Professional Documents
Culture Documents
028120-SPL-005 Pipeline Installation Rev. C
028120-SPL-005 Pipeline Installation Rev. C
PROJECT SPECIFICATION
PIPELINE INSTALLATION SPECIFICATION
TABLE OF CONTENTS
Page
1.0 SCOPE 3
2.0 CODES AND COMPANY SPECIFICATIONS............................................................................3
3.0 DEFINITIONS...............................................................................................................................4
4.0 GENERAL REQUIREMENTS......................................................................................................4
5.0 PROCEDURES..............................................................................................................................5
6.0 EQUIPMENT.................................................................................................................................9
7.0 SURVEYS......................................................................................................................................9
8.0 OFFSHORE PIPELAY................................................................................................................10
9.0 RISER/OFFSET FABRICATION................................................................................................12
10.0 RISER/OFFSET INSTALLATION..............................................................................................13
11.0 SHORE APPROACH...................................................................................................................14
12.0 ONSHORE PIPELINE INSTALLATION....................................................................................15
13.0 ALLOWABLE INSTALLATION STRESSES............................................................................20
14.0 DIVING OPERATIONS..............................................................................................................21
15.0 WELDING...................................................................................................................................22
16.0 WELD INSPECTION AND REPAIR..........................................................................................26
17.0 FIELD JOINT COATING............................................................................................................28
18.0 COATING REPAIRS DURING INSTALLATION.....................................................................31
19.0 SPAN RECTIFICATION AND CROSSINGS.............................................................................32
20.0 PIPELINE PRE-COMMISSIONING...........................................................................................33
21.0 CLEAN-UP..................................................................................................................................34
22.0 PAINTING...................................................................................................................................34
23.0 INSPECTION, TESTING AND APPROVAL.............................................................................34
24.0 REPORTING................................................................................................................................34
25.0 GUARANTEE..............................................................................................................................35
Page 2 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
1.0 SCOPE
This Specification covers material, labour, supervision, equipment, inspection and testing for the
installation of subsea and onshore pipelines and risers.
Page 3 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
3.0 DEFINITIONS
The definitions pertinent to this Specification are contained in document number 028120-ACG-
001.
Page 4 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
5.0 PROCEDURES
Prior to mobilization, CONTRACTOR shall update and/or develop in detail the material and
equipment descriptions and specifications; proposed installation methods, planning and scheduling;
and installation procedures for doing the work. This documentation shall be submitted to
COMPANY for approval at least one month prior to mobilization of equipment spreads.
The submissions shall be in the form of manuals which detail assumptions and supporting
calculations. Data shall be sufficient to show compliance with the relevant codes, standards and
Specifications. For documentation provided in the form of computer output, CONTRACTOR shall
furnish descriptions of the output and computer programs.
The documentation is to include the information described below :
5.1 Detailed Drawings
CONTRACTOR shall submit detailed design and shop drawings prior to installation.
Drawings shall be revised and re-issued after construction as part of the as-built data
package.
5.2 Material Descriptions and Certificates
CONTRACTOR shall submit samples of the proposed materials together with the
Manufacturer's relevant technical data and certified test results for COMPANY approval.
CONTRACTOR shall not proceed with the procurement of the proposed materials prior to
obtaining written approval from COMPANY.
5.3 Equipment Specifications and Descriptions
Descriptions and specifications for the complete pipelay spread shall be submitted, including
but not limited to, the following :
All major equipment onboard the pipelay vessel
Plan and profile of the vessel including production ramp layout, pipe shoe layout,
work station locations
Number, capacity, location and control/operating characteristics of tensioners
Type and capacity of abandonment/recovery winch
Number of davits and their location/capacity
Number of anchor winches, size and type of anchors, size and length of anchor
lines
Number and capacity of cranes
Plan and profile of the pipelay stinger, including dimensioned cross-section, pipe
roller support locations, buoyancy characteristics and hydraulic control system (if
applicable)
All other vessels (eg Handling Tugs, Pipe Supply Barges, Diving Vessels,
Survey vessels, Dredging or Excavation Vessels etc) and related equipment
Onshore construction equipment (eg excavators, cranes, pipe handling equipment
etc)
Type and capacity of onshore pullin winch
Onshore Access, Services and Support Facilities (eg access roads, power
supplies, storage areas, temporary accommodation etc)
Welding and radiographic inspection equipment
Field joint coating equipment
Experience resumes of key personnel.
