Cox's Bazar Airport - Detailed Design Report
Cox's Bazar Airport - Detailed Design Report
Cox's Bazar Airport - Detailed Design Report
Design Report
DEVELOPMENT
OF
COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
CONTENTS
1. INTRODUCTION ............................................................................................................... 1
1.1 BACKGROUND ................................................................................................................................ 1
i
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
3.2.6 Apron....................................................................................................................................... 27
ii
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
iii
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
6.3.1 Siting Criteria for Instrument Landing System (ILS): ............................................................ 102
6.3.2 Instrument Landing System Configuration and Layout Plan ................................................ 105
6.5.1 Siting Criteria for Air Traffic Control Communication System ............................................... 107
6.5.2 Air Traffic Control Communication System Configuration and Layout Plan ......................... 108
6.6.2 Automatic Meteorological Observation System Configuration and Layout Plan .................. 111
iv
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
INDEX OF TABLES
Table 2.1 Primary Control Point (BM & TBM) ................................................................................ 4
Table 2.11 Borehole : SB-6 / Ground water level : GL. -1.0m ......................................................... 12
Table 2.12 Borehole : SB-9 / Ground water level : GL. -0.5m ........................................................ 12
Table 3.1 The construction work items for 1st Phase Development of Cox’s Bazar Airport ........... 14
v
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Table 4.8 Flexible ACN at Indicated Gross Weight and Strength .................................................. 51
Table 6.4Instrument Landing System Requirement and Layout Plan .......................................... 105
Table 6.6 DVOR/DME System Requirement and Layout Plan .................................................... 107
Table 6.7 Siting Criteria for ATC COMMUNICATION SYSTEM ................................................... 107
Table 6.8 Air Traffic Communication System Requirement and Layout Plan ............................... 108
Table 6.10 AMOS System Requirement and Layout Plan ........................................................... 110
vi
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
INDEX OF FIGURES
Figure 2.1 Disputed Area for Topo Survey ...................................................................................... 5
Figure 3.5 LLZ Critical Area beyond the end of 17 Runway .......................................................... 25
Figure 3.6 ICAO Typical Turn Pad for 180-degree Turn ................................................................ 27
Figure 3.9 Cox’s Bazar Airport Layout Plan for 1st Phase ............................................................. 31
Figure 4.13 ILP - PARKING APRONS AT HONG KONG INTERNATIONAL AIRPORT ................. 54
vii
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Figure 5.2 Runway Threshold/End lights Configuration(Include Wing Bar lights) .......................... 78
Figure 6.1 Typical Localizer Critical and Sensitive areas dimension variations ........................... 124
Figure 6.2 Typical Glide Path Critical and Sensitive areas dimension variations ......................... 124
viii
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
ABBREVIATION
AASHTO American Association of State Highway and Transportation Officials
GP Glide Path
LLZ Localizer
ix
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
SSALF Simplified Short Approach Lighting System with Sequenced Flashing Lights
x
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
1. INTRODUCTION
1.1 BACKGROUND
One of the most important aspects of the Consulting Services of Cox’s Bazar
Airport(CXB) Development Project is to assure that the project assists the
Bangladesh Government in achieving its goal of spreading tourism industry and
cargo flights to all over the world with high potential for development.
In keeping with this policy, the GOB approved the Cox’s Bazar’ Special
Development Project which aims to contribute to the international development by
attracting new tourist and investments to Cox’s Bazar. The focus of the project is to
contribute to the country’s national promotion of the tourism industry.
1.2 OBJECTIVES
The project aims to develop the airport to fulfill all the above objectives.
The main objective of the project is to enhance operational facilities of the airport ,
which is the one of development of infrastructure for Cox’s Bazar Tourism.
The following indicates the project objectives the consultant team will achieve during
the course of the project:
To improve the facilities for the wide-body aircraft operation
To install the saftey facilities for Cat-I operation (precision instrument approach)
To extend the facilities to meet air traffic demand
To adjust the facilities for satisfying ICAO standard
To add the facilities for achieving above objectives
Topographical Survey
Soil Investigation
1
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Earthwork
Pavement
Storm Water Drainage
Embankment Protection
Surface Treatment
Miscellaneous Works
ALS
AGL
Power Supply & Control/Monitoring System
ILS
DVOR/DME
Aeronautical Telecommunication System
AMOS
2
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
According to the AIP of Bangladesh, the existing Cox’s Bazar Airport is situated 2km
from the town of Cox’s Bazar at the coordinates of N 21° 26’ 59.13” / 91°57’ 53.31
E and occupies a land area of 88.73 hectares. The elevation of the airport is 3.66m
(12ft) above mean sea level.
The coordinates 17 Runway threshold is N 21° 27’ 40.75” / 91°57’ 44.92 E, and 35
runway threshold is N 21° 26’ 34.78” / 91°57’ 58.22 E
However, the result of topographical survey, some differences is found between AIP
and Survey.
Total survey area is 583 acre including river & land area, 9 BM (3 permanent BM, 6
temporary BM) are established in the airport site.
These BMs will act as control points, X, Y co-ordinate data collected by DGPS.
The coordinates system is based on BTM which is Bangladesh Practice.
Description of BTM:
Tentative name: Bangladesh Transverse Mercator
Projection: Transverse Mercator
Ellipsoid: Everest 1830
Scale factor :0.9996
Central Meridian:90 (E)
Latitude of Origin: 0(Equator)
False Easting:500,000
False Northing:-2,000,000
3
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
In order to connect the site levels to the national leveling network, a double-run level
survey was conducted between the nearest national benchmark (PWD). PWD is
situated on the approximately 1km northern area from CXB, BWDB rest
house.datum of PWD RL =7.81m.
4
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
At present, the planned area for new apron and taxiway have a lot of villages and
now the government is looking for the new area for these villages’ residences, so
that the topographical survey couldn’t be conducted in that area within the stage-I
period of this project.
Therefore, consultant will design for the new apron and taxiway as assuming the
topographical shape with around area which is already surveyed.
It should be changed to the result of design for this area before construction.
5
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
1) General
The ground stability of proposed site was examined by predicting a settlement
which could be hazardous to structure foundation.
The examination was conducted to the loose sandy soil layer partially detected in
the site.
The De Beer method, predict settlement on sandy soil layer using N-value, was
applied in this study because mechanical properties of soil are hard to be tested due
to difficulties in undisturbed soil sampling from sandy soil.
( De Beer method )
Po ΔP Settlement
No. H(cm) N
(kgf/cm2 ) (kgf/cm2 ) (cm)
3) Result
The proposed site is mostly consist of dense sandy soil layer and has good
condition for structure foundation. Although some settlement was predicted on loose
6
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
sandy soil layer, this would not be hazardous to structure in service stage because it
is immediate settlement that is occurred during banking process.
1) General
The analysis for stability of slope needs to consider subsurface structure, soil
characteristics, height of slope and topography of site.
The applied analysis method should well reflect the movement of slope.
7
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
1m of bum in every 5m of
Fill 0~5m 1:2.5
height
3) Standardized factor of safety for slope stability
a. Applicable minimum factor of safety for Fill
The aspect of subsurface was general fluvial deposit that thickness of each layer
was hard to be divided and it only showed difference of N-value depending on the
deposit time and conditions. Hence, there were deeper layers having lower N-value
than shallower layer but generally the surface layer had comparably loose condition.
The shear strength was decided considering N-value, relative literature and
empirical information and etc.
8
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Original ground
Soil Fill
SM(N < 10) SM(N > 10)
Friction angle() 25 30 30
5) Result
Dry season Fs = 1.615 > 1.5 OK Wet season Fs = 1.374 > 1.3 OK
1) General
The purpose of this study is to evaluate liquefaction potential of the proposed site
and to make a safe construction.
9
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
a. Seed's method
- Simplified method : Seed & Idriss' method, Reference for road bridge of Japan,
Ishihara's method and etc
The Seed & Idriss' method simply evaluates liquefaction potential comparing ratio of
resistance strength against liquefaction from N-value and shear stress from
earthquake based on observation of field performance in previous earthquakes.
Cyclic stress ratio developed in the soil due to earthquake
10
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
SPT resistance
Evaluation
3) Result
The evaluation results by Seed & Idriss' simplified method are as follow.
