Post Test Chapter 1
Post Test Chapter 1
Post Test Chapter 1
Solution:
1. Erg Manufacturing Company has developed the following overhead cost formulas:
Cost Formula Depreciation $500 Set-up $400 plus $0.20 per machine-hour Lubrication
$50 plus $0.25 per machine-hour Utilities $0.40 per machine-hour Based on these cost
formulas, the total overhead cost expected for Erg Manufacturing Company if 200
machine hours are worked is:
Ans. $1,120
Fixed Variable
Cost Cost Total
Portion Portion Cost
Lubricants (variable cost = $0.25 × 200) $50 $50 $100
Utilities (variable cost = $0.40 × 200) $80 80
Depreciation $500 500
Setup (variable cost = $0.20 × 200) $400 $40 440
Total cost $1,120
2. You are applying the scattergraph method and find that the regression line you have
drawn passes through a data point with the following coordinates: 7,500 units and
$10,000. The regression line passes through the Y axis at the $4,000 point. Which of
the following is the cost formula that represents the slope of this line?
Ans. Y=$4,000+$0.80X
Variable cost = Change in cost ÷ Change in activity
= ($10,000 – $4,000) ÷ (7,500 – 0) = $0.80
Since the regression line passes through the Y axis at the $4,000 point, the $4,000
represents the fixed costs.
Therefore, the cost formula would be Y=$4,000+$0.80X.
Therefore, the cost formula for total electrical cost is $11,517 per period plus $7.96 per
machine-hour, or Y = $11,517 + $7.96X
5. Timchak Corporation reports that at an activity level of 9,900 units, its total variable
cost is $919,116 and its total fixed cost is $259,974. What would be the total cost, both
fixed and variable, at an activity level of 10,100 units? Assume that this level of activity
is within the relevant range.
Ans. $1,197,658
Variable cost per unit: $919,116 ÷ 9,900 units = $92.84 per unit
The cost function is:
Y = $259,974 + $92.84X
Y = $259,974 + $92.84(10,100)
Y = $1,197,658
Therefore, the cost formula for total cost is $46,500 per period plus $85 per clienthour,
or Y = $46,500 + $85X.
8. Jackson, Inc., is preparing a budget for next year and requires a breakdown of the
cost of steam used in its factory into fixed and variable components. The following data
on the cost of steam used and direct labor hours worked are available for the last six
months: Cost of Steam -Direct Labor-Hours July $ 15,850 -3,000 August 13,400 -2,050
September 16,370 -2,900 October 19,800 -3,650 November 17,600 -2,670 December
18,500 -2,650 Total $101,520 -16,920 If Jackson uses the high-low method of analysis,
the estimated variable cost of steam per direct labor hour would be:
Ans. $4.00
Variable cost = Change in cost ÷ Change in activity
= ($19,800 – $13,400) ÷ (3,650 – 2,050) = $4.00
9. Shown below are units produced and total manufacturing costs for the past four
months at Minga Manufacturing Corporation: Units Produced -Total Cost Jul 120 -
$446,000 Aug 150 -$508,000 Sep 180 -$668,000 Oct 160 -$574,000 What is Minga's
cost formula for total manufacturing cost under the high-low method?
Ans. Y = $2,000 + $3,700X
Variable cost = Change in cost ÷ Change in activity
= ($668,000 – $446,000) ÷ (180 – 120) = $3,700
Therefore, the cost formula for total cost is $2,000 per period plus $3,700 per unit, or Y
= $2,000 + $3,700X.
10. Wright Company has observed that at an activity level of 5,000 units the cost for
maintenance is $6,500, and at 10,000 units the cost for maintenance is $9,000. Using
the high-low method, the cost formula for maintenance is:
Ans. $4,000 plus $.50 per unit
Variable cost = Change in cost ÷ Change in activity
= ($9,000 – $6,500) ÷ (10,000 – 5,000) = $0.50
Therefore, the cost formula for total maintenance cost is $4,000 per period plus $0.50
per unit, or Y = $4,000 + $0.50X.