Page 5 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Details of the navigation and positioning system to be used on the pipelay and survey vessel
shall be submitted by CONTRACTOR.
5.4 Installation Planning and Scheduling
Detailed planning and scheduling shall be submitted for the proposed installation of the
pipelines, risers and temporary works including all activities such as procurement, coating,
mobilization, surveying, installation, hydrotesting, and demobilization. This document is to
include details of the proposed installation schedule and sequence of operations for the
installation and testing.
5.5 Installation Procedures
Detailed installation procedures, drawings and associated calculations shall be submitted for
the following operations:
Anchor patterns
Normal subsea pipelay operations
Subsea pipelay start-up and termination
Subsea pipelay abandonment/recovery
Subsea pipelay lift/riser handling for riser setting operations
Subsea pipelay across existing pipelines and cables
Subsea tie-in assembly and installation
Shore approach pipelay and excavation
Suspended pipelay operations
Dredging
Backfilling
Rock dumping
Coral excavation and blasting
Shore pull-in
Onshore pipelay (pipe lowering)
Onshore crossings of existing pipelines, cables, roads and drains
Free span correction
Onshore tie-in installation
Buckle detector specifications and buckle detection procedures
Contingency procedures for dry and wet buckle repair
Anode installation procedures
Survey procedures
Temporary works
The CONTRACTOR shall supply detailed stress analyses, and describe the procedures and
methods to be used to control installation stresses during the operations.
The procedures shall allow for contingency operation in the event of adverse weather,
adverse soil type, equipment breakdown, collisions, accidents and other events outside the
normal installation envelope.
5.6 Welding Requirements
The following shall be submitted :
Welding procedure and repair welding procedure specifications.
Page 6 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 8 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Necessary Approvals, permits, licenses etc from relevant Authorities shall be acquired by
CONTRACTOR before any procurement, transportation, storage and use of explosives.
CONTRACTOR shall employ trained personnel for handling and usage of the explosive
materials.
Before commencement of any blasting activities, CONTRACTOR shall submit the blasting
schedule and type of explosive used including the curriculum vitae of the personnel involved
to COMPANY for approval. Blasting shall only commence once approval is obtained from
COMPANY and all other relevant parties.
A copy of all relevant documents shall be submitted to COMPANY for approval.
5.15 Temporary Works
Temporary works shall be designed and constructed in a safe manner and according to good
engineering practice. The design of all temporary works shall be approved by a suitably
qualified Engineer and supported by appropriate calculations.
Temporary works shall be designed to operate under all anticipated conditions of tidal loads,
water depth, soil type, soil loads, weight loads, installation loads and equipment loads.
6.0 EQUIPMENT
Spares - CONTRACTOR shall provide at the site suitable spares for all equipment, particularly for
hydrotest and radiographic equipment and pigs.
Vessels - Where water borne transportation is to be employed, the vessels, loading and offloading
procedures, and sequence and method of seafastening must be specifically planned and approved
by COMPANY and a Third Party Surveyor acceptable to COMPANY. All vessels used for either
carriage or towage must be classed by an internationally recognized society, have a current loadline
certificate, and be manned and operated in accordance with the Rules of Class and the flag under
which they are registered. The powered vessel's horsepower rating together with supporting
calculations to prove that the vessel is sufficiently powered for the anticipated load shall be
submitted for COMPANY's prior approval, however the available towing horsepower shall be a
minimum of 1500 horsepower. Tugs shall be capable of maintaining a minimum speed of 4 knots
under moderate weather/sea conditions.
Lifting Equipment – All lifting equipment used during construction shall be suitably rated and shall
be supplied with valid certification, for review by COMPANY.
Grouting Spread – if required for span correction the CONTRACTOR shall furnish a complete
grouting spread.
Work Sites – CONTRACTOR shall provide all temporary onshore work sites and access roads
required for construction and installation, including the provision of services and utilities.
CONTRACTOR shall upgrade and maintain any existing unsealed roads used for access.
7.0 SURVEYS
CONTRACTOR shall be solely responsible for the acceptable positioning and position fixing of
the pipelay vessel, survey vessels and other vessels and equipment.
The offshore positioning system shall give continuous and adequate coverage over the entire work
area throughout the duration of the Work. The accuracy of any offshore position fix shall be +15ft
with a repeatability of +7.5ft. CONTRACTOR shall, as a minimum, provide a range system such
that a minimum of 3 range fixing computations are carried out at all times.
