Download as pdf or txt
Download as pdf or txt
You are on page 1of 44

Health and Safety

Executive

Safety and environmental


standards for fuel storage sites
Process Safety Leadership Group
Final report
Safety and environmental standards for fuel storage sites
Final report

Appendix 2 Guidance on the application


of layer of protection analysis (LOPA) to
the overflow of an atmospheric tank
Introduction

1 The scope of this appendix is confined to the filling of atmospheric storage tanks which meet
the requirements of the scope defined within this report.

2 Throughout this report reference is made to the British Standard versions of the international
standards IEC 61508 and 61511. The British Standards are the official English-language versions
of the European Standards approved by CENELEC and are identical with the equivalent IEC
standard. The use of British Standard references is because the primary focus of the guidance
has been the application of the LOPA technique in the context of United Kingdom health, safety
and environmental legislation.

3 This guidance should not be used for occupied building assessments or land use planning
purposes due to the current uncertainty in the explosion mechanism.

Overview of LOPA methodology for Safety Integrity Level determination

4 The term ‘LOPA’ is applied to a family of techniques used for carrying out a simplified- (often
referred to as a semi-) quantified risk assessment of a defined hazardous scenario. As originally
conceived, the LOPA methodology applied simple and conservative assumptions to make the risk
assessment. In this approach, factors are typically approximated to an order of magnitude. Over
time, some operating companies have applied greater rigour to the analysis so that the LOPA may
now incorporate and summarise several more detailed analyses such as fault trees and human
reliability assessments.

5 As a result the LOPA methodology covers analyses ranging from being little different in terms of
complexity to a risk graph, to little short of a detailed quantified risk assessment (see Figure 21). Both
of these extremes, and everything in between, are legitimate applications of the LOPA methodology.
The simple order of magnitude approach is often used as a risk screening tool to determine whether
a more detailed analysis should be performed. In some cases, the use of fault tree analysis and event
tree analysis, supported by consequence/severity analysis may be more appropriate than using the
LOPA methodology.

6 The LOPA technique has been developed and refined over a number of years, and is described
more fully in the CCPS concept book Layer of Protection Analysis.57 This appendix draws extensively
on the guidance given in the book. However, where the advice in the CCPS BOOK on protection
layers claimed for basic process control system (BPCS) functions is not consistent with BS EN 61511;
the more conservative approach of BS EN 61511 should be followed. Where relevant, these
differences are highlighted, and the requirements of BS EN 61511 should be given precedence.

7 LOPA is often used to identify the shortfall in meeting a predetermined dangerous failure
target frequency. For the purposes of this guidance, this shortfall, if it exists, is associated with
the average probability of failure on demand of a demand mode safety function required to meet
the target dangerous failure frequency. The identified shortfall is equated to the required SIL of a
safety instrumented function (SIF), as defined in BS EN 61511.

82
Safety and environmental standards for fuel storage sites
Final report

8 There are several ways of describing a hazardous scenario. The simplest convention is to
include in the description:

■■ the unwanted serious event (the consequence); and


■■ its potential cause or causes (initiating event(s)).

9 Hazardous scenarios can be derived by a number of techniques, eg Hazard and Operability


Studies (HAZOP), Failure Modes and Effects Analysis (FMEA) and What If. These studies will
typically provide at least one initiating event, a high level description of the consequences (although
details of the severity are rarely provided) and may also provide information on the safeguards.

Quantified Risk
Assessment

Fault Tree
Increasing complexity

Analysis
Human Reliability
Assessment
Complex
LOPA

Simple order
of magnitude
LOPA

Risk
graph

Increasing conservatism

Figure 21 Relationship of LOPA technique to other risk assessment methodologies

10 Once the hazardous scenario has been identified, the LOPA proceeds by defining and
quantifying the initiating events (including any enabling events and conditions) more fully and then
identifying and quantifying the effectiveness of the protection layers and conditional modifiers which
may prevent the scenario from developing or allow it to develop to the defined consequence.

11 It is helpful to adopt a systematic approach to identifying the critical factors which will prevent
the initiating event from leading to a loss of containment and those which, once containment is
lost, will prevent the undesired consequence from occurring. Essentially, this means considering
the analysis in terms of a bow-tie diagram, with the LOPA being the aggregation of a number of
individual paths through the bow-tie diagram which result in the same undesired consequence.

12 It is also important to adopt a systematic approach to identifying the consequence of interest


for the LOPA from the range of possible outcomes. Annex 2 shows the right-hand side of a bow-
tie diagram representing a possible range of consequences to the environment from the overflow
of a storage tank.

13 The critical factors can then be divided between prevention protection layers (on the left-hand
side of the bow-tie), mitigation protection layers (on the right-hand side of the bow-tie) and conditional
modifiers. Further guidance on protection layers and conditional modifiers is given later in this report.

83
Safety and environmental standards for fuel storage sites
Final report

14 In algebraic terms, the LOPA is equivalent to calculating fiC in the equation below:

K L M N
f =Σ fi x Π Pim x Π PFDij x ΠP
c I EE PL CM
ik
i=1 m=1 j=1 k=1

Where:
c I EE PL CM
f fi is the calculated
Pim frequency
PFDof consequence Pik C summed over all relevant initiating failures
and with credit taken for all ijrelevant protection layers and conditional modifiers.
c I EE PL CM
f fi is the frequency
P PFD of initiating failure
Pik i leading to consequence C
im ij

c I EE PL CM
f fi Pim is PFD
the probability that
Pikenabling event or condition m will be present when initiating
failure i occurs.
ij

EE PL CM
Pim PFDij is the P
probability of failure on demand of the jth protection layer that protects against
consequence
ik
C for initiating event i.
PL CM
PFDij Pik is the probability that conditional modifier k will allow consequence C to occur for
initiating event i.

15 The calculated value of fC is then compared with a target frequency. The target frequency
may be derived from detailed risk tolerance criteria, or may take the form of a risk matrix. This
comparison allows decisions to be made on whether further risk reduction is required and what
performance any further risk reduction needs to achieve, including the SIL, if the additional
protection layer is a SIS.

16 Some variants of the LOPA methodology determine the harm more precisely in terms of
harm caused to people and harm to the environment. This approach, which is required by the
tolerability of risk framework for human safety, Reducing risks, protecting people,58 requires
consideration of additional factors such as the probability of ignition, the performance of
containment systems, and the probability of fatality. For a similar perspective of environmental
issues assessors should consult the relevant Environment Agency sector BAT guidance. All of
these factors may be subject to considerable uncertainty, and the way the LOPA is carried out
needs to reflect this uncertainty. Uncertainties are present in all calculations but sensitivity analysis
can be used to help understand the uncertainty.

17 The product of the LOPA should be a report which identifies the hazardous scenario(s)
being evaluated, the team members and their competencies, the assumptions made (including
any supporting evidence) and the conclusions of the assessment, including the SIL of any SIS
identified. The format and detail of the LOPA report should facilitate future internal review by the
operating company and should also reflect the likelihood that it may be scrutinised by an external
regulator and other third parties.

18 It is important to emphasise that the LOPA methodology is a team-based methodology


and its success relies on the composition and competence of the team. The team should have
access to sufficient knowledge and expertise to cover all relevant aspects of the operation. In
particular, for the risk assessment of an existing operation, the team should include people with
a realistic understanding of operational activities and tasks – recognising that this may not be
the same as what was originally intended by the designer or by site management. Any LOPA
study should be carried out from scenario definition to final result using the knowledge of what is
actually done.

84
Safety and environmental standards for fuel storage sites
Final report

19 This guidance supports both simple and more complex applications of LOPA to assess the
risks arising from a storage tank overflow. The simpler applications are associated with greater
conservatism and less onerous requirements for providing supporting justification. The more
complex applications will often require greater amounts of supporting justification and may
require specialist input from experts in human factors analysis, risk quantification, dispersion and
consequence modelling. Also, as the analysis becomes more complex, it may prove harder to
provide long-term assurance that the assumptions in the assessment will remain valid. Users of
this guidance should therefore not only consider what factors are currently relevant, but also what
is required to make sure that they continue to be relevant.

