CLJ 2018 3 635 Chrislailaw
CLJ 2018 3 635 Chrislailaw
award’) and the Persatuan Penapis Minyak Sawit Malaysia Final Appeal A
Board Award (‘final appeal board award’) be recognised as binding and be
enforced by entry as a judgment in terms of the award. The defendant
objected to the plaintiff’s application and contended that ss. 38 and 39 of the
Act did not apply to international arbitration and submitted that the
plaintiff’s application must be dismissed. The High Court found in favour of B
the plaintiff and allowed the recognition and enforcement of the final
arbitration award and the final appeal board award. The defendant’s appeal
to the Court of Appeal was dismissed on the grounds that s. 38 of the Act
covered international arbitral awards. The Federal Court, however, directed
that the case be remitted to the High Court to be heard on its merits of the C
defendant’s challenge under s. 39 of the Act before a new judge. The matter
to be determined was whether the defendant had successfully proved any of
the grounds under s. 39 of the Act to challenge the recognition of the
international arbitral award. The defendant raised a preliminary objection in
relation to s. 38 that the plaintiff could not seek to recognise and enforce both
D
the final arbitration award and the final appeal board award. The defendant,
in further opposing the recognition and enforcement by the plaintiff, relied
on ss. 39(1)(a)(iv) and/or (v) and also ss. 39(1)(b)(ii) of the Act, namely on
the following grounds (i) the final appeal board had acted outside the terms
of arbitration stipulated in the plaintiff’s request for arbitration and/or
contains decisions on matters beyond the scope of the submission to E
arbitration; and (ii) both the final award and final appeal board award were
in conflict with the public policy of Malaysia in that they were inconsistent
with the PORAM terms and would be unfair to the seller.
Held (allowing plaintiff’s application in encl. 1):
F
(1) There was no merit in the preliminary point raised for the defendant on
the ground that even though there were two decisions of the arbitral
bodies (namely, the final arbitration award and the final appeal board
award), the latter award was delivered by the appeal board as a result
of an appeal filed by the defendant against the arbitration tribunal award. G
Once the appeal board had heard the appeal and delivered its decision,
the decision or the award by the final appeal board would be the final
award or the concluded award. Hence, the award to be recognised and
enforced obviously would be the final award by the final appeal board.
(para 27)
H
(2) The arbitration clause or term was provided under item 12 of the initial
contract/sold note. The plaintiff had referred the parties’ dispute to the
arbitration tribunal pursuant to the arbitration term provided under the
initial contract/sold note. The defendant did not take any objection on
the arbitration proceedings and as a matter of fact submitted itself within I
the jurisdiction of the two arbitral bodies even though the sales contract
did not provide for an arbitration clause. Thus, the defendant’s
Hafeez Iqbal Oil & Ghee Industries (Pvt) Ltd v.
[2018] 3 CLJ Alami Vegetable Oil Products Sdn Bhd 637
A contention that the appeal board had acted outside the submission of the
arbitration was clearly an afterthought. Item 12 of the initial contract or
the sold note not only provided for arbitration but also stipulated that
arbitration must be governed by the PORAM Rules and Kuala Lumpur
was nominated as the seat of arbitration. (paras 38-40)
B
(3) The appeal board had dealt with the precise dispute contemplated by the
parties and fell within the terms of the submission to arbitration,
namely, the issue pertaining to the performance bond being the primary
or central issue to the dispute. The final appeal board award did not
contain decisions on matters beyond the scope of the submission to
C arbitration. The appeal board had derived its decision within the scope
of submission of the arbitration. Therefore, the contentions of the
defendant that the appeal board had exceeded its scope was without
merit and therefore must fail. The circumstance in s. 39(1)(a)(iv)
and/or (v) of the Act was never proven by the defendant. (paras 44 &
D 45)
(4) Both the plaintiff and the defendant had voluntarily chosen and agreed
to arbitrate their dispute according to PORAM Rules, which provides
that the decision of the arbitral tribunal shall be final and conclusive.