Page 9 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Prior to the start of offshore operations, all combinations of ranging positioning equipment
(including spares) shall be calibrated on a suitable onshore baseline of about the same length as the
operational ranges to be used during the Work. No uncalibrated equipment shall be used during any
part of the position fixing operations, and COMPANY shall maintain the right to reject any part of
the Work completed with or any data recorded with uncalibrated equipment. All rejected Work
using uncalibrated equipment shall be repeated immediately after completion of the Work to ensure
that the equipment has remained consistent during the period of installation works.
Onshore positions shall be provided to an accuracy of be +1ft with a repeatability of +0.5ft.
CONTRACTOR shall be responsible for the preparation of all necessary precomputations and
preplotting. During the Work, results of position fixing shall be electronically recorded and
displayed in the form of both printed and plotted results.
The personnel carrying out positioning shall include at least one qualified surveyor acceptable to
COMPANY who shall be available at the location at all times during the execution of the Work.
CONTRACTOR shall survey the pipeline routes prior to the installation of the pipelines to locate
installations (roads, pipeline or cable crossings etc), obstructions (rock outcrops, debris, etc.) or
geographic features (rivers, drains, soil types, sudden contour changes) which may affect the
installation of the pipelines.
Crossed pipelines and cables shall be surveyed within the route corridor with a colour video
camera, acoustic profiler depth recorder, depth of burial pipe tracker and position locating device.
Crossings of third party cables shall be surveyed in accordance with Specification 028120-SPL-010
Subsea Cable Crossing Specification.
In addition to the prelay route survey, a complete hydrographic survey of the offshore sections
shall be made immediately after the pipeline has been laid and prior to flooding the offshore
sections to ensure that there are no spans in excess of the limiting stress values in the hydrostatic
test and operation conditions.
Trenched or dredged sections shall be surveyed both after trenching/dredging and after laying to
demonstrate that the required trenching/dredging depth has been achieved (laying may be
performed before or after trenching/dredging depending on the procedure). The survey shall
include colour video camera, acoustic profiler depth recorder, depth of burial pipe tracker and
position locating device.
Crossings (both the crossing and the crossed pipeline, cable, road or drain) shall be videoed before
and after installation for a distance of 160 ft from the crossing point. Span rectifications shall be
videoed before and after the rectification Works to a distance of 30 ft past each end of the span.
Risers, riser clamps, Wyes and flanges shall be videoed after installation.
A final as-built survey shall be made after all work is complete and shall include the final route,
anode locations, span and crossing positions, configurations and depth of burial, etc. All survey
data shall be included with the as-built data.
CONTRACTOR shall submit results of these surveys to COMPANY immediately on their
completion and shall include the results and reports as part of the as-built data.
Page 10 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
At approaches to platforms, shore crossings , and other subsea pipeline terminus points, the
final position of the pipeline shall be such that the end of the line is positioned accurately
with respect to the relative position of the platform or other terminus. From this point, the
installation tolerance shall increase linearly to + 50 ft at a point 1500 ft from the platform. In
addition, the pipeline shall be placed within + 2° of the planned alignment over the first 500
ft nearest the platform.
Prior to riser setting operations, the pipeline may be temporarily positioned out-of-tolerance
as necessary to allow for clearance as the pipelay vessel lays by an existing structure.
However, the length of line which is temporarily positioned out-of-tolerance shall not be
longer than that which can subsequently be lifted and moved into alignment by the riser
installation vessel. During any such temporary placement, the pipeline shall not be allowed
to cross other existing pipelines in the area.
8.2 Anchoring of Vessels and Barges
CONTRACTOR shall observe any area restrictions or prohibitions regarding anchoring of its
vessels or barges as may be defined by COMPANY prior to or during the installation works.
CONTRACTOR shall at all times monitor and check the anchors for evidence of anchor
dragging and shall immediately take action to correct any such condition. CONTRACTOR
shall keep COMPANY fully informed concerning anchor dragging occurrences and the
action taken to correct such problems.
Where CONTRACTOR requires to deploy its anchors or anchor lines within 3000 ft of any
existing platform, pipelines or other subsea facility, CONTRACTOR shall ensure that all
anchoring is performed such that the anchors are deployed with a minimum clearance of 300
ft of such existing facility and such that the anchor cables do not come in contact with the
existing facility.
