Method Statement - Installation of Conduits & Fitting - Rev 1
Method Statement - Installation of Conduits & Fitting - Rev 1
Method Statement - Installation of Conduits & Fitting - Rev 1
Document No xxxxxx
Revision History
1
Rev.
No. Revision Revision Approved Description Status
Date by by of Revision
Prepared by
Name
Signature
Title
Organization TAMIMI PEB Date 29/10/2020
Reviewed by
Name
Signature
Title
Organization TAMIMI PEB Date 29/10/2020
Approved by
Name
Signature
Title
Organization Date
Table of Contents
2
1 SCOPE OF WORK
2 ACCESS/EGRESS
3 LIGHTING
5 MATERIALS
7 PROGRAMME
9 TRAINING
10 SUPERVISION
11 WORKING HOURS
12 HOUSE KEEPING
13 OTHER INFORMATION
1. SCOPE OF WORKS:
1.1. This method statement is applicable to all conduiting related to electrical fire works at site for the
AMAALA TRIPLE BAY CONSTRUCTION VILLAGE
2. ACCESS/EGRESS:
The Access/Egress to the site for the easy movement of workmen, material and
3
equipment will be carried out in a safe manner. Any obstacle shall be properly cleared
either manually or employing suitable equipment (Back Hoe). The area for compaction shall be
identified, marked & cleared of obstructions if any. This clearing shall consist of rocks or other obstructions
that will interfere with proper compaction of the areas.
3. LIGHTING:
Safety Lighting
Tamimi PEB will provide Safety lighting at the entry point/s of the project as such
adequate to the basic security of the site premises or in accordance with the project
requirements.
Task Lighting
Tower light or portable light is use in the dark or in reduced visibility, lights will be fitted
and used to enable the work area to be adequately illuminated. In addition, amber
flashing beacons that give warning of the presence of the vehicle will be fitted and used
if necessary.
General
Generally, if otherwise required Tamimi PEB will provide adequate lighting facility
wherever there is a necessity for the lighting for the safety of its employees, material,
equipment or any other asset of Tamimi PEB or Client.
7. PROGRAMME:
6
1. Waste Management
7
5. Water Protection:
Fuels, oils, greases and hydraulic fluids must be stored in bunded compounds a minimum of 50m
from the watercourse.
Excavators will be modified to operate with biodegradable hydraulic oil.
Diesel to be stored in double skinned tanks/diesel bowsers – refueling of plant to only take place
if drip trays are in position
Refueling of machinery will be carried out in bunded areas.
Runoff from machine service and concrete mixing areas must not enter the watercourse;
Stockpile areas for sands and gravel will be kept to a minimum size, 50m away from the
watercourse;
Runoff from the above will only be routed to the watercourse via suitably designed and sited
settlement ponds/filter channels;
Settlement ponds should be inspected daily and maintained regularly;
Temporary crossings will be designed to the criteria laid down for permanent works;
Watercourse banks will be left intact if possible.
If they have to be disturbed, all practicable measures should be taken to prevent soils from
entering the watercourse.
General
Personal Protective Equipment and selection refer to Employer Requirement (AML-
DEV-H&S-GLE-0014 Personal Protective Equipment) for minimum requirements for
selection, use and maintenance of PPE.
Communication and Fire Precautions
Petrol operated plant and tools are not permitted on-site without obtaining the
Supervising Consultant's approval.
Portable halogen lamps are not permitted for use as task lighting (stand lights).
LPG cylinders and other highly flammable liquids shall not be stored within the
building under construction. The use of these shall be restricted to those quantities
required for daily use and they shall be removed to the safe storage area each day
after use.
Acetylene is to be strictly controlled by means of the permit system.
Other flammable liquids (such as paint) shall be stored safely within suitable metal
containers/storage huts.
Other materials, particularly combustible materials, shall be brought to site and
stored using the ‘just in time’ approach to avoid excessive fire loading of the
construction building.
Fire resistant materials shall be used for the temporary protection of building
finishes, materials and plant such as Monoflex and Correx and for the containment,
protection of materials delivered to site.
Site operations shall be coordinated and sequenced to maintain unobstructed fire
exit routes
Unattended sources of potential fire ignition such as bitumen boilers and space
heaters shall not be permitted at any time.
Adequate fire extinguishers shall be provided for all fire hazard related site activities.
8
The workforce shall be adequately trained in the safe use of fire extinguishers.
A Hot Works Permit procedure shall be in force for all types of hot works such as
burning, welding, and abrasive wheel operations.