The defendant was, therefore, estopped from asserting that the award
E was inconsistent with the PORAM Rules. It is trite law that those who
make a contract to arbitrate their dispute should be held to their bargain.
(paras 48 & 49)
(5) The defendant had clearly failed to prove that the award was in conflict
with the public policy of Malaysia. It is trite law that the contravention
F
of public policy argument ought not to be utilised as a facade to re-open
settled matters in the arbitration. The defendant here did not make any
application under s. 37(1)(a)(i) to (vi) or under (b)(ii) of the Act. The
failure in applying to set aside the award under s. 37 of the Act on the
same grounds now attempted to be raised under s. 39 of the Act led to
G the inescapable conclusion that the issues raised by the defendant in this
application lacked bona fide intent and was obviously an afterthought.
The defendant had ultimately failed to discharge the burden of proof to
prove that the defendant’s challenges against the recognition under s. 38
of the Act fell within any of the circumstances under s. 39 of the same
H Act. (paras 52-54)
Case(s) referred to:
Alami Vegetable Oil Products Sdn Bhd v. Hafeez Iqbal Oil & Ghee Industries (Pvt) Ltd
[2016] 7 CLJ 19 CA (refd)
Allianz General Insurance Company (M) Bhd & Ors v. Kapar Energy Ventures Sdn Bhd
I [2016] MLJU 1515 (refd)
Archer Daniels Midland Co lwn. TTH Global (M) Sdn Bhd [2016] 1 LNS 1282 HC (refd)
Berjaya Times Square Sdn Bhd v. M Concept Sdn Bhd [2010] 1 CLJ 269 FC (refd)
638 Current Law Journal [2018] 3 CLJ
Cheah Theam Kheng v. City Centre Sdn Bhd (In Liquidation) & Other Appeals [2012] A
2 CLJ 16 CA (refd)
Colliers International Property Consultants (USA) v. Colliers Jordan Lee and Jaafar
(Malaysia) [2010] MLJU 650 (refd)
Open Tyre Joint Stock Company Efirnoye (“EFKO”) v. Alfa Trading Ltd [2012] 1 CLJ
323 HC (refd)
B
Legislation referred to:
Arbitration Act 2005, ss. 38(1), (2), 39(1)(a)(i), (ii), (iii), (iv), (v), (vi), (vii)
For the plaintiff - RS Sodhi; M/s Ajit & Co
For the defendant - Gregory Ling & CS Hui; M/s Ranjit Singh & Yeoh
C
Reported by Suhainah Wahiduddin
JUDGMENT
(Enclosure 1- Application pursuant to s. 38(1) of the Arbitration Act 2005)
Azimah Omar J: D
Introduction
[1] This originating summons (encl. 1) relates to an arbitration matter. By
its encl. 1, the plaintiff is seeking from this court for an order that the
Persatuan Minyak Sawit Malaysia Award of Arbitration Final Award dated E
11 February 2009 and the Persatuan Penapis Minyak Sawit Malaysia Final
Appeal Board Award dated 24 May 2010 made by the Persatuan Penapis
Minyak Sawit Malaysia against Alami Vegetable Oil Products Sdn Bhd, be
recognised as binding and be enforced by entry as a judgment in terms of the
award.
F
[2] The plaintiff’s encl. 1 is filed pursuant to s. 38(1) of the Arbitration
Act 2005 (“Act”).
The Background Facts
[3] The plaintiff (Hafeez Iqbal Oil & Ghee Industries (PVT) Ltd) is a G
limited liability company incorporated under the laws of Pakistan, based in
Pakistan.
[4] While the defendant (Alami Vegetable Oil Products Sdn Bhd) is a
Malaysian based limited liability company incorporated under the laws of
Malaysia. H
[5] Through a broker, Intra Oil and Fats Sdn Bhd (Intra Oil), the plaintiff
and the defendant had entered into an agreement to sell and purchase 10,000
Metric Tonne (MT) of RBD Palm Olein in bulk.
