Volume - 3 - Tech Specifications - Package-5 13.09.2021
Volume - 3 - Tech Specifications - Package-5 13.09.2021
AND
BIDDING DOCUMENT
(NATIONAL OPEN COMPETITIVE PROCUREMENT)
Volume -3
Section VII
Part- A & B : Technical Specification
Part- C : MSIP & ESMP Requirements
Section VII Works Requirements (Scope of Work)
Scope of Works
Road, Culverts and Protection Works:
21. Construction of suitable Entry and Exit facility to existing properties: As per site
requirement
22. Construction of suitable Mitigation measures for ongoing construction bridges: As per
site requirement
23 Mitigation Measures at Associated Facilities (At Locations of Construction of Bridges
under CRF Scheme)
Section VII Works Requirements (Project Location Map)
Page 3 of 189
Section VII Works Requirements (Project Location Map)
Page 4 of 189
Section VII Works Requirements (Technical Specifications)
Technical Specification
PART A- STANDARD SPECIFICATIONS
The Standard Specifications comprise "Specifications for Road and Bridge Works (Fifth
Revision, August 2013)”, issued by the Ministry of Shipping, Road Transport & Highways
(MoSRT&H), Government of India and published by the Indian Roads Congress.
Bidder, if does not already possess a copy of the above, may purchase the same from the
Secretary, Indian Road Congress, Jamnagar House, Shahjahan Road, New Delhi, 110 001.
Section VII Works Requirements (Technical Specifications)
Defective Works
All defective works are liable to be demolished, rebuilt and defective materials replaced by
the contractor at his own cost. In the event of such works being accepted by carrying out
repairs etc., as specified by the Engineer, the cost of repairs will be borne by the contractor.
Site Information
The information given hereunder and provided elsewhere in these documents is given in good
faith by the Employer but the Contractor shall satisfy himself regarding all aspects of site
conditions and no claim will be entertained on the plea that the information supplied by the
Employer is erroneous or insufficient.
Section VII Works Requirements (Technical Specifications)
In general, the topography of the road is mountainous. Elevation ranges from 450 metres to
over 6,826 (Reo Purgyil) metres above sea level. The region extends from the Shivalik range
of mountains (barely mountainous region). At 7,026m Reo Purgyil is the highest mountain
peak in the state of Himachal Pradesh. The general physiographic divisions from south to
north are: The outer Himalayas (Shivaliks), The lesser Himalayas (central zone), The Great
Himalayas (northern zone), Zanskar range (shilla Peak-kinnaur, Pangi chamba)
General Climatic Conditions
The maximum average temperature is around 25 degrees C. The temperature varies from a
maximum of 26 degrees C during the summer (July to September) to a minimum of -4
degrees during the coldest winter (January and February).
The normal average annual rainfall in the project area is approximately 1200 mm. Most of it
occurs during the monsoon months of July through September.
Seismic Zone
The works are located in Seismic Zone-IV & V as defined in IRC: 6-2017.
Page 7 of 189
Section VII Works Requirements (Technical Specifications)
Additional Specifications
The additional specifications shall comprise of specifications for particular items of work not
covered in Part – A and Part - B above.
The following Appendices describing additional specifications have been added to the Part –
A, Standard Specifications:
CLAUSE A-1 PLANTATION OF TREES AND HEDGES
CLAUSE A-2 CHUTE DRAIN FOR HIGH EMBANKMENT SECTIONS
CLAUSE A-3 UTILITY DUCTS
CLAUSE A-4 CONTROL BLASTING
CLAUSE A-5 SPECIFICATIONS FOR SCARIFICATION OF EXISTING
PAVEMENT AND PROVIDING OVERLAY WITH GRANULAR
BASE/DBM.
CLAUSE A-6 FILLING OF OPEN WELLS
CLAUSE A-7 WAY SIDE AMENITIES AND TRUCK PARKING SITES
CLAUSE A-8 CURING USING LIQUID MEMBRANE FORMING COMPOUND
CLAUSE A-9 SPECIFICATION FOR GUARD POST
CLAUSE A-10 SPECIFICATION FOR PASSENGER SHELTER
CLAUSE A-11 SPECIFICATION FOR PAINTING OF STRUCTURES WITH
SYNTHETIC ENAMEL
CLAUSE A-12 CONSTRUCTION OF GABION WALL
CLAUSE A-13 CONSTRUCTION OF RE WALL WITH GABION WIRE MESH
SYSTEM
CLAUSE A-14 GROUTED DOWELS FOR SLOPE STABILITY AND PROTECTION
WORKS
CLAUSE A-15 TEMPORARY BARRICADING FOR STOPPAGEW OF CUT
MATERIAL FROM SPREADING ON THE ROAD
CLAUSE A-16 SEISMIC RCC RESTRAINERS
CLAUSE A-17 STREET LIGHTING
CLAUSE A-18 TECHNICAL SPECIFICATIONS FOR ELECTRICAL UTILITY
SHIFTING MATERIALS
CLAUSE A-19 BIO ENGINEERING WORKS
In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC, BIS,
ASTM, AASHTO and BS in that order. Where even these are silent, the construction and
completion of the works shall conform to sound engineering practice as approved by the
Engineer.
Page 8 of 189
Section VII Works Requirements (Technical Specifications)
The Specifications for Electrical Works shall be “Specifications for Electrical Works -
Internal Works (Part -1) and External Works (Part -2), 1994 or latest, published by Central
Public Works Department (CPWD), Government of India
Page 9 of 189
Section VII Works Requirements (Technical Specifications)
Page 10 of 189
Section VII Works Requirements (Technical Specifications)
Page 11 of 189
Section VII Works Requirements (Technical Specifications)
peak in the state of Himachal Pradesh. The general physiographic divisions from south to
north are: The outer Himalayas (Shivaliks), The lesser Himalayas (central zone), The Great
Himalayas (northern zone), Zanskar range (shilla Peak-kinnaur, Pangi chamba)
General Climatic Conditions
The maximum average temperature is around 25 degrees C. The temperature varies from a
maximum of 26 degrees C during the summer (July to September) to a minimum of -4
degrees during the coldest winter (January and February).
The normal average annual rainfall in the project area is approximately 1200 mm. Most of it
occurs during the monsoon months of July through September.
The Project road traverses through the snow bound area.
Seismic Zone
The works are located in Seismic Zone-IV & V as defined in IRC: 6-2017.
Page 12 of 189
Section VII Works Requirements (Technical Specifications)
Additional Specifications
The additional specifications shall comprise of specifications for particular items of work not
covered in Part – A and Part - B above.
The following Appendices describing additional specifications have been added to the Part –
A, Standard Specifications:
CLAUSE A-1 PLANTATION OF TREES AND HEDGES
CLAUSE A-2 CHUTE DRAIN FOR HIGH EMBANKMENT SECTIONS
CLAUSE A-3 UTILITY DUCTS
CLAUSE A-4 CONTROL BLASTING
CLAUSE A-5 SPECIFICATIONS FOR SCARIFICATION OF EXISTING
PAVEMENT AND PROVIDING OVERLAY WITH GRANULAR
BASE/DBM.
CLAUSE A-6 FILLING OF OPEN WELLS
CLAUSE A-7 WAY SIDE AMENITIES AND TRUCK PARKING SITES
CLAUSE A-8 CURING USING LIQUID MEMBRANE FORMING COMPOUND
CLAUSE A-9 SPECIFICATION FOR GUARD POST
CLAUSE A-10 SPECIFICATION FOR PASSENGER SHELTER
CLAUSE A-11 SPECIFICATION FOR PAINTING OF STRUCTURES WITH
SYNTHETIC ENAMEL
CLAUSE A-12 CONSTRUCTION OF GABION WALL
CLAUSE A-13 CONSTRUCTION OF RE WALL WITH GABION WIRE MESH
SYSTEM
CLAUSE A-14 GROUTED DOWELS FOR SLOPE STABILITY AND PROTECTION
WORKS
CLAUSE A-15 TEMPORARY BARRICADING FOR STOPPAGEW OF CUT
MATERIAL FROM SPREADING ON THE ROAD
CLAUSE A-16 SEISMIC RCC RESTRAINERS
CLAUSE A-17 STREET LIGHTING
CLAUSE A-18 ELECTRICAL WORKS
CLAUSE A-19 BIO ENGINEERING WORKS
In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC, BIS,
ASTM, AASHTO and BS in that order. Where even these are silent, the construction and
completion of the works shall conform to sound engineering practice as approved by the
Engineer.
Page 13 of 189
Section VII Works Requirements (Technical Specifications)
The Specifications for Electrical Works shall be “Specifications for Electrical Works -
Internal Works (Part -1) and External Works (Part -2), 1994 or latest, published by Central
Public Works Department (CPWD), Government of India
Page 14 of 189
Section VII Works Requirements (Technical Specifications)
Page 15 of 189
Section VII Works Requirements (Technical Specifications)
Page 16 of 189
Section VII Works Requirements (Technical Specifications)
Page 17 of 189
Section VII Works Requirements (Technical Specifications)
“The quarry charts enclosed with the Tender Documents indicate the
location of quarries and other sources from which naturally occurring
materials are available, for guidance of the Contractor. The Contractor
shall identify quarries; borrow areas and other sources of materials
required for the work. Contractor shall satisfy himself that the required
materials are available in adequate quantities and complying with the
requirements of specifications. No claims shall be entertained on account
of non-availability of materials and increase in leads etc.
It is the sole responsibility of the Contractor to arrange the quarries,
borrow areas etc., on license / lease basis or otherwise, and study in
detail before tendering, the scope of taking the quarry on lease. Advance
information must be collected by the contractor regarding the procedure
laid down and the consequent delay in arranging the quarries on lease
and must make alternative arrangement to procure the quarry products
from lease holders. No separate payment will be made for arranging such
quarries, borrow areas, etc.”
CLAUSE 109 SETTING OUT
Sub-Clause 109.3
Add following Para at end of sub-Clause
The intervals for setting out of centreline as given above is for general
guidance only and the contractor may be required to carry out the setting
out at more closer intervals as deemed fit by the Engineer. The decision
of Engineer in this regards shall be final and binding. No extra payment
claims shall be admissible for this reduced interval.
Sub-Clause 109.8
In 1st sentence, replace”……. having a standard deviation of ± 2mm per
km,……” with ”……. having a standard deviation of ± 1mm per km
double run leveling,……
In 2nd sentence, replace”……. having an accuracy of one second.” with
”……. having an accuracy of 0.5 second.”
CLAUSE 110 PUBLIC UTILITIES
Sub-Clause 110.2
Add following as 2nd paragraph to the sub-clause 10.2
The contractor will not be entitled for any additional compensation for
delay in cutting of trees, shifting of utilities and removal of
encroachments by the service provider/concerned authorities/public
utility bodies.
Sub-Clause 110.4
Page 18 of 189
Section VII Works Requirements (Technical Specifications)
Sub-Clause 110.7
Add following as 2nd paragraph to clause 110.7
The Employer will make payments for cutting trees and shifting of
utilities, wherever required. The contractor shall obtain necessary
approval from such authorities after payments by the Employer and also
in cases where payments are not required to be made for such shifting.
The Employer will also write to all concerned department/service
provider organization for expedite and facilitating cutting of trees,
shifting of utilities and removal of encroachments, etc.
Sub-Clause 110.8
Add following as 2nd paragraph to clause 110.8
Page 19 of 189
Section VII Works Requirements (Technical Specifications)
Page 20 of 189
Section VII Works Requirements (Technical Specifications)
Page 21 of 189
Section VII Works Requirements (Technical Specifications)
“The use of any herbicide or other toxic chemical shall be subject to the
approval of the relevant Authorities and strictly in accordance with the
manufacturer’s instructions. The Engineer will be given at least six (6)
working days notice of the proposed use of any herbicide or toxic
chemical.
A register of all herbicides and other toxic chemicals delivered to the
site, shall be kept and maintained up to date by the Contractor. The
register shall include the trade name, physical properties and
characteristics, chemical ingredients, health and safety information, safe
handling and storage procedures, and emergency and first aid procedures
for the product.”
Sub-Clause 111.8 Environmental Protection
Sub-Clause 111.8.1
Add the following text at the end of 1st Paragraph of Sub-Clause
111.8.1:
Water tankers with suitable sprinkling system shall be deployed along
the haulage roads and in the work sites. Water shall be sprinkled
regularly all along the routes to suppress airborne dusts from
truck/dumper movements particularly on unpaved roads. The sprinkling
shall be carried out minimum twice a day as intstrucuted by the Engineer
to suit site conditions.”
After Sub-Clause 111.8.4 Add the following new Sub-Clauses 111.8.5
to 111.8.8
Sub-Clause 111.8.5
Haulage Roads
Existing roads used for hauling shall be strengthened and/ or widened by
the Contractor in accordance with the requirements for normal and
construction traffic. Where such roads do not exist, the Contactor shall
construct project specific single lane paved roads in settlement areas and
gravel roads in open areas conforming to the Ministry of Shipping, Road
Transport and Highways (MOSRT&H) specifications.
The alignment of the haulage roads shall be fixed to avoid agricultural
land to the extent possible. In unavoidable circumstances, suitable
compensation shall be paid to the people whose land will be temporarily
acquired for the duration of the operations. The compensation shall cover
for loss of income for the duration of temporary acquisition and land
restoration. Prior to the construction of the haul roads, topsoil shall be
stripped and stockpiled for re-use.
Material dumping sites shall be access controlled to prevent the
unauthorized entry of the people, grazing cattle and stray animals.
Page 22 of 189
Section VII Works Requirements (Technical Specifications)
Haulage roads shall be reinstated upon completion of hauling for the use
of local communities.”
Sub-Clause 111.8.6
Equipment and Vehicles used for the Works
Equipments and vehicles deployed for the construction activities shall
not be older than 5 years. Equipments used for road and bridge works
shall be based on new technology and shall generate noise and pollutants
not exceeding the limits specified by the relevant State Authorities.
Vehicles and machineries used for road and bridge works are to be
regularly maintained to conform to the National Air Quality Standards.
Sub-Clause 111.8.7
Noise Control
The Contractor shall consider noise as an environmental constrain in the
planning and execution of the Works.
The Contractor shall take all necessary measures so that the operation of
all mechanical equipment and construction processes on and off the site
shall not cause any unnecessary or excessive noise, taking in to account
applicable environmental requirements. The Contractor shall use all
necessary measures and shall maintains all plant and silencing
equipment in good conditions so as to minimize the noise emission
during construction works.
Any member of the work force likely to be exposed to beyond their
threshold noise levels shall be provided with protective equipment, such
as earplugs, and shall be rotated every four hours.
Construction operations shall be limited to daytime hours only,
particularly in the settlement areas.
Sub-Clause 111.8.8
Vibration Control
The Contractor shall take measures during construction activities to
control the movement of the work force and construction
machinery/equipment, and to avoid/ minimize activities, which produce
vibrations.
Sub-Clause 111.10
Control and Disposal of Wastes
Add the following sentence between 1st and 2nd sentence of Sub-
Clause 111.10
The Discharge Standards promulgated under the Environment protection
Act, 1986, shall be adhered to strictly. All waste arising from the project
Page 23 of 189
Section VII Works Requirements (Technical Specifications)
Page 24 of 189
Section VII Works Requirements (Technical Specifications)
Page 25 of 189
Section VII Works Requirements (Technical Specifications)
Page 26 of 189
Section VII Works Requirements (Technical Specifications)
“The Contractor shall be fully responsible for the adequate safety of all
site operations and methods of construction.”
Add the following paragraph after 4th paragraph of Sub-Clause
“The design and layout of all traffic management devices shall be in
accordance with the roadwork’s drawings, the Traffic Management
Planand as per IRC:SP:55-2014 or as otherwise directed by the
Page 27 of 189
Section VII Works Requirements (Technical Specifications)
Page 28 of 189
Section VII Works Requirements (Technical Specifications)
Any serious work zone safety deficiency by the contractor in the site-
specific traffic management plan approved by the Engineer having failed
to provide in fulfiiling the approved plan in the repair or maintainenance
of existing or temporary roadways, or provide sufficient or appropriate
warning signs, lights, barricades, traffic control, etc. he shall instruct the
Contractor, in writing, to provide required repairs and maintenance and
take such actions as he considers appropriate for protection of traffic,
pedestrians, employees and the works within a specified time. If the
Contractor fails to respond within the time given by the Engineer, the
same shall be treated as “fundamental breach of contract “. and the
Engineer may suspend works which interfere with traffic until such time
as the Contractor provides required repairs and maintenance as the
Engineer has directed, or the Engineer may arrange to provide the
required repairs and maintenance at cost to the Contractor, these costs
being deducted from payment due to the Contractor under the Contract
along with liquidated damages.