20 Although this guidance focuses on the LOPA technique, other techniques such as fault tree
analysis or detailed quantitative risk assessment, used separately, may be a more appropriate
alternative under some circumstances. Quantified methods can also be used in support of data
used in a LOPA study. It is common practice with many dutyholders to use detailed quantified risk
assessment where multiple outcomes need to be evaluated to characterise the risk sufficiently,
where there may be serious off-site consequences, where the Societal Risk of the site is to be
evaluated, or where high levels of risk reduction are required.

21 As the LOPA study proceeds, the team should consider whether the complexity of the
analysis is still appropriate or manageable within a LOPA or whether a more detailed technique
should be used independently of the LOPA technique. Where a more detailed analysis is
undertaken, much of this guidance will still be applicable. In all cases the analyst is responsible
for ensuring that the appropriate level of substantiation is provided for the complexity of the study
being undertaken.

22 To simplify the use of this guidance, a flow chart mapping out the overall process is included
(Figure 22).

85
Safety and environmental standards for fuel storage sites
Final report

Select tank for study

Decide whether considering Harm to People or Harm See ‘Consequence assessment’


to Environment and determine the severity paragraphs 23-35 and ‘Risk
of the harm for the scenario being assessed tolerance criteria’ paragraphs 36-53

Could it be both?

Systematically identify all initiating events and related See ‘Initiating events’
enabling events/conditions that could (if all other paragraphs 54-76
measures fail) lead to the harm being considered and
document the scenarios for each

For each initiating event list those risk reducing See ‘Protection layers’
measures (prevention and mitigation protection layers, paragraphs 77-122 and
conditional modifiers etc) that relate to that initiating ‘Conditional modifiers’
event, including any existing or proposed high-level paragraphs 123-148
safety instrumented function

Conduct LOPA to calculate the frequency of harm


for that initiating event

Repeat for all relevant initiating events

Sum the frequency of harm from all initiating events See ‘Risk tolerance criteria’
paragraphs 36-53

Compare this total with target frequency for


the level of severity

Reassess the total


YES Is the risk NO frequency of harm
ALARP?

See section 4

Has Identify further risk


harm both to reduction measures
NO people and to the YES and the required
environment been performance of any
evaluated? measure including the
SIL if the additional
measure is a SIS

Finish

Figure 22 Flowchart for application of LOPA process

86
Safety and environmental standards for fuel storage sites
Final report

Consequence assessment

Overview
23 This guidance is concerned with the prevention of the overflow of an atmospheric storage
tank. Such a scenario is only one part of the wider picture of risks associated with storage tank
operations. Therefore, the dutyholder of the storage facility should bear in mind that even once the
risks of a tank overflow have been addressed, there may be other severe events resulting from
(for example) failures of integrity in the tank floor and walls which should also be evaluated before
the risk assessment of the facility can be considered complete. For these cases, techniques other
than LOPA may be appropriate.

24 In the case of the overflow of a gasoline tank, several outcomes are possible with different
safety and environmental consequences:

■■ Prior to the Buncefield explosion, the most likely consequences from the overflow of an
atmospheric storage tank would have been assumed to be a flash fire and/or pool fire. The
size of the flash fire would probably have been limited because the influence of vaporisation
from an atomised liquid cascade was not recognised and the flash fire would have been
associated with evaporation from an assumed quiescent pool in the bund. In either case, the
most serious outcome may well have been assumed to be a single fatality somewhere on the
operating facility with the off-site consequences being managed through evacuation.
■■ Following the explosion at Buncefield, the most severe human safety consequence should
now be assumed to be an explosion that may cause damage to occupied buildings or places
where people may congregate. The explosion will be accompanied by a flash fire and will
probably result in multiple pool fires.
■■ The Buncefield explosion and subsequent fires caused environmental damage due to the
contamination of ground and surface water by oil products and firefighting agents. Some of this
damage was the result of failures of secondary containment during the fires and insufficient tertiary
containment to retain contaminated firefighting water. Experience of leaks from tanks at other sites
has been that where the bunds are permeable, ground water contamination can occur.

Individual Risk and scenario-based assessments


25 This guidance addresses four types of assessment for overflow protection: three for safety risk
and one for environmental risk. These are as follows:

■■ Individual Risk assessment, where the calculation is typically performed for a specified
individual (often characterised by ‘the person most at risk’ and referenced to a specific job role
or a physical location). Typically the calculation takes one of two forms: the risk from a tank
overflow is aggregated with contributions from other relevant hazards and then compared
with an aggregated risk target; alternatively, the risk from the single overflow scenario may be
calculated and compared with a target for the contribution to Individual Risk derived for a single
scenario. Individual Risk should aggregate all risks to that individual not just major accident risks.
Consideration of Individual Risk is required within the COMAH safety report for an establishment.
■■ Scenario-based safety risk assessment, where the calculation estimates the frequency with
which the hazardous scenario will lead to the calculated consequence (a certain number of
fatalities within the total exposed population). The distinction between this calculation and an
Individual Risk calculation is that this calculation does not focus on any specific individual but
instead considers and aggregates the impact on the whole population. A single scenario-based
risk assessment does not account for all the sources of harm to which an individual may be
exposed in a given establishment. When scenario-based LOPA is carried out, Individual Risk
should also be considered to ensure that Individual Risk limits are not exceeded.
■■ Societal Risk assessment: Where the scenario contributes significantly to the Societal Risk of
the establishment an assessment should be made. For top-tier COMAH sites, consideration
of Societal Risk is required within the COMAH safety report and, if applicable, could be more
stringent than Individual Risk.
■■ Scenario-based environmental risk assessment, where the consequence is assessed against
a range of outcomes.

87
Safety and environmental standards for fuel storage sites
Final report

26 The distinction between an Individual Risk assessment and a scenario-based safety


assessment is important for how the consequence is calculated and for how this is presented in
the LOPA. It is of particular relevance to how some protection layers (in particular evacuation, see
paragraphs 118–122) and conditional modifiers (probability of presence and probability of fatality,
see paragraphs 142–145) are applied.

27 For a scenario-based assessment, there may be no single value for factors such as
occupancy or probability of fatality that can be applied across the entire exposed population. If
this is the case, it is not appropriate to represent the factor in the LOPA as a protection layer or
conditional modifier. Instead the factor should be incorporated into the consequence assessment
by subdividing the exposed population into subgroups sharing the same factor value and then
aggregating the consequence across all the subgroups.

Estimating the consequences of a Buncefield-type explosion


28 The full details of the explosion at Buncefield are not fully understood at the current time,
although the explosion appears to be best characterised by the detonation of at least part of the
vapour cloud formed by the overflow (RR71859). The available evidence suggests over-pressures
of at least 200 kpa within the flammable cloud, but rapidly decaying outside the cloud for the
prevailing conditions and Buncefield.

29 Given the limitations on current understanding, it is appropriate to apply the precautionary


principle as outlined in Reducing risks, protecting people and the policy guidelines published by
the United Kingdom Interdepartmental Liaison Group on Risk Assessment: The Precautionary
Principle: Policy and Application.60 As described in Reducing risks, protecting people, the
precautionary principle ‘rules out lack of scientific certainty as a reason for not taking preventive
action’. Therefore this guidance offers judgements based on the information currently available in
recognition that future developments in modelling and understanding may allow these judgements
to be revised.

30 Currently there is no widely available methodology for estimating the size, shape and rate
of development of the flammable cloud that could be formed from a storage tank overflow.
The behaviour of the explosion and effects cannot be predicted with the more commonly used
models such as the multi-energy model. More sophisticated models may be able to estimate
the explosion hazards and risks for particular sites. Otherwise it is proposed that consequence
assessments are based on the experience of the Buncefield incident.

31 In estimating the spread of the flammable cloud, the simplest assumption is that it spreads in
all directions equally. This assumption is conservative and is considered reasonable if there are no
topographical factors influencing directionality. At wind speeds of less than 2 m/s, it is assumed
that the wind direction is too variable and hard to measure reliably to have a significant directional
impact. However, the spread of the flammable cloud at Buncefield was influenced by local
topography and the cloud did not spread equally in all directions even under very low wind speed
conditions. The influence of topography will need to be considered on a case-by-case basis and
should be justified by supporting evidence. This may involve specialised dispersion modelling as
standard models cannot reproduce the source term from the plunging cascade and may not be
reliable at very low wind speeds. The effort to produce such a justification may only be worth
making if the directionality has a significant impact on the consequence.