[6] For confirmation of the said sale of 10,000 MT of RBD Palm Olein I
in bulk between the plaintiff and the defendant, Intra Oil had on 8 July 2006
issued an initial contract/sold note (RBDOLN/0607018) to both the plaintiff
Hafeez Iqbal Oil & Ghee Industries (Pvt) Ltd v.
[2018] 3 CLJ Alami Vegetable Oil Products Sdn Bhd 639
A (a) At para. 5.2 of the appeal board award, the appeal board had noted
that the respondent had appealed against the arbitration tribunal’s
decision primarily on two grounds.
(1) Whether the Respondent had failed to perform his contractual
obligations in not posting a Performance Bond (PB), and
B whether there were circumstances that discharged the
Respondent from so posting the Performance Bond; and
(2) Whether the Claimant was in breach of contract by proposing
to establish a Letter of Credit (L/C) that provided for payment
on the basis of weights and quality final at the port of discharge,
C instead of at the port of loading.
(b) The relevant findings on the first ground of appeal with regards the
issuance of the performance bond by the defendant (seller).
The board had referred to both the initial contract/sold note dated the
8 July 2006 and the sales contract and had made these findings:
D
5.9 The appeal Board notes that the Initial Contract was not
objected to as to its terms at the time by the Respondent.
5.10 The Appeal Board also finds that the provision in the Sales
Contract relating to the provision of the Letter of Credit is not
E inconsistent with that in the Initial Contract.
5.11 It must be presumed that the Sales Contract ought to reflect the
agreement of the parties in the Initial Contract, unless there is
some evidence that there was further negotiation of these terms
between the Initial Contract and the Sales Contract. No such
evidence was tendered.
F
5.12 Furthermore, as the obligation in the Initial Contract as to the
provision of the Letter of Credit had already been performed
(“Already received”), it would be unconscionable if the
corresponding provision in the subsequent Sales Contract were
to be given an interpretation which was inconsistent with that
G in the earlier Initial Contract.
5.12A. Finally, the Respondent’s message to the Claimant on 19 July
2006 states as follows:
Thanks for arranging the amendments in the Letter of Credit.
5.13 This is not a response that would be expected from a party who A
is anxiously awaiting a Letter of Credit, as is now being
contended.
We find this message from the Respondent to the claimant to
be the absolute confirmation and agreement of the Respondent
as to its understanding of its obligations to provide a B
Performance Bond as soon as the draft Letter of Credit was
tendered.
5.15 If that is the case, then the draft Letter of Credit which was already
received by the Respondent as of 8th July 2006 would have discharged
the claimant’s initial obligations in respect of the Letter of Credit until the
C
Respondent tendered a Performance Bond, upon which the Claimant
would be obliged to tender an operative Letter of Credit within 3 days.
5.16 The Claimant would therefore be within its rights to declare
default if Respondent did not tender a Performance Bond as
soon as it received the draft Letter of Credit, as happened in
this case. D
A court to stress that the applicability of s. 38 of the Act is not a live issue
in the present case as the Federal Court had not allowed any questions
to deter the application of the provision with regard to international
arbitral award. It remains that s. 38 of the Act is sufficiently wide to
cover international arbitral awards. The only matter to be determined
B by this court is whether the defendant had successfully proven any of the
grounds under s. 39 of the Act to challenge the recognition of the
international arbitral award.
(i) It is utterly crucial to be appreciated that the merits dealt with by both
of the counsels, and this court is not the exactly the merits of the finding
C of any of the arbitral tribunal, but the merits of the defendant’s challenge
within the purview of s. 39 of the Act. And this is exactly in line with
the decision of the Federal Court. Even the submission by the defendant
is generally tailored to s. 39 of the Act.