11
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Depth N Result
1.5 6 2.70 2.20 1.51 9.06 0.98 0.242 0.100 0.22 0.91 NG
3.0 6 5.40 3.40 1.36 8.16 0.97 0.475 0.090 0.31 0.64 NG
4.5 16 8.10 4.60 1.26 20.16 0.95 0.700 0.222 1.02 1.46 OK
6.0 19 10.80 5.80 1.18 22.42 0.93 0.917 0.247 1.43 1.56 OK
7.5 50 13.50 7.00 1.12 56.00 0.92 1.126 0.616 4.31 3.83 OK
9.0 46 16.20 8.20 1.07 49.22 0.90 1.327 0.541 4.44 3.35 OK
Depth N Result
1.5 9 2.70 1.70 1.59 14.31 0.98 0.242 0.157 0.27 1.11 OK
3.0 12 5.40 2.90 1.42 17.04 0.97 0.475 0.187 0.54 1.14 OK
4.5 32 8.10 4.10 1.30 41.60 0.95 0.700 0.458 1.88 2.68 OK
6.0 35 10.80 5.30 1.21 42.35 0.93 0.917 0.466 2.47 2.69 OK
7.5 33 13.50 6.50 1.15 37.95 0.92 1.126 0.417 2.71 2.41 OK
Depth N Result
1.5 10 2.70 1.65 1.60 16.00 0.98 0.242 0.176 0.29 1.20 OK
3.0 11 5.40 2.85 1.42 15.62 0.97 0.475 0.172 0.49 1.03 OK
4.5 17 8.10 4.05 1.30 22.10 0.95 0.700 0.265 1.07 1.53 OK
6.0 19 10.80 5.25 1.22 23.18 0.93 0.917 0.255 1.34 1.46 OK
7.5 17 13.50 6.45 1.15 19.55 0.92 1.126 0.215 1.39 1.23 OK
9.0 29 16.20 7.65 1.09 31.61 0.90 1.327 0.348 2.66 2.00 OK
10.5 24 18.90 8.85 1.04 24.96 0.88 1.519 0.275 2.43 1.60 OK
12.0 23 21.60 10.05 1.00 23.00 0.87 1.704 0.253 2.54 1.49 OK
12
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Factor of Safety
Range of liquefaction
Depth (m)
Standard
Hence, the loose sandy soils on surface layer are suggested to be excavated and
filled up again by step compaction to prevent liquefaction.
13
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
As the master plan of CXB, the items of construction work for the 1st phase
development is decided and summarized as shown below. According to the
following table, the consultant team will conduct to design for Phase-I of the 1st
Phase Development
Table 3.1 The construction work items for 1st Phase Development of Cox’s
Bazar Airport
1st Phase
Construction items
Phase-I Phase-II
A. Civil Works
1) Overlay of the existing runway ○
2) Widening of the existing runway & shoulders ○
3) Extension of runway to 678m from end of R/W 17 ○
4) Provision of overruns (150m) ○
5) Provision of runway end safety areas ○
6) Securing Radio Altimeter Operation Area for LLZ ○
7) Relocation of Fence for securing Runway Strip and
○
installation of gate
8) Construction of turning pad, two connecting taxiways ○
9) Construction of New apron ○
10) Upgrading existing apron for cargo aircrafts ○
11) Removal of existing buildings ○
12) Construction of security road and airport services road ○
13) Construction Access Road ○
14) Construction Car Parking Area ○
15) Embankment for extension area ○
16) Earthwork, storm water drainage work for airside area ○
17) Earthworks, storm water drainage works and landscaping
○
for landside area
18) Provision of marking and sign board for airside ○
19) Construction duct and manhole ○
20) Removal of obstacles in airside ○
14
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
1st Phase
Construction items
Phase-I Phase-II
B. Building Works
1) Passenger Terminal Building ○
2) Cargo Terminal Building ○
3) Operation and Control Tower ○
4) Administration Building ○
5) Fire Fighting Station ○
6) Power House ○
7) Pump House ○
8) Transmitter Building ○
9) VIP Building ○
10) GSE Maintenance Building ○
11) Quarters ○
C. Utility Works
1) Power Supply Systems ○
2) Water Supply Systems ○
3) Sewage treatment Systems ○
4) Fuel Farm ○
D. NAVAIDs Works
1) Installation of CAT-I ILS system for R/W 17 ○
2) Installation of DVOR ○
3) Air Traffic Control Communication System ○
4) Automatic Meteorological Observation System (AMOS) ○
E. Airfield Lighting Works
1) Installation of Approach Lighting System for R/W17 ○
2) Installation of SSALF for R/W35 ○
3) Installation of Aeronautical Beacon ○
4) Installation of Ligths for Runway, Taxiway and Apron ○
5) Installation of power supply system for airfield lighting ○
6) Installation of control and monitoring system for airfield
○
lighting
15
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
3.2.1 General
1) Purpose
The main purpose of this Design is to investigate and utilize the safest, the most
efficient, and economical layout of the master plan based on ICAO and FAA
standards.
3) Facility Division
Runway system : Runway, Runway Strip, Overrun, etc.
Taxiway system : Two Taxiways connecting Apron
Apron system : Passenger Apron, Existing Cargo Apron
Landside facilities : This not scope of phase-I, so the master plan layout will be
applied
1) Geometric Design
The airport layout is influenced by the obstacle separation distances required to
meet the ICAO Standards and Recommended Practices to reflect the size code of
the critical aircraft type for which the airfield design is intended to cater. The
International Civil Aviation Organization (ICAO) categories aircraft both in terms of
the runway reference field length required for operations and the size of the aircraft
reflecting principally the wingspan of the aircraft.
Under this classification system as like table 3.1, the largest type of aircraft
expected to operate into CXB after completing this project on a regular basis is a
Code 4E aircraft, represented by the B747 and B777, which are designated as the
critical aircraft types for geometric design.
16
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
However, the runway length, new apron and turn pad are applied to the standard
Code 4D aircraft, A310 which is assumed as the largest aircraft for 1st phase.
2) Pavement Design
According to latest FAA standard, pavement design is not depend on the heaviest
aircraft, but the annual aircraft fleet mix.
Each class of aircrafts currently operational and proposed new class of aircrafts to
be operational in the future will be considered in pavement structure design.
Therefore, annual flights of each class of aircrafts should be calculated based on
the Aircraft Demand Forecast.
According to Air traffic demand forecast, Code E aircraft is not operated until 2035.
So the pavement will be constructed in accordance with the fleet mix of Code D and
C aircrafts for economic efficiency.
3.2.3 Runway
1) Length of Runway
The length of a runway must be designed on the basis of the aircraft that requires
the longest runway out of those that will use the runway.
To determine the length, the aircraft specification manual published by the
manufacturers need to be referred.
The runway length must conform to the minimum requirement needed for take-off
and landing. This condition depends on the maximum official take-off weight,
17
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
standard atmospheric condition, and aircraft type and engine arrangement under
the no wind and no longitudinal slope of the runway. Aircraft manufacturers specify
the compensation of runway length by elevation, temperature and effective runway
slope.
Runway lengths will be computed based on the existing longest runway length
requirement among ICAO Code D class aircrafts. Future expansion of airport
runways is being considered to accommodate Code E aircrafts.
18
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
For referring, the required runway length of other aircrafts which is expected to
operate at CXB in the future are reviewed.
As result of analysis for runway length, the length of runway should be extended
to 2,743m (9,000ft) to accept the wide-body such as A310, A300 and B777-200
without limitation of weight, and the other wide-body such as B767-300, A340-300
and DC-10-30 should be operated this runway with limited take-off weight.
2) Width of Runway
According to the ICAO standard, the width of a runway should be not less than the
appropriate dimension specified in the following tabulation.
19
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
As shown in Table 3.6, this Design will consider 45m and 7.5m width for runway
and shoulder, respectively, based on ICAO standards; and 45m and 10m width for
runway and shoulder, respectively, based on FAA standards.
The width of runway should be extended to 60m including shoulder to accept
Code 4E aircraft for ultimate phase, therefore, main runway width should be widen
to 45m and added to 7.5m on each side.
3) Slopes on Runways
Table 3.7 shows the maximum allowed slope change. The specification concerning
the sight distance presents another constraint to the allowed longitudinal slope.
If the slope needs to be changed, it must be designed not to obstacle the view.
Code Numbers
Division
1 2 3 4
Maximum slope 2.0% 2.0% 1.5% 1.25%
Maximum Average Slope 2.0% 2.0% 1.0% 1.0%
Maximum Slope Change 2.0% 2.0% 1.5% 1.5%
Maximum curved surface
0.4% per 30m 0.4% per 30m 0.2% per 30m 0.1% per 30m
change rate
(7,500m) (7,500m) (15,000m) (30,000m)
(minimum radius of curvature)
According to design, the existing runway will be planned to level as like existing
status and the extension area will be -0.1% to the new end of runway considering
dike height.
20
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Code Letter
Division
A B C D E F
Maximum
2% 2% 1.5% 1.5% 1.5% 1.5%
Transverse Slope
4) Runway Strip
Code numbers
Division
1 2 3 4
length Length extended more than 60m from both ends of the
runway
precision approach
75m 75m 150m 150m
runway
Width non-precision
75m 75m 150m 150m
approach runway
non-instrument 30m 40m 75m 75m
runway
Graded area provides an area clear of objects which may endanger aircrafts. The
strip includes a graded portion which should be so prepared as to not cause the
collapse of the nose gear if an aircraft should leave the runway.
21
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Moreover, the standard transverse slope of a runway strip is shown Table 3.10
transverse slope of the runway area was planned to have 1.5%~2.5%
corresponding according to the existing site condition.