32 The following distances (Table 7) are considered to be a conservative approximation of


the hazard zones for a Buncefield-type explosion and, in the absence of other information, are
recommended as a method by which operators can determine relevant hazard zones.

88
Safety and environmental standards for fuel storage sites
Final report

Table 7 Hazardous zones for a Buncefield-type explosion


Zone name Zone size (measured Comment
from the tank wall)
HSE research report RR718 on the Buncefield explosion
mechanism indicates that over-pressures within the flammable
cloud may have exceeded 2 bar (200 kPa) up to 250 m from
the tank that overflowed (see Figure 11 in RR718).
A r < 250 m
Therefore within Zone A the probability of fatality should be
taken as 1.0 due to over-pressure and thermal effects unless
the exposed person is within a protective building specifically
designed to withstand this kind of event.
Within Zone B there is a low likelihood of fatality as the
over-pressure is assumed to decay rapidly at the edge of the
cloud. The expected over-pressures within Zone B are 5–25
B 250m < r < 400 m kPa (see RR718 for further information on over-pressures).
Within Zone B occupants of buildings that are not designed
for potential over-pressures are more vulnerable than those in
the open air.
Within Zone C the probability of fatality of a typical population
C r > 400 m can be assumed to be zero. The probability of fatality for
members of a sensitive population can be assumed to be low.

Note: the distances are radii from the tank wall as this is the location of the overflow (see Figure
23). Bund layouts can vary significantly, so measuring the distances from the bund wall would not
provide a consistent approach.

Zone C

Zone B

Zone A

250m 400m

Tank

Figure 23 Hazardous zones for a Buncefield-type explosion

89
Safety and environmental standards for fuel storage sites
Final report

33 The zones within Table 7 are provided as a conservative basis. The zones may be adjusted on
a case-by-case basis, due to site-specific factors such as:

■■ Site topography. The Buncefield site is reasonably level other than higher ground to the south.
This appears to have affected the spread of the cloud such that it extended 250 m to the
north and 150 m to the south. Therefore if a site is not level, distances shorter than Table 7
may be appropriate for the ‘uphill’ direction. Similarly, if a site has a significant slope, then it
would be appropriate to consider distances longer than Table 7 in the ‘downhill’ direction.
■■ Significant sources of ignition within Zone A. If there are ‘continuous’ sources of ignition closer
to the tank than 250 m located in a position that could be contacted by the cloud, then it is
very likely that the cloud will ignite before it reaches 250 m. This would mean that the distance
to the edge of Zone A is less than 250 m and CM2 (Probability of ignition) is likely to be 1.
Examples of ‘continuous’ sources of ignition are boilers, fired heaters and surfaces that are
hot enough to ignite the cloud. Typically, automotive, internal combustion engines are not a
reliable source of ignition. However, an automotive starter motor is a known ignition source.
■■ Duration and rate of transfer into the tank. The quantity of petrol that overflowed Tank 912 at
Buncefield from initial overflow to ignition was approximately 300 tonnes. If the transfer rate or
overflow duration is estimated to be significantly different to that at Buncefield, then this may
affect the formation and size of the cloud. An estimate of cloud generation could be made
based on modelling such as the ‘HSL entrainment calculator’ and a 2 m cloud height (for
further information see Appendix 1).

34 Other factors that should be considered when estimating the consequence to people are:

■■ Hazards resulting from blast over-pressure can be from direct and indirect sources. For
example, indirect sources of fatal harm resulting from an explosion can be missiles, building
collapse or severe structural damage (as occurred at Buncefield).
■■ People on and off site within the relevant hazard zones should be considered as being at risk.
People within on-site buildings such as control rooms or offices that fall within the hazard
zones as described above should be considered at risk unless the buildings are sufficiently
blast-rated.
■■ The base case should be ‘normal night time occupancy’ – see CM1 ‘Probability of calm and
stable weather’. However, a sensitivity analysis should consider abnormally high occupancy
levels, eg road tanker drivers, visitors, contractors and office staff who may be present
should the calm and stable conditions occur during normal office hours (see paragraph 131).
Additionally, sensitive populations just beyond the 250 m, eg a school or old people’s home,
should also be considered.

Environmental consequences
35 This guidance also covers the environmental risks associated with a storage tank overflow.
The consequences may be direct (pollution of an aquifer if the overflowing gasoline penetrates
the bund floor) or indirect (pollution arising from firefighting efforts). The consequence will need
to be determined on a case-by-case basis after consideration of the site-specific pathways to
environmental receptors, the condition of secondary and tertiary containment arrangements,
the location and type of specific receptors, and any upgrades planned to meet Containment
Policy requirements (COMAH CA Policy on Containment of Bulk Hazardous Liquids at COMAH
Establishments).

Risk tolerance criteria

General
36 Risk tolerance criteria can be defined for human risk and for environmental risk on the basis
of existing guidance. In addition, dutyholders may also have risk tolerance criteria for reputation
risk and business financial risk. However, there is no national framework for such criteria and
decisions on the criteria themselves and whether to use such criteria in addition to those
presented here lie with the dutyholder. No specific guidance is given in this report to evaluating

90
Safety and environmental standards for fuel storage sites
Final report

reputation risk or business financial risk but much of this report will be of assistance in carrying
out such evaluations.

37 Regulation 4 of the COMAH Regulations requires dutyholders to ‘take all measures necessary
(AMN) to prevent major accidents’. This is equivalent to reducing risks to ALARP. HSE’s semi-
permanent circular Guidance on ALARP decisions in COMAH61 states that:

‘The demonstration that AMN have been taken to reduce risks ALARP for top-tier COMAH
sites should form part of the safety report as required by regulations 7 and 8 of the COMAH
Regulations… For high-hazard sites, Societal Risks/Concerns are normally much more relevant
than Individual Risks, but Individual Risk must still be addressed’.

38 See also paragraphs 108 and 109 of A Guide to the COMAH Regulations L111.62

39 For each ‘in scope’ tank with the potential of an explosion following an overflow, the
tolerability of risk of the major accident hazard scenario must be assessed. A risk assessment
should address the categories described in paragraph 25.

Scenario-based safety risk assessment


40 LOPA, like most risk assessment tools, is suitable for this type of risk assessment, using the
following approach:

■■ determine the realistic potential consequence due to the hazardous scenario (in this case the
number of fatalities due to an explosion following an overflow from a specific tank);
■■ estimate the likelihood of the scenario; and
■■ locate the consequence and likelihood on the following (or similar) risk matrix (Table 8).

Table 8 Risk matrix for scenario-based safety assessments


Likelihood of ‘n’ fatalities Risk tolerability
from a single scenario
10-4/yr – 10-5/yr Tolerable if ALARP Tolerable if ALARP Tolerable if ALARP
10 /yr – 10 /yr
-5 -6
Broadly acceptable Tolerable if ALARP Tolerable if ALARP
10-6/yr – 10-7/yr Broadly acceptable Broadly acceptable Tolerable if ALARP
10-7/yr – 10-8/yr Broadly acceptable Broadly acceptable Broadly acceptable
Fatalities (n) 1 2–10 11–50

41 Table 8 is based on HSE’s Guidance on ALARP decisions in control of major accident


hazards (COMAH) SPC/Permissioning/12. Note that a scenario-based risk assessment with a
single fatality is not the same as an Individual Risk calculation.

42 This assessment should be repeated for each ‘in-scope’ tank in turn. Where there is a
large number of in-scope tanks (eg ten or more) the aggregate risk from all of the tanks may be
adequately addressed by the individual and societal assessments detailed below, but may require
a separate assessment.

Individual Risk assessment


43 The tank overflow scenario may contribute to the risks to individuals, either on-site or off-
site. Where the total risk of fatality to any individual (the Individual Risk) from the activities at the
hazardous establishment exceeds a frequency of 10-6 per year (see Reducing risks, protecting
people paragraph 130), additional risk reduction measures should be considered, either at the
tank or elsewhere, to reduce the risk so far as is reasonably practicable. This exercise should form
part of the safety report demonstration for an establishment considering the risk from all major
accident hazards.