If CONTRACTOR requires to deploy an anchor across a pipeline and / or subsea cable, the
anchor shall be deployed with a minimum clearance of 600 ft from the pipeline/cable.
During such anchoring, CONTRACTOR shall take precautions so that no anchor line
contacts the existing pipeline or subsea cable.
During the above instances, CONTRACTOR shall record the position of each anchor, the
manner in which the anchor was handled and moved, and the position of the pipelay vessel
during anchor moves. All such anchor positioning data shall be presented to COMPANY as
part of the as-built pipeline data.
8.3 Pipe Joint Marking and Recording
Sequential joint numbers (a minimum 5" in height) shall be painted on every joint laid. The
numbers shall be painted in the upper quadrant on each side of the joint. CONTRACTOR
shall maintain a continuous record of each pipe joint incorporated into the pipeline and shall
log each joint's identification number, the joint length, weight coating thickness, type of joint
(anode, etc.), and the date when the joint was welded and laid.
8.4 Anode Joints
CONTRACTOR shall install anode joints at the specified interval. Special care shall be
taken by CONTRACTOR to ensure that the electrical bond on anode joints is not damaged
during handling and installation.
8.5 Start-up
CONTRACTOR shall design and fabricate a start-up head. The end of the pipeline shall be
closed with a welded pipe cap prior to pipelay start-up. Holdback cables for start-up shall not
be secured to platforms unless approved by COMPANY. A deadman or other suitable
anchor shall be used for start-up operations.
Page 11 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 13 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Clamps on the risers shall be closed and bolted, but left loose until completion of the
hydrostatic tests. Following completion of the hydrostatic tests and depressurization of the
test medium, all riser clamps shall be tightened in accordance with the drawings. This is to
allow maximum settlement before putting load on the clamps.
10.3 Riser Guards
CONTRACTOR shall remove and reinstall any existing riser guards as necessary to
facilitate riser installation and shall install any new riser guard. Any damage to the jackets,
guards or risers during guard removal and installation shall be repaired by CONTRACTOR
at its expense.
Page 14 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
The pipe specific gravity and backfill shall be engineered to prevent vertical movement of
the pipe through the soil in 100 year storm conditions or due to seismic activity.
The CONTRACTOR shall ensure that the pull-in winch and or tackle blocks have sufficient
tension capacity for the pull-in.
Page 15 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 16 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 17 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Where practicable, the whole of the excavation shall be kept clear of water during
the WORK.
CONTRACTOR shall make available temporary bridging to provide safe
pedestrian and light vehicle access across the trench.
12.5.2 Disposal of Water from Excavations
CONTRACTOR shall submit as part of CONTRACTOR Environmental
Management Plan, detailed proposals with regard to ground water control,
including but not limited to, ground de-watering and stabilisation equipment,
wherever appropriate.
CONTRACTOR shall not discharge anything other than clear water to a
watercourse, running or dry. Discharges containing material in suspension shall
require prior settlement or other treatment to arrest solids and clarify such waters in
order to prevent pollution.
CONTRACTOR shall comply with the requirements of relevant authorities and
shall be responsible for obtaining the necessary consents in respect of the discharge
of effluent as required by such authorities.
The rectification of any damage or nuisance arising from the disposal of water
from the Work shall be the responsibility of CONTRACTOR.
12.6 Crossings
12.6.1 Road Crossings
CONTRACTOR shall inspect and photographically record the condition of every
road affected by the pipeline route before commencing any work. Construction of
each crossing shall be in accordance with CONTRACTOR's procedures, detailed
Drawings and the requirements of other COMPANY contractors.
12.6.2 Crossing Requirement in the Vicinity of Overhead and Underground Services
CONTRACTOR shall obtain contact details for the various authorities and other
COMPANY contractors responsible for overhead and underground services
affected by the Work. Prior to commencing work near any such services,
CONTRACTOR shall submit procedures for working near such services and gain
the written consent of the respective authorities/third party contractors.
12.6.3 Pipe Jack / Auger Bore / Directional Drill Crossings
CONTRACTOR shall submit detailed method statements, design calculations and
Drawings in respect of any proposals to construct any crossing/s using the pipe
jack, auger bore, micro-tunnelling or directional drilling methods.
