PO07249 Low Voltage Testing Manual
PO07249 Low Voltage Testing Manual
PO07249 Low Voltage Testing Manual
APPARATUS TESTING
MANUAL.
DOCUMENT CONTROL 92
1.1 Purpose
This manual provides the necessary information for authorised electrical workers to perform mandatory
network testing to ensure the safety of persons connected to the Evoenergy distribution system, and to
ensure a safe and reliable electricity supply to the customer.
1.2 Scope
This manual provides details of mandatory low voltage testing to be performed by electrical workers both
within the distribution network and at the network boundary. The manual does not cover specific testing
performed by specialist sections such as Protection and Quality of Supply.
It is the responsibility of all qualified electrical workers to understand and where required, perform the
processes included within this manual. Mandatory testing of the low voltage network and connected
installations must be conducted to mitigate safety risks to staff and the public.
Mandatory testing must be conducted by authorised workers holding ESI trade qualifications, and up to date
training and authorisation to perform testing as a part of the following tasks:
Installation, repair, and replacement of overhead or underground distribution network service lines
and their subsequent energisation by connection to the low voltage distribution network
Reconnection of a customer installation to the low voltage distribution network
Installation, repair, replacement and augmentation of distribution network underground or overhead
mains conductors and cables
Installation, or reconnection of distribution network overhead or ground-mounted distribution
transformers
Installation, or reconnection of low voltage distribution network switchboards
Installation, fault repair and replacement of low voltage distribution network assets
Power quality and electric shock investigations
Connection of portable generating sets to the low voltage distribution network or installation
The contents of this manual must be applied in conjunction with all other relevant policies and procedures
including
Worksite hazard identification
Risk assessment and control utilising appropriate SWMS, JRA and the Electrical Safety Rules
Commissioning and related network procedures
This section allows approved test personnel to break the seals on meters
to gain access to terminals for testing
All broken seals must be reinstated by an Evoenergy authorised person
Further PPCE controls identified during the JRA process must be utilised to
control hazards identified.
Tong ammeter/voltage
tester;
Voltage proving unit; Phase rotation tester;
Fluke 374 Tong Ammeter
Fluke PRV 240 Voltage SEW 890 PR Phase Indicator
Stock No 1191074 Proving unit
Stock No 1189237
Stock No 1203582
Non-calibrated voltage testers including test lamps are NOT an Evoenergy approved
means for testing the LV Network
4.5.4 Storage
Test equipment is sensitive to environmental conditions and to mechanical damage and must be stored as
per the manufacturer’s recommendations.
The tester, test leads and components should be stored in the supplied protective case, kept dry and away
from heat and sunlight and in a place where the equipment cannot fall or be crushed.
Test equipment must not be left on the dashboards of vehicles. Equipment must be stored where it will not
be subjected to mechanical damage
4.5.5 Cleaning
Test equipment is sensitive to chemicals and must only be cleaned as per the manufacturer’s
recommendations. Dust may be removed with a soft cloth, slightly dampened with water with tester turned
off.
4.5.6 Batteries
Batteries must be in good condition for test apparatus, it is recommended spare batteries be carried for test
equipment. To prevent batteries with differing amounts of charge being used all batteries must be replaced
at once.
4.5.7 Replacement of fuses
Fuses may only be replaced with parts that meet the manufacturer specification (noted in the instruction
manual)
4.5.8 Damaged test equipment
Where a piece of test equipment or its accessories are found to be faulty or unserviceable, the item shall
have an Out of Service Tag attached and the item removed from service as per Lock Out/Tag Out
procedure PO07244. In these circumstances, any Worker is authorised to attach an Out of Service tag. The
Out of Service Tag shall be prominently displayed and clearly labelled with contact name, phone number,
date and details of why the tag has been applied – for example, a description of what is wrong with the item.
Out of Service Tags shall be attached using a zip tie or other method that will prevent the tag from being
inadvertently removed.
If the pre or post-test inspection identifies defects or hazards that are likely to cause electrical shock or
damage to property, or may impact the safety or integrity of the tests, revisit JRA and assess the
identified risks and applicable controls. If these risks cannot be adequately mitigated by the
implementation of controls, testing should not proceed and your supervisor must be notified.