91
Safety and environmental standards for fuel storage sites
Final report

Societal Risk assessment


44 The scenario of an explosion following a tank overflow may contribute significantly to the
societal risk associated with an establishment. If this is the case, then the scenario should be
included in the Societal Risk assessment within the safety report for the establishment. As
described in the HSE COMAH SPC/Permissioning/12:

‘Societal Risk is the relationship between frequency of an event and the number of people
affected. Societal concern includes (together with the Societal Risk) other aspects of
society’s reaction to that event. These may be less amenable to numerical representation
and include such things as public outcry, political reaction and loss of confidence in the
regulator, etc. As such, Societal Risk may be seen as a subset of societal concern.’

45 Assessing a scenario in terms of the numbers of potential fatalities does not address
all aspects of societal concern, but is an indicator of the scale of the potential societal
consequences. The fatalities may be onsite and/or offsite. Other aspects of societal concern are
outside of the scope of this risk assessment guidance.

46 A scenario with the potential for more than ten fatalities may contribute significantly to the
level of Societal Risk from the hazardous establishment. Therefore the scenario should also be
considered as part of the safety report Societal Risk assessment.

47 A scenario with the potential for ten or less fatalities may not represent a significant Societal
Risk and a judgment will need to be taken over its inclusion.

48 Reducing risks, protecting people provides one Societal Risk tolerance criterion, that the
fatality of ‘50 people or more in a single event should be regarded as intolerable if the frequency
is estimated to be more than one in five thousand per annum’ (paragraph 136). This risk criterion
is applied to a ‘single major industrial activity’ as a whole, where a single major industrial
activity means an industrial activity from which risk is assessed as a whole, such as all chemical
manufacturing and storage units within the control of one company in one location or within a site
boundary.

49 There is currently no nationally agreed risk tolerance criterion to determine when the level of
Societal Risk is ‘broadly acceptable’. This assessment is site-specific, and would therefore need to be
performed for the establishment as part of the safety report demonstration and agreed with the CA.

50 LOPA is not normally used to assess Societal Risk because a Societal Risk assessment
typically requires the evaluation of a range of scenarios. This is typically carried out using
quantified risk assessment techniques such as fault and event trees. There is no universally
agreed method of presenting the results of a Societal Risk assessment, but commonly used
methods include F-N curves and risk integrals.

Scenario-based environmental risk assessment


51 There are currently no published environmental risk criteria for Great Britain with the same
status as those for safety in Reducing risks, protecting people. Information on tolerability of
environmental risk has also been produced for options assessment in section 3.7 of Integrated
Pollution Prevention and Control (IPPC) and Environmental Assessment and Appraisal of BAT
IPPC H1 Version 6 July 2003.63 The tolerability criteria from this reference is summarised in matrix
form in Table 9 below. Further guidance on environmental risk matrix can be found in Annex 5 of
HSE’s SPC/Permissioning/11.64

52 Dutyholders seeking to demonstrate compliance with the COMAH Regulations should adopt
an approach consistent with the information provided in Tables 9 and 10 and with that in their
COMAH safety reports and pollution prevention control permit applications.

92
Safety and environmental standards for fuel storage sites
Final report

Table 9 Tolerability of environmental risk


Category Acceptable if Acceptable if reduced Unacceptable if
frequency less than as reasonably practical frequency above
and frequency between
6 Catastrophic 10-6 per year 10-4 to 10-6 per year 10-4 per year

5 Major 10-6 per year 10-4 to 10-6 per year 10-4 per year

4 Severe 10-6 per year 10-2 to 10-6 per year 10-2 per year

3 Significant 10-4 per year 10-1 to 10-4 per year 10-1 per year

2 Noticeable 10-2 per year ~ 10+1 to 10-2 per year ~10+1 per year

1 Minor All shown as acceptable – –

53 For the purposes of this guidance, the categories from Table 9 have been aligned to COMAH
terminology as follows:

■■ ‘Acceptable if frequency less than’ equates’ to the ‘Broadly acceptable region’;


■■ ‘Acceptable if reduced as low as is reasonably practicable and frequency between’ equates to
the ‘Tolerable if ALARP region’;
■■ ‘Unacceptable if frequency above’ equates to the ‘Intolerable region’.

Table 10 Risk matrix for environmental risk

Category Definitions
6 Catastrophic –– Major airborne release with serious off-site effects
–– Site shutdown
–– Serious contamination of groundwater or watercourse with extensive
loss of aquatic life
5 Major –– Evacuation of local populace
–– Temporary disabling and hospitalisation
–– Serious toxic effect on beneficial or protected species
–– Widespread but not persistent damage to land
–– Significant fish kill over 5 mile range
4 Severe –– Hospital treatment required
–– Public warning and off-site emergency plan invoked
–– Hazardous substance releases into water course with ½ mile effect
3 Significant –– Severe and sustained nuisance, eg strong offensive odours or noise
disturbance
–– Major breach of permitted emissions limits with possibility of prosecution
–– Numerous public complaints
2 Noticeable –– Noticeable nuisance off site, eg discernible odours
–– Minor breach of permitted emission limits, but no environmental harm
–– One or two complaints from the public
1 Minor –– Nuisance on site only (no off-site effects)
–– No outside complaint
Source From information in IPPC document Integrated Pollution Prevention and Control (IPPC) and
Environmental Assessment and Appraisal of BAT

Initiating events

54 The next stage of the LOPA is to identify all the significant initiating events that can cause
the defined safety or environmental consequence and to estimate the frequency (likelihood) of
their occurrence. An initiating event can be considered as a minimum combination of failures and

93
Safety and environmental standards for fuel storage sites
Final report

enabling events or conditions that are capable of generating the undesired consequence – in this
case, the overflow of a gasoline storage tank. Initiating events place demands on protection layers.

Identifying initiating events


55 One of the issues identified in the sample review of LOPAs in HSE’s research report RR716
was that the identification of initiating events was not comprehensive and therefore that the
frequency of demands on protection layers may have been underestimated. It is important that
the process for identifying initiating events is comprehensive and that it is carried out with the
involvement of those who have to perform the tank-filling operation.

56 Potential causes of tank overflow should be considered in each of the following categories:

■■ Equipment failures: for example failures of level measurement systems (gauges, radar
devices, suspended weights), valves and other components; also failures of site services and
infrastructure that could affect safe operation (eg loss of power, utilities, communications
systems);
■■ Human failures: in particular errors in executing the steps of the filling operation in the proper
sequence or omitting steps; and failures to observe or respond appropriately to conditions or
other prompts. Possible errors may include but not be limited to:
–– incorrect calculations of the ullage in a tank (leading to an overestimate of how much
material can be safely transferred into the tank);
–– incorrect verification of dips or incorrect calibration of level instrumentation;
–– incorrect routing of the transfer (sending material to the wrong tank);
–– incorrect calculation of filling time or incorrect setting of stop gauges;
–– failure to stop the transfer at the correct time (eg missing or ignoring the stop gauge and/or
succeeding alarms).
■■ External events: for example:
–– changes in the filling rate due to changing operations on other tanks or due to changes
within a wider pipeline network;
–– failure to terminate filling at the source (remote refinery, terminal or ship) on request from
the receiving terminal;

One systematic way of identifying initiating events is to prepare a demand tree. This is described
in detail and illustrated by example in Annex 3.

Estimating initiating event frequencies


57 The LOPA requires that a frequency is assigned to each initiating event. The frequency may
be derived in several ways:

■■ Where the initiating event is caused by the failure of an item of equipment, the failure rate per
year may be derived from the failure-to-danger rate of the equipment item.
■■ Where the initiating event is caused by the failure of a person to carry out a task correctly and
in a timely manner, the initiating event frequency is calculated as the product of the number
of times the task is carried out in a year and the human error probability (HEP) for the task. In
this case, the time at risk (see Annex 4) is already included in the number of times the task is
carried out in a year and no further factor should be applied.
■■ Where the initiating event is taken to be the failure of a BPCS control loop (when it does not
conform to BS EN 61511), the minimum frequency which can be claimed is 1E-5 dangerous
failures per hour.

