Inspection XXX In Verifying
No Activity Frequency Acceptance Criteria
XXX YYY ZZZ Charge Documents
A reference line preferably at 1m to be marked on the
3c Check for level mark vertical reinforcement of column/Shear walls to be
marked.
Level marks are to be in intervals at 1.5m to 2 m in
3d Check for spacing of level marks order to maintain and facilitate the installation of slab Insp: Check list
/beam and its inspection
Before erection panels to be cleaned properly, ensure it
3e Check for application of form release agent is free from any unwanted dust and particles and
approved quality shuttering oil is applied.

4 INSPECTION DURING MIVAN INSTALLATION

To be start from inner corners with required temporary


4a Check on first fixing panels
supports.

4b Check on fixing of flat ties To be fixed along with internal wall formwork

To be fixed in line and level with ties provided as per the


4c Check on fixing of subsequent panels
approved details.
To be fixed by nailing one set of pin and wedge at
4d Fixing of vertical formwork
300mm
To be installed from the first hole at bottom and the
space of each pin from the bottom is
4e Check for sequence of installation of pins
50,150,300,600,900, 1200,1500,1800,2100, 2250,2350
Spacing shall not exceed 300mm
The spacing shall not exceed 300mm irrespective of the
4f Check for pin on the slab panel panel length. The first pin must be at the hole position
of 100mm. Insp: Check list
The raking shore /temporary side supports to be
4g Check for raking shore (temporary side supports) installed on both sides of the column and wall form
work.
The beam bottom formwork, prop head, inner corner
formwork to be installed according to the sequence.
numbering based on the approved drawing to the
4h Check for installation of beam panels required level.
All horizontal connections of pin and wedge shall be
fixed from top to bottom to avoid adverse effect during
vibration of concrete.
To be started after completing the installation of beam
4i Check for installation of slab formwork
work as per the details of sequence/numbering
Ensure provisions for all the services work
4j Check for MEP installations installation/cut outs were made in coordination with
respective trades.
Kickers are fixed on the external wall formworks in
accordance with the required height for the formation of
4k Check for kicker assembly the slab concrete and matching the flat tie notching of
wall formwork on the upper layer. Check to ensure that
the vertically of the kicker is correctly aligned.

Page 3 of 6
Inspection XXX In Verifying
No Activity Frequency Acceptance Criteria
XXX YYY ZZZ Charge Documents

Before handing over the work to the subsequent activity


4l Check for cleaning
ensure that all the area is cleaned properly.
Insp: Check list
All the installations of the panels – bothe verticals and
4m Check for level and line of vertical panels installed horizontal shall be checked for line, level and correct
positioning of the panels.

Page 4 of 6
COMPANY NAME Project Project Name
INSPECTION CHECKLIST
PLASTERING WORKS
MIVAN
ITP Inspection No. Location
FORMWORK
Prepared by Applicable Drawing

Sign
# Description Result Date
XXX YYY

1 DOCUMENTATION REVIEW

1a Check Formwork Detailed design Drawings

1b Check for Material Approvals - Different parts of Mivan shuttering works

1c Check for Method statement / and method of erection details

2 INSPECTION OF INCOMING MATERIALS.

2a Storage of material

2b Formwork materials, panels, pins, wedges, and other accessories

3 PRE-WORK INSPECTION

3a Availability of materials

3b Check on numbering of panels

3c Check for level mark

3d Check for spacing of level marks

3e Check for application of form release agent

4 INSPECTION DURING MIVAN INSTALLATION

4a Check on first fixing panels

4b Check on fixing of flat ties

4c Check on fixing of subsequent panels

4d Fixing of vertical formwork

4e Check for sequence of installation of pins

4f Check for pin on the slab panel

4g Check for raking shore (temporary side supports)

4h Check for installation of beam panels

4i Check for installation of slab formwork

4j Check for MEP installations

4k Check for kicker assembly

4l Check for cleaning

4m Check for level and line of vertical panels installed

Page 5 of 6
CONCLUSION  Accepted  Accepted with Comments  Rejected

COMMENTS

XXX (Contractor) YYY (Consultant) Client


Name
Sign
Date

Page 6 of 6