All tests listed in this document follow the basic principles of sufficiently trained
workers being able to assess the correct test points, use the correct equipment,
perform condition checks, and set up and use test equipment as per below
The test personnel should expect a result and if the measured result is not as
expected, take appropriate action.
PRIOR TO DISCONNECTION
1. Complete JRA, including review and implementation of controls from relevant SWMS in accordance with
PO06100 Job Risk Assessment (pre-start) including mandatory PPCE
2. Perform Test 1 - PROXIMITY. OR Test 12 – POLE LEAKAGE DETECTION for pole inspectors
3. Perform Pre-test inspection
4. Perform Test 10 – PHASE ROTATION.
On mains if service neutrals remain unbroken
On each service if neutral broken
Any voltage may indicate alternative supplies are present. Alternate supplies must
be isolated prior to the installation being energised
6. Perform Test 8 – INSULATION RESISTANCE TESTING for in-service cable baseline results
7. Install LV bonders as per Earthing Construction Manual
PERFORM WORK
12. Perform Test 3 - NEUTRAL IDENTIFICATION and attach neutral identification tag
13. Perform Test 6 – POLARITY.
14. Perform Test 5 – VOLTAGE TESTING
15. Perform Test 10 - PHASE ROTATION.
16. Perform Test 9 – NETWORK PHASING.
17. Connect all cable ends as required by network.
18. Perform Test 1 - PROXIMITY.
19. Complete Post-test inspection.
PRIOR TO DISCONNECTION
1. Complete JRA, including review and implementation of controls from relevant SWMS in accordance with
Job Risk Assessment (pre-start) including mandatory PPCE
2. Perform Test 1 - PROXIMITY.
3. Perform Pre-test inspection.
4. Perform Test 10 - PHASE ROTATION.
Any voltage may indicate alternative supplies are present. Alternate supplies must
be isolated prior to the installation being energised
PERFORM WORK
RESTORE POWER
PRIOR TO DISCONNECTION
1. Complete JRA, including review and implementation of controls from relevant SWMS in accordance with
Job Risk Assessment (pre-start) including mandatory PPCE
2. Perform Test 1 - PROXIMITY
3. Perform Pre-test inspection
4. Perform Test 10 – PHASE ROTATION.
On mains if service neutrals remain unbroken
On each service if neutral broken
Any voltage may indicate alternative supplies are present. Alternate supplies must
be isolated prior to the installation being energised
6. Perform Test 8 – INSULATION RESISTANCE TESTING for in-service cable baseline results
7. Install LV bonders as per Earthing Construction Manual
The network boundary at an underground point of entry is the customer side of the
service fuses and the customer side of the service neutral link as per the Electricity
Network Boundary Code 2017
PRIOR TO DISCONNECTION
1. Complete JRA, including review and implementation of controls from relevant SWMS in accordance with
Job Risk Assessment (pre-start) including mandatory PPCE
2. Perform Test 1 - PROXIMITY.
3. Perform Pre-test inspection
4. Perform Test 10 - PHASE ROTATION.
6. Perform Test 8 – INSULATION RESISTANCE TESTING for in-service cable baseline results
PERFORM WORK
RESTORE POWER
9.1.1 General
Proximity testing must be conducted:
on approach to conductive structures/ enclosures such as meter boxes, PoE enclosures, padmount
substations, conductive poles (see 9.14 Test 12 Pole leakage detection), roof gutters, riser brackets
etc. Conductive elements mounted to non-conductive poles should also be checked
after the energisation of equipment within or connected to the conductive structure/enclosure, or in
the vicinity of equipment that may be energised.
at conductive structures near to fallen conductors such as fences and hand rails
Proximity testing is a non-contact, indication only test for the presence of a hazardous voltage in a
conductive structure or enclosure prior to physical contact being made by a worker.