[18] Hence, this court now shall determine the plaintiff’s application
D
namely; whether or not the plaintiff is able to recognise and enforce the final
award and the final appeal award pursuant to the new s. 38 of the Act and
most pertinently, whether there are grounds for the refusal of such
recognition or enforcement pursuant to s. 39 of the Act.
The Law - Section 38 And 39 Of The Act
E
[19] The new s. 38 of the Act provides as follows:
Recognition and enforcement
(1) On an application in writing to the High Court, an award made in
respect of an arbitration where the seat of arbitration is in Malaysia
F
or an award from a foreign State shall, subject to this section and
section 39 be recognised as binding and be enforced by entry as a
judgment in terms of the award or by action.
(2) In an application under subsection (1) the applicant shall produce-
(ii) the arbitration agreement is not valid under the law to which
the parties have subjected it, or, failing any indication
thereon, under the laws of the State where the award was
made;
(iii) the party making the application was not given proper notice E
of the appointment of an arbitrator or of the arbitral
proceedings or was otherwise unable to present that party’s
case;
(iv) the award deals with a dispute not contemplated by or not
falling within the terms of the submission to arbitration; F
(v) subject to subsection (3), the award contains decisions on
matters beyond the scope of the submission to arbitration;
(vi) the composition of the arbitral tribunal or the arbitral
procedure was not in accordance with the agreement of the
parties, unless such agreement was in conflict with a G
provision of this Act from which the parties cannot derogate,
or, failing such agreement, was not in accordance with this
Act; or
(vii) the award has not yet become binding on the parties or has
been set aside or suspended by a court of the country in H
which, or under the law of which, that award was made; or
(b) if the High Court finds that:
(i) the subject-matter of the dispute is not capable of settlement
by arbitration under the laws of Malaysia; or
I
(ii) the award is in conflict with the public policy of Malaysia.
Hafeez Iqbal Oil & Ghee Industries (Pvt) Ltd v.
[2018] 3 CLJ Alami Vegetable Oil Products Sdn Bhd 647
C
[22] It remains as a rule of law that the above s. 38 of the Act provides that
a party who had obtained an arbitration award (where the seat of arbitration
is in Malaysia irrespective of the award being international or domestic) can
apply to the High Court for an order that the award be recognised as binding
and be enforced by entry as a judgment in terms of the award or by action.
D [23] Meanwhile, s. 39 of the Act expressly provides the numerous
instances where such an application for recognition can be refused at the
request of the party against whom it is invoked. It is for the party against
whom the application is invoked, to produce evidence or proof to the
satisfaction of the court that instances under s. 39(1)(a), (i) to (vii) has been
established.
E
[24] The plaintiff’s application is supported by an affidavit in support
affirmed by Sheikh Muhammed Ikram a/l Sheikh Muhammed Yaqoob on
30 October 2012.
The Preliminary Objection
F
[25] At the commencement of the hearing of the plaintiff’s application, the
defendant raised a preliminary point in relation to s. 38 that the plaintiff
cannot seek to recognise and enforce both the final arbitration award the final
appeal award. It was submitted by counsel for the defendant that two
decisions by the two arbitral bodies were arrived on different reasoning and
G
awarded different amounts of compensation. Furthermore, the compensation
amounts awarded were based on a different calculation/formula.
[26] It was submitted by counsel for the defendant that if the plaintiff were
to recognise and enforce both the final award and final appeal award, such
H enforcement would lead to confusion as to what was the basis for the award
in favour of the plaintiff. Hence, the plaintiff can only seek to recognise and
enforce the final appeal award.
[27] This court finds no merits in the preliminary point raised by counsel
for the defendant simply on the ground that even though there are two
I decisions of arbitral bodies, (namely; the final arbitration award the final
appeal award) the latter award was delivered by the appeal board as a result
of an appeal filed by the defendant against the arbitration tribunal award.