As with any quantitative risk assessment technique, it is important that where probabilities or
frequencies are assigned numerical values, these values are supported by evidence. Wherever
possible, historical performance data should be gathered to support the assumptions made.
Where literature sources are used, analysts should justify their use as part of the LOPA report.

94
Safety and environmental standards for fuel storage sites
Final report

Enabling events/conditions
58 Enabling events and conditions are factors which are neither failures nor protection layers but
which must be present or active for the initiating event to be able to lead to the consequence.
They can be used to account for features inherent in the way the tank-filling operation is
conducted. An example would be that the tank can only overflow while it is being filled, and so
certain factors such as instrument failure may only be relevant during a filling operation. This is an
example of the ‘time at risk’, and further guidance on how to include this is given in Annex 4.

59 Enabling events and conditions are expressed as probabilities within the LOPA – ie the
probability that the event or condition is present or active when the initiating failure occurs. The most
conservative approach would be to assume that enabling events or conditions are always present
when an initiating failure occurs (the probability is unity), but this may be unrealistically conservative.
The guidance in Annex 4 provides information on how to develop a more realistic figure.

60 Enabling events and conditions are typically operational rather than intentional design features
and may not be covered by a facility’s management of change process. Therefore caution needs
to be taken when the ‘time at risk’ factor includes operational factors that are likely to change.
Examples may include:

■■ the number of tank-filling operations carried out in a year (which may change as commercial
circumstances change);
■■ the proportion of tank fills which are carried out where the batch size is capable of causing
the tank to overflow (it may be that the tank under review normally runs at a very low level and
would not normally be able to be filled to the point of overflow by typical batch sizes);
■■ the tank operating mode (if the tank is on a fill-and-draw operating mode so that the level is
more or less static).

While each of these considerations is a legitimate enabling event or condition, caution needs to be
taken in taking too much credit for them. It is quite possible that any or all of these circumstances
may change as part of normal facility operations without the significance for the validity of the
LOPA being recognised in any management of change process.

Special considerations

Failures of the basic process control system (BPCS) as initiating events


61 The term ‘basic process control function’ (BPCF) was developed to differentiate between
the functional requirement for process control (what needs to be done) and the delivery of the
functional requirement through the basic process control system (how it is done). The terminology is
intentionally analogous to the terms ‘safety instrumented function’ and ‘safety instrumented system’.

62 Although the definitions in BS EN 61511 are not always explicit in this area, a BPCS can
include both a fully automated control system and a system that relies on one or more people to
carry out part of the BPCF. The BPCS is considered to comprise all the arrangements required to
effect normal control of the working level in the storage tank, including operational controls, alarms
through the BPCS and the associated operator response. For the purposes of the LOPA and the
type of scenario under consideration, the BPCS would typically include several of the following:

■■ a level sensor on the tank;


■■ field data marshalling and communications systems;
■■ input/output cards;
■■ central processing units (logic controller, processing cards, power supplies and visual
displays);
■■ operators and other workers required to perform the normal control function required to
control the level of the storage tank;
■■ communication arrangements between operators if more than one operator is required to
carry out the control function;
■■ final elements (which may be a remotely or locally operated valve or pump).

95
Safety and environmental standards for fuel storage sites
Final report

63 Refer to Annex 5 for a more detailed discussion about the treatment of the BPCS in the LOPA
for the overflow of an atmospheric storage tank.

64 BS EN 61511 sets a limit on the dangerous failure rate of a BPCS (which does not conform
to IEC 61511) of no lower than 1E-5/hr. This limit is set to distinguish systems designed
and managed in accordance with BS EN 61511 from those that are not. For example minor
modifications to hardware and software elements in a BPCS may not routinely be subject
to the same rigour of change control and re-evaluation required for a SIS that complies with
BS EN 61511. The 1E-5 dangerous failures per hour performance limit should be applied to the
system(s) that implement the BPCF taken as a whole, whether operating as a continuous closed-
loop system or whether relying on the intervention of a process operator in response to an alarm.

65 The performance claimed for the BPCS should be justified, if possible by reference to actual
performance data. For the purposes of analysis, the performance of a given BPCS may be worse
than the 1E-5 dangerous failures per hour performance limit but cannot be assumed to be better
(even if historical performance data appears to show a better standard of performance) unless the
system as a whole is designed and operated in accordance with BS EN 61511.

66 The elements comprising the BPCS may be different for different filling scenarios. In particular,
while the tank level sensor may be the same, the human part of the BPCS may change (if multiple
people and/or organisations are involved) and also the final element may change (eg filling from a
ship may involve a different final element from filling from another tank). In each case, the elements
of the BPCS should be defined for each mode of operation of the tank and should be consistent
with what is required by operating procedures.

67 There are two main approaches when dealing with initiating events arising from failures in the
BPCF within the LOPA:

■■ In the first and most conservative approach, no credit is taken for any component of the
BPCS as a protection layer if the initiating event also involves the BPCS. The failures involving
the BPCS may be lumped into a single initiating event or may be separately identified. This
approach is consistent with simple applications of LOPA. See Annex 5 for further discussion.
This approach fully meets the requirements of BS EN 61511.
■■ The second approach is to allow a single layer of protection to be implemented where there
is sharing of components between the BPCS as an initiator and the BPCS as a layer of
protection. Where credit for such a layer is claimed, the risk reduction factor is limited to ten
and the analysis must demonstrate that there is sufficient independence between the initiating
event and the protection layer (see Annex 5 for further details). For example, a failure of an
automatic tank gauge would not necessarily prevent consideration of the same operator who
normally controls the filling operation responding to an independent high level alarm as a
protection layer, whereas a failure of the operator to stop the filling operation at the required
fill level may preclude consideration of their response to a subsequent alarm. This approach
meets the requirements of BS EN 61511 providing all the associated caveats are applied and
adequate demonstrations are made.

68 It is always preferable to base performance data on the actual operation under review, or
at least one similar to it. Care needs to be taken in using manufacturer’s performance data for
components as these may have been obtained in an idealised environment. The performance in the
actual operating environment may be considerably worse due to site- and tank-specific factors.

Additional aids to tank filling operations


69 Operators may be able to configure their own alarms to advise when a tank filling operation
is nearing its programmed stop time (‘stop gauges’). Software systems may also help with
scheduling tasks by keeping track of all the tank movement operations being carried out and
ordering the required tasks.

96
Safety and environmental standards for fuel storage sites
Final report

70 Some tank monitoring systems include alarms and systems which monitor for ‘stuck’ tank
gauges and ‘unscheduled movement’.

71 While these are useful aids to operation, neither the systems themselves nor the human
interface with them are designed or managed in accordance with BS EN 61511. Therefore the
credit to be taken for them should be limited. As they also typically rely on the same operator
who has to bring the transfer to a stop, it is not appropriate for them to be considered as a
protection layer. Instead they may be considered as a contributing factor to the reliability claimed
for the operator, for example in relation to error recovery, in carrying out the basic process control
function, and are therefore part of the basic process control system.

72 Care needs to be taken to identify situations where the operator has come to rely on the
‘assist’ function to determine when to take action. It is important to identify this type of situation to
avoid making unrealistic reliability claims.

The role of cross-checking


73 Many tank-filling operations include a number of cross-checking activities as part of the
operation. These may include checks before the transfer starts (eg routing valve line-up, tank dips,
available ullage) and periodic checks during the filling operation (eg to confirm the filling rate, carry
out tank dips or check for unusual instrument behaviour).

74 Depending on the circumstances, cross-checks may be represented in the LOPA as modifiers


to the initiating event frequency or as part of a protection layer. If the initiating events include a
contribution for misrouting, then the frequency of misrouting may be adjusted if a suitably rigorous
cross-check is carried out. If the tank filling operation requires an initial tank dip to be carried out, the
frequency of the dip being incorrectly carried out or recorded may be affected by a suitable cross-
check. If the tank filling operation requires periodic checks of the level to be carried out, this may
provide an opportunity to identify that a level gauge has stuck or that the wrong tank is being filled.

75 Cross-checks can provide an opportunity to detect and respond to an error condition,


whether the condition has been caused by a human error or an equipment failure. The amount of
credit that can be taken for the cross-check will depend on the specifics of what is being checked
and the degree of independence of the check. This is discussed in more detail in Annex 6.

