De-Com - For Existing 8 12 Inch - Pipeline - TRA1
De-Com - For Existing 8 12 Inch - Pipeline - TRA1
Field /Terminal; NEB - AL DABBIYA TRA Ref. No TRA # 2268 Date 07/05/2019
Team Members : TRA Team TRA Member TRA Member TRA Member TRA MEMBER TRA Member TRA Member Job Performer
Leader ( JO ) (Area ADCO HSE TCM HSE Construction RSME HSE Construction RSME
Authority) (Tecnimont) (RSME)
Name:
Signature
Team Members :
Name:
Signature .
1. Mobilization of Load falling from the Improper secured Fatality H ADNOC E-PTW system Close supervision JO/Sup M Yes
Equipment, trailer loads Property in place Thorough visual inspection
Tools and Collision with other Movement of vehicles damage Follow ADNOC Road of the area and ground
Materials vehicles Wide load extended Personal injuries Safety Guidelines condition shall be carried
Hit by the extended from vehicle Environment Proper escorting out
load from other Improper damages provided Only approved routes to be
vehicle rigging/loading Load secured followed
Equipment / vehicles practice appropriately Daily driver checklist shall
fall on the open Uncontrolled Maintain safe distance be maintained
during operations Unauthorized entry Crane operator and crane or load accordingly
Line of fire Inadequate riggers shall be certified Do not leave suspended
Pinch points barricade / signages by ADNOC Onshore load unattended
Hit the adjacent Lack of flagman approved third party The safe working load and
structure and Incompetent operator Good preventive and the maximum working
facilities and rigger maintenance radius shall be maintained
Uneven slippery programme for Daily checklist shall be
surface and obstacles equipment followed maintained by operator prior
Mechanical failure Maintain good to use
Congested area housekeeping and Signalling shall be done only
Nearby structures and implement waste by one rigger
facilities management as per Two tag lines with sufficient
procedure length shall be provided to
Adequate access / guide the load
egress shall be Provide barricades and
maintained safety signage
Proper coordination Assigned trained flagman
during the operation of Maintain good housekeeping
the crane and implement waste
First aider and fire management as per
fighter shall be procedures
available Adequate access / egress
shall be maintained
Proper coordination during
the operation of the crane
Maintain safe distance from
line of fire
Avoid pinch points – keep
attention & eyes on the task
Proper coordination among
various disciplines and work
groups
Lifting operation shall be
suspended if wind speed
exceed 17 knots.
T- Card system shall be in
place.
4. Pig Launching, High pressure hose Loose connections Personnel injury H E-PTW in place Authorized persons only JP/IA M Yes
Pig Receiving & Release of energy Damage hose & Asset damage Approved method allowed to enter the area
Pigging Noise connections statement & TRA must Bolts, hoses, connection
Environment
Fire Excessive pressure be available at site should be consistent to the
impact
Toxic gas Bolts failure / failure Calibrated pressure pressure rate
Fatality gauges Continues monitoring of
(Hydrocarbons / of PSV
H2S) Failure of fittings H2S detector pressure
Follow environmental
parameters (rain, sand
storm, fog visibility)