648 Current Law Journal [2018] 3 CLJ
Once the appeal board has heard the appeal and delivered its decision, thus A
the decision or the award by the final appeal board would be the final award
or the concluded award. Hence, the award to be recognised and enforced
obviously would be the final award by the final appeal board.
The Plaintiff’s Case
B
[28] It was submitted by the plaintiff’s counsel that the plaintiff has duly
complied with both requirements in this application and is entitled to the
order prayed for, until and unless the defendant can bring itself within s. 39
of the Act.
[29] Counsel for the plaintiff submitted that the defendant has not identified C
in their affidavits of which are the exact provisions of s. 39(1)(a)(i) to (vii)
that the defendant is invoking.
[30] Counsel for the plaintiff further submitted that under s. 39 of the Act
the defendant is required to prove the grounds of refusal by affidavit
evidence. The failure of the defendant to state the specific provision relied D
upon in its affidavit should appropriately lead the court to dismiss
defendant’s challenge under s. 39 of the Act. Regarding this contention,
counsel for the plaintiff had referred to the case of Archer Daniels Midland Co
lwn. TTH Global (M) Sdn Bhd [2016] 1 LNS 1282; [2017] 7 MLJ 325.
E
The Defendant’s Opposition
[31] In opposing the plaintiff’s application, the defendant filed the
following affidavits:
(i) affidavit in reply affirmed by Sultan Alaudin a/l KS Mohamed Ismail
on 22 February 2013 (Sultan Alaudin). F
A Ground (i): the final Appeal Board had acted outside the terms of
Arbitration stipulated in the plaintiff’s Request for Arbitration and/or
contains decisions on matters beyond the scope of the submission to
arbitration
[33] It was submitted on behalf of the defendant that the appeal board had
B considered matters outside the terms of the submission to arbitration and this
has occasioned a circumstance under s. 39(1)(a)(iv) and/or (v) of the Act.
With regards to this ground, counsel for the defendant had submitted the
following argument:
(i) the plaintiff in its request for arbitration had requested for arbitration
C of the dispute arose between the plaintiff and the defendant under
Contract Number: AV/BLK-1700(M)/06 dated 10 July 2006 which
was the sales contract.
(ii) it is not in dispute that the sales contract constituted a binding contract
between the plaintiff and the defendant and the said sales contract
D
contained terms and conditions which has been agreed upon between
the parties.
(iii) notwithstanding the fact that in the request for arbitration, the plaintiff
had only cited that the dispute between the plaintiff and the defendant
E
arose from the sales contract, the appeal board when considering the
appeal before them had referred and considered not only the sales
contract but also the initial contract/sold note issued by Intra Oil. The
appeal board in this case had found that the said initial contract/sold
note constituted the actual binding agreement between the plaintiff and
the defendant. The appeal board had gone further to consider cl. 12
F
of the initial contract/sold note and concluded that the draft letter of
credit which was issued by the plaintiff to the defendant was a
sufficient compliance of the plaintiff’s obligation to issue letter of
credit. Since the plaintiff had issued the letter of credit, it was
incumbent on the defendant upon receipt of the letter of credit to
G prepare and issue the performance bond.
(iv) the appeal board had therefore derived its decision from the wrong
contract namely; outside the sales contract, and hence acted outside
and beyond the terms of the submission to arbitration (which only
stipulated the sales contract). Consequentially, the award by the
H
appeal board gives rise to the circumstance under s. 39(1)(a)(v) of the
Act.
(v) when the appeal board had considered matters outside the sales
contract, the appeal board had gone out the parol evidence rule. The
I
application of terms or matters outside the sales contract constituted
a clear violation of the way in which contracts should be interpreted.
On this contention, counsel for the defendant had relied on the Federal
Court’s decision in the case of Berjaya Times Square Sdn Bhd
v. M Concept Sdn Bhd [2010] 1 CLJ 269; [2010] 1 MLJ 597.