76 Various human reliability assessment techniques may be used to evaluate the effectiveness of
cross-checking activities – eg THERP (Technique for Human Error Rate Prediction) and HEART
(Human Error Assessment and Reduction Technique). It is important that any assessment is made
by a competent human reliability specialist and that it is based on information provided by the
operators who actually carry out the filling operation.

Protection layers

General principles
77 The LOPA methodology relies on the identification of protection layers, and in specifying
protection layers it is important that all the rules for a protection layer are met. A valid protection
layer needs to be:

■■ effective in preventing the consequence; and


■■ independent of any other protection layer or initiating event; and
■■ auditable, which may include a requirement for a realistic functional test.

78 Note that the requirement for all three criteria to be met for each protection layer is a stronger
requirement than in the Informative Annex D to BS EN 61511-3, where these requirements
are only applied to so-called ‘independent layers of protection’. The approach adopted in this
guidance is consistent with the approach in the CCPS book Layer of Protection Analysis.

97
Safety and environmental standards for fuel storage sites
Final report

Effectiveness
79 Care needs to be taken in ensuring that each of these requirements for a protection layer is
met and avoid the type of errors described in Annex 1.

80 A protection layer must be effective. This requires that the layer has a minimum functionality
that includes at least:

■■ a means of detection of the impending hazardous condition;


■■ a means of determining what needs to be done; and finally
■■ a means of taking effective and timely action which brings the hazardous condition under
control.

81 If any of these elements are missing from the protection layer, the layer is incomplete or
partial and the elements should be considered an enhancement to another protection layer. For
example, the presence of a level detection instrument with a high level alarm which is independent
of the normal level instrument used for filling control is not a complete protection layer in its own
right. A full protection layer would require consideration of the arrangements for determining what
action is required and the means of making the process safe, for example an independent valve/
pump shut-off.

82 For the layer to be effective, it must be capable of bringing the hazardous condition under
control and prevent the consequence from developing without the involvement of any other
protection layer or conditional modifier. The requirement for timeliness may require careful
consideration of the dynamics of the scenario and when any response from a protection layer
may be too late to be effective. Where people are involved, care needs to be taken over the
human factors of the response.

Independence
83 A protection layer needs to be independent of other protection layers and of the initiating
event. This is a requirement of clause 9.5 in BS EN 61511-1 and is a key simplifying feature of
LOPA. To ensure that protection layers are independent, it is vital that they are clearly identified.
(See Annex 5 for further details.)

84 The simplest application of LOPA requires absolute independence between protection layers,
as well as between protection layers and initiating events. Therefore, if a proposed protection layer
shares a common component with another protection layer or initiating event (eg a sensor, human
operator, or valve), the proposed protection layer could not be claimed as a separate protection
layer. Instead, the proposed protection layer would have to be included as part of the initiating
event or other protection layer.

85 A more detailed application of LOPA requires ‘sufficient’ rather than absolute independence
between protection layers or between a protection layer and an initiating event. The principles
within BS EN 61511-1 and 61511-2 (eg clauses 9.4, 9.5 and 11.2) present the requirements on
the BPCS when used as a protection layer. For example a detailed evaluation would need to be
performed of the possible failure modes of each element of the protection layer – typically involving
techniques such as Failure Modes and Effects Analysis, Human Reliability Assessment and Fault
Tree Analysis. Great care needs to be taken in using this approach to ensure that consistent
assumptions about the condition of equipment or people are made throughout the analysis.

Auditability
86 Protection layers need to be auditable. In this context, audit means far more than simply a
management system audit. In broad terms, auditing refers to the continued assessment of system
performance, including all the necessary supporting arrangements. The process of testing is
required to ensure that a layer of protection will continue to function as originally intended and that
the performance has not degraded. The details of this will vary with the details of the protection
layer, and may require programmed functional tests. Formal auditing of management systems
will also be required to ensure that not only do technical components of the protection layer

98
Safety and environmental standards for fuel storage sites
Final report

continue to perform at the right level, but also that the overall performance of the management
system remains at the right level. Whatever the details, the auditing needs to address the following
questions:

■■ How can the performance of this protection layer be degraded?


■■ What needs to be checked to make sure that the performance has not degraded?
■■ How often do the checks need to be carried out?
■■ How can it be confirmed that all the required audits are being carried out with sufficient
rigour?

87 For example, routine inspection, testing and maintenance of a level sensor may provide
assurance that the sensor will continue to operate, and likewise for the final element. Where
people are involved in the protection layer, an ongoing means of demonstrating their performance
against defined criteria will need to be developed. This may involve a combination of management
system checks (eg by verifying training records and confirming that key documents are available
and up-to-date) and observed practical tests (eg carrying out emergency exercises, testing
communications arrangements and reviewing the presentation of information by instrumentation
systems). Additionally, some form of testing that is analogous to the functional test required for
hardware systems should be developed. Regardless of the details for a specific protection layer, it
is essential that records of the various ‘audits’ are retained for future examination and reference.

Prevention layers

General process design


88 An underlying assumption is that the storage tanks being studied by the LOPA are capable
of producing the hazard in question by complying with the scope requirements. This does
not mean that tanks outside the scope present no risk, but these other risks have not been
specifically considered in developing this guidance. For example, if the tank is equipped with an
overflow arrangement which precluded the formation of a vapour cloud, this would take the tank
outside the scope of this guidance. However, even if the tank has an overflow arrangement which
prevents the formation of a large vapour cloud from a liquid cascade, significant safety hazards
may still arise from the evaporation and ignition of a liquid pool in the bund, and significant
environmental hazards may arise if the liquid leaks through the walls or floor of the bund. The
guidance in this report may assist in the assessment of these scenarios.

89 Issues to do with the mode of operation of the tank (eg typical parcel sizes for filling, normal
operating levels) are accounted for as enabling events and conditions forming part of the initiating
event (see paragraphs 54–76).

The basic process control system as a protection layer


90 It may be possible to take credit for the BPCS as a protection layer if sufficient independence
can be demonstrated between the required functionality of the BPCS in the protection layer
and any other protection layer and the initiating event. Clauses 9.4 and 9.5 of BS EN 61511-1
and BS EN 61511-2 present the requirements on the BPCS when used as a protection layer. In
particular, BS EN 61511-1 9.5.1 states:

‘The design of the protection layers shall be assessed to ensure that the likelihood of
common cause, common mode and dependent failures between protection layers and
between protection layers and the BPCS are sufficiently low in comparison to the overall
safety integrity requirement of the protection layers. This assessment may be qualitative or
quantitative.’

91 The demonstration of independence is most straightforward if the initiating event does not
involve a failure of the BPCS, eg if the initiating event involves misrouting flow to the storage tank
and there is sufficient independence between the person making the routing error and the person
controlling the filling of the tank.

99
Safety and environmental standards for fuel storage sites
Final report

92 If the initiating event involves a failure of part of the BPCS, the simplest approach under a
LOPA would be to discount any further protection layer operating through the BPCS. Some
analysts may consider this approach excessively conservative for their situation. However, other
analysts and some operating companies are known to apply this approach because of the
difficulties associated with making the required demonstrations. Annex 5 gives further guidance on
the level of independence required where more than one function is delivered through the BPCS.

93 Claims for risk reduction achieved by the BPCS should meet the requirements of BS EN 61511-1
and 61511-2 (eg clauses 9.4, 9.5 and 11.2).

Response to alarms
94 Dutyholders should review and where necessary revise the settings of the level alarms on
their tanks in accordance with Appendix 3. Where the alarm settings meet the requirements,
it is considered legitimate to consider operator response as a protection layer under suitable
conditions.

95 Where process alarms are delivered through the BPCS, consult Annex 5 for further guidance
on independence when credit is being claimed for more than one function implemented through
the BPCS. The analysis should meet the requirements of BS EN 61511-1 (for example clauses
9.4, 9.5 and 11.2).

96 The wider considerations of operator response to alarms are discussed in Annex 8. Where the
alarm is delivered through the BPCS, the risk reduction factor of the alarm layer should be limited
to at best 10 in accordance with BS EN 61511-1 clause 9.4.2.

