Leave leak path

test chart

Close
Open

test pump

ANNULAR TEST

Install PLUG tester with 5 or 3 ,5 single DP .


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close Annular. Close inside choke line valve
pressure test with 250-300 psi for 5 min
pressure test with 3500 psi for 5 min
Leave leak path bleed off pressure from testing unit

coflex hose

SOV
Leave leak path

test chart

Close
Open

test pump

UPPER PIPE RAM TEST

Install PLUG tester with 5 or 3 ,5 single DP .


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close PIPE RAMS. Close inside choke line valve
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
Leave leak path bleed off pressure from testing unit

coflex hose

SOV
Leave leak path

test chart

Close
Open

test pump

UPPER PIPE RAM TEST

Install PLUG tester with 5 or 3 ,5 single DP .


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close PIPE RAMS. Close HCR choke line valve
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
Leave leak path bleed off pressure from testing unit

coflex hose

SOV
Leave leak path

test chart
Close
Open

test pump

UPPER PIPE RAM TEST

Install PLUG tester with 5 or 3 ,5 single DP .


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close PIPE RAMS. Close MAIN VALVE CHOKE MANIFOLD
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
Leave leak path bleed off pressure from testing unit

coflex hose

SOV
t

Close
Open

BLIND SHEAR RAMS TEST

Install PLUG tester with 5 or 3 ,5 single DP . REMOVE DRILL PIPE


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close BLIND SHEAR RAMS. Close INSIDE KILL LINE VALVE AND FIRST 3 VALVES CHOKE MANIFOLD
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
Leave leak path bleed off pressure from testing unit

coflex hose

SOV test chart

test pump
t

Close
Open

BLIND SHEAR RAMS TEST

Install PLUG tester with 5 or 3 ,5 single DP . REMOVE DRILL PIPE


open side out lets . Install test pump KILL LINE
take out non return valve " NRV"
pump through kill line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close BLIND SHEAR RAMS. Close OUTSIDE KILL LINE VALVE AND SECOND 3 VALVES CHOKE MANIFOLD
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
Leave leak path bleed off pressure FROM TEST UNIT

coflex hose

SOV test chart

test pump
t

Close
Open

NRV/BLIND SHEAR RAMS TEST

Install PLUG tester with 5 or 3 ,5 single DP . REMOVE DRILL PIPE


open side out lets . Install test pump on choke manifold.
Install non return valve " NRV"
pump through choke line to fill up BOP
Open SOV's , ensure leak path is there
non return valve Flush test pump
This test takes short period to pump up
close BLIND SHEAR RAMS. OPEN KILL LINE VALVES AND SECOND 3 VALVES CHOKE MANIFOLD
pressure test with 250-300 psi for 5 min
pressure test with 4500 psi for 5 min
bleed off pressure FROM TEST UNIT

coflex hose

SOV test chart

test pump