If in the opinion of the Engineer the Contractor has failed to properly to
provide and repair or maintain existing or temporary roadways, or
provide sufficient or appropriate warning signs, lights, barricades, traffic
control, etc. he shall instruct the Contractor, in writing, to provide
required repairs and maintenance and take such actions as he considers
appropriate for protection of traffic, pedestrians, employees and the
works. If the Contractor fails to respond within the time given by the
Engineer, the Engineer may suspend works which interfere with traffic
until such time as the Contractor providesrequired repairs and
maintenance as the Engineer has directed, or the Engineer may arrange
to provide the required repairs and maintenance at cost to the Contractor,
these costs being deducted from payment due to the Contractor under the
Contract.
Sub-Clause 112.6 Measurements for payment and rate
Replace the paragraphs in the sub-clause with the following
paragraphs
All arrangement for traffic during construction including temporary
safety barricades, temporary traffic signs, providing traffic safety, flag
mans round the clock and control devices where necessary, temporary
diversions and temporary cross drainage structures, if required, and
construction of treated shoulders for traffic during construction, as
mentioned hereafter, shall be payable separately as per relevant items in
the BOQ if provided, else treat the items as incidental to the works.
Temporary safety barricade shall be measured in linear meter-month.
The contract unit rate for the temporary safety barricade shall be
payment in full for the cost all labour, materials, installation,
maintenance or replacement, shifting of temporary units from one
Page 29 of 189
Section VII Works Requirements (Technical Specifications)
location to other and refilling the temporary holes made in the ground
including removing debris and all other incidentals to complete the work
in all respect. These temporary units shall not be used in any permanent
work in the project.
Temporary traffic signs shall be measured in Number - month. The
contract unit rate for the temporary traffic signs shall be payment in full
for the cost all labour, materials, installation, maintenance or
replacement, shifting of temporary traffic signs from one location to
other and refilling the temporary holes made in the ground including
removing debris and all other incidentals to complete the work in all
respect. These temporary traffic signs shall not be used in any permanent
work in the project.
Traffic safety and control devices shall be measured in Number - month.
The contract unit rate for the traffic safety and control devices shall be
payment in full for the cost of all procurement, installation, maintenance
or replacement, shifting of traffic safety and control devices from one
location to other and all other incidentals to complete the work in all
respect. These traffic safety and control devices shall not be used in any
permanent work in the project.
CLAUSE 113 GENERAL RULES FOR THE MEASUREMENT OF WORKS
FOR PAYMENT
CLAUSE 113.2
Replace the paragraphs in the sub-clause with the following
paragraph
“The rates in the Bill of Quantities are deemed to include the costs of
haulage from the source of supply to the site for all materials required
for the works.”
CLAUSE 113.3 MEASUREMENT OF PAVEMENT THICKNESS FOR
PAYMENT ON VOLUME BASIS
Delete the second sentence of paragraph 5 " The average thickness
of the pavement course…….in writing” and add the following:
“The levels indicated on the Drawings or as modified by the Engineer
are the levels to which the works shall be completed. The average
thickness of pavement course at any section shall be the arithmetic mean
of the difference of levels before construction at all the grid points and
the levels after construction at the same grid points provided that the
actual accomplished levels lie within the tolerances provided in the
specifications. No measurement or payment shall be made for
bituminous mixes laid in excess of the thickness or width shown on the
drawings or specified by the Engineer.”
Add the following new sub-Clause 113.6 after Clause 113.5
Page 30 of 189
Section VII Works Requirements (Technical Specifications)
Page 31 of 189
Section VII Works Requirements (Technical Specifications)
Page 32 of 189
Section VII Works Requirements (Technical Specifications)
Page 33 of 189
Section VII Works Requirements (Technical Specifications)
Page 34 of 189
Section VII Works Requirements (Technical Specifications)
Sub Nos.
S. No Item, Specifications
No. Required
300°C
xvi) Rain Gauge 1 Set
xvii) Timer 0-60 minutes with alarm & 1/5 sec accuracy. 3 Sets
Page 35 of 189
Section VII Works Requirements (Technical Specifications)
Page 36 of 189
Section VII Works Requirements (Technical Specifications)
Page 37 of 189
Section VII Works Requirements (Technical Specifications)
Page 38 of 189
Section VII Works Requirements (Technical Specifications)
· type of equipment
· Identification codes (name and inventory code)
· Manufacturers name
· Year of manufacture
· Proposed assignments on the project
The Engineer shall check the performance and output of each item of
equipment during the Site Trials specified for each construction process
and carried out as specified in Clause 901.16.
Page 39 of 189
Section VII Works Requirements (Technical Specifications)
No separate payment shall be made for any work included in this Clause
and the costs shall be deemed to be included in the rates of the relevant
items entered in the Bill of Quantities.
Clause 123 Added New Clause as Safety Provisions
The Contractor shall, throughout the execution and completion of the
Works and the remedying of defects therein, ensure proper safety
measures including the following:
i) Suitable scaffolds shall be provided for workmen for all work that cannot
safely be done from the ground, or from solid construction except for
such short period work as can be done safely from ladders. When a
ladder is used, an extra labourer shall be engaged for holding the ladder
and if the ladder is used for carrying materials as well, suitable foot-holds
and hand-holds shall be provided on the ladder, which shall be having
inclination not steeper than 1 horizontal to 4 vertical;
ii) Scaffolding or staging more than 3.25 metres above the ground or floor,
swinging or suspended from an overhead support or erected with
stationary support, shall have a guard rail properly attached, bolted, and
otherwise secured at least 1 metre high above the floor or platform of
such scaffolding or staging and extending along the entire length of the
outside and ends thereof with only such openings as may be necessary
for the delivery of materials. Such scaffolding or staging shall be so
fastened as to prevent it from swaying from the support of structure;
vi) All trenches, 1.5 metres or more in depth, shall at all times be supplied
with at least one ladder for each 20 metres in length or fraction thereof.
Ladder shall be extended from bottom of trench to at least 1 metre above
surface of the ground. Sides of a trench which is 1.5 metres or more in
depth shall be stepped back to give suitable slope or securely held by
Page 40 of 189
Section VII Works Requirements (Technical Specifications)
vii) Before any demolition work is commenced and also during the process
of this work, all roads and open areas adjacent to the work site shall
either be closed or suitably protected;
ix) All practical steps shall be taken to prevent danger to persons employed
by the Employer, from risk of fire or explosion, or flooding. No floor,
roof or other part of a building shall be so overloaded with debris or
materials as to render it unsafe;
xiii) Stone breakers shall be provided with protective goggles and protective
clothing and shall be seated at sufficiently safe intervals;
xiv) When workers are employed in sewers and manholes, which are in use,
the Contractor shall ensure that manhole covers are open and manholes
are ventilated for at least one hour before workers are allowed to enter
them. Manholes so open shall be cordoned off with suitable railing and
provide warning signals or boards to prevent accident to public;
xv) Whenever men are employed on the work of lead painting, the following
precautions shall be taken:
- No paint containing lead or lead products shall be used except in
the form of paste or ready made paint;
- Suitable face masks shall be supplied for use by workers when
paint is applied in the form of sprayer or when a surface having
lead paint is to be dry rubbed for removal of the paint;
- Overalls shall be supplied by the Contractor to workmen and
adequate facilities shall be provided to enable workers to wash
during and on close of day’s work;
xvi) Use of hoisting machines and tackle including their attachments,
anchorage and supports shall conform to the following:
a) These shall be of good mechanical construction, sound material
and adequate strength and free from patent defects and shall be
kept in good working order and properly maintained.
b) Every rope used in hoisting or lowering materials or as a means
of suspension shall be of durable quality and adequate strength,
free from defects and inspected daily.
Page 41 of 189
Section VII Works Requirements (Technical Specifications)
Page 42 of 189
Section VII Works Requirements (Technical Specifications)
Page 43 of 189
Section VII Works Requirements (Technical Specifications)
“Removal of stumps & roots of trees of any size girth cut by other
agencies and back filling to required compaction as specified in this
clause shall be considered incidental to the clearing and grubbing
operations and no separate payment shall be made for the same.”
Delete Third and fourth paragraph of sub-clause 201.5
Sub-Clause 201.6 Rates
Sub-Clause 201.6.1 Delete 2nd line and substitute with the following
“These will also include removal of stumps and roots of trees of 300mm
in girth size as well as stumps left over after cutting of any size girth
carried out by other agency, removal of sign boards, hoarding boards,
including their foundations, excavation and back filling to required
density, where necessary, and handling, giving credit toward salvage
value of material removed, stock piling and disposing of the stocked
materials with all lifts and leads.”
CLAUSE 202 DISMANTLING CULVERTS, BRIDGES AND OTHER
STRUCTURES/ PAVEMENTS
Sub-Clause 202.4 Back-filling
After word “operations” in first line add “and wells encountered in
the alignment”.
Add following to end of sub-clause 202.4
“The wells may be capped thereafter if directed by the Engineer”.
Sub-Clause202.5 DisposalofMaterials
Delete the text of Sub-Clause and replace with:
Materials determined by the Engineer as having salvage value shall be
placed in neat stacks of like materials within the Right of Way as
directed by the Engineer with all lifts and leads upto the project road
limits.
All materials obtained from dismantling operations, which, in the
opinion of the Engineer connot be used or auctioned, shall be removed
from the site by the Contractor and disposed off at the nearest tip or
other approved location in accordance with all statutory requirements.
The Engineer may permit the disposal of boulders, concrete fragments
and other incombustible materials by burial within the road reserve,
outside paved area. When buried, the top of these materials shall not be
less than 300mm below finished surface level.
Sub-Clause 202.7 Rates
Add following at the end of this sub clause:
The contract unit rates for various items of rebate shall be on the full
quantities obtained from dismantling.
Page 44 of 189
Section VII Works Requirements (Technical Specifications)
Page 45 of 189
Section VII Works Requirements (Technical Specifications)
Page 46 of 189
Section VII Works Requirements (Technical Specifications)
Page 47 of 189
Section VII Works Requirements (Technical Specifications)
Page 48 of 189
Section VII Works Requirements (Technical Specifications)
Page 49 of 189
Section VII Works Requirements (Technical Specifications)
Para 8 of this Clause given below Table 300-2 shall read as under:
“The contractor shall at least 7 working days before commencement of
construction of embankment and the subgrade; submit the following to
the Engineer for approval:
1) The values of maximum dry density and optimum moisture
content obtained in accordance with IS: 2720 (Part 8) for each fill
material proposed to be used in the construction of embankment
and subgrade.
2) The graphs of Density plotted against moisture content from
which each of the values in (i) above of maximum dry density
and optimum moisture content were determined.
3) The dry density-moisture content-CBR relationships, heavy
compactive efforts conforming to the IS 2720 (part 8) for each of
the fill material proposed to be used in the sub grade.
The above information shall form the basis for compaction only upon its
approval by the Engineer.”
Sub-Clause 305.3 Construction Operations
Sub-Clause 305.3.4 Compacting Ground Supporting Embankment/Sub grade
Para 1 of this clause shall be read as:
“Where necessary the original ground shall be levelled, scarified, mixed
with water and then compacted by rolling to facilitate placement of first
layer of embankment so as to achieve minimum dry density as given in
Table 300-2”.
Add at the end of Para 2
”Backfilling layers in pits, trenches and below the original ground are to
be compacted to the relative natural ground density. The natural ground
density shall be determined by conducting field density tests at three
widely spaced locations along the central line of the proposed additional
carriageway at a depth between 0.5m to 1.0m. Samples of natural ground
Page 50 of 189
Section VII Works Requirements (Technical Specifications)
are collected at each location, and are tested in accordance with IS: 2720
(Part 8). The relative density (i.e. the percentage of the field dry density
to the laboratory maximum dry density) is assessed for each sample, and
the greatest relative density obtained is selected as the “natural ground
density”. If the natural ground density is less than 85% then these are to
be compacted after necessary watering so as to achieve not less than
85% of relative compaction”.
“Where necessary to facilitate compaction of the sub grade to 97%
relative compaction as stated above, a further depth below the sub grade
of maximum thickness of 0.2m shall be loosened, watered and
compacted in accordance with Sub Clause 305.3.5 and 305.3.6 to not
less than 95% of dry density determined in accordance with IS:2720
(Part-8)”.
Sub-Clause 305.3.6 Compaction
The second Para of this Clause shall read as under:
"Vibratory roller of not less than 80-100 KN static weight with plain or
pad foot drum or pneumatic tyre roller of 300 KN weight having tyre
pressure of at least 7 kg/sqcm shall be used for compaction.”
Insert the following sentence before the last sentence of Paragraph 5.
“The co-relation between sand replacement densities and nuclear gauge
densities shall be based on trials with minimum 30 coherent density
measurements”.
Sub-Clause 305.4.6.1 Embankment construction under water:
In 4th Sentence, replace”……. particle size not exceeding 75mm” with
particle size not exceeding 200mm”.
Sub-Clause 305.8 Measurement for Payment
Para 1 shall be read as:
Earthwork in embankment/sub-grade construction shall be measured
separately by taking cross sections at intervals after clearing and
grubbing and if necessary compaction of original ground before the
embankment work starts and after its completion and computing the
volumes of earthwork in cubic metre. For the purpose of calculating the
quantities the contractor shall use the software approved by the
Engineer, the same shall be installed at Engineer’s and employer’s
offices with no additional costs”.
Sub-Clause 305.9 Rates
Sub-Clause 305.9.1
Insert “Unsuitable material including of marshy soil” in Place of Suitable
Material appearing in the second line of item (iii) Add “including
Page 51 of 189
Section VII Works Requirements (Technical Specifications)
Page 52 of 189
Section VII Works Requirements (Technical Specifications)
SECTION400 SUB-BASES,BASES(NONBITUMINOUS)ANDSHOULDERS
CLAUSE401 GRANULARSUBBASE
Sub-Clause 401.1 Scope
Add the following at the end of this Clause:
“A site trail shall be performed using the proposed mix. The trail length
of minimum 60m and for full width of the pavement, shall be outside the
main works. The main work shall not start until the trail length has been
approved by the Engineer. After approval has been given, the material
and mix proportions, construction procedures shall not be changed
without the approval of the Engineer”
Sub-Clause 401.2 Materials
Sub-Clause401.2.1 This Clause shall be read as under:
"The material to be used for the work shall be a crushed stone only as
per the grading required. Only mixed material shall be brought at work
site and in no case mixing of such material at work site shall be
permitted. The material shall be free from organic or other deleterious
constituents and conform to GSB / Drainage layer Grading V of Table
400-1.
CLAUSE 401.2.2 PHYSICAL REQUIREMENTS
Add at the end of this clause as under:
“The Contractor shall, at least 21 working days before the
commencement of the construction of the sub-base course, submit to the
Engineer, the results for approval of the laboratory testing on the
physical properties defined above. The construction of the sub-base
course shall be taken up only upon the Engineer’s approval of the
material.”
Sub-Clause 401.2.3 A new clause shall be added as follows:
Itshallbeensuredpriortoactualexecutionthatthematerialtobeusedinthesub-
basehasaminimumCBRvalueof30%andotherphysicalrequirementswhenc
ompactedandfinished.
WhendirectedbytheEngineer, thisshallbeverifiedeitherby performing
CBR tests
inthelaboratoryorbyconductingDCPtest.TheCBRtestsshallbeconductedon
specimensoakedfor4daysandcompactedto98%ofthemaximumdrydensitya
sperIS:2720(Part8).
CLAUSE 403 CEMENT TREATED SOIL SUB-BASE/BASE
The title of this Clause shall be read as follows:
“CEMENT STABILISED UPPER SUB-BASE”
Page 53 of 189
Section VII Works Requirements (Technical Specifications)
Page 54 of 189
Section VII Works Requirements (Technical Specifications)
and percentage passing 0.425mm Sieve Size) values not more than 25 per
cent, 6 per cent and 90 respectively.