12.6.4 Watercourses
In the design and construction of watercourse crossings, CONTRACTOR shall
abide by the requirements of all relevant authorities and shall ensure that sufficient
notice of commencement of work is served to enable review and approval by such
authorities. Minimum cover requirements shall be attained as specified in the
CONTRACT documents and Drawings.
12.7 Lowering-In Operations
Prior to commencing pipeline installation CONTRACTOR shall issue to COMPANY for
approval, calculations demonstrating that the pipeline will not be exposed to unacceptable
stress conditions during installation.
Page 18 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Excavated material, selected if necessary, shall be deemed suitable for pipe bedding and
surround if it does not contain particles of sharp stone greater than 10mm in size or any other
hard or unsuitable material. Particles of 10mm size shall not form more than 10% of the
material to be placed.
Prior to lowering the pipeline into the trench, the trench bottom shall be checked to ensure it
is free of rock, sharp projections and other deleterious materials. If required,
CONTRACTOR shall install COMPANY approved bedding material prior to lowering the
pipeline into the trench.
Where practicable, the trench shall be free of water during lowering-in operations. In wet
crossings or where effective de-watering is impractical, as determined by COMPANY,
CONTRACTOR shall demonstrate that the trench is free of rocks, sharp projections and
other deleterious materials and features that could damage the coating.
In such cases, CONTRACTOR shall also demonstrate that the trench bottom is graded to
adequately support the pipe along its entire length. CONTRACTOR shall ensure that the
pipeline is installed in a configuration that does not create overstressing.
Any damage to the pipe coating indicated by holiday detection during the lowering operation
shall be repaired, before lowering-in is completed.
12.8 Backfilling and Reinstatement
12.8.1 General
Backfilling operations shall closely follow pipelaying. CONTRACTOR shall
ensure that “As-Built” survey work is completed prior to backfilling.
CONTRACTOR shall submit a detailed schedule of all roads detailing location,
reference and proposed permanent reinstatement Specification to COMPANY.
12.8.2 Reinstatement of Right-of-way, Roads, Tracks and Hardstandings
Prior to commencing Work, CONTRACTOR shall submit for COMPANY
approval, reinstatement procedures for the pipeline right-of-way, and associated
construction roads, tracks and hardstandings.
All reinstated ground and vegetation shall be completed, consistent with adjacent
soil and vegetation conditions.
12.8.3 Backfilling
Generally where sharp stones greater than 10mm in size or other hard or unsuitable
material is found on the trench bottom and cannot be removed then
CONTRACTOR shall lay a 150mm layer of suitable pipe bedding material,
sourced from a licensed/certified supplier.
Where excavated material cannot be used as agreed by COMPANY, suitable
imported material shall be utilised.
After installation of the pipe suitable fill material shall be placed around the pipe in
300mm layers. Where imported or suitable selected material is used, intimate
backfill shall be placed up to a 150mm layer above the pipe. The remainder of the
backfill shall be placed in layers no greater than 300mm to top of subsoil.
Where selected or imported material is not required, backfill, from trench bottom,
shall be placed in layers no greater than 300mm to top of subsoil.
Page 19 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 20 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Maximum Allowable
Combined Stress
Operation (% of SMYS)
Handling, shipping, storing 85
Page 21 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Not withstanding the allowable stress limitations given in this section, CONTRACTOR shall check
that the combined effects of bending, tension and external hydrostatic pressure during installation
do not subject the pipeline to a local buckling type failure. The local buckling analyses shall be
based on accepted industry methods and shall consider an initial pipe out-of-roundness of 2%.
15.0 WELDING
All welding procedures, welder/welding operator qualifications, welding, weld repair, inspection
and testing shall be in accordance with API 1104 except where modified herein.
No backing rings of any type shall be used. Welding inserts may be employed.
The carbon equivalent for the test material shall be recorded in the welding procedure qualification.
Full penetration butt welds shall be mandatory.
For offshore pipelay, welding procedures shall be conducted using the same equipment and set up
as on the lay barge.
All welding procedures and welder/welding operators shall be qualified using the same or
equivalent equipment proposed to be used during installation.
15.1 Welding Processes
Welding shall be done by any or combination of the following processes :
(a) Shielded Metal Arc Welding (SMAW).
(b) Gas Metal Arc Welding (GMAW), provided sufficient proof of history.
(c) Flux Cored Arc Welding (FCAW) (with or without gas shielding), provided
sufficient proof of history and competence.
