Name : Dayananthan Sivalingam

Active Mobile No. +971-508580357

Active Skype ID . dayamek


SYNOPSIS:
Looking for a challenging career and assignments in the field of project engineering & management in
industrial projects and infrastructure sector to utilize my skills in an organization which offers
professional growth while being flexible and innovative and to be recognized as an efficient &
competent individual having good interpersonal, technical and managerial skills.
PROFESSIONAL SUMMARY:
I am a certified PMP, having 14+ years of overall working experience (13+ Gulf Experience) in Planning
and Project management in EPC, Oil & Gas, and I am currently working in Fortune Engineering Energy
Services L.L.C, UAE. as a Lead Engineer - Planning & Control
EDUCATION AND TRAINING:
 Certified “Project Management Professional(PMP)" from Project management institute, USA in the year
2021. PMP ID # 31933261
 Bachelor of Engineering in Mechanical Engineering with First Class from Government College of
Engineering at Salem affiliated to Anna University Chennai in the year - 2008
 Diploma in Project Planning & Management at CADD Centre, Velachery, Chennai in the year - 2009.
 HSC with First Class & SSLC with First Class with Distinction from Town Hr. Sec. School (State Board) at
Kumbakonam in the year 2004 & 2002.
 Certified Training Course on ASME SEC-VIII Div-2 from HSB Global Standards, Abu Dhabi.
 Certified Training Course on Schedule Risk Analysis using Deltek Acumen Risk from crunchtech,
Dubai
 Certified Training Course on H2S & BA competency (Level -II) from Numero Uno Training &
Consulting, AUH.
INVOLVEMENTS:
 Project Planning & Control
 Project & Schedule risk Analysis
 Delay analysis & Claim management
 Stakeholder management
Professional Experience:
Period Jan 2019 – till Date
Organization Fortune Engineering & Energy services L.L.C,UAE
Projects Handled EPC for Replacement Of Obsolete Sales Gas Metering Systems
This EPC project to Replace Obsolete Sales Gas Metering Systems 20 Nos.
in Maqta, Ruwais, Bab/Buhasa, Asab (Eastern & Western Abi Dhabi regions)
at different Consumer Receipt Stations of ADNOC Gas processing
Project Scope/Description COMPANY. Which includes Civil, Mechanical / Piping, Electrical,
Instrumentation, F&G/FACP Control systems, Telecommunications (RTU /
SDH / DCS / CTMMS), with various Shutdown works in ASAB, BAB, Buhasa
Plants.
Position Lead Planning & Project Control
 Job Responsibilities:
➢ Understanding the Contract requirements, identifying of contractual milestones and Developing Scope
summary / Project charter for the project.
➢ Preparation of the Contract Schedule & Cost Baseline with resource & cost loading & Basis of Schedule (BOS) in
accordance with Owner’s/Client’s Project procedures/ specification and ensuring the quality of the schedule
through analysis.
➢ Reviewing of Vendor’s / Sub- contractor planning packages & monitoring & control the same.

1
Name : Dayananthan Sivalingam

Active Mobile No. +971-508580357

Active Skype ID . dayamek


➢ To update & forecast with actual progress on approved baseline.
➢ To Identify the critical path activities from schedule and developing action plans to avoid critical or potential
impact.
➢ To Prepare Work Front Analysis
➢ Liaise with Contractor's Management and planning representatives to clarify and ensure the delivery of planning
information in accordance with the requirements of the overall project execution strategy.
➢ Presenting detail planning information such as Ghantt Charts, Manpower histograms, Progress S-Curves,
Commodity Curves, Progress measurement sheets & consolidated reports.
➢ To perform Cost & Project Performance analysis and Ensure that all cost, planning and document control reports
are prepared and issued in accordance with the Project Coordination Procedure & Earned value management
System.
➢ Preparation & Estimation of CTN’s & additional works for the variation claims as per contract provisions.
➢ To monitor schedule deviations and tracking the delays, Interface with the management & Client regarding
delays to avoid Liquidated Damages/Penalty.
➢ To Prepare and maintain Delays register and drafting the contractual letters to client (if any delay by client) and
PM assisting for the project acceleration cost estimation & proposal.
➢ To develop Recovery schedule/Acceleration/EOT Packages schedules along with delay analysis and relevant
backups.
➢ To Prepare & submit the Progress Reports, look ahead schedules on Daily, Weekly, Monthly basis with
Manpower & Equipment status.