The proximity detector is only effective on AC and will indicate a voltage has been detected when the tip of
the device is placed in the proximity of 50-1000 Volts. The tip should be on or near the object being tested
As it is a non-contact device that utilises capacitive coupling to detect voltage, it can be affected by adjacent
live equipment. If a live structure or enclosure is detected, verify the voltage present with a voltmeter and
independent earth. If a voltage is present the worker must control the hazard by isolation or barricading,
danger tag the isolating equipment, notify your supervisor and record in Cityworks
Live test
Test before you touch
6. Test the voltage tester on a known low voltage source or approved proving unit
7. Isolate and danger tag if voltage present and record any measured voltage.
Investigate or report issue as per 9.2.3 Escalation process for live structure/enclosure
9.2.2.2 Electrical apparatus
1. Perform testing fundamentals checks
2. Ensure tester is switched to the correct function and range for AC voltage, e.g. 0-600 volts
3. Test the voltage tester on a known low voltage source or approved proving unit.
4. Install independent earth at a minimum distance of 2 metres from any conductive object embedded in the
ground connected to the system under test and connect to voltage tester lead
6. Disconnect independent earth and voltage test between each phase until each combination is tested. A
reading of 0 volts must be indicated on the voltage test device.
7. Prove voltage tester on known low voltage source or approved proving unit
Live test
Do not break neutral until actives are opened
9.3.1 General
The distribution network neutral conductor must be identified, confirmed by testing and tagged prior to any
connection being made to the network neutral. Active conductors must be identified by testing to ensure
correct phases present and voltage is within tolerance
4. Install independent earth at a minimum distance of 2 metres away from any conductive object embedded
in the ground connected to the system under test and connect independent earth to voltage tester lead
5. Isolate supply.
Live Test
Neutral integrity is critical in maintaining a safe network
The integrity of an electricity distribution system neutral is essential to ensure the safety of persons, and
property.
Neutral integrity testing is used to:
Confirm that the neutral has been correctly identified
Identify ineffective neutral connections
Neutral integrity must be tested in the following circumstances:
After installing, jointing, re-terminating or replacing UG or OH services and network mains
When a high neutral to earth voltage is measured
Electric shock investigation
Investigation of power quality complaints such as high, low, large deviations (flicker) or phase
voltage imbalances.
This manual details two tests to verify the integrity of the neutral connected to an installation, both may be
required depending on results of fault loop impedance test, see 9.4.3
Test 4A - NEUTRAL INTEGRITY BY FAULT LOOP IMPEDANCE utilises a fault loop impedance test device
to measure the impedance of the neutral circuit between the installation and the transformer that supplies it.
Test 4B NEUTRAL INTEGRITY BY INDEPENDENT EARTH AND VOLTMETER measures the potential
(voltage) difference between the neutral conductor and independent earth with a voltmeter.
Fault loop impedance (ZLN) measures of the impedance of the entire loop including the
active (line), neutral and transformer winding. Separate neutral impedance and line
impedances measured by some instruments may be used to assist in identifying the
cause of a high fault loop impedance reading.
Checking connections:
Measuring voltage drop across a connector, should 0V, any volts dropped are a result of impedance from a
poor connection see image above.
Live test
N terminal (blue), via black test lead, to service neutral (for PoA, connect alligator clip to head of test
bolt).
L terminal (red), via red test lead, to each service phase
Do not re-energise the installation until advised that it is safe to do so. If reasonably
practicable visually inspect the service and mains between the installation and the
transformer, pay particular attention to connections and terminations being loose,
burnt, damaged or missing
7. If an issue on the neutral is identified and rectified, re-perform this test to verify neutral integrity, keep any
failed connectors or components and raise a Guardian incident, including relevant information and
photographs.
8. Restore the service neutral (remove test bolt and replace with shear-bolt from house neutral connector
for PoA) – ensure all connections under test are re- tightened and pull tested.