(d) Submerged Arc Welding (SAW) for double jointing only.
The use of other welding processes shall require the approval of COMPANY.
The following list of essential variables shall add to and/or modify the essential variables
specified in Paragraphs 2.4 and 9.5 (as applicable) of API 1104 :
Change in Pipe Material (Any change in pipe grade or Manufacturer or any
change in chemical composition or processing by a single Manufacturer)
Change in Position (A change from rolled to fixed or vice versa, a change from
vertical to horizontal or vice versa, change from vertical down to vertical up or vice
versa)
Change in Filler Metal (Any change in size, type or AWS classification including
a change in Manufacturer, even within an AWS classification)
Change in Travel Speed (A change of more than + 25%)
Change in Welding Current
Change in Heat Requirements (Any reduction of minimum, addition, or deletion
of preheat, interpass heat, or post heat temperature)
Decrease in number of root bead and hot pass welding operators.
Page 22 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 24 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Before line-up for welding, all beveled ends shall be carefully cleaned on the site in
order to remove oxide, paint, oil, grease, salts and all foreign material which could
harm the weld quality. The internal and external surfaces of the pipe shall be
cleaned up to a distance of at least 1" from the bevel. Appropriate cleaning tools,
such as metal brushes, grinders, or files shall be used for this purpose.
Immediately prior to the line-up of the pipes, CONTRACTOR shall inspect the
uncoated pipe ends internally and externally for nicks, dents, general damage,
laminations and other surface defects.
Butt welding of unequal thickness pipes shall require tapering of the thicker pipe to
a 1:4 taper or 14° angle to the horizontal plane. This is required only when the
difference in wall thickness exceeds 3/32".
15.5.2 Joint Swabbing
Each joint of pipe shall be swabbed immediately prior to joining with a canvas belt
disc. The disc shall have a steel support at least 3/16" smaller than the nominal
inside diameter of the pipe. Any dirt, mill scale or other foreign substance inside
the pipe shall be removed prior to alignment for welding. In the event that the
support ring will not pass through a joint, that joint shall not be incorporated in the
pipeline and shall be clearly marked as a reject and removed from the work site.
15.5.3 Preheat
In addition to any requirements specified in the welding procedure, systematic
preheating and drying of the steel surface near the weld area shall be done when
the surface is wet. Preheat shall be continuously monitored 3” from bevel edge and
interpass temperature shall be measured at bevel edge.
15.5.4 Alignment and Use of Alignment Clamps
The alignment of abutting ends shall be such as to minimize the offset between
surfaces and to allow for contraction during welding. Nowhere shall the pipe be
sprung into place.
Any misalignment shall be reduced to a minimum by rotation of the pipes to obtain
the best fit or by other approved methods. Cold dressing shall be used in cases of
slight misalignment and any hammering shall be carried out using only a bronze
headed hammer. Hot dressing shall not be used.
Internal line-up clamps shall be used for pipe diameters 8.625" and larger.
External line-up clamps shall be used for pipe diameters less than 8.625", tie-in
welds and flange/fitting connections.
Internal line-up clamps shall not be removed until the root pass is completed unless
authorized otherwise by COMPANY. When an external clamp is used, four equal
length, equally spaced segments of the root bead shall be completed before the
clamp is removed. The accumulative length of the four segments shall not be less
than 60% of the pipe circumference.
15.5.5 Root Bead and Hot Pass
The root bead and hot pass shall be 100% completed in the first welding station.
Pulling on the root bead is strictly prohibited. The hot pass shall be started no later
than 5 minutes after completion of the root bead pass.
The maximum permissible penetration of the root bead into the bore shall be 1/8"
with no localized penetration exceeding 5/32".
Page 25 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
The root pass shall be carried out by a minimum of two welders or welding
operators, working simultaneously and so placed to cause minimum distortion of
the pipe.
15.5.6 Fill Passes
Electrode start and finish points shall be staggered from pass to pass. Power
grinders shall be used to feather starts and stops as well as high points on the weld
bead.
After completion of the third or following passes, welding operations may be
suspended (and the joint allowed to cool down) provided that the thickness of the
weld metal deposited is at least 50% of the pipe wall thickness. Upon restarting,
depending on the material, wall thickness and welding process, preheating to the
full length shall be carried out.