Period May 2017 to Jan 2019


Organization Adyard Abudhabi L.L.C
Project Title  EPC of HETL-Pipe Line Extension to POF Berth 8 & 9, UAE.
 Installation of Ultrasonic Flow Meters in 16" gas line at ZWSC GGII -
Offshore, Abu Dhabi, UAE.
 EPC Replacement /Upgrade of CGIP Flare Piping & GGII Glycol
Regeneration system at ZAKUM-Offshore
Project Scope/Description
 EPC for new Third Instrument Air Compressor package at BUHASA,
AUH, UAE.
 Renewal of Helideck at CF platform (CFP-Trident) on Mubaraz
offshore field, AUH, UAE
 Job Responsibilities:
➢ Understanding the Contract requirements, identifying of contractual milestones and Developing Scope summary
/ Project charter for the project.
➢ Preparation of the Contract Schedule & Cost Baseline with resource & cost loading & Basis of Schedule (BOS) in
accordance with Owner’s/Client’s Project procedures/ specification and ensuring the quality of the schedule
through analysis.
➢ Reviewing of Vendor’s / Sub- contractor planning packages & monitoring & control the same.
➢ To update & forecast with actual progress on approved baseline.
➢ To Identify the critical path activities from schedule and developing action plans to avoid critical or potential
impact.
➢ To Prepare Work Front Analysis
➢ Liaise with Contractor's Management and planning representatives to clarify and ensure the delivery of planning
information in accordance with the requirements of the overall project execution strategy.

2
Name : Dayananthan Sivalingam

Active Mobile No. +971-508580357

Active Skype ID . dayamek


➢ Presenting detail planning information such as Ghantt Charts, Manpower histograms, Progress S-Curves,
Commodity Curves, Progress measurement sheets & consolidated reports.
➢ To perform Cost & Project Performance analysis and Ensure that all cost, planning and document control reports
are prepared and issued in accordance with the Project Coordination Procedure & Earned value management
System.
➢ Preparation & Estimation of CTN’s & additional works for the variation claims as per contract provisions.
➢ To monitor schedule deviations and tracking the delays, Interface with the management & Client regarding
delays to avoid Liquidated Damages/Penalty.
➢ To Prepare and maintain Delays register and drafting the contractual letters to client (if any delay by client) and
PM assisting for the project acceleration cost estimation & proposal.
➢ To develop Recovery schedule/Acceleration/EOT Packages schedules along with delay analysis and relevant
backups.
➢ To Prepare & submit the Progress Reports, look ahead schedules on Daily, Weekly, Monthly basis with
Manpower & Equipment status.

Position Senior Engineer–Planning

Period July 2016 to May 2017


Organization Petron Emirates Contracting & Manufacturing Co. LLC
Project Title AL TAWELLAH ALUMINA REFINERY PROJECT, EMAL, ABU
Project Scope/Description DHABI, UAE
Job Description :
Understanding the Contract requirements, identifying of contractual milestones and Developing Scope statement
/Project charter for the project.
➢ Preparation of the Contract Baseline Schedule with resource & cost loading & Basis of Schedule (BOS) in
accordance with Owner’s/Client’s Project procedures/ specification and ensuring quality of the schedule through
analysis.
➢To update & forecast with actual progress on approved baseline by Bi-weekly and conducting schedule review
meetings with medium level project stake holders.
➢Determining milestone to support project schedule. Generating and evaluating of resource loaded Mini
Schedules, 3week & 90 Days Lookaheads.
➢Identifying critical activities from schedule and developing action plans to avoid potential impact.
➢To Prepare Work Front Analysis(WFA) to ensure the optimal usage of resources in order to make daily & weekly
targets.
➢Presenting detail planning information such as Gantt, PERT Charts, Progress & Commodity S-Curves, consolidated
reports(CDB) on Daily, Weekly, Monthly basis with Resource status.
➢To perform Cost & Project Performance analysis and Ensure that all cost, planning and document control reports
are prepared and issued in accordance with the Project Coordination Procedure & Earned value management
System.
➢Analysing of Plan Vs actual of Installation rates/ productivity & indicate/alarming on weekly basis to
management.
➢Preparation of RTO’s & additional works for fabrication/ erection works with claims.
➢To monitor schedule deviations and tracking the delays, Interface with the management & Client regarding delays
to avoid Liquidated Damages/Penalty.
➢To Prepare and maintain Delay register and drafting the contractual letters and assisting PM for the building