Code numbers
Division
1 2 3 4
Transverse slope 3% 3% 2.5% 2.5%
5) Overrun
Runway overruns keep the probability of serious damage to an aircraft to a
minimum in the event that the aircraft runs off the runway end during a takeoff or
landing, or lands short during a landing. Overruns are required for the landing and
takeoff area. Table 3.11 shows the dimensional requirements for overruns. Overrun
profiles are shown in Figure 3.3
22
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Actually the overrun required 300m length, but the CXB airport is used to temporary
operation by BAF, so that overrun will be installed 150m with consideration of the
difficulty of extending to riverside.
Runway end safety area should be installed at the an additional area beyond the
ends of the runway strip and it should be required to extend from the end of a
runway strip for as great a distance as practicable, but at least 90m.
Runway end safety area should, as far as practicable extend from the end of the
runway strip to a distance of at least 240m where the code number is 3 or 4.
REAS of 17 runway will be paved additionaly to the approximately 50m from the end
of paved area for securing 150m and more 150m can be secured in front of LLZ.
23
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
However, if the RESA of 36 runway is extended to 300m from the end of runway, it
should be considered the environmental impact for embankment protection, so the
runway end safety areas will be secured 90m which is mandatory criteria of ICAO
standard for minimizing the impact of river environment.
The longitudinal slopes of a runway end safety area should not exceed a downward
slope of 5%.
The localizer is one of the ILS equipment, it should be installed within the 300m
from the end of 17 runway. And the critical area for localizer should be established
around localizer as shown Figure 3.5
For securing that area, the end of south area should be extended to approximately
300m more from existing fence.
24
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
3.2.4 Taxiway
ICAO Standards will be applied for the design of taxiway. Table 3.12 shows the
taxiway width, shoulder width and taxiway strip width based on ICAO and FAA
standards.
25
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
2) Slopes on Taxiways
Taxiway transverse slope based on ICAO standards are as follows:
Code Letter
Division
A B C D E F
Maximum
3% 3% 1.5% 1.5% 1.5% 1.5%
Slope
Maximum
curved
Grade surface 1% per 1% per 1% per 1% per 1% per 1% per
change rate 25m 25m 30m 30m 30m 30m
(minimum (2,500m) (2,500m) (3000m) (3,000m) (3,000m) (3,000m)
radius of
curvature)
Maximum transverse
2% 2% 1.5% 1.5% 1.5% 1.5%
slope
1) Method
The typical trapezoid turn pad recommended by ICAO is adapted. The dimension is
determined to comply with the minimum edge clearance of 4.5 m by tracing aircraft
gear tracks where an aircraft completes 180-degree turn as shown in Figure 3.6.
The assumptions for producing the gear tracks are:
- At the entry of aircraft to the turn pad from the runway, the aircraft turns left 30
degrees.
- The nose wheel steering angle is 45 degrees, and complete 180-degree turn
within turn pad.
26
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
MD-11
3.2.6 Apron
The capacity of the present passenger apron is one of the critical issues for the
present demand level. Several airlines have requested to increase their flights
to/from the airport, but due to the limited capacity of parking stands of aircraft, such
request is limited.
27
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
The required number of parking positions for both passenger and cargo apron is
estimated based on the demand forecast for 2010 as shown in Table 3.15
- (unit : stands)
Number of st
Apron Class Type 1 Phase
Stands Present
Medium Jet B-737 class - -
International Large Jet A310 class - 1
Total - 1
Medium
Dash-8 class 1 -
Turbo-prob
Large
Domestic ATR 72-class - -
Turbo-prob
Large Jet B737 class - 4
Total 1 4
Medium
HS-748X class 5 5
Cargo Turbo-prob
Total 5 5
Total 6 10
2) Layout Plan
New apron and existing apron expansion are designed based on the following
principles:
New designed plan is shown in Figure 3.6. The concept for new design is that the
parking location for A310-300 at the center of the apron and each two stands beside
Code D stand The necessary clearance in accordance with FAA and ICAO
standards are confirmed.
28
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
Code letter
Distribution
A B C D E F
Location of aircraft stand taxilanes and apron taxiways should provide separation
distance between the centre line of these taxiways and an aircraft at the stand not
less than the dimensions given in table 3.17 below
29
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-I
30
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Figure 3.9 Cox’s Bazar Airport Layout Plan for 1st Phase
31
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.1 GENERAL
Analysis of the market outlook for the air transport sector serving Cox’s Bazar
suggests that the market is in the early stages of development. Partly as a result of
the operating limitations of the existing airport, a high potential for growth appears to
exist in all present market sectors served by the airport. A significant opportunity
exists to develop new routes, and better serve some of the existing longer sectors,
particularly with development of the existing airport that would not be restricted in
terms of runway length or capacity.
4.2 EARTHWORKS
The following codes and standards will be used for design of runway, taxiway and
apron design.
Aerodrome Reference Code for the New Airport is ICAO Code 4E as stated in
Chapter 3.
2) Runway Strip
Runway Strip will be 2,863 meter long and 300 meter wide surrounding the runway.
The maximum slopes of the runway strip are as follows;
32
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
3) Taxiway Strip
The width of taxiway strip will be 47.5m both sides measured form the centerline of
the taxiway. The maximum slopes of the taxiway strip are as follows
a. Transverse slopes within 22m from the taxiway centerline: 2.5%
4) Apron
Apron will be 259m wide and 164m long. The maximum slope of the apron will be
0.75% .
4.2.3 Elevations
Ground Level
Location Remarks
Highest Point Lowest Point
Runway 7.150 6.345
33
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
According to the result of soil investigation, there are some layers which N value is
under 10 on the filling area for runway extension as shown in the Figure 4.1
This loose sand layer should be replaced to the sequential lifts capable of being
compacted to the required density and re-compacted for runway pavement.
34
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4 PAVEMENT
4.4.1 General
1) Purpose
The design procedure presented in this chapter provides a method of design based
on layered elastic and three-dimensional finite element-based structural analysis
developed to calculate design thicknesses for airfield pavements. The design method
is computationally intense, so the FAA developed a computer program called
FAARFIELD to help pavement engineers implement it.
2) Application
The procedures and design software identified in this Project are intended to provide
pavement thickness design standards for all airfield pavements.
3) Design Program
FAARFIELD is based on the cumulative damage factor (CDF) concept, in which the
contribution of each airplane in a given traffic mix to total damage is separately
analyzed. Therefore, the FAARFIELD program should not be used to compare
individual airplane pavement thickness requirements with the design methods
contained in previous versions of the AC that are based on the “design aircraft”
concept. Likewise, due care should be used when using FAARFIELD to evaluate
pavement structures originally designed with the thickness design curves in previous
versions of this AC. Any comparison between FAARFIELD and the design curve
methodology from previous versions of this AC must be performed using the entire
traffic mix.
35
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The Asphalt Binder Performance grade recommendations are altered somewhat for
the distinctive climates of the Coxbazar Airport region. For the Runway surface, PG
76-16 and PG 82-16 are recommended.
Two types of base courses are defined: stabilized and unstabilized (aggregate). A
stabilized base course may be required as described in paragraph 317.
36
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Modulus,
Layer Poisson’s Ratio
psi (MPa)
Stabilized (flexible)
150,000 (1 035)
Variable Minimum
400,000 (2 760) 0.35
Variable Maximum
400,000 (2 760)
P-401/403 Asphalt
Stabilized (rigid)
250,000 (1 720)
Variable Minimum
700,000 (4 830)
Variable Maximum 0.20
500,000 (3 450)
P-304 Cement Treated Base
700,000 (4 830)
P-306 Econocrete Subbase
The above minimum and maximum modulus values were determined on the basis of
producing thickness designs comparable with the CBR design procedures. Therefore,
typical laboratory test data for stabilized materials should not be used in preparing
input data for FAARFIELD designs. If it is necessary to establish a modulus for a
variable base layer the following guidance should be used:
For flexible pavement design, the minimum modulus value of 150,000 psi (1 034
MPa) corresponds to a base course equivalency factor of 1.2 and the maximum
value of 400,000 psi (2 758 MPa) corresponds to a base course equivalency factor of
1.6 previously used in CBR method. The equivalency factor represents the ratio of
the thickness of a standard aggregate base layer (Item P-208) to a base layer of
higher quality in the CBR method. The choice of base course modulus value can
have a significant effect on total thickness of a flexible pavement.
When a variable modulus layer is first created, the modulus is automatically set to the
minimum value.
(4) Unstabilized (Aggregate) Base Course.
The standard aggregate base course for flexible pavement design is Item P-209,
Crushed Aggregate Base Course. In FAARFIELD, P-209 Crushed Aggregate
corresponds to the standard material. Item P-208, Uncrushed Aggregate, is not
suitable as a base course material. Item P-208, when used as a base course is
subject to the restrictions in paragraph 310. The modulus of aggregate layers is
computed automatically and cannot be changed manually.