Before mixing with cement, the fraction of material passing 22.4mm sieve
shall have a Laboratory CBR (4-day soak) value of 75 or more, when
tested in accordance with IS: 2720 (Part 16) and samples prepared at 98%
of Maximum Dry Density and Optimum Moisture Content corresponding
to IS: 2720 (Part 8).”
Page 56 of 189
Section VII Works Requirements (Technical Specifications)
Page 57 of 189
Section VII Works Requirements (Technical Specifications)
Page 58 of 189
Section VII Works Requirements (Technical Specifications)
Page 59 of 189
Section VII Works Requirements (Technical Specifications)
After the words “required operations” in second line of this clause, add
the words “except the items of tack coat and prime coat (if any).” The
rate shall include the provision of adequate bitumen in the mix to
provide the characteristics listed in Table 500-7.
CLAUSE 505 DENSE GRADED BITUMINOUS MACADAM
Sub-Clause 505.2.1
Bitumen
Add the following at the end of this para: Paving bitumen of VG 30
Grade shall be Used.
Sub-Clause 505.2.2
Coarse Aggregates
Delete “Crushed Gravel or other hard material” from 1st line of 1st para
and replace with “crushed boulders”.
Replace word “crushed gravel” in para 2 with “crushed boulders”
Add the following at the end of this clause:
“The constituents of the aggregates shall be produced by integrated
crushing and screening plant (Impact or Cone type of capacity
200T/hour) and, unless otherwise instructed by the Engineer, crushing
shall be carried out in at least two stages. The fraction of material
passing through 4.75mm sieve shall also be crusher run screening only.”
Further, at the bottom of the Table 500-8 table add
“Aggregate should satisfy both the tests Los Angles Abrasion Value and
Aggregate Impact Value”
Sub-Clause 505.2.3
Delete the words “or Naturally Occurring Mineral or a Combination of
the two”
appearing in the first sentence of the clause.
Sub-Clause 505.2.4
The first sentence of this clause shall read as “Filler shall consist of
cement as approved by the Engineer”
Sub-Clause 505.2.5
Aggregate Grading and Binder Content Add below as follows
***“The grading of the aggregate mix as used in work shall be a smooth
curve within and approximately parallel to the envelope in Table 500-
10”.
Page 60 of 189
Section VII Works Requirements (Technical Specifications)
Page 61 of 189
Section VII Works Requirements (Technical Specifications)
Page 62 of 189
Section VII Works Requirements (Technical Specifications)
Page 63 of 189
Section VII Works Requirements (Technical Specifications)
Clause 801.4.1 The first and second sentence of clause shall read as follows:
Sign posts shall be of GI pipe 80 mm dia.(Confirming to IS:1239) or as
shown in the drawing. Post shall be embedded in concrete (M-15) for
safeguard against theft. The cost of signpost and its foundation complete
including excavation
& concrete shall be deemed to be included in the rate of signboard.
Page 64 of 189
Section VII Works Requirements (Technical Specifications)
The post below ground shall be painted with three coats of red lead
paint”.
Sub-Clause 802.4.3
Replace “1.5mm” with 2.0mm” in the fourth line.
CLAUSE 803 ROAD MARKINGS
Sub-Clause 803.2 Materials
This clause shall read as under:
“Road markings shall be hot applied thermoplastic compound and the
materials shall meet the requirements as specified in Clause 803.4.
The road markings shall be laid in one layer with appropriate road
marking machine approved by the Engineer. Before the road-marking
machine is used on the permanent works, the satisfactory working of the
machine shall be demonstrated on a suitable site, which is not part of the
permanent works. The rate of application shall be checked and adjusted
as necessary before application on a large scale is commenced, and
thereafter daily."
Sub-Clause 803.3 This clause deleted.
Sub-Clause 803.5 This clause deleted.
Clause 803.6.6 Tolerances
i) General
Road traffic markings shall be constructed to accuracy within the
tolerances given below:
The width of lines and other markings shall not deviate from the
specified width by more than 5%.
The position of lines, letters, figures, arrows and other markings shall not
deviate from the true position specified by more than 20 mm.
The alignment of any edge of a longitudinal line shall not deviate from
the true alignment by more than 10 mm in 15 m.
The length of segments of broken longitudinal lines shall not deviate
from the specified length by more than 150 mm.
In broken lines, the length of segments and the gap between segments
shall be as indicated on the Drawings. If these lengths are altered by the
Engineer, the ratio of the lengths of the painted sections shall remain the
same.
Line and curves, whether broken or unbroken, shall not consist of chords
but shall follow the correct radius.
ii) Faulty Workmanship or Materials
Page 65 of 189
Section VII Works Requirements (Technical Specifications)
a) TriangularObjectMarkershallbe300mmsidewithfourredreflectors,
madeoutof2mmthickaluminiumsheet,facetobefullycoveredbyhigh
intensitygradewhiteretroreflectivesheetingofencapsulatedlenstype
asperclause801.Thebackground/border/symbolsshallbemadebyscr
een-
printingofdesiredcolouraspersigndetails.Thesignplateshallbefixed
with6mmdia.aluminiumrivetsonMSangleironframe.Theangleironf
rameshallbemadewithangleofsize
40mmx40mmx5mm.Thesignshallbefixedwithnut-
bolts&weldingonMSpipe50mmdia(NB-
MW)and500mmhighorasshown inthedrawings.
b) Rectangularhazardmarker600mmx300mmmadeoutof2mmthickal
uminiumsheet,facetobefullycoveredbyhighintensitygradewhiteret
roreflectivesheeting ofencapsulatedlenstype. The
background/border/symbolsshall bemadebyscreen-
printingofdesiredcolouraspersigndetails.Thesignplateshallbefixed
Page 66 of 189
Section VII Works Requirements (Technical Specifications)
with6mmdiaaluminiumrivetsonMSangleironframe.Theangleironf
rameshall bemade withangleof size40mmx40mmx5mm.The
signshall befixedto80mmdia (NB-MW) MSpipe or asshown inthe
drawings.
c) RoadwayIndicatorsshallbe1000mmhighmadewith100mmdia.NB
mediumweight MSpipe.Onereflectorof high
intensitygraderetroreflective
sheetingwithencapsulatedlensshallbeprovidedontopofthereflector.
Thewhite&redreflectorshallbeprovidedalternativelyof40mmwidth
,sothattotalwidthofreflectorshallbe120mm.Awiremeshcoverof150
mmheightshallbeprovidedon top or as shown in the drawings.
d) Allcomponentsofsigns&supportsshallbethoroughlydescaled,clean
ed,primedandpaintedwithtwocoatsofepoxypaint.Thesignbackside
shallbewithgreycolourandpostshallbewhitecolour/alternatewhite
&blackbands.Thepostbelowgroundshall bepainted withthreecoats
ofred lead.
CLAUSE 807 BOUNDARY STONES
Sub-Clause 807.1 Scope
Add at the end of Para 1, “The boundary stones shall be of concrete as
shown in drawing.” The words ‘HPPWD’ or as specified name should be
engraved on each stone appropriately.
CLAUSE 809 TUBULAR STEEL RAILING
Sub-Clause 809.1 Scope
This Clause shall read as under:
“The work shall consist of supplying, fixing and erecting tubular
Galvanized Iron (GI) railing including providing inserts, fixing
arrangement on the crash barrier or at other places as shown in the
drawings and as directed by the Engineer.”
Sub-Clause 809.2
This Clause shall read as under:
“The railing shall be of GI pipe OD 100 mm @ 8.82 kg/m. It shall be
galvanized (zinc coated, 0.22 kg/ sq. metre; minimum single spot)
confirming to relevant IS Codes or as shown in the drawings.”
Sub-Clause 809.5 Rate
The word ‘painting’ shall be replaced with ‘galvanizing’.
Page 67 of 189
Section VII Works Requirements (Technical Specifications)
Page 68 of 189
Section VII Works Requirements (Technical Specifications)
Page 69 of 189
Section VII Works Requirements (Technical Specifications)
Page 70 of 189
Section VII Works Requirements (Technical Specifications)
Page 71 of 189
Section VII Works Requirements (Technical Specifications)
· Any remaining length less than 500m shall be included with the
section immediately preceding it and an average roughness
determined for the total section.
· The roughness count shall be determined by the average of three
replicate test runs. Roughness testing shall be carried out using a
Roughometer at 32 km/hr in accordance with IRC and CRI
guidelines. The Roughometer shall be calibrated against a
MERLIN as outlined in IRC and CRRI guidelines. If the vehicle
is changed the Roughometer shall be re-calibrated with the
newvehicle.
CLAUSE 903 QUALITY CONTROL TESTS DURING CONSTRUCTION
CLAUSE903 QUALITYCONTROLTESTSDURINGCONSTRUCTION
Sub-Clause903.4TestsonBituminousConstructions
AddthefollowingnewSub-Clauses903.4.4&903.4.5
Sub-Clause903.4.4 CharacteristicstobetestedoncompletedBituminousLayers
Thecharacteristicstobetestedoncompletedbituminouslayersare:Relativeco
mpaction Layerthickness
Fortestingtheabovecharacteristics,thefollowingsamplingcriteriashallapply
:
a) RandomSampling
Whentestinganylot,oranisolatedsection,whichisobviouslydefectiveo
rexhibitsabnormalvariationofthecharacteristicsunderconsideration,al
lsamplesshallbetaken ina randompattern.
b) LotSize
Thelotsizeshallnormallybeasectionlaidandcompactedinoneprocessa
ndforwhichessentiallythesame
materialshadbeenused.Whereproductionisonacontinuousbasis,alotsh
allnormallymeanone-
dayproductionandshallnotexceedtwofulldaysproduction.However,th
eEngineerforinvestigatingcompliancewiththespecifications
mayordera lotofanysmallersize, if:
· Thefactorsaffectingthecharacteristicsunderinvestigationexhibitab
normalvariationwithinthenormallotsize
· Thearea isobviously defective orof poorer qualitythat ofthe rest;
· Therateof productionisveryhigh.
Sub-Clause903.4.5 Bituminous mix shall be spread with paver fitted with electronic
sensing device and string line arrangement (supported by steel pegs @
5m apart) on either side of paving width for automatic levelling, surface
evenness and profile control. Use of string line is compulsory to provide
signal to the electronic sensing device fitted with a Paver Finisher”.
Page 72 of 189
Section VII Works Requirements (Technical Specifications)
The finished bituminous layers (DBM and BC) shall be tested for
workmanship (immediately before allowing traffic) by measuring
roughness, longitudinally, separately for each lane with the Calibrated
Towed Fifth Wheel Bump Integrator. Calibration of Bump Integrator
device shall be carried out using the procedure recommended in the
World Bank Technical Publication No. 46. The measured roughness
shall not exceed a value of 2000 mm/km for finished DBM and BC
layers.
Note:Contractorshallarrangethecoreextractionmachineathiscostandshallt
akecoresoftheexecutedbituminousworksjointlywithEngineerwithoutanyext
racost.
Page 73 of 189
Section VII Works Requirements (Technical Specifications)
Page 74 of 189
Section VII Works Requirements (Technical Specifications)
Page 75 of 189
Section VII Works Requirements (Technical Specifications)
Page 76 of 189
Section VII Works Requirements (Technical Specifications)
Page 77 of 189
Section VII Works Requirements (Technical Specifications)
The dosage should be finalized on the basis of field trial and special
mechanical devices should be used for dispensing the admixture in the
batching/mixing plant. No addition of admixture after dosage is
permitted (including addition in transit mixers).
Manufacturer’s experts should be available for consultation/trouble-
shooting of problems associated with their product. The conditions of
storage, shelf life etc., as specified by the manufacturer should be strictly
observed. The manufacturer’s Quality Assurance Plan during process of
production should be obtained and filed for reference/record.
CLAUSE 1014 STORAGE OF MATERIALS
Sub-Clause 1014.3 Aggregates
The following shall be added to this Clause:
"Aggregates shall be stored or stockpiled in such a manner that
segregation of fine and coarse sizes will be avoided and also that the
various sizes will not become intermixed before proportioning. They
shall be stored, stockpiled and handled in such a manner that will
prevent contamination by foreign materials."
CLAUSE1015 TESTS AND STANDARDS OFACCEPTANCE
Add the following as Para 3:
Independent testing of pre-stressing steel shall be carried out by the
Contractor for each consignment from each source at site in the
laboratory approved by the Engineer before use. The tests shall be
carried out for the properties as listed in clause 7.2.1 of BS- 5896:1980.
These tests are in addition to the tests carried out by the Manufacturer.
Page 78 of 189
Section VII Works Requirements (Technical Specifications)
Page 79 of 189
Section VII Works Requirements (Technical Specifications)
Sub-Clause1402 MATERIALS
Replace this clause by following
“Stone to be used, besides quarry stone, shall be obtained by dressing the
boulders of average diameter not less than 300 mm and at least five faces
shall be chiseled. All other materials used in stone masonry shall confirm
to Section 1000 except cement mortar which shall confirm to clause
1304.”
Page 80 of 189
Section VII Works Requirements (Technical Specifications)
CLAUSE1501 DESCRIPTION
The Clause shall read as below.
The Contractor shall prepare a formwork mobilization and utilization
plan and submit the plan for Engineer’s approval at least 28 days before
the commencement of construction of structures. The requirement of
formwork shall be worked out considering the overall construction
program of all the structures to be cast in one or more stages, as
specified in the drawings. The plan shall take into account the time
required for erection of formwork, retention in position, stripping, and
removal and subsequent use in the next and subsequent structures.
Notewithstanding Engineer’s approval of mobilization plan, if due to any
reason, Contractor has to arrange additional formwork, to meet the
requirements of the construction program, it shall be done by the
Contractor without any extra cost to the Employer.
CLAUSE 1502 MATERIALS
This Clause shall read as under:
"All materials shall comply with the requirements of IRC-87.
Material and components used for formwork shall be examined for damage
or excessivedeterioration before use/reuse and shall be used only if found
suitable after necessary repairs.
Only steel formwork shall be used. The steel used for forms shall be of
such thickness that the forms remain true to shape. All bolts should be
countersunk. The use of approved internal steel ties or plastic spacers shall
be permitted.
Structural steel tubes used as support for forms shall have a minimum wall
thickness of 4 mm."
CLAUSE 1503 DESIGN OF FORMWORK
Sub-Clause 1503.1
Add at the end of this Sub-clause “The work of formwork shall not
commence without approval of the Engineer”
Sub-Clause 1503.2
The following shall be added at the end of this Clause:
“For distribution of load and load transfer to the ground through staging, an
appropriately designed base plate must be provided which shall rest on firm
sub-strata”.
Page 81 of 189
Section VII Works Requirements (Technical Specifications)
Page 82 of 189
Section VII Works Requirements (Technical Specifications)
Page 83 of 189
Section VII Works Requirements (Technical Specifications)
Page 84 of 189
Section VII Works Requirements (Technical Specifications)
Page 85 of 189
Section VII Works Requirements (Technical Specifications)
Page 86 of 189
Section VII Works Requirements (Technical Specifications)
Page 87 of 189
Section VII Works Requirements (Technical Specifications)
Page 88 of 189
Section VII Works Requirements (Technical Specifications)
SECTION1800 PRE-STRESSING
CLAUSE1802 GENERAL
Add the following as the last paragraph of this clause:
Prestressing system shall conform to FIP Recommendation
"Recommendations of acceptance of post-tensioning systems", June
1993.
CLAUSE 1803 MATERIALS 562
Add at the end of second paragraph
“The joint between the end of coupler and the duct shall be sealed with
heat shrink tape to prevent penetration of slurry during concreting. The
couplers of adjacent ducts should be staggered at least 300mm apart.”
Couplers and splices shall be larger in diameter than ducts joined.
Strands shall not be placed in the ducts before concreting. The ducts
shall be sealed at the ends by plastic caps to prevent water from entering.
Cables shall be threaded after concreting. In such cases a temporary
tendon shall be inserted in the sheathing, or the sheathing shall be stiff
ended by other suitable method during concreting. The sheathing
supports shall be such as to prevent floatation of empty cable duct during
concreting.