650 Current Law Journal [2018] 3 CLJ
(vi) the appeal board had no reason to conclude that a “draft” letter of A
credit was agreed upon by the parties when there was no mention of
the word “draft” in the sales contract. Hence, the conclusion that a
“draft” letter of credit was sufficient amounted to a material change
in the already clear terms of the sales contract.
B
(vii) when the sales contract provided that the letter of credit or L/C will
be “operative within three working days upon receipt of the
2% unconditional performance bond …”. It must mean that the letter
of credit had to have first been issued before the performance bond.
Otherwise, the sales contract would have used the word “issued”
rather than “operative”. C
A and consideration must only be given to the terms and conditions contained
in the sales contract. Given that situation, the arbitral bodies should only
focus on the sales contract and must not take into account the initial contract
or the sold note.
[36] In essence the defendant argues that, when the appeal board in this
B
case had considered the initial contract or sold note in arriving at its decision,
the appeal board had gone outside the submission of the arbitration, and
therefore has occasioned a circumstance in s. 39(1)(a)(iv) and/or (v) of the
Act.
C
[37] In analysis, this court will first begin by setting out what was covered
or provided under the sales contract. The sales contract provides the
following particulars:
CONTRACT NO : AV/BLK-1700(M)/05 DATE: 10TH JULY 2008
QUANTITY : 10,000 MT
E
COMMODITY : RBD PALM OLIEN IN BULK
…. : 0.10% MAX
IV : 58 MIN
F MELTING POINT (ADCB CC 3-25) : 24 DEG. C MAX
I SWIFT : SCBLMYXXXXX
ORIGIN : MALAYSIA
[38] It must be noted and observed here that the sales contract did not
provide a term for arbitration. The arbitration clause or term is provided
under item 12 of the initial contract/sold note. In the present case, the C
plaintiff had referred the parties’ dispute to arbitration tribunal pursuant to
the arbitration term provided under the initial contract/sold note. The
defendant did not take any objection on the arbitration proceedings and as
a matter of fact submitted itself within the jurisdiction of the two arbitral
bodies even though the sales contract did not provide for arbitration clause.
D
[39] Here, it is crystal clear that when the dispute was referred to the
arbitration tribunal it was pursuant to the initial contract/sold note and this
was accepted by the defendant readily and willingly. And on top of that, the
defendant who was not happy with the award of the arbitration tribunal had
filed an appeal to the appeal board. E
[40] In addition to that, this court agrees with the submission of counsel for
the plaintiff that the defendant’s contention that the appeal board had acted
outside the submission of the arbitration, was clearly an afterthought. Item
12 of the initial contract or the sold note not only provides for arbitration
but also stipulates that arbitration must be governed by the PORAM Rules F
and Kuala Lumpur was nominated as the seat of arbitration.
[41] Thereto, this court opines that the defendant cannot be allowed to
willy-nilly elect when the initial contract or the sold note should apply or
should not apply at its whims and fancies. Upon the defendant submitting
itself to the jurisdiction of arbitration by virtue of item 12 of the initial G
contract/sold note, thus, it entails that the rest of the terms provided under
the initial contract or the sold note must also have similar application. Both
the arbitral bodies are justified in making reference to both the sales contract
and the initial contract/sold note and consider the same. Upholding the same
principle, the Court of Appeal in the case of Cheah Theam Kheng v. City Centre H
Sdn Bhd (In Liquidation) & Other Appeals [2012] 2 CLJ 16 had held the
following:
In other words of Sir Nicolas Browne-Wilkinson VC in Express Newspapers
Plc v News (UK) Ltd and Others (1990) 3 All ER 376 at pp. 383 to 384: There
is a principle of law of general application that it is not possible to I
approbate and reprobate. That means you are not allowed to blow hot
and cold in the attitude that you adopt. A man cannot adopt two
Hafeez Iqbal Oil & Ghee Industries (Pvt) Ltd v.