37
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The modulus values of the sublayers decrease with increasing depth of a sublayer
within the aggregate layer and are also dependent on the modulus of the layer below
the aggregate layer.
Aggregate layers can be placed anywhere in the pavement structure except at the
surface or subgrade. The following additional restrictions also apply:
Only one crushed layer and one uncrushed layer may be present in a structure. This
is for compatibility with the “Modulus” procedure. (Sublayering by the “Modulus”
procedure accounts for thick layers, and multiple layers of a single aggregate type
are not necessary.) The maximum number of aggregate layers that may be present
in a structure is therefore two, one of each type.
If crushed and uncrushed layers are adjacent, the crushed layer must be above the
uncrushed layer (to be compatible with the “Modulus” procedure).
The modulus value displayed in the structure table for an aggregate layer is the
average value of the sublayer modulus values. The only exception is for newly
created layers, in which case the modulus values of 75,000 psi (517 MPa) and
40,000 psi (276 MPa) are displayed for crushed and uncrushed respectively. These
default modulus values are never used in calculations.
FAARFIELD, by default, computes the structural thickness required for the base
course. Since it is assumed that the subbase layer provides the equivalent bearing
capacity of a CBR 20 subgrade, the structural base course thickness is computed as
the thickness required to protect a subgrade of CBR 20.
For traffic mixtures with airplanes exceeding 100,000 pounds (45 400 kg), a
stabilized base course is required. The minimum stabilized base thickness is 5
inches (127 mm). When a stabilized base is used, an additional step is added to the
automated base thickness design procedure. After the thickness of the aggregate
base structurally required to protect a CBR 20 subgrade is computed (step 1 above),
the required thickness of the stabilized base is obtained by dividing by 1.6. The
required stabilized base thickness thus obtained is compared with the 5 inch (127
mm) minimum requirement, and the larger of the two values is selected as the design
stabilized base course thickness.
38
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
*Values are listed for reference. However, when the traffic mixture contains airplanes
exceeding 100,000 lbs. (45 400 kg) gross weight, a stabilized base is required.
In addition, any material suitable for use as a base course can also be used as a
subbase course with a stabilized base layer.
39
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
(7) Subgrade.
The subgrade is assumed to be infinite in thickness and is characterized by either a
modulus or CBR value. Subgrade modulus values for flexible pavement design can
be determined in a number of ways. The procedure that will be applicable in most
cases is to use available CBR values and substitute in the relationship:
CBR = 1500ⅹE, (E in psi)
This method will provide designs compatible with the previous FAA design procedure
based on the CBR equation. Although FAARFIELD requires input of the material
elastic modulus, direct input of CBR values is also acceptable
The concrete surface must provide a texture of nonskid qualities, prevent the
infiltration of surface water into the subgrade, and provide structural support to the
airplanes. The quality of the concrete, acceptance and control tests, methods of
construction and handling, and quality of workmanship are covered in Item P-501,
Portland Cement Concrete Pavement.
(1) SUBBASE.
The standard FAA subbase for rigid pavements is 4 inches (100 mm) of Item P-154,
Subbase Course. In some instances, it may be desirable to use higher-quality
materials or thicknesses of P-154 greater than 4 inches (102 mm). The following
materials are acceptable for use as subbase under rigid pavements:
40
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Rubblized Portland cement concrete can also be used as a subbase for rigid
pavements.
(4) SUBGRADE.
41
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
42
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
where:
For existing pavements the E modulus can be determined in the field from non-
destructive testing (NDT) such as falling-weight deflectometer (FWD) tests and this
may be necessary if direct testing of the subgrade is impractical. If the subgrade is
accessible then the k-value can be determined directly by plate-load testing. If the k-
modulus can be determined by plate load testing, or is otherwise available, then the
k-value should be input directly into the FAARFIELD program without first converting
to E modulus.
The designer is cautioned that the obtained values are approximate and engineering
judgment should be used in selecting a design value.
43
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
44
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4.2.4 ACN-PCN
ACN is defined as a number that expresses the relative effect of an aircraft at a given
weight on a pavement structure for a specified standard subgrade strength.
The ACN-PCN system is structured so a pavement with a particular PCN value can
support, without weight restrictions, an aircraft that has an ACN value equal to or less
than the pavement’s PCN value. This is possible because ACN and PCN values are
computed using the same technical basis.
45
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
International Cargo
Flights Domestic Passenger Flights General Aviation
Passenger Flights Flights
Aircraft B737-800 A-310 Dash-8 ATR-72 B737/MD82/MD83 HS-748 General Aviation
1) TP-4, TP-7 CBR data was excepted because test data curve was incorrected
2) Calculated CBR was below
d2 = 3.18 (number of data > 10)
Average = 9.9
Standard deviation = (CBRmax - CBRmin) / d2 = (15.6-6.7)/3.18 = 2.8
Design CBR = Average - Standard deviation = 9.9 - 2.8 = 7.1(≒7)
Test Test Test Test Test Test Test Test Test Test Test Test Test Test Test
-1 -2 -3 -4 -5 -6 -7 -8 -9 -10 -11 -12 -13 -14 -15
10.7 6.7 15.6 3 10.7 10.9 5.8 8.4 9.5 6.9 10.8 8 11.3 9.6 9.3
Incorrect Incorrect
1) Design variable
Design life = 20 years
Pavement Type = Asphalt
46
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Traffic mix.
As the FAARFIELD, flexible pavement is to be designed for the airplane traffic mix in
table 4.4.
The subgrade CBR is 7 (E=10,500 psi). Since the traffic mix includes jet airplanes
weighing 100,000 pounds (45 359 kg) or more, an asphalt stabilized base will be
used.
47
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4.3.4 ACN-PCN
ACN - PCN was calculated using the COMFAA 3.0 developed by FAA.
Because of that operating aircrafts gross weight is light, PCN value was calculated
42.3. For satisfying PCN 70, Airplane traffic mix have to change include heavy weight
aircraft.
48
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
For satisfying PCN 70, Assumed the traffic mix include B747-400ER(ICAO, Category
E)
1) Design variable
Design life = 20 years
Pavement Type = Asphalt
Traffic mix.
As the FAARFIELD, flexible pavement is to be designed for the airplane traffic mix in
table 4.6.
The subgrade CBR is 7 (E=10,500 psi). Since the traffic mix includes jet airplanes
weighing 100,000 pounds (45 359 kg) or more, an asphalt stabilized base will be
used.
49
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
50
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4.4.3 ACN-PCN
ACN - PCN was calculated using the COMFAA 3.0 developed by FAA.
Table 4.8 shows traffic parameters and the ACN of the traffic aircraft for all subgrade
categories. All traffic aircraft were added using the aircraft library embedded in
COMFAA. ACN code is 77.8/F/C
Gross % GW on Tire
No. Aircraft Name A(15) B(10) C(6) D(3)
Weight Main Gear Pressure
1 B747-400ER 913,000 93.6 230 56.7 63.4 77.8 99.8
2 DualWheel75 72,000 95 90 19.2 21.2 22.5 23.9
3 DualWheel60 64,500 95 90 16.7 18.6 19.9 21.3
4 DualWheel45 46,499 95 90 10.4 12.4 13.7 15
5 DualWheel45 41,006 95 90 8.7 10.6 11.7 13.1
6 MD83 161,000 94.76 195 42.4 45.9 50 53.1
7 A310-200 315,041 93.2 192.9 37.1 41.1 49.5 64.8
8 B737-800 174,700 93.56 205 42.8 45.3 50.3 55.2
51
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
1) Design variable
Design life = 20 years
Overlay Pavement Type = Asphalt
As the FAARFIELD, flexible pavement is to be designed for the airplane traffic mix in
table 4.4.
The subgrade CBR is assumed 10(E=15,000 psi).
1) Prepolymer sealant.
2) 80mm IPS concrete block paving with mechanical interlock.
3) 10 mm laying course sand (compacted thickness).
52
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
53
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Existing Apron will be used temporary for standing of cargo aircrafts (Code C) until
constructing of new cargo apron.
Actually, existing apron area is divided two part, one is rigid pavement and other is
asphalt overlay on the rigid pavement, so expanding area may construct by same
type and thickness.
However, the expanding area is not big and the only one area for rigid pavement, so
this area is suggested to construct flexible pavement by calculated thickness of new
taxiway by air traffic demand for more efficiency and easiness of construction.
4.4.4.7 Shoulder
1) Design variable
Design life = 10 years
Pavement Type = Asphalt
Traffic mix.
For designing Shoulder, Use 1% Departure Traffic of Maximum gross weight airplane
54
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
55
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4.4.8 Overrun
Traffic condition applicable to design is based on the traffic volume of large vehicles
which run to one way per day. There is no the detailed traffic volume for the landside.
In this design, Traffic B based on 250~1,000 vehicles per day is applied.
Traffic Volume Type Traffic Volume for Large Vehicle (car/day, one way)
L Below 100
A 100 ~ 250 below
B 250 ~ 1,000 below
C 1,000 ~ 3,000 below
D Above 3,000
Note : Large vehicle indicates freight car, bus, and special automobiles.