Add the following as additional sub-clause Sub-
CLAUSE 1803.2.3 CORRUGATED HDPE SHEATHING DUCTS
When high-density polyethylene (HDPE) sheathing ducts are specified,
the material for the ducts shall be with more than 2 percent carbon black
to provide resistance to ultraviolet degradation and shall have the
following properties:
Specific Density : 0.954 g/cm3 at 23°C
Yield Stress : 18.0 N/mm2
Tensile Strength : : 21.0 N/mm2
Shore Hardness D-3 sec. 60
:
Value
-15 sec. Value : 58
Notch impact strength at 10 KJ/m2
:
23°C
-40°C : 4 KJ/m2
Coefficient of Thermal
Expansion for 20°C - : 1.50 x 10-4 KJ/m2
80°C
The thickness of the wall shall be 2.3 + 0.3 mm as manufactured and 1.5
mm after loss in the compression test, for duct size upto 160 mm OD.
Page 89 of 189
Section VII Works Requirements (Technical Specifications)
The ducts shall be corrugated on both sides. The ducts shall transmit full
tendon strength from the tendon to the surrounding concrete over a
length not greater than 40 duct diameters.
These ducts shall be joined by adopting any one or more of the following
methods, as convenient to suit the individual requirements of the
location, subject to the satisfactory pressure tests, before adoption.
· Screwed together with male and femalethreads.
· Joining with thick walled HDPE shrink couplers with glue. This
can also be used for connection with trumpet,etc.
· Welding with electro fusion couplers.
The joints shall be able to withstand an internal pressure of 0.5 bar for 5
minutes as per test procedure given in Appendix-1A of IRC: 18 - 2000.
CLAUSE1804 TESTING OF PRESTRESSING STEEL ANDANCHORAGE
Add following Paragraphs to the section.
The frequency of such tests should be as follows:
1. For acceptance of the tendon at the stage of submission of
tendons, the manufacturers certificate together with the data of
previously conducted and most recent test results of "Acceptance
Testing" is acceptable subject to further testing as givenbelow.
2. Acceptance Testing for theworks
a) Static load test for tendon-anchorageassembly
· A series of three tests using the proposed combination of
anchorage systems and the prestressing strand/wire/bars.
All the tests should meet the followingrequirements.
· Residual deformations of anchorage components after the
test should confirm the reliability of the anchorage.
· The increase in the displacements between the anchorage
components as well as between the prestressing steel and
anchorage components should not be disproportionate to
the increase in tendon force.
· The above relative displacements during the 0.8Fpk load
stage should stabilize within the first thirty minutes of the
load duration of 1 hour.
· The mode of failure of tendon should be by the fracture of
the prestressing steel. Failure of the tendon should not be
induced by the failure of anchorage components.
· The measured anchorage efficiency should be: (Refer
CEB/FIP Guidelines for details).
Page 90 of 189
Section VII Works Requirements (Technical Specifications)
Page 91 of 189
Section VII Works Requirements (Technical Specifications)
Page 92 of 189
Section VII Works Requirements (Technical Specifications)
SECTION2000 BEARINGS
Page 93 of 189
Section VII Works Requirements (Technical Specifications)
Sub-Clause2006.1 General
Add “Provisions of IRC83 (Part III) shall be applicable for POT, POT
cum PTFE, PIN and Metallic Guide Bearings”
CLAUSE2009 MEASUREMENTS FORPAYMENT
Add the following after Para 2:
"Tar Paper bearings shall be measured in square meters."
New CLAUSE ADD NEW CLAUSE AS UNDER:
“Tar Paper bearing shall be reinforced bitumen laminated Kraft paper
conforming to IS-1398”.
Page 94 of 189
Section VII Works Requirements (Technical Specifications)
CLAUSE2106 TOLERANCES
Reference to Tolerance shall be made to Clause 1715.
Page 95 of 189
Section VII Works Requirements (Technical Specifications)
SECTION2200 SUB-STRUCTURE
Page 96 of 189
Section VII Works Requirements (Technical Specifications)
Page 97 of 189
Section VII Works Requirements (Technical Specifications)
SECTION2600 EXPANSIONJOINTS
Page 98 of 189
Section VII Works Requirements (Technical Specifications)
Page 99 of 189
Section VII Works Requirements (Technical Specifications)
Stones, brickbats, unsuitable earth and other rubbish, all roots, and
weeds etc. other undesirable growth met with during excavation shall be
separated out and unserviceable material removed from the site as
directed. Useful material, if any, shall be stacked properly and
separately. Good earth in quantities required to replace such discarded
stuff shall be brought and stacked at site by the Contractor, depth not
more than 50cm from ground level. The pit shall be treated for termite
by raking the soil upto 50mm and treated with 5% Aldrin or Chloradang
dust in soil.
The tree hole shall be manured with powdered neem/caster oil cake
along with farm yard manure/dump manure screened through 16mm
sieve and these shall be uniformly mixed with the excavated top soil
after the manure has been broken down to powder (size of particles not
to exceed 6mm in any direction) in equal proportion. A 2m high sapling
of trees shall be placed at the centre of the hole and then the mixture
shall be filled into the hole upto the level of adjoining ground and then
profusely watered to enable the soil to subside. The refilled soil shall
then be dressed evenly with its surface about 50 to 75mm below the
adjoining ground level or as directed by the Engineer.
The planting shall be completed soon after completion of the median.
Circular Mild Steel Tree Guard with Bars
The tree guard shall be 90cm in diameter.
The tree guards shall be formed of (i) 3 Nos. 25 x 25 x 3mm angle iron
verticals 1.95m long excluding splayed outward at lower end upto an
extent of 5 cms, (ii) 3 Nos. 25 x 5mm MS flat rings fixed as per design
(iii) 15 Nos. 1.55m long 6m dia bars. Each ring shall be in two parts in
the ratio of 1:2 and their ends shall be turned in radically for a length of
4cm at which they are bolted together with 8mm dia and 30mm long MS
bolts and nuts.
The vertical iron shall be welded to rings along the circumference with
electric plant 15 Nos. bars shall be welded to rings at equal spacing
along the circumferences of ring. The lower end of the angle iron
verticals shall be splayed outwards upto an extent of 5cm. The lower end
of the flat of lower ring shall be at the height of 1.95m. The middle ring
shall be in the centre of top and lower ring. The bars shall be welded to
the rings as directed by the Engineer. The entire tree guard shall be given
two coats of paint of approved brand and of required shade over a
priming coat of ready mixed primer of approved brand. The design of
the tree guard shall be approved by the Engineer.
3.3 Planting of Hedges
The hedges saplings shall be planted in two rows, one each along each
edge of the median. Bed for the saplings shall be prepared with
The toe wall below ground level shall be of plain cement concrete of M
15 grade to Clause 1700, as shown in the Drawings.
Dumped riprap for erosion protection at ground level, it shall be
constructed as shown in drawing with hard, unweathered and durable
rubble stone of size 150 to 250 mm.
3 Construction Operations
At the locations where the chute drains are to be installed, a rectangular
cut on the side slope of the embankment along the line of the chute drain
shall be made. The Concrete bed with PCC M-10 shall be laid with semi
circle in the middle. The laying & jointing of pipe shall be done with
Cement Mortar 1:3, when concrete in bed is still green. The sloping bed
of the drain shall be to a regular line and suitably compacted to provide a
firm bed.
The water collection arrangement shall be constructed with cement
concrete of grades as shown in drawing at shoulder edge between two
chutes for guiding the surface water into the chute.
The toe wall shall be constructed with PCC M-15 as shown in drawing.
The Rip-Rap/ stone pitching 300mm thick shall be constructed upto 1m
on either side of the drain and at ground level as shown in the drawings.
4. Measurement for Payment
The Chute Drain shall be measured and paid in running metre. The
Contract unit rates specified for Chute drain shall be inclusive of all
leads and lifts for excavations, concreting of pipe bed, placing and
jointing of pipes with Cement Mortar, construction of PCC toe wall, rip-
rap/stone pitching for erosion protection and drainage arrangement
between two Chutes at shoulder edge, etc. for completing the chute
construction.
CLUASE A-3 UTILITY DUCTS
Scope
The work shall consist of laying and jointing of R.C.C. Utility Ducts in
accordance with the requirements of these specifications.
Materials
Reinforced concrete pipes shall be of NP 4 type conforming to IS: 458 as
shown in the drawings.
Laying of Pipes
Laying of Pipes shall be carried out in accordance with clause 2905; the
Pipes shall be fitted and matched so that when laid in work they shall
have a smooth uniform invert.
Jointing
The Pipes shall be jointed either by collar joint or flush joint. Caulking
shall be carried out as directed by the Engineer. The provisions of clause
2906 of the specifications shall be followed to the extent applicable. The
Engineer’s decision shall be final and binding.
Back Filling
Where directed by the Engineer shall be carried out in accordance with
clause 2907 of the specifications.
Closing of Ends
The ends of Pipes shall be closed with plastic covers to prevent ingress
of foreign materials
Measurement of Payments
The utility ducts shall be measured from end to end in linear meter.
Rate
The contract rate for ducts shall include the cost of pipes including
collars and covers, handling and storing of Pipes, laying in positions and
jointing, construction of head wall and inspection chamber, complete
and all incidental works necessary for completion. Excavation including
back filling where necessary shall not be measured and paid separately
and the same shall be included in the rate for Utility Ducts.
CLUASE A-4 CONTROL BLASTING
GENERAL
The specifications for excavation in rock are covered by
MOSRT&H“Specifications for Road & Bridge Works” (4th revision
2001), vide section 300. The following specifications are additional and
supplementary to the same.
CONTROL BLASTING
Whenever required by the Engineer, the rock blasting shall be controlled
so that vibration generated during the blasting do not cause damage to
the building and installation around built up areas. Similarly, the rock
pieces should not fly off the pits and thus damage the buildings and
installation and life and limb of people around. Apart from the general
precautions mentioned in the MOSRT&Hspecifications, following
protective measures and limits for use of explosives are suggested as
guidelines.
PROTECTIIVE MEASURES
a) Short delay blasting with light charges shall be used.
b) The blast hole shall be covered with 0.6 to 1.0 sq.m. Mild steel
plate of minimum 6 mm thickness.
PERSONNEL
Excavation by blasting will be permitted only under the personal
supervision of competent and licensed blasters and trained workmen.
All supervisors and workmen in-charge of preparation, handling, storage
and blasting work shall be adequately insured by the Contractor.
Storage shall be in charge of a very reliable person approved by the
Engineer, who may, if necessary conduct police enquiries as to his
reliability, antecedents etc. The contractor shall have to produce a
security for the person in-charge of the explosives, if and when required
by the Engineer, of the civil authorities of the district.
The Contractor shall make sure that his supervisors and workmen are
fully conversant with all the rules to be observed in storing, handling and
use of the explosives. It shall be ensured that the supervisors in charge
are thoroughly acquainted with the details of the handling of explosives
and blasting operations.
CLUASE A-5 SPECIFICATIONS FOR SCARIFICATION OF EXISTING
PAVEMENT AND PROVIDING OVERLAY WITH GRANULAR
BASE/DBM
Where existing pavement is to be overlayed with a granular base of less
than
500 mm, total thickness shall be scarifies in accordance with Sub-Clause
501.8.3.2. Where the existing pavement contains multiple bituminous
layers, the scarification shall be to the underside of the lowest
bituminous layer. The contractor will verify that all bituminous layers
have been removed using appropriate methods as approved by the
Engineer. The bituminous surfacing material removed from the existing
pavement may be used in other parts of works provided it complies with
the relevant clauses and approved by the Engineer.
After scarification and removal of all the bituminous layers from the
existing pavement to be overlayed, to the full satisfaction of the
Engineer, the existing pavement shall be lightly sprinkled with water, if
necessary, and rolled with three passes of 80-100 kN smooth wheeled
roller. The existing pavement shall then be proof rolled with 8 tonne
single drum vibrating roller in the presence of the Engineer who shall
determine the suitability of the existing pavement for overlay.
After proof rolling, where the overlay includes a sub-base layer of
compacted thickness less than 75mm, the surface prepared for the
overlay shall be lightly tined as directed by the Engineer. No tinning is
required in case compacted thickness of sub-base layer of overlay is
more than 75mm.
Note: (1) Materials for filling of wells of sizes less than 1m in diameter
shall be mixture of natural sand and gravel. (2) The selected materials
(soils and sand-gravel mixtures) shall have MDD (as per IS2720, Part-
8) not less than 16.0 kN/m3. The sand-gravel mix shall be as per sub
clause 2504.
The size of the coarse material in soil shall not exceed 25 mm. In case of
sand-gravel mixtures, the maximum particle size shall not be more than
75 mm. Sand-gravel mixtures with excessive amounts of gravel (>30%)
shall not be permitted.
3. Construction Operations
a) Removal of Obstructing Materials
i. All debris such as pump, metal wires and rods, pipes, any other
equipment, floating materials and logs, degradable and also not
degradable materials that would cause incomplete filling of the
voids shall be removed from the bed of wells so that the selected
fill materials do not slump or settle afterwards. The removal and
disposal shall also cover all plastic materials (e.g. used polythene
bags, pipes etc.), sewage, dead animals, boulders etc. as directed
by the Engineer.
ii. In case of lined open wells, the lining shall be dismantled up to
the level of natural ground level or one metre in height,
whichever is higher.
b) Disinfect Standing Water in Open Wells
i. All open wells with standing water shall be disinfected to kill
microorganisms. This can be accomplished using by adding
chlorine bleach @ 5 litres of chlorine bleach for every 2,500
litres of standing water and as directed by the Engineer.
fans and complete wiring, providing water supply including all pipes,
fittings, tanks, tube well, pumps, valves etc. complete, septic tank, sewer
lines, drains, boundary wall, internal surfaced roads, lawns etc. complete
with specifications as shown in the drawings.
2. Maintenance
The contractor should arrange to maintain the way side amenities, truck
parking sites till the issue of Taking Over Certificate.
3. Measurement
The measurement for construction completion of way side amenities and
truck parking sites with all provisions of furnishing shall be on square
metre of the payable area shown in the drawings.
4. Rate
The Contract unit rate for constructing and providing way side amenities
and truck parking site complex which include cost of all the operations
involved in the construction of the complex connected services, fittings,
furnishing, land scaping, electrical items like wiring, switching, fitting of
lights, fans, fire extinguisher etc. complete, providing water supply and
including all types of necessary fitting of tube-wells, pumps and valves
etc. complete, septic tank, sewer lines, drains furnishing internal road
etc. complete, and as shown in drawings.
CLUASE A-8 CURING USING LIQUID MEMBRANE FORMING COMPOUND
1. General
Liquid membrane forming compound are sometimes permitted to be
used by the engineer for curing concrete for part or whole of the total
curing period as specified in sections dealing with concrete construction.
These membranes reduce the loss of water from concrete during early
hardening period and some type of compounds also help in reducing the
temperature-rise of concrete exposed to the radiation from the sun. These
specifications cover the type and use of such compounds. However, the
use of the same will need specific permission from the engineer, who
may require a number of tests to be carried out for establishing the
conformity of the product to these specifications and to establish that the
curing compound and its method of use does not have any unacceptable
effect on the quality of concrete. The cost of the initial acceptance
testing and the quality control testing will be borne by the owner, if the
method has been specified as a requirement by the engineer. If on the
other hand, it is suggested by the contractor as an alternative to wet-
curing, the full cost of testing will be borne by him and deemed to be
included in his rates for concreting. The cost of curing in any case will
be deemed to be part of the concrete rates and will not be paid extra.
oil bound and shall be approved by the Engineer. There shall be three
white and three black bands alternately placed.
Measurement for payment of posts
The measurement shall be in number.
Rate
The contract unit rate for guard posts shall be paid in full compensation
for furnishing of all labour, materials, tools, equipment for construction,
fixing, painting at site and all other incidental costs necessary to
complete the work to these specifications.
CLAUSE A-10 SPECIFICATION FOR PASSENGER SHELTER
1. Scope
The work consists of providing passenger shelter including seating
arrangement and raised footpath as per drawing.
2. Description
2.1 Passenger Shelter
Passanger shelter shall be construction with basement, loead bearing
walls and RCC roof slab and internal and external paint.