9. TRAINING
10. SUPERVISION:
10.1 All Electrical Site activities shall be carried out under the supervision for the following
personnel
10.1.1 Foreman
10.1.2 Supervisor
10.1.3 Site Engineer
10.1.4 QC Inspector
9
(END OF DOCUMENT)
10
Cell Risk
3. Wire Pulling Excessive Employees Bruises / fracture / Inspect the area for Site Engineer, D 2 1 Close Site Engineer, 1
movement of performing the crushing injury any obstruction for Supervisor, supervision to Supervisor, E
force activity, from dropped load possible slip, trips Forman the activity Forman
and fall to the worker
Slip, trips and Rupture of inter- Report and
fall. vertebral (slipped Wear Personal rectify hazard
disc) in the lower Protective Equipment arising in the
Contact with spline. (PPE) gloves, working area
sharp helmet, safety shoes
materials Muscle strain and
sprain. Plan the activity and
Flying dust ensure doing the job
harmful Cut from sharp safety and avoid
materials edges of the load damage the wire or
cable during pulling
Bruises / fracture /
crushing injury
from dropped load
4. Wire Electrical Employees Sever Injury or Temporary Site Engineer, C 3 13 Obtain work Site Engineer, C 8
Insulation Hazard performing the even fatality from barricades the area Supervisor, permit Supervisor,
Test using activity, Megger tester and install signage’s Forman Forman
Megger Electric electrocution to avoid entry of Close
Tester shock, burns, Inspector, unauthorized supervision to Staff are
potential for Contractors, Electric shock, personnel the activity made aware
fire. Visiting staff burns, potential for of the
fire. Toolbox meeting All electrical AMAALA
must be conducted equipment standard and
and discussed the undergoes guidance on
hazard routine visual electrical
inspection and safety
Proper testing as
communication to the appropriate to
12
workers performing the equipment
the test
5. Lighting Slip, trips and Employees Bruises / fracture / Use PPE when Site Engineer, D 2 1 Staff are made Site Engineer, 1
Fixture fall. performing the crushing injury performing the Supervisor, aware of the Supervisor, E
Installation activity, from dropped load activity Forman AMAALA Forman
Contact with Injury / fracture Inspect ladder before Standard and
sharp due fall from using, do not use guidance
materials heights while defective or damage
installing lighting ladder When using a
Flying dust fixtures using a ladder one
harmful ladder Work areas kept person will
materials clear e.g. no boxes assist and hold
and other materials the ladder to
could trip and slip avoid falling
hazards.
6. Manual Lifting of Employees Rupture of inter- Lifting equipment to Site Engineer, D 2 1 Small items Site Engineer, 1
Handling heavy objects carrying out the vertebral (slipped be used (certified) to Supervisor, should be put Supervisor, E
by single task. disc) in the lower minimize human Forman in cages or Forman
worker. spline. involvement. palletized for
People in the ease of
Bulky or vicinity. Muscle strain and Design the task to movement.
unsecured sprain. reduce human Work areas to
items involvement in the have
Lifting of Cut from sharp lifting. demarcation
sharp objects. edges of the load and be cleared
Ensure operatives of unauthorized
Unusual Bruises / fracture / are physically fit for personnel.
strength, crushing injury the task.
height of from dropped load Consideration
operatives. Weight of the object should be
to be lifted must be given to
Incorrect known. If over 25 kg, reducing the
lifting assistance is weight
technique. required. although this
may mean
Slip, trips and If weight is between increasing the
fall. 25 kg and 50 kg, frequency of
lifting belt is required handling.
Excessive and correct training
13
movement of must be given to all Where the
load personnel on the size, surface
lifting task. texture of the
load makes it
difficult to
grasp,
consideration
should be
given to the
provision of the
handles,
handgrips to
improve the
grasp.
Any loads to be
handled should
not have sharp
corner, jagged
edges.
7. Hand & Electric shock Operation Internal burns / Where use of 220v Site Engineer, D 2 5 Any Site Engineer, D 1
Electrical Personnel external burns, (+) is unavoidable, Safety Officer, transformers Supervisor,
Tools Moving tool death, secondary use a residual current Operators used should be
bits. injury (e.g. falling device (RCD) or an center tapped
from ladder). earth leakage circuit to earth.
Torque / breaker (ELCB)
sudden Eye injury from protection device. Temporary
movement of flying particles or electrical
the tools e.g. dust. The supply voltage repairs should
high power Injuries from must be within the not be allowed.
drill hitting a impact and operating range as Repairs should
hidden entanglement with marked on the tool be sent back to
reinforcement moving tool bits. plate. the ACC Plant
and twisting. Department
Musculoskeletal Trailing cables must where effective
Flying injuries from not be at the path of and safe
particles from torques / sudden other workers. repairs can be
the tool. movement of tool. made.
Plugs and socket
Flying dust Hand / arm injury should be water If adjustment or
from cooling from the tool, resistant and color changes need
14
fans. including burns coded. Not domestic to be made,
when heat is appliances. tools should be
Vibration generated. disconnected
Tools should either from the mains
Trailing Hand / arm be earthed or double- supply.
electrical vibration insulated.
cables, syndrome, Injury Equipment
tripping following trips or should be
hazard. falls. inspected by
Noise. the user before
Noise induced each period of
hearing loss. use to ensure it
Respiratory injury is not
from airborne dust. damaged.
Electrical
equipment will
be inspected
and maintained
as per
manufacturer’s
recommendatio
n by a
competent and
trained
electrician at
the Plant
department.
8. Fall of a Falling from All operatives Injury to operatives Inspect ladder D 2 5 All workers on Site Engineer, D 1
person, object height working at height. working in the area properly when use. site must have Supervisor,
& material Access or Workers in the below from falling Don’t use defective received site
from height. ladder vicinity of height objects. or damage ladder specific safety
collapse working induction.
Using operations. Serious injury or Full body harness is
incomplete fatality from falling required for anyone Pre-task
ladder rang from height. working above 1.8 m meeting
Injury from in height from ground between
falling objects level. Supervisor and
(e.g. drop workers to
tools) All personnel should discuss Risk
Falling be trained to a level assessment
15
materials of competence and any other
sufficient to enable relevant items.
them to carry out Records to be
their work while kept of
ensuring the safety attendees.
and health of
themselves and Toolbox talks
others. to be given to
Daily checks from workers on
Section foremen. subjects
Management and relevant to task
Safety department to being carried
have frequent tours. out that.
Standing rule that
any worker, where Records to be
human life is in kept of
danger, can stop the attendees.
work.
16