In Traffic B road, if Design CBR for subgrade soil is 7%, the target value is set to
TA=21cm and total thickness(H)=38cm. Compute the pavement thickness, and verify
TA and H as shown below:
TA = (1.0 × 5) + (0.8 × 15) + (0.25 × 20) = 22 > 21cm
H= 5 + 15 + 20 = 40 > 38 cm ∴ O.K
56
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The Security & service road is a road of which the traffic is very small. It is based on
Traffic L which one-way traffic per day is under 100 vehicles.
Design CBR applies CBR=7% equal to that of apron pavement.
Total 30cm
57
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.4.7 Conclusion
58
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
59
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The FAA design practice will be applied for the design of storm water drainage of the
entire airport. Some of the applicable standards are published in the following manuals:
"Airport Drainage" (A/C 150/5320-5C) published by U.S Department of Transport,
Federal .Aviation Administration (FAA), 2006
"Design Guideline of Airport Drainage Facility, Underground Roads and
Common Utility Trenches" published by the Civil Aviation Bureau, Ministry of
Land, Infrastructure and Transport of Japan, 2005
1) Return Periods
In accordance with the FAA Standards, 5-year storm frequency is applied ;
a. Return Period of Airside area : 5 years
b. Return Period of Landside area : 5 years
2) Runoff
Runoff is calculated using this Rational Method or equivalent in accordance with this
formula:
1
Q C I A
360
Q = Runoff (m3/sec)
C = Runoff Coefficient
I = Rainfall Intensity(mm/hr)
A = Catchment Area(ha)
Runoff Coefficient C will be based on the retention characteristics of the surface under
consideration. The following values will be used and will be weighted according to area in
the case of multiple classifications;
Application:
a. Asphalt/Concrete pavement 0.80
b. Sandy soils, with turf (below 2% slope) 0.13
c. Cultivated Area 0.60
60
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
3) Rainfall Intensity
The rainfall intensity-duration pattern shown in Figure 4.16 is used in cox-bazar area( i.e
Chittagong)
I = 4180 / t +18
Where, I = Rainfall Intensity (mm/hr)
t = inlet time(min)
4) Inlet velocity
In accordance with the FAA Standards, inlet time would be used as flows
61
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
a. Inlet Time : t1
(FAA formula)
6) Calculation of discharge
The manning’s formula shown below is applied
Q=AXV
So, the comparison with runoff and discharge would be needed to evaluate the drainage
design
The airport drainage system will be divided into two areas as shown in Figure 4.4.2.
This general layout has been designed to minimize box culvert or pipe culvert and
crossing underneath the runway and taxiways.
62
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The catchment areas of drainage system of Cox’s bazaar airport will be designed
according to the catchment area. However, the runoff will be increased due to the
development of the airport (new buildings and pavements will increase the runoff
coefficient, and the new drainage system will concentrate the discharge in a shorter
period of time). In order to minimize the charge of flow volume and to avoid flooding
and irrigation problems downstream, outfall of each drainage system will be attached to
designed flow lines, as shown in Figure 4.18.
63
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
64
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
65
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.6.1 Object
Unit : m
1 in 10 4.16 -0.50
1 in 20 4.42 -0.08
1 in 50 4.76 0.46
The possibility of big surge which is caused serious impact by weather condition such
as Cyclon is low because the water level is shallow as like 0~2.0m, and the distance
66
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The end of runway extension area is located on the river bank of Moheshkhali River
which is changed the water lever frequently by the ebb and flow of the tide.
In the estuary, the vast open sedimentary field is made up, and several natives live
around that area.
According to the result of site survey, special embankment protection such as sea
wall may be not economical, so general embankment protection of dike is proposed
to the reclamation area for the runway extension.
1 : 1 : 2.5
2
Sand Reclaim
67
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
0.5
E.L. (+)6.00
0.2
Cap Con'c
400¡ ¿
400¡ ¿
1 50(È £
¾Èº í· Ï)
1 1 : 2.5
:2
H.W.L. (+) 4.00
Sand Reclaim
G.L
Mat(º ÎÁ ÷
Æ÷)
0.5
M.S.L. (+) 2.00
0.5
± â
à ÊCon'c 0.5
○ The proposed dike protection design is based on site condition of surveying time
and limited data.
○ Later, the embankment protection should be considered reinforcement of section by
changing of reclamation method and materials and careful investigation of natural
condition.
68
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.7.1 Marking
69
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Items
Figures Characteristics & Colors
Type
- Magnetic azimuth
Designation (Direction 05, 23)
marking
- White Color
- Distance between
threshold : 900m
- Longitudinal spacing : 150m
from the threshold
Touchdown
- Pairs of marking
zone
3 pairs : 2EA
marking
2 pairs : 2EA
1 pair : 2EA
- Width : 1.8m, Gap : 1.5m,
Length : 30m , White line
70
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Items
Figures Characteristics & Colors
Type
- Distance between
threshold : 40m
Aiming point
- W : 10m, L : 60m
- White line
Runway
- Reverse V shape by
Pre-threshold Aircraft approach direction
marking - W : 90㎝, G : 30m
- Yellow line
SMGCS - W : 30㎝
Center line - Yellow line with 15cm Black
marking line at both sides.
71
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Items
Figures Characteristics & Colors
Type
Non- Dotted line
movement - Dotted line with 1m width of
area 1m gap
boundary Line = 15cm - Yellow color
Dotted line
marking
- Width : 15㎝
Equipment - Red line
restraint - It should be marked to be
area marking able to stand GSE
equipments
Apron
- Width : 15㎝
Equipment - White dotted line ; 1m long
staging area at 1m gap
- It should be marked to be
marking
able to stand GSE
equipments
Stop line
- Stop line by aircraft type is
marking by
marked on surface of Gate.
A/C
72
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4.7.2 Fence
A fence or other suitable barrier should be provided on the airport to deter the
inadvertent or premeditated access of an unauthorized person onto a non-public area
of the airport.
B. Screening Gate
The gate installed on the road for going in and out of airport operating area shall be
controlled by guard.
- Selection of zinc hot dip plating material with strong resistance to corrosion
Airside/Adjacent Area Fence
- Installing a security block fence to block up outsiders' access
- Selection of concrete block material with strong resistance from outer impact.
73
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Airside/Adjacent
1 Wire
area
Split Block +
Airside/Terminal
2 Chain-Link
& Landside area
fence
74
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
5.1 GENERAL
The scope of these design criteria is to provide a minimum requirement for the
airfield lighting system design of the Cox’s Bazer Airport.
Airfield Lighting System(hereinafter “ALS”) consists of light and colour is the facility
which helps airports to take off and land safely.
75
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
All works specified will be in accordance to all applicable sections of the latest edition
of the following codes and standards:
ICAO Annex 14 Volume Ⅰ, Aerodrome Design and Operations – Fifth
Edition(July 2009)
ICAO 9157-AN/901 Aerodrome Design Manual, Part 4, Visual Aids – Third
Edition, 1993
ICAO 9157-AN/901 Aerodrome Design Manual, Part 5, Electrical System – Third
Edition, 1983
FAA Advisory Circulars 150/5340, 5345
IEC - International Electro-technical Commission
IEEE - Institute of Electrical & Electronics Engineer
NEC - National Electrical Codes
The airfield lighting system will fully conform to ICAO Annex14 Standard and
76
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The airfield lighting layout, operational performance, and requirement will be strictly
in accordance with the current edition of ICAO Annex14 Volume 1 (Aerodromes),
Aerodrome Design Manual Part 4 (Visual Aids) and Part 5 (Electrical System) and
other applicable ICAO standard, Airfield lightings to be provided will consist of
following systems for this category-Ⅰ of runway/taxiway and apron operations;
9) Stopway Lights
All elevated equipments installed within runway and taxiway obstacle limitation zones
will be light-weight on frangible mounted bases ;
Airfield lighting fixtures will be equipped with prefocus halogen lamps of rated life not
77
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Runway edge lights will be elevated fixed lights showing variable white in accordance
with ICAO specifications of Annex14, Vol.1, para.5.3.9, including Appendix 2, Figure
A2.9. The lighting will be shown at all angles in azimuth necessary to provide
guidance to a pilot landing or taking off in either direction.
The edge lights will be placed along the full length of the Runway, uniformly spaced
in to rows at intervals of not more than 60 m. Inset high intensity bi-directional runway
edge lights are to install at intersections of runway and taxiway.
600m
60m
3m
Runway
Threshold
Runway Edge
: Runway Edge Light (W/Y)
: Runway Edge Light (W/W)
Runway threshold lighting will be inset unidirectional lights showing green in the
direction of approach to the runway. Runway threshold lights will be in accordance
with the ICAO specifications of Annex14, Vol.1, para.5.3.10, including Appendix 2,
Figure 2.3.