Basement with stone masonry. The basement shall be raised minimum
450mm from ground level.
Walls are load bearing walls with 230mm thick brick masonry walls for
all the shelter upto slab height and above the slab parapet wall shall be
constructed. Roof shall be covered with RCC slab with grade 1:1.5:3 (1
part cement : 1.5 parts sand : 3 parts stone chips) with required
reinforcement and provide outer projection as sajja around the shelter.
It shall have seating arrangement with 50mm thick R.C. slab with mix of
concrete for seating slab and back shall be nominal one with 1:1.5:3 (1
part cement : 1.5 parts sand : 3 parts stone chips) with required
reinforcement and it will be finished with neat cement punning not lass
than 3mm thickness. Entrance steps shall be constructed with neat
cement finishing.
The flooring shall be with 25mm thick I.P.S. flooring (M20) over
100mm thick M-15 grade concrete.
Waterproof treatment shall be done above the RCC roof slab.
The exposed surfaces internal and external of the structure shall be
painted with two coats of cement based water proof paint of make and
brand approved by the Engineer Bus shelter complete as per approved
drawing as directed by the Engineer.
All works shall be done as per Technical Specifications sections 1300,
1700 & 1900 and drawings.
Materials
Wires:
All wires shall be galvanised and PVC coated. The follwing shall be the
diameter of different types of wires.
a) Mesh Wire :- Internal diameter 2.77 mm and external diameter 3.70
mm.
b) Selvedge Wire :- Internal diameter 2.2 mm and external diameter
3.20 mm.
c) Lacing Wire :- Internal diameter 2.2 mm and external diameter 3.20
mm.
Mesh :-
The Mesh of the gabion box be hexagonal in shape with opening size 80
x 100 as shown in the drawings.
Box :-
The box size shall not be larger than 3 m x 1.5 m x 1 m nor smaller than
1m x 1 m x 1 m. Wherever the length of the box is more than 1.5 m
diaphragms are to be provided such that nowhere the continuous length
of the box is more than 1.5 m. Diaphragms shall be manufactured of the
same material as the parent gabion and have selvedge wire through out
their perimeter.
Fabrication
Wire mesh unit shall be manufactured with all components mechanically
connected at the production facility. The external face, reinforcing panel,
and lid of the Wire mesh shall be woven into a single unit. The ends,
back, and diaphragm shall be factory connected to the base. All
perimeter edges of the mesh forming the basket shall be selvedged with
wire having larger diameter
The facing element of a unit is divided into two cells by means of a
diaphragm positioned at approximately 1 m centres. The diaphragm shall
be secured in position to the base so that no additional lacing is
necessary at the job-site.
The procedure for using lacing wire consists of cutting a sufficient
length of wire (+ / - 1.0m), and first looping and / or twisting the lacing
wire to the wire mesh. Proceed to lace with alternating double and single
loops through every mesh opening approximately every 150 mm, pulling
each loop tight and finally securing the end of the lacing wire to the wire
mesh by looping and / or twisting.
Rock Fill
Rock for gabion unit filling shall be angular to round, durable and of
such quality that it shall not disintegrate on exposure to water or
weathering during the life of `the structure. The size of rock shall range
between 250 mm and 400 mm. The range in sizes shall allow variation
of 5% oversize and / or 5% undersize rock provided that it is not placed
on the exposed surface.
Backfill Material
Backfill Material shall be made of a good quality free draining, granular
and / or selected fill. The recommended soil gradation is in the range of
0.02 mm to 6 mm or as indicated by AASHTO T-27 and FHWA Demo
82. Soils outside of this range may be suitable subject to the approval of
the Engineer.
Tests
All following tests on the mesh and lacing wire must be performed prior
to manufacturing the mesh:
i. Wire
a) Tensile Strength: The wire used for manufacturing of Gabion or
equivalent System and the lacing wire shall have a tensile
strength of (38-48 kg / mm2), in accordance with ASTM A 641-
97.
b) Elongation: The test must be carried out on a sample at least 30
cm long. Elongation shall be less than 10% in accordance with
ASTM A 370-92.
c) Zinc coating: Minimum quantities of zinc according to ASTM A
641-97 Class III soft temper coating.
d) Adhesion of Zinc coating: The adhesion of the zinc coating to the
wire shall be such that, when the wire is wrapped six turns
around a mandrel having four times the diameter of the wire, it
does not flake or crack when rubbing it with the bare fingers, in
accordance with ASTM A 641-97.
ii. PVC (Polyvinyl Chloride) coating
a) Specific gravity: 1.30-1.35 kg / m3 in accordance with ASTMD
792 Table 1.
b) Hardness: Between 50 and 60 shore D, according to ASTM D
2240.
c) Tensile strength: not less than 20.6 Mpa according ASTMD 412-
92.
d) Modulus of elasticity: Not less than 18.6 Mpa according to
ASTM D 412-92.
loops through every mesh opening approximately every 150 mm, pulling
each loop tight and finally securing the end of the lacing wire to the wire
mesh by looping and / or twisting.
Tolerances
Wire Zinc coating in accordance with ASTM A641-97 Class III soft
temper coating.
Gabion unit: ± 5% on the length, width, and height Mesh opening
Tolerances on the hexagonal, double twisted wire mesh opening shall
not exceed 16% and 4% on the nominal dimension D values.
Standard Codes
ASTM A 641-97 Specification for Zinc Coated (Galvanized) Carbon
Steel Wire.
ASTM A 370-92 Test Methods and definitions for Mechanical Testing
of Steel Products
ASTM A 90-93 Test Method for Weight (Mass) of Coating on Iron and
Steel Articles with Zinc or Zinc Alloy Coating
ASTM A 313-92 Specification for Chromium- Nickel stainless and Heat
resisting steel springs wire
ASTM A 764-93 Specification for Steel Wire, Carbon, Drawn
Galvanized and Galvanized at size for Mechanical springs
Construction Technique
Assembly
The Gabion units are supplied folded flat and packed in bundles. The
facing section of the units are assembled individually by erecting the
sides, back, ends, and diaphragm, ensuring that all panels are in the
correct position, and the tops of all sides are satisfactorily aligned. The
four corners of the basket shall be connected first, followed by the
internal diaphragm to the outside walls. All connections shall be made
using lacing wire or ring fasteners. The use of ring fasteners shall be
done in accordance with the manufacturer’s recommendations.
Installation
Prior to installing the assembled gabion unit system, the foundation on
which the units are to be placed shall be cut or filled and graded to the
lines and grades shown in the drawings. Surface irregularities, loose
material, and vegetation shall be removed during the preparation of the
foundation.
Filling of Gabion Units
The gabion units or boxes shall be assembled individually by erecting
sides, back, ends and diaphragms, ensuring that all panels are in the
correct position, and the tops of all sides are satisfactorily aligned. The
four corners of the box shall be connected first, followed by the internal
diaphragm to the out side walls. All connections shall be made using
lacing wire.
Prior to installing the assembled units, the foundation on which the
Gabion wall is to be placed shall be cut or filled, compacted and graded
to the lines and grades shown in drawings as per Section 300. Surface
irregularities, loose material and vegetation shall be removed during the
preparation of the foundation.
The gabion units shall be carried to their final position and connected
with adjoining empty units, along the vertical and top edges of their
contact surfaces as per manufacturers recommendations or as directed by
the Engineer. When a structure requires more than one layer of units, the
upper layer shall be connected to the top of the lower layer along the
front and back edges as per manufacturer’s recommendations or as
directed by the Engineer.
Then boxes shall be filled with rock as specified in Clause A-8.3.3
During the filling operation some manual stone placement is required to
minimize voids. For vertical or near vertical structures the exterior of the
box shall be carefully hand placed to give a neat, flat and compact
appearance. Care shall be taken when placing fill material to assure that
the sheathing of the PVC coated box will not be damaged.
The boxes shall be filled in stages so that local deformation may be
avoided. That is, at no time shall any box be filled to a depth exceeding
300 mm higher than that of the adjoining cell. It is also recommended to
slightly overfill the boxes to allow for settlement of the rock.
Internal connecting wires
Internal connecting wires shall be used when a structure requires gabion
unit layers to be stacked on top of each other. Internal Connecting Wires
shall connect the exposed face of a unit to the opposite side of the unit.
An exposed face is any side of a unit that will be exposed or unsupported
after the structure is completed. In this respect, lacing wire shall be used.
Connecting wire shall be installed after filling of each layer of 300 mm
or 250 mm as the case may be.
Placement of the Backfill
Prior to starting this operation a non-woven geotextile filter shall be
placed at the facing section and backfill interface. The characteristics of
the non-woven geotextile shall be as specified by the Engineer. The
geotextile should have a 500 mm return at both top and bottom.
The granular backfill shall be done in lifts of approximately 300 mm.
Compacting is to proceed parallel to the wall, ensuring that the
compacting machine does not within 1000 mm of the rear of the face
section. The homogeneity of the backfill and the level of compaction
required shall be ensured.
Lid Closing
Once the boxes are completely full, the lids shall be pulled tight until the
lid meets the parameter edges of the box. The lid must then be tightly
laced and / or fastened along all edge ends, and tops as shown in
approved drawings.
Measurement for Payment
Gabion walls so constructed shall be measured in cubic metre of finished
work.
Rate
The contract unit rate for the construction of Gabion walls shall be in
cum and cover the cost of excavation or filling for foundation, double
twisted wire mesh, rock filling including transportation, laying, all
labour, testing, technical supervision and all incidentals necessary for
completing the work according to these specifications. The cost also
covers the provision of technical expert advice, design and working
details which shall be arranged by the Contractor. Transportation of rock
fill shall be incidental to the work and shall not be paid extra.
CLAUSE A-13 CONSTRUCTION OF RE WALL WITH GABION WIRE MESH
SYSTEM
This work shall consist of providing and laying factory manufactured
gabion with wire mesh of approved design, filled with approved rock
fill, structural backfill with lids closed all as per design, drawings and
Technical Specifications and as approved by the Engineer.
General
The Contractor shall be required to provide complete design including its
foundation and details engineering with working drawing in required
numbers. This shall be supported by certificate from the supplier of
gabions that he has proven experience in supplying and placing gabions
for major highway projects and providing technical backup using in
house facilities.
Gabion Wire Mesh System being a specialised work, the Contractor
shall ensure expert supervision by specialist from the technology
provider time to time.
The Gabion wall shall be designed with the given specification using
proven system design certified with ISO 9001 / 2 or equivalent as
approved by the Engineer. The designer may adopt system design for
Gabion wall following any proprietary patented technique.
No extra cost either for patent or any design or expert supervision shall
be made to the Contractor.
Glossary
a) Double Twisted Wire Mesh: A non-ravelling mesh made in
mechanically twisting continuous pars of wires through three and
half turn (commonly called double twisted) which are then
interconnected in the adjacent wires to form hexagonal shaped
openings.
b) Mesh Size: The average distance measured at right angles
between twisted sides over meshes.
c) Selvedge wire: Terminal wire used to edge the wire mesh
perpendicular to the double twist by mechanically wrapping the
mesh wires around it at least 2.5 times.
d) Edge wire: Terminal wire used to edge the wire mesh parallel to
the double twist by continuously weaving at mechanically into
the wire mesh.
e) Lacing wire: The Zinc + PVC coated metallic wire which
interconnects empty units, closes and secure stone filled units.
f) Stiffener: A length of Zinc Coated steel wire used for support of
facing by connecting the front panel to the back or side panel of a
gabion or across the corners of gabion cell. Stiffener formed at
the project site is of wire having the same diameter as for the
lacing wire.
g) Geosynthetic: Geosynthetic is a general classification for all
synthetic material used in geotechnical engineering applications.
It includes geotextiles and geonets. The material shall be as per
Section 700.
Materials
Wires: -
All wires shall be galvanised and PVC coated. The following shall be the
diameter of different types of wires.
a) Mesh Wire: - Internal diameter 2.77 mm and external diameter
3.70 mm.
b) Selvedge Wire: - Internal diameter 3.20 mm and external
diameter 4.20 mm.
c) Lacing Wire: Internal diameter 2.2 mm and external diameter
3.20 mm.
d) Stiffener Wire: - Internal diameter 2.2 mm and external
diameter 3.20 mm.
Mesh: -
The Mesh of the box and reinforcing wire mesh panel shall be hexagonal
in shape with opening size 80 x 100 as shown in the drawings.
Box: -
The box size shall not be larger than 3 m x 1.5 m x 1 m nor smaller than
1m x 1 m x 1 m. Wherever the length of the box is more than 1.5 m
diaphragms are to be provided such that nowhere the continuous length
of the box is more than 1.5 m. Diaphragms shall be manufactured of the
same material as the parent gabion and have selvedge wire through out
their perimeter.
Fabrication
Wire mesh unit similar to Gabion unit shall be manufactured with all
components mechanically connected at the production facility. The
external face, reinforcing panel, and lid of the Wire mesh shall be
woven into a single unit. The ends, back, and diaphragm shall be factory
connected to the base. All perimeter edges of the mesh forming the
basket shall be selvedged with wire having larger diameter
The facing element of a unit is divided into two cells by means of a
diaphragm positioned at approximately 1 m centres. The diaphragm shall
be secured in position to the base so that no additional lacing is
necessary at the job-site.
The procedure for using lacing wire consists of cutting a sufficient
length of wire (+ / - 1.0m), and first looping and / or twisting the lacing
wire to the wire mesh. Proceed to lace with alternating double and single
loops through every mesh opening approximately every 150 mm, pulling
each loop tight and finally securing the end of the lacing wire to the wire
mesh by looping and / or twisting.
Rock Fill
Rock for the facing section of a Wire Mesh unit shall be hard, angular to
round, durable and of such quality that it shall not disintegrate on
exposure to water or weathering during the life of the structure. The
rocks shall range between 150 mm and 300 mm. The range in sizes shall
allow for a variation of 5% oversize and/or 5% undersize rock, provided
that it is not placed on the exposed surface. The size shall be such that a
minimum of three layers of rock must be achieved when filling the 1 m
high unit and a minimum of two layers for the 0.6 m high units.
Backfill Material
Backfill Material shall be made of a good quality free draining, granular
and / or selected fill and shall be Mechanically Stabilised. The
recommended soil gradation is in the range of 0.02 mm to 6 mm or as
indicated by AASHTO T-27 and FHWA Demo 82. Soils outside of this
range may be suitable subject to the approval of the Engineer.
Tests
All following tests on the mesh and lacing wire must be performed prior
to manufacturing the mesh:
I. Wire
a) Tensile Strength: The wire used for manufacturing of Gabion or
equivalent System and the lacing wire shall have a tensile
strength of (38-48 kg / mm2), in accordance with ASTM A 641-
97.
b) Elongation: The test must be carried out on a sample at least 30
cm long. Elongation shall be less than 10% in accordance with
ASTM A 370-92.
c) Zinc coating: Minimum quantities of zinc according to ASTM A
641-97 Class III soft temper coating.
d) Adhesion of Zinc coating: The adhesion of the zinc coating to the
wire shall be such that, when the wire is wrapped six turns
around a mandrel having four times the diameter of the wire, it
does not flake or crack when rubbing it with the bare fingers, in
accordance with ASTM A 641-97.
II. PVC (Polyvinyl Chloride) coating
a) Specific gravity: 1.30-1.35 kg / m3 in accordance with ASTMD
792 Table 1.
b) Hardness: Between 50 and 60 shore D, according to ASTM D
2240.
c) Tensile strength: not less than 20.6 Mpa according ASTMD 412-
92.
d) Modulus of elasticity: Not less than 18.6 Mpa according to
ASTM D 412-92.
e) Abrasion resistance: The percentage of the weight loss shall not
be less than 12%, according to ASTM D1242-92.
f) Creeping corrosion: The percentage of corrosion of the wire from
a square cut end shall be less than 25 mm when the specimen has
been measured for 2000 hrs in a 5% solution of HCl
(hydrochloric acid 12 Be)
III. Accelerated aging test
a) Salt spray test: Test period 3,000 hours, test method ASTM
B117-94.
Standard codes
ASTM A 641-97 Specification for Zinc Coated (Galvanized) Carbon
Steel Wire.
