TOKYU-WIKA JOINT OPERATION

Jakarta Mass Rapid Transit Project


Inspection and Test Plan
CP101&CP102

Construction of Mass Rapid Transit Jakarta


Contract Package CP101 & CP102

INSPECTION AND TEST PLAN FOR


INSULATION WORKS (CP101-CP102)

TWJO - ITP - E&M - 0012 - revA

TOKYU-WIKA JOINT OPERATION

When viewed in ACONEX this document is Controlled, this means:

1. Distribution is centralized - in this case through ACONEX. Any improvement suggestions should be forwarded to the
Quality Control Engineer
2. Each copy is issued to a particular person or organization.
3. Copy holders will be automatically issued with any amendments through ACONEX.
4. Photocopies of this document are uncontrolled and users should confirm validity inACONEX prior to use.

TWJO-ITP-E&M-0012 revA
TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan

Revision History Sheet


Rev No. Date Description of Revision

A 26-Oct-16 Submitted for Approval

Approval:

Quality Assurance Manager Date

TWJO-ITP-E&M-0012 revA Revision History Sheet


TOKYU-WIKA JOINT OPERATION

Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan

Contents

1. Inspection and Test Plan

Cover Sheet
Revision History
Contents
Covered Scope Activity
Flow Chart
Inspection and Test Plan for Insulation Works (CP101-CP102)

2. Checklist
TWJO-ITP-E&M-0011-CHK-0001 rev A Insulation Ducting Works
TWJO-ITP-E&M-0011-CHK-0002 rev A Insulation Pipe Works
TWJO-ITP-E&M-0012 revA Contents
TOKYU-WIKA JOINT OPERATION

Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan

Covered Scope Of Activity


Inspection and Test Plan for Insulation Work is needed to ensure the installation of Insulation Work
will be carried out as per approved MSA, Approved method statement and Good For Construction
Drawing.
This ITP will be applicable for installation of insulation works, devided into three categories Duct work
insulation (AHU & FCU), Chilled Water Pipe Insulation (AHU & FCU), Refrigerant & Condensate
water pipe insulation (PEU) in All building at CP 101&CP 102 such as:
- Site Administration Office (D01)
- Workshop Office (D02)
- Infrastructure Maintenance Office (D03)

Scope of this Inspection and Test Plan Material check and Visual check. The inspection work by QC
Engineer of subcontractor for Internal Inspection, checked by QC Engineer of TWJO and JMCMC
Engineer as the Acceptance for the Result of Inspection. Inspection and test plan for duct work
insulation cunducted by unit ,and pipe work insulation work shall be conducted zone by zone (sample
schematic drawing is attached).

Picture 1. Measuring Tape

TWJO-ITP-E&M-0012 revA Contents


TOKYU-WIKA JOINT OPERATION
Jakarta Mass Rapid Transit Project
Inspection and Test Plan
CP101&CP102

Flow Chart

Start

Submit
Material Sample Approval (MSA), Revise
Method Statement (MS),
Inspection & Test Plan (ITP)

MSA, MS, ITP Not OK


Approved?

OK

Material Preparation
1. Spesification of material Insulation
2. Surface Cleaning Repair

Not OK
OK
Installation insulation work Not OK

OK

Internal Check Not OK

OK
Not OK
Submit Request For Inspection (RFI)

OK

 
JMCMC and TWJO
Joint Inspection (material & Visual, Check)

OK

End

TWJO-ITP-E&M-0012 revA
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project

INSPECTION AND TEST PLAN FOR INSULATION WORKS FOR CP101-CP102


`
Description of Activity: This ITP will be Applicable for Insulation Works for CP101 - WMS No: TWJO-MST-0105 ITP NO: TWJO-ITP-E&M-0012 revA
CP102

Responsibility Matrix for


Conformance Standard/ Responsible carrying test
Frequency of Test And TWJO Format Or
SN. Activity Description Reference Procedures/ Compliance Criteria TWJO/SUBCO Revision
Inspection Subcon Format
Drawing number NT
Subcon/
TWJO Engineer
Supplier

Subcont QC
Material sample Approval
Once Before Personnel &
1 Approval For Material Insulation (TWJO-MSA-0129, TWJO- Approved Material Supplier Certificate P R R A
Procurement TWJO QC
MSA-0141 )
Engineer
2 Preparation Before Installation

Subcont QC TWJO-ITP-E&M-
Once Before Insulation No Spatter, Mill Scale, Oil, Personnel & 0012-CHK-
- Surface Preparation NA P W I A
work Process Grase and rust TWJO QC 0001,0002, Insulation
Engineer Works Checklist

Subcont QC TWJO-ITP-E&M-
Material sample Approval
Once Before Insulation Personnel & 0012-CHK-
- Material Insulation Check (TWJO-MSA-0129, TWJO- ASTM C-533-13 P W I A
work Process TWJO QC 0001,0002, Insulation
MSA-0141 )
Engineer Works Checklist
3 Check After Installation
Subcont QC TWJO-ITP-E&M-
Once After Insulation Good For Construction Personnel & 0012-CHK-
- Visual Installation Check As Per Drawing P W W A
Work Drawing TWJO QC 0001,0002, Insulation
Engineer Works Checklist

Legends P: Perform R: Review I: For Information only H: Hold point W: Witness point NA: Not Applicable RW: Random Witness

Prepared by: Approved by:

Name: Name:

Signature: Signature:

All approved ITPs and related records shall be stored on TWJO server under Quality Assurance folder with a hard copy in office file.
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project

INSPECTION AND TEST PLAN FOR INSULATION WORKS FOR CP101-CP102


`
Description of Activity: This ITP will be Applicable for Insulation Works for CP101 - WMS No: TWJO-MST-0105 ITP NO: TWJO-ITP-E&M-0012 revA
CP102

Responsibility Matrix for


Conformance Standard/ Responsible carrying test
Frequency of Test And TWJO Format Or
SN. Activity Description Reference Procedures/ Compliance Criteria TWJO/SUBCO Revision
Inspection Subcon Format
Drawing number NT
Subcon/
TWJO Engineer
Supplier

TWJO-ITP-E&M-0012 RevA Page 1 of 1

TWJO-ITP-E&M-0011 RevA Page 2 of 2 #VALUE!