Runway end lights will be fixed unidirectional lights showing red in the direction of the
runway. The runway end lights will be in accordance with ICAO specifications of
Annex14, Vol.1, para5.3.11, including Appendix 2, Figure 2.3.
78
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Threshold lights and runway end lights will be installed at the extremity of the runway;
Threshold lights will be uniformly spaced between the rows of the runway edge lights
at intervals of not more than 3m. Runway end lights will consist of eight lights
symmetrically disposed about the runway center line in two groups with the lights
uniformly spaced in each group.
Elevated threshold high intensity unidirectional wing bar green light is to provide the
ICAO photometric performances for use in runway operation conditions.
Wing bar lights shall be symmetrically disposed about the runway centre line at the
threshold in two groups, i.e. wing bars. Each bar shall be formed by at least 10m
outward from, and at right angles to, the line of the runway edge lights, with the
innermost light of each wing bar in the line of the runway edge lights.
3) Precision Approach Lighting System with Capacitor Discharge Lights (Runway 17,
CAT-Ⅰ)
Approach lights will be fixed unidirectional high intensity light is to provide the ICAO
photometric performance for use in category Ⅰconditions. The lights will be in
accordance with ICAO specifications of Annex14, Vol.1, para.5.3.4, including
Appendix 2, Figures A2.1 (white light).
The approach lighting system will consist of a row of lights on the extended center
line of the runway, extending over a distance of 900m from the runway threshold and
placed at longitudinal intervals of 30m. In addition the system will have at 300m from
79
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
the threshold. The center line of the approach system will consist of four lights,
showing variable white, forming a barrette of 4.5m length.
The crossbar provided at 300m from the threshold will extend on both aides of center
line to a distance of 15m from the center line.
300m±15m
10.5m
30m±3m
30m
Runway
Centerline
4m
10.5m
4.5m
Centerline Barret
10.5m 2.25m
80
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
4) Simple Approach Lighting System with Capacitor Discharge Lights (Runway 35,
SSALF)
The lights will be in accordance with ICAO specifications of Annex14, Vol.1,
para.5.3.4, including Appendix 2, Figures A2.1 (white light).
Center line barrette lights shall be placed at longitudinal of 60m on the extended
center line of the runway extending over a distance of 420m from the threshold.
Crossbar lights shall be placed at 300m from the threshold, as nearly as practicable
in horizontal straight line at right angles to, and bisected by, the line of the center line
lights. The lights of the crossbar shall be spaced so as to produce a linear effects,
expect that, when a crossbar of 18m is used, gaps may be left on each side of the
center line. These gaps shall be kept to a minimum to meet local requirements and
each shall not exceed 6m.
270m±15m
300m Cross bar
150m±15m
10.5m
30m±3m
30m
Runway
Centerline
10.5m
4.5m
Centerline Barret
10.5m 2.25m
81
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The PAPI system will be in accordance with ICAO specifications of Annex14, Vol.1,
para.5.3.5 and ICAO Aerodrome Design Manual, Part 4, Chapter 8.4. The system will
consist of a wing bar of four sharp transition multi-lamp units located on the left side
of the runway spaced 9m apart with the inner light unit being 15m from the runway
edge. The system will be suitable for both day and night operation. The light intensity
distribution of the light units will be as per Annex14, Vol.1, Appendix 2, figure A2-23.
Each light will project a beam of light having white color in its upper part and a red
color in its lower part. The light units will be arranged in such manner that a pilot of
aircraft during approach, will see: four white light units when 3.0° above the approach
slope; three white and one red light units when 10° above the approach slope; two
white and two red when on the approach slope; one white and three red when 10°
below the approach slope; four red when 3.0° below the approach slope.
The distance of the PAPI from the runway threshold will be suitable to provide
adequate wheel clearance over the threshold for all types of aircraft landing on the
runway and will be harmonized with the Instrument Landing System (ILS) glide path.
Obstacle Protection Surface (OPS) will also be considered in determining the
optimum PAPI location.
About 400m
Runway
15m 9m 9m 9m
Approach
82
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Taxiway
4m
90m
Figure 5.6 Runway Guard Lights Configuration
Runway distance remaining Marker Signs are located along the sides of runway, to
indicated the runway distance remaining increment 300m.
300m 300m(TYP.)
20m
83
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
8) Stopway Lights
Stopway Lights shall be placed along the full length of the stopway and shall be in
two parallel rows that are equidistance from the center line and coincident with the
row of the runway edge lights.
Stopway Lights shall also be provided across the end of a stopway on the line at right
angles to the stopway axis as near to the end of the stopway as possible and, in any
case, not more then the end.
Stopway Lights will be in accordance with the ICAO specifications of Annex14, Vol.Ⅰ,
para 5.3.15.
less than 60m
3m
3m
Runway
Threshold
Stopway
1.5m
Runway Edge
Taxiway Edge Lights shall be provided at the edge of a runway turn pad, holding bay,
apron, etc., intended for use at night and on a taxiway not provided with taxiway
center line lights and intended for use at night.
The lights on a straight section of a taxiway will be spaced at uniform longitudinal
interval of not more than 60m. The lights on a curve will be spaced at interval less
than 60m so that a clear indication of the curve is provided.
Taxiway Edge Lights shall be fixed lights showing blue. The lights shall show up to at
least 75˚ above the horizontal and at all angles in azimuth necessary to provide
guidance to a pilot taxiing in either direction.
Taxiway edge Lights will be in accordance with the ICAO specifications of Annex14,
Vol.Ⅰ, para 5.3.17.
84
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
"Z"
"Z"
(UNIT : m)
RADIUS (R) DISTANCE (Z) RADIUS (R) DISTANCE (Z)
4.5 6.0 90.0 24.0
7.5 8.0 120.0 28.5
15.0 10.5 150.0 33.0
22.5 12.0 180.0 36.0
30.0 15.0 210.0 43.5
45.0 16.5 240.0 49.5
60.0 18.0 270.0 55.5
75.0 21.0 300.0 60.0
Mandatory and information guidance signs will be in accordance with ICAO Annex 14,
Vol.1, para,5.4, including Appendix 4, and IACO Aerodrome Design Manual, Part 4,
Chapter 11.
Signs shall be frangible. Those located near a runway or taxiway shall be sufficiently
low to preserve clearance for propellers and the engine pods of jet aircraft.
85
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The beacon will be located on the aerodrome in a location such that the beacon is
not shielded by objects in significant directions and does not dazzle approaching
pilots.
The wind direction indicators will be in accordance with ICAO specification Annex 14,
Vol.1, para.5.1.1. The wind cone will provide a clear indication of the direction of
surface wind and a general indication of the wind speed.
The wind cone will be in a form of fabric cone installed on a mast. The cone will be
3.6m long and 0.9m diameter at larger end. Its color will be international orange or
red-and-white, as required. The mast will be approximately 6m high and its
construction will allow servicing of the cone from The ground. Swivel mechanism will
be sealed type, maintenance free.
The location of at least one wind direction indicator should be marked by a circluer
band 15m in diameter and 1.2m wide.
Wind cones will be illuminated.
86
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Adequate illumination is required to help pilots taxi aircraft into and out of terminal
parking rates, to facilitate loading and unloading of passengers and cargo, fuelling
and other general activities, to service vehicle movement and to maintain overall
security.
Apron flood lightings will be provided for the 6 passenger terminal gates and at the
two westerly remote aircraft stands. The flood lightings will be in accordance with
ICAO recommendations of Annex 14, Vol.1, Paragraph 5.3.21 and ICAO Aerodrome
Design Manual, Part 4, Chapter 13.
The average illuminate will be as follow:
Aircraft stands:
Horizontal illuminate ─ 20 lux with a uniformity ratio (average to minimum) of not
more than 4 to 1;
Vertical illuminate ─ 20 lux at a height of 2m above the apron in relevant
direction; and
Horizontal illuminate ─ 50 percent of the average illuminate on the aircraft
stands with a uniformity ratio (average to minimum) of not more than 4 to 1.
Fifty percent (50%) of lights at the Apron and westerly remote aircraft parking
positions will be supplied from the main substation emergence power system. High
Intensity Discharge (HID) lamps of 1,000W will be stylized. Additional 1,000W quartz
will be installed at each aircraft stand and bus loading/unloading area. They will
provide reduced illumination during the time of restarting of HID lamps upon a normal
power failure.
Luminaries will be of a high cut-off to pervert glare affecting pilots and nearby air
traffic controllers. Fixtures will be mounted on up-down poles. Lighting will be
87
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
controlled from the Airfield Lighting substation and control tower. Power for apron
floodlighting will be supplied from the Airfield Lighting substation power distribution
system.
Obstacle lights will be in accordance with ICAO Annex 14, Vol. 1, para.6.3. The
obstacle lights will be provided at specified locations such as airside pad transformer,
and apron floodlighting poles, field equipment towers, etc. It is anticipated that the
use of low intensity obstacle lights will be adequate. The low intensity lights will be
fixed red incandescent. Obstacle lights will be supplied from emergency power
source and operated by photocells.