ASTM A 370-92 Test Methods and definitions for Mechanical Testing
of Steel Products
ASTM A 90-93 Test Method for Weight (Mass) of Coating on Iron and
Steel Articles with Zinc or Zinc Alloy Coating
ASTM A 313-92 Specification for Chromium- Nickel stainless and Heat
resisting steel springs wire
ASTM A 764-93 Specification for Steel Wire, Carbon, Drawn
Galvanized and Galvanized at size for Mechanical springs
Construction Technique
Assembly
Wire mesh units are supplied folded flat and packed in bundles. The
facing section of the units are assembled individually by erecting the
sides, back, ends, and diaphragm, ensuring that all panels are in the
correct position, and the tops of all sides are satisfactorily aligned. The
four corners of the basket shall be connected first, followed by the
internal diaphragm to the outside walls. All connections shall be made
using lacing wire or ring fasteners.
The use of ring fasteners shall be done in accordance with the
manufacturer’s recommendations.
Following assembly of the facing section the reinforcing panel shall be
unfolded to the required length behind the facing section and the
shipping folds removed. They can be removed by placing the fold over a
2” x 4” (5 cm x 10 cm) steel board and walking along the sides.
Installation
Prior to installing the assembled Wire mesh system units, the
foundation on which the units are to be placed shall be cut or filled and
graded to the lines and grades shown in the drawings. Surface
irregularities, loose material, and vegetation shall be removed during the
preparation of the foundation.
The Wire mesh system units are carried to their final position and
connected with the adjoining empty units along the vertical and top
edges of their contact surfaces using the same connecting procedure(s)
described before. Whenever a structure requires more than one layer of
units, the upper layer shall be connected to the top of the lower layer
along the front and back edges of the contact surface using the same
connecting procedure(s) described before.
High Yield Deformed - Steel having a Yield strength of 460 MPa to 500
MPa, and a Rupture strength of 600 MPa.
Material Property Requirements
Water
As per Appendix – 1800/III (All appendices have references to
MOSRT&H Specifications for Road and Bridge Works)
Cement
As per Appendix – 1800/III
Sand
As per Appendix – 1800/III
Admixtures
As per Appendix – 1800/III
Grout
As per Appendix – 1800/III
Equipment
The following equipment shall be used for the purposes of drilling and
grouting dowels.
Drilling Equipment
Drilling of holes is commonly done by a rotary or rotary percussion
handheld or remotely operated drill equipment. It must be capable of
providing a stable drill hole having dimensions within the permitted
tolerance and which is free of obstructions or major protrusions so that
the bar can be inserted without undue resistance.
Grout mixer and Agitator
As per Appendix – 1800/III
Grout Pump
As per Appendix – 1800/III
Water pump
As per Appendix – 1800/III
Grout Screen
As per Appendix – 1800/III
Connections and air vents
As per Appendix – 1800/III
Construction and Installation Requirements
Drilling
The drill holes for rock dowels are commonly produced by a rotary or
rotary percussion mechanism with air or water used as flushing medium.
The drilling machine or technology employed may be handheld or
remotely operated drill rigs. The diameter of drill hole shall be minimum
25 mm larger than dowel diameter.
Installation of Dowel
The boreholes are cleaned by flushing with compressed air or water. The
dowel is inspected for damages or corrosion, immediately prior to
installation. The dowels of required lengths are inserted into the hole till
it touches the hole end.
Grouting
Grout shall be injected to fill the hole completely. This will be ensured
when the grout of the same consistency comes out of the hole. In case
the length of dowel protrudes from the hole, it shall be covered by
concrete by hand packing.
Measurement for Payment
The quantity to be paid for dowels shall be in linear metre of individual
dowels properly installed and grouted.
Rate
The contract unit rate for the installation of dowels shall include
approval of design and drawings by the Engineer. All excavation works
and the cost of all materials, drilling of holes, transportation, installation
and grouting etc. Any dowel which because of blockage can not serve its
intended purpose shall not be paid for.
CLAUSE 15 TEMPORARY BARRICADING FOR STOPPAGE OF CUT
MATERIAL FROM SPREADING ON THE ROAD
Description
The work shall consist of fabricating, supplying and erecting at site the
Mild Steel Barricading, including painting a coat of steel primer and two
coat of synthetic enamel paint conforming to Additional Technical
Specifications Clause A-7, removing, carriage and re-erecting at other
desired locations the Mild Steel Barricades complete as per Drawings
and as directed by the Engineer. The units shall be kept always in
working conditions. The repair/ replacement of ant member shall be the
responsibility of the contractor.
Materials
The barricading shall be made of M.S. Structural Steel as per the
drawing and approved by the Engineer.
Fabrication
The temporary barricading shall be factory manufactured as per the
drawings.
The work shall conform to the following sections of MOSRT&H
Specifications.
Excavation in foundations Section 300
Structural concrete Section 1700
Structural Steel Section 1900
Fixing at Site
Erection
The Temporary Barricading units shall be erected true to the levels,
grades and verticality. They shall be secured to the foundation by mean
of foundation bolts in cement concrete. The lateral support shall be
provided by the steel anchor stay wires (wherever required) which shall
be fixed to the rock / ground by means of spikes and nails. Various units
shall be jointed together by means of bolts and nuts as shown on the
drawing.
Reuse
The temporary barricades shall be put to reuse wherever required. To do
so, the foundation nuts and spikes of stay wire shall be removed and the
units fixed at the desired location as per Sub-Clause A-15.4.1 above.
Measurements for Payment
The temporary barricades shall be measured in numbers for the new
supply and erection.
The re-erection shall be measured in linear meters.
Salvage Value
The contractor shall take back these temporary barricades in full quantities
after the completion of the project or earlier as per direction of the
Engineer by paying at the rate of 50% of his quoted rate or Rs. 4,500/- per
meter, whichever is more as salvage value to the Employer. Recovery for
the salvage value shall be made in Final Payment certificate. These
temporary units shall not be used in any permanent work in the project.”
Rate
The contract unit rate for supplying the complete barricading unit as per
drawing will include the fabrication, applying a coat of approved steel
primer, two coats of synthetic enamel as per Additional Technical
Specifications Clause A-7, supplying steel stay wires, spikes, nails and
foundations bolts etc.
The contract unit rate for erecting the temporary barricades will include
initial erection, including founding and fixing stay wire etc, removal of
barricading units, spikes and nails, stay wire and cutting foundation bolts
and re-erecting at desired locations in proper foundations with
foundation bolts and stay wires etc. including maintenance and
replacement of damaged parts and bringing the unit to working
conditions to the satisfaction of the Engineer.
ADDITIONAL POINTS
8. The above list is not exhaustive. All works required to complete the system as
per standard code of practice are deemed to be included in the scope of
contractor.
9. Before commencement of the work, the contractor shall submit working
drawing/shop drawings & cable schedules for approval of
consultant/employer. The works has to be carried out on the basis of approved
drawings only.
10. All equipment shall be procured from approved manufacturers only. The
equipment shall meet the requirement of IS codes & all the routine tests
required by the Employer/Consultant are to be carried out by the contractor
without any additional cost.
II. GENERAL SPECIFICATIONS
1. Cable conductor shall be either copper or aluminium stranded and specified as
per drawings. Size and type specified on the drawing and specification shall
not be substituted by any other size/type without prior approval of
Employer/consultant.
2. Cable Accessories
a) Single compression cable gland, heavy duty type nickel plated (coating
thickness not less than 8 to 10 microns) made from Brass consisting of
gland body with hexagonal head, compressor nut, flat check nut,
neoprene rubber seal and a metal washer.
b) Double compression weatherproof cable gland. Same as above and
consisting of gland body nut, gland body, gland nipple, neoprene
rubber seal for outer sheath, rubber washer armour clamping ring,
armouring clamping core check nut, skid washers.
3. Termination of all cables shall be done through cable boxes, brass cable gland
of proper size and a brass Earthing tag.
4. Termination of all single core and multi-core cables shall be done through
tinned copper lugs of proper size and same shall be crimped with the help of
hydraulic crimping machine.
5. Telephone cables and power cables shall not be allowed to run side by side,
but shall be separated to avoid interference due to induction.
7. Brass bolts, nuts and washers shall be used for termination of cables strips on
earth plates, bus bars, breaker terminals.
8. All cables and wiring for power, lighting and control for main LT distribution
panel or feeder pillars to poles/equipments shall be the actual measured length
of cables laid.
11. Loop system shall be adopted for lighting wiring. Joints in wires shall not be
allowed.
12. Each circuit will be controlled by MCB/fuse in the lighting panel. All circuit
and points shall be suitably numbered for identification, which will have to be
approved.
13. Each light outlet or fan or socket shall have an individual separate 5A SP
control switch unless otherwise specified. Group control shall be placed on
the phase wire.
14. Only one twin flexible cord of copper conductor minimum size 23/0076 shall
be attached to a ceiling rose.
15. Single phase socket above 5A rating and small size motor shall be connected
to the power distribution panel.
18. Lighting poles shall be earthed by providing galvanised iron pipe electrode
and 25 x 5 mm GI earth strip as earth conductor.
19. All the metal clad equipment like breakers, panels, capacitor bank enclosure,
switch fuse units, bus bar chambers, DBs, pumps, motors, cable trays and
20. Bare earthing strips/conductors shall not be laid touching the cables.
21. Conduits shall be UPVC conduit concealed in wall ceiling slab. Size of
conduits shall be min. 20 mm dia.
22. The distance between any two earth stations shall be about 3 mtrs.
23. All the light fittings, switch sockets, fans, heaters, geysers, etc. shall be
earthed by earth conductors of the adequate size and through proper tinned
copper lugs.
24. Wherever cables and PVC pipes are run on walls the same shall be supported
on MS cleat and aluminium saddles and out of 25 x 2 mm strips.
25. Distance between two adjoining supports or cleats for cables, PVC pipes, PVC
conduits, PVC casing, trunking and earthing strip shall be between 250-400
mm on straight run and the same shall be reduced on bends or at junctions or
where direction of run is changing.
26. The reinstated area (after excavation and completion of laying any cables,
pipes, etc.) shall be finished at a slightly higher level than the adjoining
undisturbed area. This is to ensure against the subsequent subsidence of
reinstated area underneath.
27. Cleating of cables on walls, inside RCC ducts etc. shall be done by specially
made 25 x 2 mm aluminium saddles GI saddles shall not be allowed.
28. Before commencement of work the contractor shall prepare and submit to the
consultant (for his approval), complete working drawings and cable schedule.
IV. Transformer
General
These shall be basically oil filled outdoor type and suitable for 3 phase, 50 Hz AC
supply of 11/0.433 kV rating.
Oil Filled Transformers
These shall be suitable for outdoor installation. The secondary winding neutral
shall be brought out to a bushing for earthing.
The transformer shall be filled with oil of requisite dielectric strength.
The transformer shall be double wound natural air cooled suitable for outdoor
installation.
The transformer shall be capable of satisfactory operation at its rated output on
normal ratio and at any voltage which does not vary from its rated primary
voltage by more than 5% and at a declared frequency which does not vary by
more than 3%.
Insulation resistance, between phases, phase to earth and between primary and
secondary shall not be less than 5M (five megachms). It shall be the
responsibility of the tenderer to guarantee this value.
The transformer shall be provided with cable box. The cable box shall be
weather, dust and vermin proof and suitable for accommodating PVC sheathed,
PVC insulated aluminium conductor cables.
The transformers shall be (delta) wound on primary and Y (star) wound on secondary.
The neutral point on the secondary side shall be brought out and terminated on to
a bushing within the cable box.
The transformer shall be protected with gang operated air break switches and
drop out fuses mounted on 2 pole structure.
The tenderer shall submit the test certificates for dielectric strength of oil used.
V. Main LT Panel/Distribution Board/Sub-Distribution Boards
These shall receive supply from secondary of transformers through MCCB
incomer & change over switch of suitable capacity depending upon the provision
of standby power.
Moulded Case Circuit Breakers (MCCB) shall be quick make, quick break and
trip free type as per IS:2516.
All Miniature Circuit Breakers (MCB's) used in outgoing circuits shall conform
to IS:8828 having interrupting rating of 9 KA.
The Main LT panel & Distribution boards, shall be in dust & vermin proof tight
sheet steel enclosure, factory assembled and suitable for floor mounting. The
degree of protection offered shall be IP:52 as per IS:2147. The enclosures shall
be reinforced with thicker plates at flange openings and hinges. Each distribution
board shall be provided with gasketed hinged cover.
The board shall be provided with suitable end plates at the top and bottom to
receive conduits, cables.
The enclosures shall be so arranged that on opening, the terminals are readily
accessible and sufficient space shall be left in the interior of enclosure for
accommodation of external conductors from their points of entry into the
enclosures upto the terminals. The terminals shall be of substantial mechanical
construction providing adequate electrical contacts for aluminium conductors.
The rear portion of distribution board shall enclose the three phases and one
neutral bus bar located one below the other in a vertical plane and mounted on
non-hygroscopic insulators. The bus bars shall be adequate and take care of
possible deformations due to effect of temperature, aging or shocks. The bus bars
shall have sufficient mechanical strength to withstand the effect of 9 kA short
circuit for 1 seconds. The surface of the insulating parts shall be designed with
ridges so arranged as to break the continuity of conducting deposit which may
form. The full load rating of any bus bar shall be at least equal to 200A. The
rating of neutral bus bars shall be equal to phase bus bar.
The MCB units shall be secured in such a way as to permit change of position or
removal without difficult or structural alteration.
All live parts of distribution board shall be protected against accidental contact
when cover is opened.
A way label shall be pasted inside the cover of the board with circuit designation
so as to indicate the circuit number and its location to which each breaker is
connected.
The board shall be complete with all necessary self contained inter-connections,
wiring, suitably engraved designation labels and circuit numbers and provided
with two external earthing terminals.
The outgoing connections shall be suitably grouped and run to terminal blocks
mounted either at the bottom or top of the panel board.
Each terminal block, shall comprise of a number connections separated by
insulating barrier.
All hardware required for mounting distribution boards shall also be supplied.
The distribution boards shall generally be fixed on frames grouted in the wall.
Not more than two wires shall be connected to one terminal. There shall be 20%
spare capacity in terminal block.
Sub-distribution boards i.e. MCB DBs shall be factory built ready to use sleek
type with facility for 3 phase incoming & 3 phase/1 phase outgoing of suitable
capacity for lighting & power circuits. These shall have IP:42 protection as per
IS:2147.
Outdoor Feeder Pillar
The outdoor feeder pillar shall be fabricated out of 2 mm thick sheet steel, and
shall be of free standing pedestal mounted pattern, with sloping canopy. The main
frame shall be out of 50 mm x 50 mm x 6 mm MS angle iron. Feeder pillar shall
have heavy duty hinges and the door shall be front open type with provision of
neoprene gaskets. The feeder pillar enclosure shall be provided with pad locking
facility and shall be dust and verminproof, having powder-coated paint finish of
approved colour over two coats of rustproof primer paint, carried out over pickled
antisulphate and anti-rust chemical treatment of the raw sheet steel.
The incoming panel shall be controlled by a 4P MCCB/MCB of suitable rating. 3
nos. phase indication lamps with 2 Amps rewirable fuse shall be provide for
checking healthiness of main supply. Suitable panel illumination circuit with
tumbler switch shall be provided inside the feeder pillar to enable night shift
technicians to attend to the feeder pillar. This lamp shall be connected from a
separate SP MCB outgoing circuit.
Outgoing feeder controls shall be by means of four pole/single pole MCBs, time-
switches and power contactors as detailed in single line diagram. Time over-
riding facility shall be through single pole MCB Isolators. Internal wiring for
time-switches and contactors shall be carried out using 7/18 PVC insulated
copper conductor wires. The bus bar shall be of aluminium and rated for 250/200
Amps. The MCBs and MCB Isolators shall be mounted on DIN channels.
Necessary space shall be provided at the bottom of the feeder pillar to allow
glanding and terminations of incoming feeder cable and outgoing feeder cables.
Necessary number of knock outs shall be provided at the bottom gland plate for
incoming and outgoing feeder cables as per details in single line diagram. The
cable alley shall have adequate working space. The removable cover and gland
plate of the cable alley shall be duly gasketed and fitted using minimum 8 mm
size nuts and bolts. Steel screws are not permissible for the purpose. Adequate
louvres shall be provided in the feeder pillar to enable natural ventilation. An
earth bus bar of adequate cross section with pre-drilled holes shall be provided
inside and two earthing studs shall be provided outside the feeder pillar.