Live Test
Used in conjunction with fault loop impedance testing
4. Install independent earth at a minimum distance of 2 metres away from any conductive object embedded
in the ground or connected to the system under test
5. Perform Test 6 - Polarity to confirm the polarity of the supply is correct
6. Isolate the supply and disconnect the neutral.
9. Measure the current on the main earth with an approved tong ammeter and record the result. If access is
not available – escalate to Quality of Supply
11. Measure and record the voltage between the supply neutral and the independent earth
13. PART C - Measure the currents flowing through both the supply neutral and the main earth.
Australian Standard Voltages and Voltage Tolerances for Low Voltage Systems
TEST CONNECT VOLTAGE TEST NOMINAL VOLTAGE
TYPE DEVICE BETWEEN VOLTAGE TOLERANCE
READING
N to E Independent Earth and Supply Neutral 0 volts 0 – 6 volts
Ø to E Independent Earth and Supply Active(s) 230 volts 216 – 253 volts
Ø to N Supply Neutral to Supply Active(s) 230 volts 216 – 253 volts
Ø to Ø Supply Active/s 400 volts 376 – 440 volts
Ø to Ø Supply Actives of same phase 0 volts 0 – 30 volts
VOLTAGE >253 volts, A - N Perform neutral integrity (Test 4A), record results on
TOLERANCE Cityworks form, note date, time and weather conditions.
Forward form to Quality of supply for action
Live Test
Essential test for proving neutral
In order for polarity testing to be effective the neutral at the installation being tested must be separated from
the earthing system at the PoE/PoA. The earth reference for testing purposes is achieved by the use of an
approved independent earth or system earth as denoted in the earthing hierarchy described in the Electrical
Safety Rules.
Polarity testing is essential to ensure:
The prevention of electric shock by identifying conditions where active and neutral conductors have
been incorrectly connected (transposed).
The transposition of active and neutral conductors will result in the energisation of the
earthing system and consequently the energising of exposed conductive parts
connected to the earthing system.
4. Install independent earth at a minimum distance of 2 metres away from any conductive object embedded
in the ground connected to the system under test and connect independent earth to voltage tester lead
5. Ensure that the neutral under test is disconnected.
8. Prove voltage tester on known low voltage source or approved proving unit
De-energised test
Identifies open circuit situations
Continuity testing is conducted prior to insulation resistance testing to ensure testing there are no open
circuit cores within the cable and to identify and verify the cores have not been transposed in a cable joint or
other connection in the circuit
Continuity testing is also utilised to verify cable “colours” to ensure the correct cores are joined in an inline
joint so that correct polarity and phasing can be achieved. Insulation tape must be used to mark cores
Coloured cable cores do not guarantee that there has not been a “roll” in a cable joint
9.9.1 Continuity testing – equipment required
PPCE as per Personal Protective Clothing and Equipment
Kyoritsu 3132A Insulation Resistance and Continuity Tester
Test leads, ideally with alligator clamps for creating temporary short circuits for testing
Communication device such as mobile phone or walkie talkie for long cable runs
Insulating materials (e.g. LV insulating mats/covers) where required as identified in the JRA or
relevant SWMS, and applied per Evoenergy procedures
9.9.2 Continuity testing steps
1. Perform testing fundamentals checks
2. Isolate equipment to be tested and perform Test 2 - PROVE DE-ENERGISED
3. Ensure that the equipment under test is isolated from equipment that may affect the test results
4. Install the shorting test leads at the remote end. If a long length of cable is being tested, a second person
with a communication device may be required to operate the short circuit test leads.
5. Select the cores or conductors to be tested. Using an approved insulation resistance tester set on the Ω
setting, test between each core until each combination of pairs is tested.
De-energised test
Hazardous voltages may exist
Insulation resistance testing is a final step prior to energisation of cables and/or equipment and must be
carried out after the cables have been terminated and/or backfilled, the backfill compacted, the cables
clamped. It is used to prove;
Equipment is safe to energise
The apparatus, conductor, associated joints and terminations are not damaged or degrading to a
point that may cause a short in the circuit, or a current leakage resulting electric shock or
temperature rise, further damaging insulation.
Cables and apparatus should not be subjected to insulation resistance tests at a test voltage that is higher
than the rated insulation value specified by the manufacturer of the equipment. This can cause damage and
premature failure of the insulation. Voltage values stated in 9.10.5 must be adhered to and care must be
taken to ensure that insulation resistance testers are set to the correct test voltage prior to testing.