88
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
All circuits will be basically interleaved and have a primary constant current maximum
of 6.6A or 20A. Each element of the system will be separately circuited and
individually controlled
2) Applicable Standards
3) Review of Standards
The requirements for circuits configuration in ICAO Aerodrome Design Manual Part 5,
Chapter 3 are as follows :
Generally for a precision approach runway, the electrical circuits will be designed so
that the failure of one circuit will not leave the pilot without visual guidance and will
not result in a misleading pattern.
Approach lights should be on two separate circuits interleaved over two circuits.
Threshold lights should be on two separate circuits interleaved over two circuits.
89
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
According to ICAO Aerodrome Design Manual Part 5, Section 3, most airfield lighting
series circuits are either 6.6A or 20A at rated intensity. Applications of Series circuits
are as show in the following table.
Runway end lights will be supplied from the runway edge lighting circuits.
Signage lighting circuits shall not be permitted to be combined with any other circuit.
Aerodrome beacon will be supplied from 240V, main s/s power supply with
emergency back-up.
Field wiring will utilize series lighting circuits operated at up to 5 kV AC with a
constant current of 6.6A and 20A. All lamps will operate airfield lighting isolating
transformers. Wiring and isolating transformers will be installed underground.
90
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
1) AFL Substation
Airfield circuits will originate from a field AFL Substations. The AFL substation will
contain power distribution equipment and Constant Current Regulators (CCRs)
specially designed for series lighting circuits
The substations will be comprised of, but not limited to, a number of equipments.
The will be, install, wire, connect, terminated, commission, and start up these items
which include:
UPS, transfer switches, batteries, control cabinets and auxiliaries;
Transformers;
High voltage/Low voltage switchgears;
CCR (Constant Current Regulator) ;
Communications interface equipments; and
Control and monitoring equipments for AFL
91
Electric Power Single line Diagram
EH
1
ALTS
EH
2
LBS,12KV (AIR CIRCUIT BREAKER) (POTENTIAL TRANSFORMER)
LA×3
EH
3 (MOLDED-CASE CIRCUIT BREAKER) (CONSTANT CURRENT REGULATOR)
PF,12KV
VCB,12KV
DIPM
V, A, kW 51
CTx2
PF,F,27 51G
92
DIPM DIPM DIPM DIPM
V, A, kW 51 V, A, kW 51 V, A, kW 51 V, A, kW 51
CTx2 PF,F,27 51G CTx2 PF,F,27 51G CTx2 PF,F,27 51G CTx2 PF,F,27 51G
TR TR
1 2
LV LV
1 2
1A PTx2 1A PTx2
DIPM DIPM
V, A, kW 51 V, A, kW 51 LV LV LV
CTx2 CTx2 6 MCCB 4P 7 MCCB 4P 8 MCCB 4P
PF,F,27 51G PF,F,27 51G
LV
3 G
GCP
ATS
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
MCCB 2P
LV
5
ELD
ZCT
UPS
LV
4 PTx2 PTx2 PTx2
1A 1A 1A
CUT OUT
ACB ACB ACB SWITCH 20CCT
PAPI 01L
PAPI 02L
Circuit Name
15KW
4KW
4KW
10KW
10KW
15KW
15KW
5KW
5KW
20KW
15KW
10KW
5KW
5KW
4KW
4KW
7.5KW
7.5KW
20KW
20KW
7.5KW
20KW
BEACON LIGHT
SFL CONTROL PNAEL#1
SFL CONTROL PNAEL#2
WIND CONE #1
WIND CONE #2
AIR CONDITIONER #1
AIR CONDITIONER #2
PLC & INTERFACE PANEL
CONTROL PC
APRON FLOOD LIGHT #1
APRON FLOOD LIGHT #2
APRON FLOOD LIGHT #3
APRON FLOOD LIGHT #4
APRON FLOOD LIGHT #5
APRON FLOOD LIGHT #6
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
2) Power Supply
Electrical power for airfield lighting will be provided from the AFL substation.
Dedicated feeders will be provided for individual circuits as required. Emergency
power will be obtained from the stand-by diesel generator.
Upstream switch board. Power supply under Cat-Ⅰ conditions will be from a
selected generator with the utility power as “stand-by”. This arrangement will satisfy
15 sec power switch over requirements between the two source as specified by
ICAO
3) Constant Current Regulators (CCR)
The design of CCR is to provide appropriate light intensity settings and control for
safe aircraft operations in various ambient/meteorological conditions. CCR’s
provision are to ensure such purpose. All the Light intensity of AFLS will be follow
international standards. The maximum rating of any CCR should not exceed 30kw.
Provisions are to be made to ensure that the CCR input/output power factor shall not
be less than 0.9. For ease of maintenance, all CCRs will be divided into two separate
compartments. Low Voltage (LV) and High Voltage(HV). The LV side provides the
control and the HV side provides the power to the lighting circuits. The LV panels will
be rack-mounted and the units will be housed in withdrawal drawers. All control units
will be of the plug and socket type. Any specialize equipment or tool will be included
with the equipment. The CCR will be designed for direct interconnection with a
computer-based network.
93
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
It is required that all the airfield lighting and control systems including, but not limited
to, AFL and NAVAIDS system be supplied from a clean-AC power supply at all times.
This power supply will be completely free from harmonic, be of true sinusoidal wave
shape, isolated and independent of utility switching, voltage & frequency
disturbances and also free from load fluctuation, unbalances, and single phasing.
Converters, inverters and filters will be required. The system shall gave 15minutes
back-up dual stationary battery including fuses, installed on a battery rack. The UPS
back-up (battery and diesel) will be supplied ten (10) to fifteen(15) times full-fated
current within 1/2 cycle to facilitate the clearing of an output load fault. The UPS will
be completed with by-pass switches and self monitoring capability suitable for local
and remote annunciation.
The system should include a day & storage fuel tanks as well as batteries, switches,
battery chargers, generator & other control modules, fusses, racks, circuits breakers,
panels, full load automatic transfer switches, control modules capable of automatic
and manual synchronization with both live and dead bus, frequency, voltage, power,
power factor and current sensors, meters, ATC or other local/remote locations. The
generator shall be able to cold start, reach system voltage and frequency within 10
seconds, synchronize and supply a full load within 30 seconds. All interlocking
schemes between the generator bus and substation switch gears will be included.
System power factor through normal or generator power will be 90% or higher.
94
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Each lighting circuit will be individually controlled from the air traffic control tower
console. On-off and light intensity select switches will be provided. The switches will
illuminate to indicate status of each lighting system. Moreover, local switches will be
installed at the regulators to allow manual override of controls from the ATC.
The control of the AFLS will be accessed via mouse equipped touch screen monitors
at suitable locations. However, the Tower Integration System will be developed by the
other contractor (Tower System Integration Contractor). The Airfield lighting control
and monitoring system will be full interfaced with the Tower Integration System.
The field devices/sensors, where fitted, will be powered from single phase electrical
source. Control input/output signal shall manually activate the sensors from various
“touch screen or mouse” monitors located in the ATC tower and AFL substations.
However, with the exception of ATC location, these functions at the remaining
locations will be inhibited or suppressed by ATC.
95
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
All primary cable will be installed in duck bank constructed by the Electrical and AFLS.
Details of the duck bank requirement including sizing and location are to be In
addition to the duct laying conduct system, isolation transformer and associated
fixture as well as identification of primary circuits will be adequately provided as
shown drawings.
96
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Duct bank for AFL System, security lighting, street lighting , ILS, flood lighting, and
each building power distribution
Review of standards:
ICAO Annex14 Aerodromes design manual Part 5(electrical system) para, 4.3.3 and
4.4 and other applicable ICAO standard;
Designed concept for duct bank:
PVC 100 m/m (earth section);
HD Steel conduit 100m/m (pavement section),
25 ~ 50 percent spare conduits(less than 4 lines: 25 percent),
Conduit laying slop 1 percent ~1.5 percent; and
Manhole installation distance:
Straight: less than 200m,
Curve: less than 100m.
97
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
6.1 GENERAL
6.1.1 Objectives
The objective of this task is to establish the design with the reasonable and affective
air navigation system; in order to have the safety flight, departure & arrival and the
reduced flight cancellation rate due to the low visibility weather condition.
Air Navigation System include Radio Navigation Aids, Air Traffic Control
Communication System and Automatic Meteorological Observation System should
be provided to allow precision approach Category I operation. The major facilities are
as follows.