Necessary danger boards shall be fixed on the front and back covers of the feeder
pillar.
The feeder pillar shall in general conform to IS : 5039 - 1969.
General arrangement drawings together with wiring data and makes and complete
technical data of components of the feeder pillar shall be submitted by the bidder
for approval before manufacturing the feeder pillar. Fabrication and assembly of
the feeder pillar shall be taken up only after obtaining approval of the drawing
from the purchaser.
Road Lighting System
GI Street/Road Lighting Poles
Poles shall be fabricated out of MS tubular steel stepped and swaged with a
welded MS base plate. The entire pole shall be hot dip galvanised. The poles
shall be installed in the following manner:-
1. Grouted in 1:2:4 concrete foundation 450 mm dia and 1 .8m height (300mm
projecting above the finished ground). The base plate shall be
300mmx300mmx10mm thick.
2. Grouted in the curb barrier upto a depth of 900 to 1000mm, the base plate
shall be 10 mm thick 250 mm diameter.
5. Cable termination strip of copper 50A capacity with looping in and looping
out facility.
8. Side arms (one or two) for fixing on the top of the pole with 3 nos. 12 mm
tapped Allen Grub screws. The arms shall be 1.5m long, spaced at an angle of
15° and terminate into a spigot of 40/60 mm dia to match the luminaire.
9. 3 core 2.5 sq.mm flexible stranded copper conductor unarmoured cable from
junction box to the terminal of luminaire.
10. GI pipe sleeves 38mm dia for incoming and outgoing cable shall be installed.
11. 25 mm dia GI pipe 300 m long for enclosing 8 SWG GI conductor required
for earthing the lighting pole shall be installed.
12. 38 mm dia GI pipe 1.20 mtr. long with perforated holes shall be installed for
earthing each lighting pole. For details refer to details of Pipe Type Earthing
Electrode under the heading of "Earthing".
13. 8 SWG GI wire about 3 mtr. long shall be used to connect the Pipe type earth
electrode to the lighting pole, earthing stud and to JB of cables.
Junction Boxes
The Junction Box for mounting on street light or general area lighting poles shall
be fabricated out of 3 mm thick sheet steel, and shall have powder coated paint
finish of approved colour over two coats of rust proof primer paint, carried out
over pickled anti-sulphate and anti-rust chemical treatment of the raw sheet steel.
The junction boxes shall be dust and vermin proof and provided with neoprene
gaskets. The front of the junction box shall open upwards, by means of heavy
duty hinges provided on the top edge. The bottom of the front cover shall have
two numbers key-operated locking arrangements. Provisions inside the junction
box shall comprise of 8 way ELMEX type 20 Amps terminal block, insulator
mounted 4 way neutral link rated 32 Amps, earthing terminal and rear side hole
(to let in luminaire wiring inside the pole) and 1 no. 6 Amps HRC fuse base and
fuse link for every luminaire. Earthing bolts shall be provided on the exterior of
the junction box as well. The bottom of the junction box shall have 2 nos knock-
outs to facilitate glanding of aluminium conductor PVC insulated armoured
cables. 2 Nos 32 mm x 6 mm thick MS plates shall be welded on the rear side of
the junction box to the complete width of the box and projecting 75 mm on either
side to take the pair of semi-circular clamps for the purpose made out of 32 mm x
6 mm flats. The clamps and the flats welded on the junction box shall be
assembled on the pole using 8 mm dia fine threaded bolts and nuts, together with
a set of flat and spring washers. Necessary holes shall be provided on the pair of
semi-circular clamps and the 32 x 6 mm flats of the junction box to suit the
diameter of the pole. The rear side of the junction box shall be provided with 13
mm bore to allow entry for wiring from the junction box to the luminaire on pole
top. The junction box shall be at a height of 300 mm above finished road level.
Detailed drawings shall be submitted for purchaser's approval before taking up
the manufacture of the junction box. Manufacture of boxes shall be taken up only
after the drawings are approved. Prior to mass manufacture, one sample set of
box and clamps shall have to be got approved by the purchaser.
Lighting Luminaries
Scope
This specification covers the design, material specification, manufacture, testing,
inspection and delivery to site and installation & commissioning of lighting
luminaries and their associated accessories.
Standards
The lighting fittings and their associated accessories such as lamps/tubes,
reflectors, housings, ballasts, etc. shall comply with the latest applicable standards
as specified. Where no standards are available, the supply items shall be backed
by test results, shall be of good quality and workmanship & any supply items
which are bought out by the VENDOR shall be procured from approved
manufacturers acceptable to the PURCHASER/ENGINEER.
Lighting Fittings - General Requirements
Fittings shall be designed for continuous trouble free operation under atmospheric
conditions as applicable in site without reduction in lamp life or without
deterioration of materials and internal wiring. Outdoor fittings shall be weather-
proof and rain-proof type and also suitable for use in dusty & vapour prevalent
atmosphere confirming to IP:65 degree of protection.
The fittings shall be designed so as to facilitate easy maintenance, including
cleaning, replacement of lamps/starters etc.
Connections between different components shall be made in such a way that they
will not work loose by small vibration.
For each type of lighting fitting the VENDOR shall supply the utilization factor
to indicate the proportion of the light emitted by the bare lamps which falls on the
working plane.
All fittings shall be supplied complete with lamps suitable for operation on a
supply voltage and the variation in supply voltage.
The fittings and accessories shall be designed to have low temperature rise. The
temperature rise above the ambient temperature shall be as indicated in the
relevant standards.
All LED lamp fittings have die-cast aluminium housing and shall be complete
with accessories like lamps, ballasts, power factor improvement capacitors,
starters wherever applicable, etc. These shall be mounted as far as possible in the
fitting assembly only. If these cannot be accommodated inside, then a separate
metal enclosed box shall be included to accommodate the accessories and in
addition with a fuse and a terminal block suitable for loop-in, loop-out
connections. Outdoor type fittings shall be provided with outdoor type weather-
proof box.
All fluorescent lamp fittings shall be complete with all accessories like ballasts,
power factor improvement capacitors, lamps, starters and capacitors for
correction of stroboscopic effect.
Each fitting shall have a terminal block suitable for loop-in, loop-out and T-off
connection by 650/1100V, 3 core , PVC insulated Copper conductor cable of 2.5
sq.mm in size. The internal wiring should be completed by the
MANUFACTURER by means of stranded copper wire and terminated on the
terminal block.
The mounting facility and conduit knock-outs for the fixtures shall be as
specified.
All hardware used in the luminaire shall be suitably plated or anodized and
passivated for use in chemical industrial and power plants.
Earthing
Each lighting fitting shall be provided with an earthing terminal suitable for
connection to the earthing conductor.
All metal or metal enclosed parts of the housing shall be bonded and connected to
the earthing terminal so as to ensure satisfactory earthing continuity throughout
the fixture.
Painting/Finish
All surfaces of the fittings shall be thoroughly cleaned and degreased. The fittings
shall be free from scale, rust, sharp edges and burrs.
Wherever enamel finish is specified, it shall have a minimum thickness of 2 mils
for outside surface and 1.5 mils for inside surface. The finish shall be non-porous
and free from blemishes, blisters and fading.
The housing shall be stove-enameled/epoxy stove-enameled-vitreous enameled or
anodized as indicated on flame-proof fittings is prohibited.
The surface shall be scratch resistant and shall show no sign of cracking or
flaking when bent through 90o over ½" dia mandrel.
The finish of the fittings shall be such that no bright spots are produced either by
direct light source or by reflection.
Decorative Type Fluorescent Fixtures
Decorative fluorescent fittings shall be provided with mounting/housing channel
cum reflectors of CRCA sheet steel, stove enameled.
Diffusers or louvres shall be provided as required. Diffusers shall be of
translucent white opal acrylic or depending upon the type of fitting.
Fittings shall be suitable for the number of lamps of specified wattage, for
directly mounting on ceiling/conduit suspended or for recess mounting in false
ceiling, as specified.
Fluorescent lamps to be mounted in the false ceiling so as to form a continuous
luminous ceiling, shall have an inside reflector of non-fluorescent power
occupying 2/3 of inner surface of the tube so that the lamp radiates light mainly in
the direction determined by the position of the reflective material.
Incandescent Fixtures
Decorative incandescent fittings when required shall be suitable for 60/100/150W
lamp, suspended or recess mounting in false ceiling. The fitting for recess
mounting shall be provided with copper anodized finished cylinder, ceiling
mounting ring and translucent acrylic crystal ring.
Industrial Type Fittings
1. These fittings shall be suitable for use with LED lamps as per requirements
and generally as described below.
2. For general industrial use in humid atmosphere, the fittings shall be provided
with CRCA sheet steel mounting/housing channel vitreous enameled and with
vitreous enameled reflector of minimum 20 SWG thickness.
3. For dusty and vapour prevalent atmosphere, the fittings shall be dust and drip
proof type, totally enclosed in sheet steel housing with a heat resistant
toughened glass cover or clear acrylic sheet. The bousing shall be epoxy
stove-enameled and neoprene gaskets shall be provided for sealing.
5. The angle of cut-off for fittings with filament lamp shall not exceed 70o and
that for fittings with fluorescent tubes shall not exceed 79o.
6. The distribution of light shall be such that at least 80% of the total luminous
flux from the fitting shall be in the lower hemi-sphere.
7. Fittings shall be suitable for the number of lamps of specified wattage, for
directly mounting on ceiling/wall and or conduit suspended.
Bulkhead Fittings
Bulkhead, weather-proof type fittings for use in corridors, staircase landings,
covered porches and low ceiling factories, shall be suitable for direct fixing to
wall/ceiling and to accommodate upto 150 watts incandescent lamp. The fitting
shall be provided with housing of cast aluminium alloy with stove enameled
finish, prismatic heat resistant glass cover hinged on to the housing and fixed by
screws. Neoprene gaskets shall be provided to make the fitting weather-proof.
For mechanical protection to glass cover, a protective wire-guard of 3 mm
galvanized wire with stove enameled finish paint shall be provided.
Street Light Fittings
The luminaire shall be HPSV type, highly efficient, pot mirror system housed in
die-cast aluminium housing.
Accessories for Lighting Fittings
Reflectors
The reflectors shall be made of CRCA sheet steel/aluminium/silvered
glass/chromium plated sheet copper as indicated for above mentioned fittings,
unless otherwise specified.
The thickness of steel/aluminium shall comply with relevant standards specified.
Reflectors made of steel shall have stove enameled/vitreous enameled/epoxy
coating finish. Aluminium used for reflectors shall be anodized/epoxy stove
enameled/mirror polished. The finish for the reflector shall be as indicated for
above mentioned fittings.
Aluminium paint on the reflectors of flame-proof lighting fittings is prohibited.
Reflectors shall be free from scratches or blisters and shall have a smooth and
glossy surface having an optimum light reflection coefficient such as to ensure
the overall light output specified by the MANUFACTURER.
Reflectors shall be readily removable from the housing for cleaning and
maintenance without disturbing the lamps and without the use of tools. They
shall be securely fixed to the housing by means of positive fastening device of
captive type.
Lamp/Starter Holders
Lamp holders shall comply with relevant standards. They shall have low contact
resistance, shall be resistant to wear and shall be suitable for operation at the
specified temperature without deterioration in insulation value. They shall hold
the lamps in position under normal condition of shock and vibration met with in
normal installation and use.
Lamp holders for the fluorescent lamps shall be of the spring loaded bi-pin rotor
type. Live parts of the lamp holder shall not be exposed during insertion or
removal of the lamp or after the lamp has been taken out. The lamp holder
contacts shall provide adequate pressure on the lamp cap pins when the lamp is in
working position.
Lamp holders for incandescent and LED lamps shall be of bayonet type upto
150W and Edison Screw type for higher Wattage lamps.
Starter holders for fluorescent lamps shall conform to the standards specified. All
material used in the construction of the holder shall be suitable for tropical use.
The starter holders shall be so designed that they are mechanically robust and free
from any operational difficulties. They shall be capable of withstanding the
shocks met within normal transit, installation and use.
Ballasts
The ballasts shall be designed, manufactured and supplied in accordance with the
relevant standards. The ballasts shall be designed to have a long service live and
low power loss.
Ballasts shall be mounted using self locking, anti-vibration fixings and shall be
easy to remove without demounting the fittings. They shall be in dust tight, non-
combustible enclosures.
The ballasts shall be of the inductive, heavy duty type, filled with thermosetting,
insulating, moisture repellent polyester compound filled under pressure or
vacuum. Ballasts shall be provided with tappings to set the voltage within the
range specified. End connections and taps shall be brought out in a suitable
terminal block, rigidly fixed to the ballast enclosure. The ballast wiring shall be
of copper wire. They shall be free from hum. Ballasts which produce humming
sound shall be replaced free of cost by the VENDOR.
Separate ballast for each lamp shall be provided in case of multi-lamp fittings,
except in the case of 2 x 20 watts fittings.
Starters
Starters shall have bimetal electrodes and high mechanical strength. starters shall
be replaceable without disturbing the reflector or lamps and without the use of
any tool. Starters shall have brass contacts and radio interference capacitor.
The starters shall generally conform to the relevant standards.
Capacitors
The capacitors shall have a constant value of capacitance and shall be connected
across the supply of individual lamp circuits.
The capacitors shall be suitable for operation at supply voltage and shall have a
value of capacitance so as to correct the power factor of its corresponding lamp
circuit to the extent of 0.95 lag or better.
The capacitors shall be hermetically sealed preferably in a metal enclosure to
prevent seepage of impregnant and ingress of moisture.
Lamps
Incandescent (GLS) lamps shall be provided with bayonet caps upto
150/Lumen/W.
LED lamps shall be life of >50,000hrs
The lamps shall be capable of withstanding small vibrations and the connections
at lead in wires and filaments/electrodes shall not break under such
circumstances.
Lamps/tubes shall conform to relevant standards and shall be suitable for supply
voltage and frequency specified.
Spare Parts
Unit prices of the items shall be quoted together with catalogue numbers.
The unit prices shall not however be limited to the above items. The VENDOR
may recommend additional spare items and quote the unit prices of the respective
items.
Tests and Test Reports
Type tests, acceptance tests and routine tests for the lighting fittings and
accessories covered by this specification shall be carried out as per the relevant
standard for the respective fittings and their accessories.
The MANUFACTURER's type and routine test certificates shall be submitted for
tests conducted as per relevant standards for the fittings and accessories. The
BIDDER shall submit with his proposal copies of available test certificates of the
fittings offered.
LT Cables
Codes & Standards
The design construction manufacture and performance of cables shall comply
with all currently applicable statutes, regulations and safety codes of the locality
where cables will be installed. Nothing in this specification shall be constructed
to release the Contractor of his responsibility.
Unless otherwise specified the cables shall conform to the latest applicable
standards.
Power Cable
Power cables should be multicore earthed 1.1 kV grade aluminium stranded
conductor colour coded, extruded/PVC insulated, extruded semi-conducting
screened over each core and insulation, extruded inner sheathed, common
extruded inner sheathed for multi core cable, galvanised steel strip armoured and
overall extruded black sheath conforming to IS-1554 Part II, 1976. Armouring of
multicore cable shall be of single layer, galvanised steel round wire or flat strip.
Wire armour should be used for cable dia over inner sheath upto 13 mm and strip
armour to be used for higher dia. The cables should be multicore and suitably
designed for variation in power supply as follows:
The voltage variation ± 10 %
Freq. variation ± 5%
Combined voltage & frequency variation ± 10 %
PVC Sheath
The PVC compound used for outer sheath shall be resistant to termites, fungus and
rodent attacks and shall have in addition the property mentioned in clause 6.0
above.
