Weather Delays and Impacts
Weather Delays and Impacts
Weather Delays and Impacts
•
normal weather to anticipate for the
time and location of project perfor-
mance.
Lyburn Construction Company,
ASBC No. 29581, 85-1 BCA 17,764
B plications of weather impacts
on the construction process,
cost engineers are able to pre-
pare better cost estimates and CPM sched-
ules. Once a weather event takes place,
—without a specific contract provi- resolution of time and cost issues can be
sion dealing with weather time exten- resolved equitably. By understanding what
sions, there is no specific standard for type of weather was involved and whether
what comparative weather data must the contract provides for recovery (time
be submitted. Some recommend a 5- and/or cost), resolution of the issue can
year minimum database, others a 50- take place quickly. However, cost engi-
year analysis. Some US federal board neers who do not understand or fail to fol-
cases have found that a 5-year period low these requirements may create an un-
is acceptable. necessary dispute, which results in added
• Little Susitna Construction Co. v. Soil costs and delays to finalizing the project.
Processing, Inc., S-7451, 1997, Su-
preme Court of Alaska—this case
dealt with the definition of turnkey Donald F. McDon-
and what risks the term inferred the ald Jr., PE CCE, is
contractor is taking. An initial delay the president of Con-
by the owner to the start of work shift- struction Performance
ed weather-sensitive work into adverse Specialists, Inc. (CPS)
winter weather conditions. The court in Tyler, TX, and is a
held that the owner could not force long-time member of
the contractor to absorb this risk. AACE International.◆
• Anderson Development Corp. v.
Coastal States, 543 S.W.2d 402 (Tex.
Civ. App. 1976)—a pipeline contrac- Welcome to the AACE
tor was forced to work in wet weather
beyond the contract period because of Bookstore!!
owner delays to the project. The court
awarded damages for the added time AACE International is your one-
and cost of weather events. Damages stop source for all of the leading
were awarded even though the weath- publications you need!
er events occurred after the original
contract period. The contractor was
due a time extension for the earlier AACE members receive
owner delays, thus pushing its work significant savings on books
into a later weather-sensitive time. from the best cost/project
• H. John Homan, Co. v. US 418 F.2d management publishers, and
522 (Ct. Cl. 1969)—a contractor was also get discounts on AACE’s
delayed by the owner and forced to own Professional Practice
perform work in wet weather and was Guides, Transactions, Cost Engi-
awarded damages because of cold
neers’ Notebook, and more!
weather operations productivity loss-
es.
• J.D. Hedin Construction Co. v. US
456 F.2d 1315 (Ct. Cl. 1972)—this is phone 800-858-COST
a famous case for owner-caused delay. or 304-296-8444
Reader Response Number 1023