97 As with other protection layers, the alarm itself is only part of the protection layer. The full
protection layer needs to include the alarm, the operator, the machine-operator interface, any
communications systems (if communications between operators is required to deliver the required
alarm function) and a final element. For the response to the alarm to be included as a protection
layer, the following requirements should be met:

■■ The alarm protection layer should not include any failed component of it which is part of an
initiating event. Therefore:
–– if the initiating event is due to a failure of the tank gauge, it would not be legitimate to rely
on an alarm generated by the same tank gauge;
–– if the initiating event involves the failure of a valve or pump to stop on demand, the alarm
protection layer cannot rely on the same valve or pump to bring the transfer to a stop.
■■ There must be sufficient time for the transfer to be brought safely to a halt.
■■ Where the initiating event is a failure within the BPCS and the alarm system uses the same
BPCS, credit for the alarm may only be taken if sufficient independence can be shown
between the alarm function and the failed BPCS elements (see Annex 5).

Safety instrumented systems


98 In LOPA studies, the normal convention is that the need for SIS is determined when all other
protection layers have been considered. If an existing SIS complies with BS EN 61511 then a
reliability performance consistent with the SIL-rating of the SIS and its design and operation
can be claimed. If any ‘instrumented protection’ does not comply with BS EN 61511 then a risk
reduction factor of no greater than 10 can be claimed for it. However, experience has shown
that it is unlikely that an instrumented protection system that does not comply with BS EN 61511
would have a reliability assessment associated with it, and therefore an assessment would have to
be made to determine the performance level that could be claimed.

Other safety-related protection systems


99 It is possible to argue that some other protection layers can be considered so long as they
meet the requirement for a protection layer set out in paragraphs 77–87 of this appendix. Such
protection layers are referred to as ‘other technology’ in BS EN 61511 and are not subject to the
performance limits required by BS EN 61511, eg pressure relief valves.

100
Safety and environmental standards for fuel storage sites
Final report

Mitigation layers
100 Mitigation layers are protection layers representing intentional design or operational measures
which become effective once primary containment has been lost. They must be relevant to the
hazardous scenario under consideration and must prevent the consequence from developing. The
same mitigation layer may be effective against some consequences but ineffective against others.
For example, bunding will not prevent the development of a vapour cloud from a storage tank
overflow, but may be effective in preventing certain kinds of environmental consequence. Possible
mitigation measures which may have an impact on the overflow of a gasoline storage tank include:

■■ overflow detection (including gas detection, liquid hydrocarbon detection and direct
observation);
■■ fire protection (to the extent which this may reduce escalation or environmental
consequences from a tank overflow, although this was not the case at Buncefield);
■■ bunding or dyking;
■■ emergency warning systems and evacuation.

101 For all these, it needs to be recognised that these mitigate the consequence but do not
prevent a release and incident. If their effect is included in a LOPA study, it is important to make
sure that they are:

■■ independent of other protection layers, especially where positive action is to be taken;


■■ properly designed to prevent the undesired consequence;
■■ effective in preventing the undesired consequence; and
■■ tested periodically to assure continued effectiveness.

102 When included in a LOPA study, the function of the mitigation layers need to be described in
terms of how they meet a demand and their reliability.

Overflow detection
103 Overflow detection may take several forms. It may be automatic, using suitably located gas/
liquid detectors to operate valves or pumps, or it may be manual, relying on operator response to
various forms of detection (including alarms raised by suitable instrumentation, visual indications
such as direct observation or via CCTV, or smell). The details of overflow detection measures will
be site-specific, and a number of factors need to be taken into consideration.

104 Where reliance is placed on operators to detect (as opposed to respond to) the overflow, the
following factors should be considered:

■■ site manning levels;


■■ procedures detailing required checks and appropriate actions;
■■ other duties performed by the operator.

105 Detection may be adversely affected where the personnel present on site have a number of
tasks to do which limit their opportunities for regular and scheduled checks of the storage area.
Any checks that are occasional and ad hoc should not be credited in the LOPA. Conversely, when
operators have sufficient time formally set aside to check the storage tanks at pre-determined
intervals during filling operations, detection becomes more likely. If regular site checks are cited as
a mitigation measure these should be set out in a formal procedure and be subject to verification.

106 Where hydrocarbon gas or liquid detection equipment is used the following factors should be
considered:

■■ the type of detection, which should be determined on a case-by-case basis and be specific
to the tank under consideration; and
■■ the location of the detector(s), and the kind of releases which can and cannot be detected; and
■■ whether the detector is connected to an alarm or provides an input for an automated
shutdown, or both.

101
Safety and environmental standards for fuel storage sites
Final report

107 On sites where hydrocarbon gas or liquid detection is used as a means of overflow detection,
the detector type, operation, maintenance and detector location are critical factors. Historically,
hydrocarbon detection systems have been found not to be highly reliable because their ability
to detect gas or liquid depends not only on the reliability of the instrument but also on their
positioning in a suitable location and their robust maintenance. Therefore, claims made for the
performance of an overflow detection system should include sufficient supporting evidence.

108 Care also needs to be taken to be realistic in specifying the required performance of an
overflow detection system because it is only a partial protection layer if it simply detects that the
storage tank is overflowing. For the protection layer to be complete and effective, it must also be
possible to take action which will stop the overflow before any vapour cloud formed can reach a
source of ignition. There are several important elements to this:

■■ It must be possible for the overflow to be detected and stopped safely (ie without expecting
an individual to approach close to the vapour cloud).
■■ The means of stopping the overflow must be independent of other layers of protection – ie
reliance cannot be put on closing valves or stopping pumps which form part of another
protection layer.
■■ The time to stop the overflow requires careful consideration given the assumption of a very
low wind speed. Under low wind speed conditions, any large vapour cloud may be persistent
and may be capable of being ignited and exploding for some time after the overflow has
stopped. Different considerations for response time would apply for an environmental
consequence where, for example, the consequence requires that the gasoline penetrates the
floor of the bund.
■■ For any detection system relying on direct observation, careful consideration needs to
be given to the human factors of the process, including the time taken for diagnosis,
communication, determination of the condition of any other failed protection layers and for
the correct action to be taken.
■■ The human–machine interface, in particular the means of alerting the operator that an
overflow has occurred and the human factors affecting the response of the operator.
■■ Where relevant, the reliability and quality of the communications arrangements, including the
presence of any radio ‘blind spots’ and areas of high background noise or distraction.
■■ Where direct observation is assumed, consideration needs to be given to the means of
observation. While the sense of smell may alert a knowledgeable person to the presence of
gasoline vapour and to the fact that the situation is abnormal, it is unlikely to allow the source
to be localised without further investigation. Even visual observation may not be sufficient if
the vapour cloud is large.
■■ Where the operating procedures for the facility require operators to investigate potential leaks,
a failure of the overflow detection protection layer may result in increased numbers of people
being vulnerable should the vapour cloud ignite. This may result in worse consequences than
would be expected from simple time-averaged observation of where people are and when.
■■ Where the response to an indication of a tank overflow requires operator intervention,
consideration needs to be given to:
–– the expected role of an operator on receipt of a signal from the gas or liquid detection
system. (How will the operator be alerted? Will it be obvious which tank is overflowing?
Which operator is expected to respond? Where will the operator be when the alert is
received? How long will it take to diagnose the situation? Are there clear instructions on
what to do? Has the situation been rehearsed?);
–– their ability to take action (which valve needs to be closed? How is the valve identified? Is it
accessible safely? How long will it take to close? How is the valve closed?);
–– the effectiveness of the action (will closing the valve in the required response time make
much of a difference? Will the gas cloud already have reached a large size?).

102
Safety and environmental standards for fuel storage sites
Final report

Fire protection
109 Fire protection systems are not a relevant mitigation layer for safety because they cannot
realistically be expected to prevent a tank overflow from igniting and exploding (as would be
expected from a prevention layer). Nor can they mitigate the damage caused by an explosion in
such a way as to protect vulnerable people who might otherwise be killed by an explosion.