Instrument Landing System
DVOR/DME (Doppler VHF Omni-direction Range / Distance Measurement
Equipment)
Air Traffic Communication System
AMOS (Automatic Meteorological Observation System)
Design criteria on the Air Navigation System for Cox’s Bazar Airport shall take the
conditions of surrounding site and facilities into account incorporating with the
standards of ICAO, FAA and Bangladesh Law and Regulations as follows:
1) ICAO Standards
The following documents to ICAO Standards used for the plan and design of airport
and support facilities, in addition to applicable technical publications, circulars and
manuals issued by ICAO will also be utilized where appropriate:
Annex 3 Meteorological Service for International Air Navigation
Annex 10 Aeronautical Telecommunications Vol.1, 2, 3, 4 & 5
Annex 11 Air Traffic Services
Annex 14 Aerodrome Design & Operation
Annex 15 Aeronautical Information Services
Doc. 9184 Airport Planning Manual Part 1
98
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
2) FAA Standards
ANO (COM) A.1 Air Navigation Order (ANO) For Radio Navigation Aids
ANO (COM) A.2 Air Navigation Order (ANO) For Aeronautical Communication
Procedures
ANO (COM) A.3 Air Navigation Order (ANO) For Communication Systems
ANO (COM) A.5 Air Navigation Order (ANO) For Aeronautical Radio frequency
Spectrum Utilization
Each runway direction has “The runway operation category” which decides the
weather minima1) and decision height2) limit. These limitations help the arrival and
departure airplane safe.
1)
“Weather minima” is the weather limit around the airport base on the runway
category.
2)
“Decision height” is the height which decides the landing or not.
The runway operation category is base on the runway length & width, the air
navigation system (radio navigation aids), meteorological observation system and the
aeronautical ground lighting system type (visual aids). If the airport meet all the basic
requirements mention above, base on the supply of radio information or not, the
runway classify as the instrument runway and non-instrument runway.
The instrument runway uses the radio wave such as LLZ, GP and DME which supply
99
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
the radio information. The non-instrument runway does not supply radio information
however the aviation light system provide visual information.
100
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
2. DVOR/DME ○ ○ ○
4. ASR/MSSR △ △ ○
5. ASDE - ○ ○
6. AMOS ○ ○ ○
The power supply switch-over times for air navigation and air field lighting systems
are dependent on the type of runway and aircraft operations to be supported. Table
6.2 indicates representative switch-over times which may be met by power supply
systems currently available.
101
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Category
CAT-Ⅰ CAT-Ⅱ CAT-Ⅲ Remarks
Facility
Localizer 10 sec 0 sec 0 sec
Glide Path 10 sec 0 sec 0 sec
Siting Criteria for Instrument and Landing System in ICAO Annex 10 and FAA Order
6750.16D are compared as given to the below table.
Siting Criteria
Item Description Remarks
ICAO FAA
Outside distance from the end of
Minimum 300m 300m~600m
runway
LLZ
Both side distance from the On the On the
centerline of runway centerline centerline
102
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
The Cox’s Bazar Airport will be operated with CAT-I. The occurrence of interference
to ILS signals is dependent on the total environment around the ILS antennas, and
the antenna characteristics. Any large reflecting objects, including vehicles or fixed
objects such as structures within the radiated signal coverage, will potentially cause
multipath interference to the ILS course and path structure. The location and size of
the reflecting fixed objects and structures in conjunction with the directional qualities
of the antennas will determine the static course or path structure quality whether
Category I, II or III. Movable objects can degrade this structure to the extent that it
becomes unacceptable. The areas within which this degradable interference is
possible need to be defined and recognized. For the purposes of developing
protective zoning criteria, these areas can be divided into two types, i.e. critical areas
and sensitive areas:
The ILS critical area is an area of defined dimensions about the localizer and
glide path antennas where vehicles, including aircraft, are excluded during all
ILS operations. The critical area is protected because the presence of vehicles
and/or aircraft inside its boundaries will cause unacceptable disturbance to the
ILS signal-in-space;
the ILS sensitive area is an area extending beyond the critical area where the
parking and/or movement of vehicles, including aircraft, is controlled to prevent
the possibility of unacceptable interference to the ILS signal during ILS
operations. The sensitive area is protected against interference caused by large
moving objects outside the critical area but still normally within the airfield
boundary.
Typical examples of critical and sensitive areas that need to be protected are shown
in Figures 6.1, 6.2. To protect the critical area, it is necessary to normally prohibit all
entry of vehicles and the taxiing or parking of aircraft within this area during all ILS
operations.
103
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Figure 6.1 Typical Localizer Critical and Sensitive areas dimension variations
Figure 6.2 Typical Glide Path Critical and Sensitive areas dimension variations
104
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
As the Instrument Landing System is an essential facility to lead the safe landing of
the aircraft on the runway, one unit of the System will be installed at ends of the
runway 17 direction of Cox’s Bazar Airport as is described at Table 6.3.
The localizer of Dual Frequency, glide path and unidirectional DME are installed
for runway operation Category-I, RVR 550m or above to be suitable for the
operation. RCSU is installed for remote controlling and monitoring the equipment
on the site is installed at the ILS/VOR Monitoring room.
The shelter to be installed at the field to accommodate the navigational aids and
communication equipment shall be made of frangible material which is easily
breakable against a certain impact in accordance with the standard of ICAO
DOC 9157.
Control and power parts of the navigational aids and communication equipment
shall be composed of the main and stand-by redundant system to build up stable,
reliable and non interrupt able operation system.
6.4 DVOR/DME
DVOR/DME sends the azimuth angle and the distance information to the
approaching aircraft using the DVOR and DME for safe trip to the final destination.
Doppler VHF Omni-directional Range (DVOR): Send the azimuth angle
information to the approaching aircraft for safe trip to the final destination.
Distance Measurement Equipment (DME): Send distance information to the
approaching aircraft for safe trip to the final destination.
Siting Criteria for Instrument and Landing System in ICAO Annex 10 and FAA Order
105
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Siting Criteria
Item Description Remark
ICAO FAA
Distance from the centerline of
- Minimum150m
runway
Distance from the centerline of
- Minimum75m
taxiway
Antenna radio disturbance distance Min. 150m
Min.300m
from surrounding ground buildings Vertical angle1.2°
DVOR/DME is to provide the aircrafts using the airport facilities with the information
on the direction and distance and to support the non-precision instrument approach
and it can be used for the aircraft with non precision approach to the runway of Cox’s
Bazar Airport.
This equipment provides the information on the direction (0~360°) and distance
of the aircrafts. Departure flight route is provided to the take off aircrafts while
approach flight route is given to the landing aircrafts. So the system is utilized for
the airport approach, take off and landing as well.
Due to the limited coverage of radio emitted by ILS, all the approaching
aircrafts should make use of VOR/DME during flight (homing, holding and
initial approaching stage) before they enter the space (extended zone of the
landing runway) where ILS signal can be used . The system is a very important
facility that should be operated with non interruption during the aircraft operation
hours and also it is an essential facility for CAT-I operation grade.
106
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Air Traffic Control Communication System use frequencies band such as HF,
VHF(118.0MHz~136.975MHz) and UHF(225MHz~ 400MHz) to send the voice and
data information between the pilot and the controller for the safe aviation traffic
control using the receiver transmitter and the control system.
Radio equipment : Send the voice and data information between the pilot and
the controller
STVS : VHF Radio equipment and control equipment control many wire system
which help smooth communication service.
Multi-transceiver : In case of VHF Radio equipment have trouble, multi-
transceiver is use as the emergency equipment
ATIS : Broadcast the airport runway condition, the weather condition, the
NOTAM information
Transmitting and receiving center for control communication shall be located at the
area without surrounding obstacles, having broad visual range and free from radio
disturbance.
107
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
6.5.2 Air Traffic Control Communication System Configuration and Layout Plan
ATC communication system for air traffic control is to provide the Air to Ground (A/G
and G/G) communication between air traffic controller and pilot to support the safe
operation and control.
VHF Tx/Rx
The dual way wireless transmitting and receiving equipment will be selected
among the most suitable facilities for approach control, departure control, ground
movement control and the apron. Duplexing system will be built for non
interrupted operation against disaster and obstacle to provide the air traffic
control with high efficiency.
- Aviation control communication, wireless transceiver channels are
Aerodrome Control, Approach Control, Ground Control, ATIS and
Emergency Control.
- The transmitting and receiving channels for the air traffic control
communication consists of Tower Control (1), Ground Control (1), ATIS (1)
and Emergency (1) and Spare (1).
108
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
Table 6.8 Air Traffic Communication System Requirement and Layout Plan
AMOS collect the weather information of runway such as the wind direction, the wind
speed, the temperature, the moisture, the pressure, the visibility and the ceiling in
real time and send to the pilot for safe takeoff and landing using the sensor, DCP,
DPU, other equipment and software and see below for more detail.
Runway Visual Range: measurement of runway visibility
Wind speed & direction sensor: measurement of wind direction and speed
Temperature sensor: measurement of temperature
Humidity sensor: measurement of humidity
Atmospheric Pressure sensor: measurement of air pressure
Ceilometer sensor: measurement of cloud height
109
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
ICAO and FAA standards require one unit of the AMOS for CAT-I to be installed at
both ends of the runway and Table 6.9 gives the guides for selecting the location
complying with the standards.
110
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1
111
DEVELOPMENT OF COX’S BAZAR AIRPORT (PHASE-I), STAGE-1