9.10.4 Insulation resistance testing of OH and UG mains and services.
Insulation resistance testing of OH and UG mains and services is mandatory in the following circumstances:
Prior to energising new installations
After the installation of any new or replacement service or mains cable or apparatus
Prior to and after the replacement, augmentation, repair or relocation of service or mains cable or
apparatus
When a cable or apparatus is suspected to have a fault
When there is any doubt about condition, particularly the integrity of insulation of a cable or
apparatus
Note: Wet and humid conditions can lower the value of insulation resistance test
results
LV apparatus must not be tested at voltages that exceed the apparatus insulation
rating.
If the apparatus has not met expected test values, field staff and/or supervisors shall request the
engineer responsible for the asset to assess the energisation of the apparatus. This may require
additional testing and/or site information, the responsible engineer will provide the advice in writing
and with supporting information, whether or not the equipment should be energised. See 9.10.9
Insulation resistance test escalation process.
4. Select the test voltage on the insulation resistance tester as defined in 9.10.5
5. Connect the test leads together and press test button. The result should be 0Ω. If the result is not 0,
check and replace the batteries and adjust the zero point as described in the manual for the insulation
resistance tester
6. Notify people in vicinity the type testing taking place and the equipment under test. Ensure people cannot
receive a shock from the test, implement controls identified by the JRA,
8. Discharge tested equipment, this can be done by the insulation resistance tester – refer testers cover for
instructions
Live Test
Must be done before connecting two potential sources of supply
The paralleling of network circuits can cause serious injury. Connection of different
phases will result in a short circuit explosive/arc flash environment.
3. Identify the neutrals on both sides of the open point by performing Test 3 – Neutral identification.
4. Test voltage between each side (1) & (2) and record results
Phase rotation testing ensures that three phase machines rotate in the correct direction. This ensures safe
and correct operation of rotating machinery.
Three phase machinery rotating in the wrong direction can cause death or serious injury to operators, failure
of machines to operate or operate correctly. This may affect refrigeration and air-conditioning equipment,
pumps etc.
Note: Correct network phasing DOES NOT ensure correct phase rotation
For reactive outages, if the phase rotation prior to loss of supply is unknown, the supply must only be
reconnected if the connected three phase equipment can be inspected to ensure correct
rotation/operation. If the there is no access or the rotation of the equipment cannot be ascertained the
service must not be connected and danger tagged until it can be proven safe to energise.
Non-contact test
Determines circuit load
9.13.1 General
Measuring the current flowing in an active, neutral or earth conductor is useful in determining circuit load, or
current share.
The measurement of current flowing in a conductor can indicate the potential for drawing a dangerous
electric arc if the circuit is opened at a certain point or if the current flowing exceeds the rated braking current
of a piece of electrical apparatus. If the maximum rated breaking load is less than the measured current, the
load must be reduced or the circuit isolated at an adequately rated apparatus
9.13.2 Effective current measurement
The tong ammeter will only provide an accurate result if measuring one conductor's current at a time. If
measuring more than one conductor, conductors must be individually tonged and results added together for
the final overall measurement.
Ensure that the tong is fully closed when taking a measurement otherwise the magnetic circuit will not be
complete and false readings of zero or lower than actual current may occur.
9.13.3 Current measurement equipment required
PPCE as per Personal Protective Clothing and Equipment
Fluke 374 Tong Ammeter
Greenlee GT12A Proximity Tester
Insulating materials (e.g. LV insulating mats/covers) where required as identified in the JRA or
relevant SWMS, and applied per Evoenergy procedures
9.13.4 Steps for current measurement with a tong ammeter
1. Perform testing fundamentals checks
2. Perform Test 1 - PROXIMITY on conductive structures and enclosures associated with the equipment
being tested
3. Ensure tester is switched to the correct function and range for AC current
4. Ensure that the voltage test leads have both been removed from the input jacks and are not wrapped
around the tester while performing current measurements
5. Open the tong and close around the conductor to be tested and ensure the tong is fully closed and the
two halves of the tong are not misaligned. Centre the conductor between the marks on each tong
Non-contact test
Performed by all Worker approaching conductive structures
9.14.1 General
Pole leakage detection conducted with an approved pole leakage detector forms part of asset inspection
tasks, however may be utilised at any time that there is uncertainty about a pole having a higher potential
than the surrounding ground.