15.5.7 Identification of Welds
Upon completing welding, the welder or welding operator shall mark his/her
identifying number on the top of the pipe using quick drying paint or permanent
marker. Metallic stamping directly on the pipe material shall not be used.
15.6 Weather Conditions
Welding shall not be permitted when weather conditions are unsatisfactory and would impair
the quality of welds. No welding shall be done if, in the opinion of COMPANY, high winds,
rain, or any other conditions are considered of sufficient magnitude to prevent satisfactory
welding. Suitable wind guards shall be provided by CONTRACTOR in windy weather.
Page 26 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 27 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 28 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
The 18" wide tape shall be applied in a continuous layer "cigarette wrap", centering on the
line of weld with a minimum 4" overlap onto itself. The width of tape shall provide full
cover of the exposed steel at the field joint.
For uninsulated pipe, two 4" wide tapes shall then be applied at each extremity of the center
tape, overlapping the latter and the yard applied coating by 2". Each 4" wide tape shall have
a 4" overlap onto itself.
Application of the tape wraps shall be in strict accordance with the Manufacturer's
instructions as well as the following :
Application of wrap shall only be on clean dry surfaces
The separation paper shall be progressively peeled back as the tape is applied
Sufficient hand tension shall be maintained to avoid air pockets, to ensure a
smooth, wrinkle-free application, proper bonding and complete conformability. The
tapes used shall be stored in a cool place to avoid mastic flow and fusion of tape layers.
The tapes held in the store shall be used in rotation.
17.5 Inspection and Repairs of Tapes
The field joint shall be visually inspected for proper surface preparation before the
application of tape and primer. After the tape coating has been applied, it shall be inspected
visually for wrinkles or damage areas.
At the discretion of COMPANY, CONTRACTOR shall inspect the field joint tape using a
spiral type holiday detector. The holiday detector used will be subject to the approval of
COMPANY. The test voltage shall be in accordance with NACE RP-02-74.
All wrinkles, holidays or other tape damage shall be repaired to the satisfaction of
COMPANY. Repair methods and procedures shall be as recommended by the tape
Manufacturer.
Any rejected tape coating shall be removed and the field joint shall be cleaned again before
applying new tape. The new tape shall be inspected.
17.6 Metal Form Installation
After the coating has been inspected and any necessary repairs made, an expendable, precut,
sheet metal form shall be wrapped over the entire field joint area such that it extends 6" back
onto each side of the yard applied concrete coating. The metal form shall be securely banded
in four places. An opening shall be cut at the top of the form for filling with mastic. The
form shall overlap onto itself as least one foot.
17.7 Mastic Application
CONTRACTOR shall supply all equipment necessary to ensure that the mastic mix is
prepared in the correct manner and poured at the desired temperature to prevent voids
forming in the field joint. The end result after application of the field joint mastic material
shall be a continuous coating, completely bonded to the tape coated pipe, to the exposed
corrosion coating areas, and to the two adjacent concrete coatings.
CONTRACTOR shall heat the mastic materials in a remelt kettle equipped with a stirrer to a
pouring temperature of between 365 and 375° F or a temperature recommended otherwise by
the Manufacturer. After the material liquefies, it shall be stirred to ensure suspension of the
aggregate in the mix. Accurate portable thermometers shall be used for checking mastic
temperatures. The material shall not be heated above 400 to 410° F, or the limiting
temperature specified by the Manufacturer. Any material which is overheated shall be
disposed of and a new mix shall be made.
Page 30 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
If it should become necessary to hold the mastic material in the kettle for an extended period
of time, the lid shall be closed, the fire flame shall be lowered and a small amount of asphalt
shall be added to replace asphalt driven off by the continued application of heat. The asphalt
content of the mix shall not exceed 20% by weight.
During filling, CONTRACTOR shall vibrate the form to ensure complete filling and to
eliminate voids or honeycombing within the joint. After filling the molds, the opening shall
be banded shut. The metal form shall not be removed from the field joint. The mastic filled
joint shall not sag more than 1 inch below the line of the adjacent concrete coating.
In the event that time does not permit sufficient cooling of the mastic, water shall be sprayed
over the field joint such that the mastic remains in place during the subsequent pulling of the
pipeline.
17.8 Inspection of Mastic
After the mastic has been applied, the whole wrapped joint shall be inspected. COMPANY
reserves the right to stop any field joint from being lowered into the sea until it has been
inspected and found satisfactory.
