ITC-FL10 Outdoor Cabinet Quick Installation Guide


This guide introduces how to install the cabinet on the concrete plinth. Outdoor cabinet
Version: MN080041CEC_01
Anchor bolt × 6
1850
150

Unit: mm Concrete plinth


CAUTION*

≥400 ≥300

612±2
Ground

800
The distance between the cabinet and the nearby Hollow
living area must be more than 10m, and the back of
the cabinet faces the dwelling place. Direction of Front Door

Wear the protective gloves while carrying the cabinet to 150 150
Embedded PVC tube 500±2 500±2
avoid scratches on the cabinet and your hands. 1850
Do not directly drag the cabinet to avoid damaging the
painting of the cabinet bottom. Front View of Concrete Plinth Top View of Concrete Plinth
The safety of the worker should always come first, if any
H = 1850

accident happens in the course of the installation.


TIPS
* The Caution items in this document do not cover all the Please build the concrete plinth according to the
safety precautions that must be observed. They provide above figures and embed six anchor bolts
only the generic safety precautions for operations. M12×220, whose exposed part is 30mm high.
FiberHome is not liable for any consequence that results
from violation of universal regulations for safety Please check the flatness of the concrete plinth
* with the level ruler after it is finished; if uneven,
*
operations and safety codes on design, production and
equipment use.。 please repair it.

* The lifting lugs are included in the accessories. Please take out
3 Removing the cover plate of the cabinet base
and install the lifting lugs before the cabinet installation.

3.1 Remove the front cover plate


1 Preparing tools
2 Locating the cabinet

NOTE NOTE
1
Prepare the following tools for the installation. Select an installation site for the cabinet
according to the installation dimension and the
space of the cabinet. 2
3

Hoisting equipment Philips screwdriver


Mounting holes

Wrenches Tape measure 1 Open the front door.


2400

700
2 Unscrew the two screws on the front cover
plate.
875

Level ruler Protective gloves


3 Lift up the front cover plate and remove it.
Unit: mm Then the mounting holes are revealed.
3100 单位:mm
3.2 Remove the back cover plate

1 Unscrew the eight screws on the back


Hex Nut M12
cover plate.

2 Remove the back plate and the mounting


holes are revealed. Spring Washer

Flat Wahser

5 Open the front door.


2 6 Secure the cabinet with the nuts, spring washers
and flat washers from the accessories.

4
7 Replace the front and back cover plate.
Installing the cabinet
8 Finish the cabinet installation and move on to the
next procedure according to your demands.

TIPS 5 Checking the installation

Before hoisting the cabinet, put


some protective materials (e.g. 1 The cabinet is installed securely.
2
sponge pad) between the cabinet 2 All the screws and nuts are tightened; the flat washers and spring washers are installed completely
and the lifting rope to protect the and properly.
cabinet from scratching.
3 The cabinet is neat and clear.
4 The paint on the surface of the cabinet is intact; if it is damaged, please repaint it in time.
1 Route the lifting rope through 5 The components and connection inside the cabinet are intact; any problem, please contact
the lifting lugs at the bottom of FiberHome immediately.
the cabinet.

2 Use the hoisting equipment to


lift the cabinet up.

3 Adjust the position of the 1


cabinet to align the mounting 3
holes with the anchor bolts in
the concrete plinth.
FiberHome Telecommunication Technologies Co., Ltd.
4 Place the cabinet carefully on Address: No.6, Gaoxin 4th Road, Wuhan, Hubei, China
the concrete plinth. Tel: 800-800-0787 400-889-0787 +86-27-87691549 Zip code: 430073
Website: http://www.fiberhome.com
获取更多相关手册,请联系烽火客服人员。
For more related manuals, please contact FiberHome Technical Support.