[2018] 3 CLJ Alami Vegetable Oil Products Sdn Bhd 653
E [45] It is this court’s judgment that that the final appeal board award did
not contain decision on matters beyond the scope of the submission to
arbitration. The appeal board had derived its decision within the scope of the
submission of the arbitration. And therefore the contentions of the defendant
that the appeal board had exceeded its scope are without merits and therefore
must fail. The circumstance in s. 39(1)(a)(iv) and/or (v) of the Act was never
F
proven by the defendant.
Court Analysis And Findings On Ground (ii)
Ground ii: both the Final Award and Final Appeal Award are in conflict
with the public policy of Malaysia in that they are inconsistent with the
G PORAM terms and would be unfair to the seller.
[46] The defendant had contended that the final award and/or the final
appeal award are in conflict with the public policy of Malaysia. This court
is in agreement with the plaintiff’s counsel that the defendant in its affidavits
does not state how the final appeal award is in conflict with the public policy
H of Malaysia.
[47] The defendant had never raised any issue in their affidavit explaining
that the award conflicted with fundamental principles of natural justice,
illegality or morality or otherwise offensive to the public policy of Malaysia.
The only ground that the defendant had raised was that somehow (though not
I
explained by the defendant) the award is allegedly inconsistent with the
PORAM terms and would be unfair against the defendant.
654 Current Law Journal [2018] 3 CLJ
[48] In the present case, both the plaintiff and the defendant had voluntarily A
chose and agreed to arbitrate their dispute according to PORAM Rules. The
PORAM Rules expressly provide that the decision of the arbitral tribunal
shall be final and conclusive.
[49] The defendant is therefore estopped from asserting that the award is
B
inconsistent with the PORAM Rules. It is trite law that those who make a
contract to arbitrate their dispute should be held to their bargain. (See: Allianz
General Insurance Company (M) Bhd & Ors v. Kapar Energy Ventures Sdn Bhd
[2016] MLJU 1515)
[50] Coming back to the issue of contravention of public policy, the law C
requires the defendant to adduce proof that the award is in conflict with the
public policy of Malaysia. The defendant here has clearly failed to prove the
same. It is trite law that the contravention of public policy argument ought
not to be utilised as a facade to reopen settled matters in the arbitration.
(See: i. Colliers International Property Consultants (USA) v. Colliers Jordan Lee
D
and Jaafar (Malaysia) [2010] MLJU 650; ii. Open Tyre Joint Stock Company
Efirnoye (“EFKO”) v. Alfa Trading Ltd [2012] 1 CLJ 323; [2012] 1 MLJ 685)
[51] The defendant here did not make any application under s. 37(1)(a)(i)
to (vi) or under (b)(ii) of the Act.
[52] This court agrees with the plaintiff’s submission that if the defendant E
was indeed serious about their contention (that the final appeal board had
acted outside the terms of arbitration stipulated in the plaintiff’s request for
arbitration and/or contains decisions on matters beyond the scope of the
submission to arbitration and that both the final award and final appeal award
are in conflict with the public policy of Malaysia) the defendant should have F
moved the court under s. 37 of the Act to set aside the award which they
failed to do.
[53] The failure in applying to set aside the award under s. 37 the Act on
the same grounds now attempted to be raised under s. 39 the Act, leads to
the inescapable conclusion that the issues raised by the defendant in this G
application lacks bona fide intent and obviously an afterthought.
[54] It is this court’s judgment that the defendant in the present case has
ultimately failed to discharge the burden of proof to prove that the
defendant’s challenges against the recognition under s. 38 of the Act falls
within any of the circumstances under s. 39 of the same Act. H
Court’s Decision
[55] Based on the above mentioned reasons, the plaintiff’s application in
encl. 1 is allowed with costs. This court also orders that the defendant to pay
the plaintiff the sum of RM10,000 as costs. I