The pole leakage detection equipment is suitable only for conductive poles such as concrete, steel and CCA
treated timber and poles that have a continuous earthing conductor run down the pole such as substation
poles, poles that have surge arrestors, catenary earthing wires, or uninsulated stay wires.
9.14.2 Pole leakage detection equipment required:
PPCE as per Personal Protective Clothing and Equipment
Approved pole leakage detector
9.14.3 Steps for pole leakage detection
1. Perform testing fundamentals checks
2. Insert the earth spike into the ground a minimum of 150mm at a minimum distance of 1m away from the
pole
3. Attach free end of earth lead to screwed terminal on earth spike assembly. Attach telescopic probe by
screwing it into the top of the instrument housing.
4. Prove the operation of the instrument by applying the probe to the test terminal on the side of the earth
spike assembly. A deflection of between 3 and 8 divisions proves correct instrument operation. If the
above deflection is not indicated by the instrument, replace the battery. Re-check for full-scale deflection,
if not achieved with a new battery, there is a fault with the instrument and it must be danger tagged and
removed from service
5. To perform leakage test, apply test probe to pole
9.15 Test 12A - Pole Leakage Detection – High Voltage Pole with
Modiewark GLM MINI
1. Switch the unit to the “ON” position, a Green LED power light will immediately illuminate, indicating good
battery condition and circuitry connectivity.
Note: Electric fields from power lines can be disturbed and redirected by objects that are
grounded.
A tree near a power line will lower the strength of an electric field which may cause
adjustments to the settings on the GLM Mini.
Other factors which influence the electric field and the initial calibration setup include rainy
and humid conditions.
9. After correct test instrument procedure has been carried out, raise the tester above the head and adjust
the sensitivity dial until the voltage in the line above is detected
Method: Placing your right hand on the tester as indicated use the other hand to move the
Sensitivity Dial slowly to the left until the alarm is a strong and continuous sound.
10. If Tester does not alarm If overhead mains cannot be detected by the GLM Mini at arm’s length at HIGH
12. It is our recommendation that with the self-test function showing correct battery voltage and circuit
operation, the self-test function can then be used as a dependable correct safety procedure to approach
the pole.
11. When the overhead line conductor is located (by the activation of the alarm), lower the tester to chest
height, at this point no alarm should be heard. The overhead field will be broken and the approach to the
pole can be made. If the tester continues to alarm at chest height raise it above the head again and
adjust the sensitivity dial one position to the left to desensitise it, then repeat step 11.
Method: By leaving the hand placed on the tester with the thumb as indicated, remove the
other hand and lower the unit to chest height. Note: When using the unit on power lines where
lower voltage mains, i.e., 415V AC are beneath the HV conductors
a null or dead zone will occur. To overcome this situation, move out from beneath the HV line until
the alert tone is heard.
12. Verify the calibration of the overhead mains again to check voltage is still present and lower to chest
height where the alert tone should dissipate. The tester should not alarm in this position or pole test will
not be correct.
13. With the tester at arm’s length approach the pole to be tested.
Method: Whilst approaching the pole keep arm out stretched and your other arm beside your
body; walk calmly and slowly towards the pole, to a point where the Test Area Label is 25mm (1
inch) from pole. If the Tester alarms while approaching the pole, stop and raise the GLM mini
towards the overhead conductors to make sure the GLM Mini is not picking up overhead field, if
field is still broken above (no alert tone) proceed to step 15.
14. If the tester does not alarm there is no significant voltage running through the pole.
Method: At this point to verify results touch the pole with unit on the end marked Test Area only.
The contact will increase sensitivity.
15. If an alert signal is heard do not panic but check your results proceed to step 16.
Method: To check your results take a step back until signal has discontinued then take a step
forward to verify activation of unit. Please note the further you are away from the pole and the
tester is alarming, the higher the leakage in that pole. A set of calibration tables are available for
switch positions and voltages if required.