3
Name : Dayananthan Sivalingam

Active Mobile No. +971-508580357

Active Skype ID . dayamek


acceleration cost.
➢Devoloping Recovery schedule/Acceleration/EOT schedules & Updating twice a day (shift basis).
➢Conducting of PDO meetings/ Attending weekly meetings and highlighting the risks, road blocks, Criticalities

Position Manager - Planning & Control

Period October 2014 to July 2016


Organization Descon Engineering Limited
Project Title  EPF OF 12 PRESSURE DRUMS for Technip
 EPF OF OF SUPER HEATER, FILTER, COAL SCRUBER
VESSELS
 NORM HANDLING, TREATMENT & DISPOSAL PROJECT,
Project Scope/Description
RUWIS, ABU DHABI, UAE
 STRATEGIC TUNNEL ENHANCEMENT PROGRAMME-
TUNNEL PUMPING STATION, UAE
Position Senior Planning Engineer
Job Description:
Bid/Tender & Operations:
 Understanding the Bid requirements & Generating Scope summary for the contract.
 Developing Schedule, collecting details from Project history (lesson learnt) and proposed project stake
holders.Generating Level-III/level-II Bid Stage Schedule
 Operating of company systems for Project Controlling including P6, MS Project.
 Developing of all planning & scheduling tools to be used in control, monitoring & reporting of project
status.
Execution Phase :
 Understanding the Contract, identifying of contractual milestones and Developing Scope statement /
Project charter for the project.
 Prep. of the Contract Baseline Schedule with resource in accordance with Client’s Project procedures/
specification and ensuring quality of the schedule through analysis.
 To update & forecast with actual progress on approved baseline by Bi-weekly and conducting schedule
review meetings with project stake holders.
 To Identify the critical path activities from schedule and developing action plans to avoid critical or
potential impact.
 Preparing Master Schedule/ Review overall project status with the PM team & operations and recommend
corrective actions where necessary.
 Presenting reports- Gantt, PERT Charts, Progress & Commodity S-Curves, consolidated reports.
 To perform Cost & Project Performance analysis and Ensure that all cost, planning reports are prepared
and issued in accordance with the Project Coordination Procedure & EVM
 Analysing productivity of actual against the planned productivity & indicate to management.
 To monitor schedule deviations and tracking the delays, Interface with the management & Client regarding
delays to avoid Liquidated Damages/Penalty
 To develop Recovery schedule/Acceleration/EOT schedules & Updating
 To Prepare & submit the Progress Reports, Look ahead schedules on Daily, Weekly, Monthly basis with
Manpower & Equipment status.
 Prep of project closing reports & lesson learnt details for Project control part.
Period October 2014 to July 2016
Organization Petron Emirates Contracting & Manufacturing Co. LLC,UAE
Project Title

4
Name : Dayananthan Sivalingam

Active Mobile No. +971-508580357

Active Skype ID . dayamek


 HOT BATH PROCESSING PLANT, EMIRATES ALUMINIUM
PHASE-II, ABU DHABI,
Project Scope/Description  HOT BATH FUME DUCT PLANT, EMIRATES ALUMINIUM
PHASE-I, ABU DHABI
 LIQUID PITCH TANK, DUBAI ALUMINIUM, DUBAI, UAE.
Position Planning / Project Control Engineer

Period September 2009 to September 2012


Organization M/S. Eversendai Engineering Qatar W.L.L Doha, Qatar.
Project Title  NEW DOHA INTERNATIONAL AIRPORT (NDIA), CENTRAL
PLANT 51, QATAR.
 DOHA CONVENTION CENTER & TOWER
Project Scope/Description  ERHAMA BIN JABER AL JALAHMA SHIP YARD, PH4A & PH5
 QATAR FACULTY OF ISLAMIC STUDIES FOR QATAR
FOUNDATION - EDUCATION CITY
Position Planning / Project Control Engineer

Period Jun 2008 to September 2009


Organization M/S. Machinaid industries, Trichy - Tamilnadu–India
Project Title  FABRICATION OF PRESSURE VESSELS COMPONENTS.
Project Scope/Description
Position Production Planning Engineer

Personal Information
Date of Birth 26-Dec-1986
Nationality Indian

Marital Status Married

Languages Known English, Tamil, Hindi, Malayalam