Page 31 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 32 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
Page 33 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
19.5 Repair
Any pipeline supports or protective covers which, in the opinion of COMPANY, have not
been installed in accordance with the details specified herein or satisfactorily shall be
rejected and immediately repaired or replaced by CONTRACTOR to the satisfaction of
COMPANY. Repairs or replacements shall be carried out using procedures previously
approved by COMPANY at no additional cost to COMPANY. CONTRACTOR shall keep
COMPANY fully informed throughout the stages of the repair or replacement Work.
21.0 CLEAN-UP
Upon completion of the pipeline installation, CONTRACTOR shall remove all surplus material
from the worksite and shall deliver such material belonging to COMPANY to the points designated
by COMPANY. All salvaged, excess, or waste materials shall be disposed of in a manner
satisfactory to COMPANY.
During installation, CONTRACTOR shall not discard any construction materials, scrap, auxiliary
installation equipment or other objects at any point along the pipeline routes.
Temporary Work Sites, storage yards and Sites on land shall be cleaned-up and the Sites returned
to their original condition. Any temporary obstructions or construction aids placed along the
pipeline route or on the platforms shall be removed at CONTRACTOR's expense unless
COMPANY specifically requests that they be left in place.
CONTRACTOR shall leave all platforms clean and free from all grease, chemicals, etc. from
testing or other operations. CONTRACTOR shall clean and touch-up the platforms, if necessary, to
return all Sites to their original condition.
22.0 PAINTING
Upon satisfactory completion of all testing and inspection, the tie-in weld from the riser to the
topside piping shall be sand blasted and coated with a Zinc/epoxy/urethane coating system as per
Service Area II, in Project Specification 028120-SPM-026, Protective Coating.
Page 34 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
24.0 REPORTING
24.1 Reports
CONTRACTOR shall prepare a daily, weekly and monthly activity reports to submit to
COMPANY for approval in duplicate.
The Daily Report shall include as minimum:
Status of the project.
Time log description of all the activities directly or indirectly affecting pipe
laying operation as well as fabrication and testing.
Time log showing coordinates of the pipelay vessel and anchor locations.
Pipe tally showing joint numbers, mill numbers, pipe section lengths, and
weights, etc.
Surveying and diving inspection results.
Field joint coating, welding inspection and repairs.
Report on gauging pig run (s).
All temperature and pressure charts and tables.
All tables of deadweight tester readings.
Pressure/Volume plots.
Tidal level records.
A full report of all operations carried out during the pigging and testing operation
including a record of all mechanical failures of equipment or pipeline, repairs effected,
and a daily log of events including the locations.
All calculations made to asses the hydrostatic test and associated conclusions.
The appropriate test forms filled out and certified by CONTRACTOR,
COMPANY and MIGAS representatives.
Record of all defects and repairs.
Safety records.
24.2 As-Built Data
CONTRACTOR shall submit to COMPANY all as-built data of the pipelines and risers with
associated offsets and clamps including all other data gathered during CONTRACTOR
operations at the site. The as-built data shall be submitted in the format and with the number
of copies required and contents in accordance with details previously agreed with
COMPANY. As-built data shall be submitted within one month after completion of Work.
CONTRACTOR shall prepare and submit to COMPANY an as-built record which lists all
pipe joint mill numbers, bend identification numbers, flange identification numbers, field
joint coatings, etc. and describes the exact location of these items within the finished Work.
In addition, CONTRACTOR shall supply a scale drawing which clearly indicates the above
information.
25.0 GUARANTEE
Material and/or equipment shall be guaranteed by CONTRACTOR to perform in accordance with
Specification requirements and to be free of defects and poor workmanship including, but not
limited to, those caused by inadequate preparation for shipment, for a period of one (1) year after
material/equipment is placed in service, but not exceeding eighteen (18) months following delivery
to the contracted destination.
Page 35 of 36
028120-SPL-005 Rev C
27-03-2003
CNOOC SOUTH EAST SUMATRA BV
SOUTH EAST SUMATRA (SES) GAS PROJECT
FRONT END ENGINEERING DESIGN
CONTRACTOR shall repair or replace all defective items during the guarantee period at no cost to
COMPANY.
CONTRATOR shall obtain a similar guarantee from Manufacturer or SUPPLIER to warrant the
raw materials provided.
Page 36 of 36
028120-SPL-005 Rev C
27-03-2003