16. Follow standard isolation procedures with a ten-metre perimeter, assess the area around pole to ensure
no conductive material have contacted pole. I.e., Fences, machinery and water, as where you are
standing may be live.
Note: If a voltage cannot be detected by the GLM Mini at arm’s length at HIGH 12, then
three possible situations can exist:
The overhead mains are not alive.
The overhead mains voltage does not have a strong enough field to be picked up.
Low voltage mains are below the High voltage conductors causing a null.
In these circumstances it is our recommendation that because the self-test function checks battery
and circuitry it can be relied upon (after the self-test procedures have been carried out) that safe pole
approach can be carried out.
Note: Electric fields from power lines can be disturbed and redirected by objects that are
grounded. A tree near a power line will lower the strength of an electric field which may
cause adjustments to the settings on the GLM Mini. Other factors which influence the
electric field and the initial calibration setup include rainy and humid conditions.
9. After correct test instrument procedure has been carried out, raise the tester above the head and adjust
the sensitivity dial until the voltage in the line above is detected.
Method: Placing your right hand on the Tester as indicated use the other hand to
move the Sensitivity Dial slowly to the left until the alarm is a strong and continuous
sound.
10. If Tester does not alarm If overhead mains cannot be detected by the GLM Mini at arm’s
length, at HIGH 12. It is our recommendation that with the self-test function showing correct battery
voltage and circuit operation, the self-test function can then be used as a dependable correct safety
procedure to approach the pole.
11. When the overhead line conductor is located (by the activation of the alarm), lower the tester to chest
height, at this point no alarm should be heard. The overhead field will be broken and the approach to the
pole can be made. If the Tester continues to alarm at chest height raise it above the head again and
adjust the sensitivity dial one position to the left to desensitise it, then repeat step 11.
Method: By leaving the hand placed on the Tester with the thumb as indicated, remove
the other hand and lower the unit to chest height.
12. Verify the calibration of the overhead mains again to check voltage is still present and lower
to chest height where the alert tone should dissipate. The tester should not alarm in this position or pole
test will not be correct.
13. With the tester at arm’s length approach the pole to be tested.
Method: Whilst approaching the pole keep arm out stretched and your other arm beside
your body; walk calmly and slowly towards the pole, to a point where the Test Area
Label is 25mm from pole. If the tester alarms while approaching the pole, stop
and raise the GLM mini towards the overhead conductors to make sure the GLM mini is
not picking up overhead field, if field is still broken above (no alert tone) proceed to
step 15.
14. If the tester does not alarm there is no significant voltage running through the pole.
Method: At this point to verify results touch the pole with unit on the end marked Test Area only.
The contact will increase sensitivity.
15. If an alert signal is heard do not panic but check your results proceed to step 16.
Method: To check your results take a step back until signal has discontinued then take a step
forward to verify
activation of unit. Please note the further you are away from the pole and the tester is alarming the
higher the leakage in that pole. A set of calibration tables are available for switch positions and
voltages if required.
16. Follow standard isolation procedures with a ten-metre perimeter, assess the area around pole to ensure
no conductive material have contacted pole. E.g., Fences machinery and water, as where you are
standing may be live.
In these circumstances it is our recommendation that because the self-test function checks battery and
circuitry it can be relied upon (after the self-test procedures have been carried out) that safe pole approach
can be carried out.
Live test
Test before you touch
6. Prove voltage tester on known low voltage source or approved proving unit switched to in both AC and
DC functions
It is assumed for the purpose of this testing that Test 9.10 Insulation resistance
testing has occurred and that all relevant steps from Section 9.10 have been
implemented.
Ensure that insulation resistance tester batteries are in good condition to test each
phase for ten minutes. If batteries go flat during these tests, the entire test will
need to be re-done after discharging the cable or equipment.
7. Notify people in vicinity the type testing taking place and the equipment under test. Ensure people cannot
receive a shock from the test, implement controls identified by the JRA,
8. Perform the test on each active core and neutral
DOCUMENT CONTROL