Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility

(Package-3)

for the five main EPC packages of the project in July.

The EPC packages, the leading contractors for each, along with their
estimated contract values, are as follows:

Package 1 (gas compression plant) – Larsen & Toubro Hydrocarbon


Engineering – $800m
Package 2 (gas processing plant) – Samsung Engineering – $1.5bn
Package 3 (utilities and interconnecting facilities) – Hyundai Engineering
& Construction – $500m
Package 4 (upstream pipelines and wells tie-in) – Saipem – $500m
Package 5 (export pipelines) – L
Aramco receives bids for Jafurah gas project Saudi Aramco has received revised techno-commercial offers from
contractors bidding for the main packages of its estimated $3.5bn
Jafurah unconventional gas development project, according to sources.

Due to the business impact of Covid-19 and low oil and gas prices,
Aramco last year halted development of the Jafurah scheme, for which
it received a capital expenditure grant of $118bn from the Saudi
government in February 2020.

Aramco is understood to have revived the Jafurah development in the


second quarter this year, asking contractors to submit revised techno-
commercial bids for the main packages of the scheme.

Aramco has undertaken the project to build a greenfield plant to process


unconventional gas from the Jafurah onshore field, located in Saudi
Arabia’s Eastern Province. It is to be commissioned in 2023, according
to the original schedule.

Jafurah gas project packages


Package one of the project, which entails installation of gas
compression facilities, is estimated to have a

News and Updates


Published Date Description

13/02/2022 Detailed Engineering works have commenced on the project

29/11/2021 Hyundai Engineering & Construction has been appointed as the main
contractor on the project.
14/11/2021 Hyundai Engineering & Construction has emerged as the lowest bidder
on the project.
(Source: MEED)
03/11/2021 The main contract tender is not yet awarded.

16/09/2021 The main contract bids are under evaluation.

19/07/2021 The following companies have submitted the main contract bids for the
project: Hyundai Engineering & Construction, Saipem, and Samsung
Engineering. Hyundai Engineering & Construction has emerged as the
lowest bidder. (Source: MEED)
08/07/2021 The client has asked the contractors to resubmit the main contract bids
and Samsung Engineering is likely to submit the bids.
16/Feb/2022 10:26:40

Page 2
Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility
(Package-3)

19/05/2021 The client has revived the project and the contractors are seeking for bid
validity extension till the end of September 2021.
12/08/2020 The project is expected to be awarded by December 2020 as the client
has asked the contractor's for bid validity till the end of 2020.
09/04/2020 JV of Hyundai Engineering and Hyundai Engineering & Construction has
been emerged as the preferred bidder and the contract expected to be
awarded by December 2020.
29/01/2020 The bid evaluation is underway and Hyundai E&C has emerged as the
lowest bidders.
22/10/2019 Wood Group is working as the Project Management Consultant (PMC)
and the project is expected to be commissioned by 2023.
30/09/2019 The bid submission has taken place and the following companies have
submitted the bids: Hyundai E&C, Samsung Engineering and Saipem.
05/08/2019 ITB has been issued with the bid submission due on September 30, 2019.
The following are the PQ shortlisted companies: L&T, JGC, Hyundai
E&C, Samsung Engineering, Dragados, Saipem, Technip and GS E&C.
25/07/2019 PQ submission has taken place and the following companies have
submitted the PQ documents: JGC Corporation, L&T Hydrocarbons,
Tecnicas Reunidas, Saipem, McDermott International, Hyundai E&C,
Samsung Engineering, Daragdos, Technip and GS E&C.
30/05/2019 The SOI has been issued and Wood Group is working as the FEED
contractor for the project.

Key project milestones


Published Date Description

15 May 2019 Main Contract Request for Prequalification, EoI

14 Jul 2019 Main Contract Prequalification Submission

30 Jul 2019 Main Contract Prequalification Shortlist

5 Aug 2019 Main Contract Tender Issue (ITB, RFP)

19 Jul 2021 Main Contract Commercial Bid Submission

29 Nov 2021 Main Contract Award

12 Apr 2024 Main Contract Completion, Commissioning

Companies and Contacts


Role Company Contact
Owner Saudi Aramco Project Engineer, Yassir Talal Bakri,Phone:(+966) 13 8720115

FEED Wood Group Project Manager, Ravi Seshadri,Phone:(+966) 13 6685555

PMC Wood Group Project Manager, Ravi Seshadri,Phone:(+966) 13 6685555

Main Contract Bidder Samsung Engineering Phone:(+82) 2 20533000

Main Contract Bidder Hyundai E&C Phone:(+82) 2 21347010

16/Feb/2022 10:26:40

Page 3
Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility
(Package-3)

Main Contract Bidder Saipem Phone:(+39) 02 44231/(+39) 25 2034088

Main Contract PQ GS Engineering & Phone:(+82) 2 7281114


Construction
Main Contract PQ Dragados Phone:(+34) 91 3439300

Main Contract PQ Samsung Engineering Phone:(+82) 2 20533000

Main Contract PQ Hyundai E&C Phone:(+82) 2 21347010

Main Contract PQ Saipem Phone:(+39) 02 44231/(+39) 25 2034088

Main Contract PQ Larsen & Toubro Phone:(+91) 44 22526000

Main Contract PQ Hyundai Engineering Phone:(+82) 22 1668114

Main Contract PQ TechnipFMC Phone:(+33) 147782400

Main Contract PQ JGC Corporation Phone:(+81) 45 682 1111

Main Contractor Hyundai Engineering Phone:(+82) 22 1668114

Potential Bidders(Main Contractors)


Company Name Contact

Samsung Engineering(1) (+82) 2 20533000

Larsen & Toubro(1) (+91) 44 22526000

Hyundai Engineering(1) (+82) 22 1668114

16/Feb/2022 10:26:40

Page 4
Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility
(Package-3)

Estimated Cash Flow


(Quarterly)

Market
Index

Page 5
Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility
(Package-3)

Gas Processing Plant projects in Saudi Arabia


awards

Value of Gas Processing Plant projects in Saudi Arabia


completing

Page 6
Saudi Aramco – COUR: Jafurah: Utilities & Interconnecting Facility
(Package-3)

Breakdown of Gas Processing Plant projects in Saudi Arabia by


status

Breakdown of Gas Processing Plant projects in Saudi Arabia by


status