Cables Size
Laying of LT Cables
a) The cables shall be laid in an excavated trench. The depth of the trench shall
be minimum 750 mm below the final ground level but shall be decided on the
number of cables to be laid in the trench so that the vertical distance between
two adjacent layers of cables shall not be less than 350 mm. The width of the
trench shall be decided on the number of cables to be laid in the trench so that
the distance between two adjacent cables shall not be less than one cable
diameter.
b) Before laying cables the bottom of the trench shall be well compacted and the
cables shall be laid on a 100 mm fine sand bedding. The second layer of 150
mm of fine sand then be spread over the cable and shall be further covered by
150 mm of compact soil. For the second layer of the cable same procedure
shall be repeated.
c) The cables shall be protected by placing precast concrete tiles or burnt bricks
over the cables on top layer of sand and for the full length of underground
cables. Where more than one cable is running in the same trench, the concrete
tiles/ bricks shall cover all the cables and shall project a minimum of 80 mm
on either side of the cables.
In any case the top layer of the cables shall be minimum 600 mm below the
finished level of the ground.
d) The top of the cable trench shall be well compacted till the finished level of
the ground and shall be approved by the construction manager/consultant if
required a laboratory compaction test shall be carried out in presence of the
Construction manager/Consultant.
e) Cables under road crossings and any surfaces subjected to heavy traffic shall
be protected by running them through hume pipes of suitable size.
Earthing System
General
The earthing system shall comply with all currently applicable standards,
regulations and safety codes of the locality where the installation is to be carried
out. Nothing in this specification shall be construed to relieve the
CONTRACTOR of this responsibility.
The installation work shall conform to the latest applicable Electricity Rules,
IS:3043 and relevant codes of practice.
Earth Electrode
Electrodes shall as far as practicable, be embedded below permanent moisture
level.
Some electrodes shall be housed in test pits with concrete covers for periodic
testing of earth resistivity. Installation of rod/pipe/plate electrodes in test pits
shall be convenient for inspection, tasting and watering.
Pipe Earth Electrodes
GI pipe shall be of medium Class-B 38 mm dia and 3.5 m length with a funnel on
the top of the pipe. A funnel with wire mesh should be screwed to the pipe.
Galvanising of the pipe shall confirm to relevant Indian Standards. GI pipe
electrodes shall be tapered at the bottom and provided with holes of 12 mm dia
drilled not less than 150 mm from each other up to suitable length from bottom.
The electrode shall be buried in the ground vertically with its top not less 20 cm
below ground level. A brick masonry chamber of 300 mm x 300 mm x 450 mm.
Method of Connecting Earthing Lead to Earth Electrode
In the case of plate earth electrodes, the earthing lead shall be securely bolted to
the plate with two bolts, nuts, checknuts and washers. In the case of pipe earth
electrodes, they shall be connected by means of a through bolts, nuts and washers
and cable socket.
All materials used for connecting the earth lead with electrodes shall be GI in
case of GI pipe and GI plate earth electrodes and of tinned brass in case of copper
plate electrodes.
The earthing lead shall be securely connected at the other end to the main board.
General Instruction on Electrical Pre-commissioning Arrangement and Tests
All tests shall be carried out by the contractor using his own instruments, testing
equipment as well as qualified testing personnel.
The results of all tests shall conform to the specification requirements as well as
any specific performance data guaranteed during finalisation of the contract.
At site all equipment shall be energised only after certification by the personnel
performing the test that the equipment is ready for energising and with
concurrence of the purchaser.
Cable Termination and Jointing
Termination and jointing of aluminium conductor power cables shall be by means
of compression method using compression type aluminium lugs. Copper
conductor control cables shall be terminated directly into screwed type terminals
provided in the equipment. Wherever control cables are to be terminated by
means of terminal lugs, the same shall be of tinned copper compression type.
Testing and Commissioning of Electrical Equipment and Installation
General
The testing and commissioning for all electrical equipment at site shall be
according to the procedure laid down below.
All electrical equipment shall be tested, installed and commissioned in
accordance with the latest relevant standards and codes of practices published by
Indian Standards Institution wherever available and stipulations and in relevant
general specifications.
In case where Indian Standards are not available these shall be carried out in
accordance with the latest standards and codes of practice published by any other
recognised National Standards Institution or latest publications of International
Electro Technical Commission (IEC).
The testing of all electrical equipment as well as the system as a whole shall be
carried out to ensure that the equipment and its components are in satisfactory
condition and will successfully perform its functional operation. The inspection
of the equipment shall be carried out to ensure that tall materials, workmanship
i) Physical inspection for removal of any foreign bodies, external defects, such
as damaged insulators, loose connecting bolts, loose foundation bolts etc.
ii) Check for the free movement of mechanism for the circuit breakers, rotating
parts of the rotating machines and devices.
iii) Check for tightness of all cable, busbars as well as earth connections in the
main earthing network.
iv) Check for clearance of live busbars and conductors from the metal enclosure.
v) Continuity checks in case of power and control cables.
vi) Checking of all mechanical and electrical interlocks including tripping of
breakers using manual operation of relay.
vii) Check and calibrate devices requiring field adjustment/calibration like
adjustment of relay setting etc.
viii) Check proper connection to earth network of all non-current carrying
parts of the equipment and installation.
ix) Check for grease, insulating/lubricate oil leakage and proper charge.
x) Check for alignment of all drawout devices like drawout type circuit breakers,
MCC cubicles etc.
xi) Checking of alarm and annunciation circuits by manual actuation of relevant
relays.
The following tests shall be carried out on the equipment
a) Low voltage switchgear (upto 1000 V AC or 1200 V DC)
i) Insulation resistance test with 1000V megger for control, metering and
relaying circuits. The minimum value of insulation resistance shall be 1
megohm.
ii) Insulation resistance test with 500 V megger for control, metering and relaying
circuits. The minimum value of insulation resistance shall be 1 megohm.
iii) Relay operation test by secondary injection method.
iv) Functional test of the control circuits.
v) Checking of setting of all relays/releases as per drawings.
vi) Effectiveness Test of ELCB, MCBs.
ohms shall not be more than 1 ohm. If necessary, with the approval of
Engineer-in-Charge additional electrode shall be provided away from the
resistance and linked to the electrodes system. Payment for such additional
electrode and interconnecting tape/wire will be paid on unit or linear basis.
c) Insulation Resistance Test
Insulation resistance test should be made before the installation is permanently
connected to the electric supply. The insulation resistance is to be measured
by using an approved portable hand operated insulation resistance tester
reading directly in ohms. The voltage of this tester shall be about 500 volts.
The insulation resistance to earth shall not be less than 1 meg. ohm when
measured with all fuse links in place, all switches closed and all poles place,
all switches closed and all poles or phases of wires are electrically linked.
2.1.5. Where roots are required for cuttings, grass clumps should be
carefully dug up. They must not be pulled hard, as this can damage the
material. They must be separated carefully by hand, using a sharp knife
or razor blade when necessary. There must be no tearing of the plant
fabric.
2.1.6. Stem cuttings must be made using sharp secateurs. The top cut
should be made at right angles to the stem and the bottom cut should be
made at 45° to the stem: this is to show the orientation of the planting.
2.1.7. Once cuttings have been made, they must be wrapped in wet
hessian jute immediately. At all times cuttings are to be kept moist and
as cool as possible, and should be wrapped in wet hessian between all
operations such as digging out of the ground, splitting out, trimming and
planting. Under any circumstances, all cuttings must be planted the same
day that they are made.
2.2. PROVISIONS OF HARDWOOD CUTTINGS
2.2.1. Hardwood cuttings must be taken from shrubs and trees of
species which are known to propagate easily by vegetative means.
2.2.2. Cuttings must be made from as many healthy individual plants
as possible. The plants from which the cuttings are taken must show
vigorous growth and good form. Mis-shaven and shunted plants should
not be considered as sources.
2.2.3. Apart from the branches from which cuttings are taken the
Contractor must under no circumstances damage plants while taking
cuttings. The Contractor is responsible for taking safety precautions and
for making all necessary arrangements with landowners, farmers and the
local district forest office, as applicable, before the making of hardwood
cuttings.
2.2.4. Hardwood cuttings must be made from stem which are between
6 and 18 months old. Materials outside this range are normally vigorous
or strong enough to survive as cuttings. The Contractor may be held
liable if the success rate of cuttings is seriously lower than the normally
excepted percentage.
2.2.5. Hardwood cuttings must be made using sharp secateurs or a
sharp saw. The top cut should be made at right angles to the stem and the
bottom cut should be made at 45˚ to show the orientation of planting.
Under no circumstances must there be any damage to the bark of cutting.
the ground; then 50 mm of 1:1 mix of sieved soil and compost; and the
bed is topped with 150 mm of 3:1 mix of sieved fertile, loamy forest
topsoil and washed sand. All sieving should be done with a mesh size of
2 mm or smaller. One square meter of such bed will contain 100 grass
slips spaced at 100 m centre within rows at 100 mm centre and climate
of the nursery.
3.2.5. Seed beds must be made very carefully for germinating small
seeds of shrubs and trees. These can be of any practical length but must
be flat and of one meter in width. They should rise to a height of 170
mm above the surrounding ground. They are made up as follows: 50 mm
of washed gravels is placed above the ground; then 50 mm of unsieved
forest soil; 50 mm of 1:3 mix of sieved forest soil and washed sand; and
the bed is topped with 20 mm of washed, sieved and sterilized sand. All
sieving should be done with a mesh size of 1 mm or smaller.
3.2.6. Standout beds should be constructed to hold seedling in
polythene pots. These can be of any practical length but must be flat and
of one meter in width. Bed floors should be above surrounding ground
level and they should have a surround preferably made from flat stones
or bricks. One square meter of standout bed will contain an average of
115 filled pots of the size specified (100×180 mm) when spaced out.
3.2.7. Beds for the propagation of bamboo culm cuttings should be
made specially. These can be of any practical length but must be flat and
of one meter width. They should rise to a height of 300 mm above the
surrounding ground. They are made up as follows: the ground below the
bed is dug to a depth of 300 mm; the bed itself is then made with 100
mm of unsieved soil on the original surface, and 200 mm of sieved soil
above this. All soil sieving should be done with a mesh size of 2 mm or
smaller. Finally, a bund 100 mm high is formed around the edge
3.2.8. Shades must be constructed over the beds and kept in position
over delicate seedlings during hours of intense sunlight, according to
need. Shades should be 750 to 1000 mm above the soil or the top of
filled pots and angled so as to be effective for as much of the day as
possible (i.e. with the lower side to the south). Bamboo stripes laced
together with coir (coconut fiber) string are particularly suitable in most
cases; but over tree and shrub seed beds thatched shades with a
polythene lining must be used
4. NURSERY OPERATION AND MANAGEMENT
a) The Contractor must operate the nursery according to a high
standard. The nursery is to be staffed well tended at all times. It
must be maintained in a clean tidy and efficient manner at all
times. Plants must always be healthy and vigorous.
4.4.5 Plants from soil beds must be wrapped in wet hessian jute.
Hardwood plants should have a ball of soil around the
roots. Grass clumps can have most of the soil shaken or
washed off.
4.4.6 Polypot seedlings should be lifted and stacked neatly in
metal or wooden trays. They must always be lifted by the
pot and never by the stem or leaves.
4.4.7 All plants are to be kept moist in a cool, shady place, until
they are loaded for transport to site. In the vehicle they
must not be stacked high. For transport on rough roads they
must be packed in carefully so that they do not fall over or
roll around. The vehicle must be shaded.
4.5 COMPOST AND MULCH PRODUCTION
4.5.1. The Contractor is to produce compost and mulch for
nursery or site operations. It is to be produced in a timely
manner in the quantities required. Compost is normally
required to sustain the long term fertility of nursery beds.
Mulch may also be used in the nursery but is normally
produced to enhance site planting works, particularly the
direct seedling of grass.
4.5.2. Compost and mulch should be made from annual and
perennial weeds of poor rooting characteristics. The
greenery should be collected when there is most material
available but before it forms seeds.
4.5.3. Collected material should be chopped finely and stored in a
mound, compost bay or pit. The maximum size for chopped
compost is 50 mm; the maximum size for chopped mulch is
150 mm.
4.5.4. Both compost and mulch should be kept moist but not
waterlogged and in an aerated condition. They should be
completely turned once a month on a regular schedule.
Compost can have cow manure mixed in to assist the
process of decomposition.
4.5.5. Neither compost nor mulch should be applied until they are
fully rotted. By this time they should be black and the parts
of individual plants should be indistinguishable. Early
application can lead to a nutrient loss in the soil if microbes
extract nitrogen to decompose the organic material.
5. FINAL SLOPE PREPARATION FOR BIO-ENGINEERING
a) The Contractor shall prepare slopes for planting operations as
required by Engineer. This shall be done according to the
5.2.2. The Contractor must ensure that the slope under instruction is
trimmed to a straight angle according to the specification. In an event a
straight profile must be obtained. All masses of loose debris especially
where it has previously been tipped at the head of the slope must be
removed.. Concavities must be filled with well compacted material or in
some cases, with dry stone detention. Convexities must be removed and
it is essential that the general profile does not have a shape giving over
steep segments.
6. SITE PLANTING AND SOWING
a) The Contractor shall plant or sow grasses shrubs trees as required
by the Engineers. This shall be done according to the
specification described hereunder as and when required. The
Contractor shall supply all necessary expertise resources and
facilities to ensure that these requirements are met.
6.3.2. it is assumed that the site will already have been prepared for
planting under a separate instructions; but it is nevertheless the
responsibilities of the Contractor to ensure that the conditions of
the site is good enough for the successful establishment of
grasses, and accords with the specifications given in clauses 5,
and 5.1 or 5.2
6.3.3. Using appropriate tools (such as tape measures and spirit level);
planting lines must be marked out with string as required.
Unless specified differently the row spacing to be marked out is
as shown in table below.
Planting configuration Slope steepness Row spacing
Random lines Slope less than 30 1000 mm centre
degrees 500 mm centre
Slope 30 to 45 degrees 250 mm centre
Slope more than 45
degrees
Contour lines Slope less than 30 1000 mm centre
degrees 500 mm centre
Slope 30 to 45 degrees 250 mm centre
Slope more than 45
degrees
Diagonal lines All slopes 500 mm centre
Down slope lines All slopes 500 mm centre
7. SITE PROTECTION
a) The Contractor is to protect a planted site for the period
specified. Protection is to include the prevention of damage to all
manner of site works and plants by local people and domestic or
Page 185 of 189
Section VII Works Requirements (Technical Specifications)
just above the ground and the aerial parts will be used to make
compost or mulch. Weeds must not be pulled out by the roots
since this disturbs the ground surface.
c) weeding should be carried out throughout the growing season. It
must be undertaken with particular diligence at the end of the
monsoon, so that there is the minimum amount of competition
during the subsequent dry season.
d) The Contractor shall carry out mulching as required throughout
the site. All plants required under the bioengineering
specifications will be mulched using material prepared as
specified under mulch preparation, or the aerial parts of weeds
cut on the site or brought from elsewhere for the purpose. The
desired plants should be kept mulched at all times but special
care must be taken in the spring, when the soil moisture deficit it
at its greatest.
e) The Contractor shall replace failed, damaged, diseased and very
weak plants, using fresh, healthy plants of the same species, at
the correct time of the year for planting. This replanting
operation will normally be carried out during the monsoon in the
year following the first planting works. Vegetation structures will
be enriched by the planting of additional cuttings or seedlings, as
instructed by the Engineer. Failed seedling areas will be reseeded
at the appropriate time of the year.
f) Lin replanting the enriched works the Engineer may specify the
use of different species. This will be done where failures or poor
performance of plants may be attributed to poor stock or an
incorrect initial choice of species.
g) All bio-engineering sites must be maintained so that there are at
least the following two storey of vegetation. In certain locations,
however, there may be a number of additional vegetation storeys.
i. in dense ground cover of healthy grass plants, in the
configuration specified at the time of planting
ii. An open canopy of shrubs or trees with a deeper rooting
network.
h) In general it is necessary to keep the upper canopy thinned in
order to maintain the lower ground cover. Most grasses require
high light intensities and become degraded if subjected to
excessive shade from the over storey. It is therefore the
Contractor’s responsibility to thin the canopy as necessary to
permit adequate levels of light to penetrate for the optimum
growth of the grass under storey.
LIST OF STANDARDS
The contractor shall provide for the use of the Project Manager technical publications,
standards and codes of practice, in the Media stipulated by Project Manager. In all cases
original publications of the edition currently in force are assumed.
The publications shall become the property of the Employer upon completion of the Contract