110 Fire protection systems may be a relevant mitigation layer for environmental damage, but this
would depend very much on the environmental consequence being assessed and whether the fire
protection system is a critical factor in preventing the consequence from developing. It will also be
closely related to the effectiveness of the secondary and tertiary containment and therefore may not
be considered a fully independent layer. The relationship of the fire protection system to other layers
of protection and the effectiveness it is assigned should be judged on a case-by-case basis.

Bunding/secondary and tertiary containment


111 Secondary and tertiary containment are not relevant protection layers against an explosion,
but are relevant to minimising the environmental consequences of a tank overflow. The
significance of secondary and tertiary containment will depend on the pathways by which the
gasoline from the tank (or any products such as contaminated firewater which may be an indirect
consequence of the overflow) may enter the wider environment.

112 If secondary containment fails, ground water may be affected. A number of incidents in
recent years have involved secondary containment failures resulting in ground water impacts.
The use of a low probability of failure on demand for ground water impacts due to secondary
containment failures should be justified.

113 Care is particularly required over paths to the environment that may not be immediately
obvious. These may include:

■■ bund floor penetrations for groundwater monitoring bore holes or pipework that may present
an easier route to groundwater than through the bulk of the bund floor;
■■ drainage arrangements for the collection and removal of rainwater and/or water that is
drained from the storage tank, especially if these rely on an operator to keep a bund drain
valve closed, or to close it after heavy rainfall. Also, if the bund includes rubble drains these
may reduce the effective thickness of the bund floor;
■■ penetrations of the bund wall, where these are inadequately sealed;
■■ degradation of the condition of earth bund walls, eg due to slumping, settlement and
burrowing animals. Also, where access arrangements into the bund result in a reduced
effective bund wall height.

114 A LOPA considering the level of reduction of risk provided by secondary and tertiary
containment requires a realistic case-by-case assessment which may take into account the extent
to which measures comply with current good practice, the means of recovery of spilt material (if it is
safe to do so) and the extent to which loss of integrity may occur for the event being considered.

115 The performance of the tertiary containment systems cannot be separated from the
emergency response arrangements and their effectiveness. For sites where excess contaminated
fire water is piped directly to a suitably sized and designed treatment plant and then to the
environment a low probability of failure on demand for the tertiary containment systems would
be appropriate. Where such excess fire water would be released directly into surface water or
allowed to spill onto the ground and hence pass to ground water, a high probability of failure on
demand would be expected to be used. The use of a high risk reduction factor for surface water
and/or ground release of excess fire water should be fully justified.

116 Where secondary and tertiary containment arrangements fully meet the requirements for bund
permeability, a low probability of failure on demand can be assigned to the protection layers. Where
there are gaps against best practice, a higher probability of failure on demand may be warranted.

103
Safety and environmental standards for fuel storage sites
Final report

117 General guidance cannot be given beyond the need for a realistic case-by-case assessment
which may take into account environmental remediation and the rate at which penetration of the
ground takes place. These considerations will be site-specific and possibly specific to each tank.

Emergency warning systems and evacuation procedures


118 Emergency warning systems and evacuation procedures may allow people to escape in
the event of a storage tank overflow, and therefore avoid harm. However, great care is required
in taking credit for such systems in the LOPA because in their own right they only constitute a
means of, possibly, making a hazardous situation ‘safe’ (by preventing the consequence from
being realised). To be a complete protection layer they need to be combined with a means of
detecting an overflow, and therefore emergency warning systems and evacuation procedures
are better considered part of an overflow detection protection layer as an alternative to (or in
combination with) closing a valve or stopping a pump.

119 In judging the effectiveness of the emergency warning system and evacuation procedures,
the following should be considered:

■■ The time it takes to activate the emergency warning system.


■■ The coverage of the emergency warning system – can it be heard in all relevant parts of the
facility, including in noisy workplaces and inside vessels, vehicles and tanks?
■■ Have the required emergency response actions been defined clearly and are they
communicated to all personnel at risk, including visitors and contractors?
■■ How is assurance gained that personnel have understood their training and that they continue
to remember what to do?
■■ Is it absolutely clear what needs to be done and how in responding to the alarm?
■■ Do any decisions need to be made on how to respond to the alarm to deal with specific site
conditions at the time?
■■ Are muster points clearly signed?
■■ Is at least one muster point located in a safe place for foreseeable site conditions?
■■ Can personnel access at least one muster point safely regardless of local conditions and will it be
obvious which muster point to go to and which route to use even in conditions of poor visibility?
■■ How long will it take personnel to escape the hazardous area and how does this compare
with the time available before ignition might occur?
■■ Are the evacuation procedures regularly tested by field tests, and what do the test results show?

120 Any credit taken for warning and evacuation systems should be fully justified in the LOPA
report.

121 While an overflow detection system combined with a warning alarm and evacuation
procedures may meet the requirements for an effective protection layer in considering the risk to
an individual, it may not do so for the overall exposed population.

122 Where the risk to a population is being considered, an overflow detection system with
a warning alarm and evacuation procedures may only be partially effective. Therefore such a
system would not meet the requirement of effectiveness for a LOPA layer of protection. In this
case, the contribution of any evacuation system should be considered in the determination of the
consequence and not as a protection layer.

Conditional modifiers

123 In this guidance, the term conditional modifiers is applied to risk reduction factors which are
either external to the operation of the facility (eg weather) or are part of the general design of the
facility without being specific to the prevention of a tank overflow (eg shift manning patterns, on-site
ignition controls). Conditional modifiers are represented in the LOPA by probabilities of occurrence,
as opposed to the probability of failure on demand used to represent a protection layer.

104
Safety and environmental standards for fuel storage sites
Final report

124 The same principles of independence, effectiveness and auditability which apply to protection
layers also apply to conditional modifiers. It is important to make sure that the conditional modifier,
as defined in the LOPA, is effective in its own right in preventing the consequence without relying
on the performance of another conditional modifier or protection layer. Where the performance of
a proposed conditional modifier is conditional on the performance of a protection layer or another
conditional modifier, it cannot be considered independent. Instead it should be considered part of
another protection layer or conditional modifier. The risk reduction should only be claimed once
and the LOPA team will need to decide where best to include it.

125 The use of a given conditional modifier may not be appropriate in all circumstances
depending on the type of calculation being performed. See paragraphs 25–27 of this appendix.

126 In many cases there may be uncertainty over what value to use for a given conditional
modifier because the factors which influence it cannot all be defined or characterised, eg where
the role of human behaviour is uncertain or where the underlying science is itself uncertain. Under
these circumstances a conservative approach should be taken, consistent with the application of
the precautionary principle (see paragraphs 23–24 of this appendix).

127 The presentation of conditional modifier probability ranges in guidance is problematic


because of the number of site- and situation-specific factors that need to be considered.
Experience has shown that any values cited in literature are often used without consideration of
any accompanying caveats and without due consideration of site- and situation-specific issues.
Therefore this guidance aims to describe the relevant factors to be considered rather than
proposing specific values. These can then be addressed as part of a reasoned justification to
support the probability used for a given conditional modifier.

CM 1 – Probability of calm and stable weather


128 The Buncefield explosion occurred during calm and stable weather conditions. There is
insufficient evidence currently available to say with certainty whether the weather needed to be
both calm and stable, whether only one of these conditions was required (and if so which), and
what wind speed limit should be applied to the ‘calm’ condition. The basis of this guidance is
that the development of a large vapour cloud with the kind of compositional homogeneity that
is believed to have existed at Buncefield required both low wind speed and stable atmospheric
conditions.

129 It is not certain from the available data what limiting value should be used to define a low
wind speed condition. This guidance recommends that a value of 2 m/s is used. Analysts are
cautioned against trying to differentiate between wind speeds lower than 2 m/s because of the
difficulties in obtaining reliable measurements under such conditions (see CRR13365). Noticeably
higher wind speeds will disperse the vapour cloud more rapidly and may make it more likely that
an ignition would lead to a fire rather than to an explosion.

130 It is also unclear at present what level of atmospheric stability is required for the development
of the kind of large vapour cloud formed at Buncefield. The release at Buncefield occurred under
inversion conditions which promote the formation of ground-hugging vapour clouds. Given the
present state of knowledge, it is recommended that the weather conditions are confined to
classes E and F on the basis that these correspond to inversion conditions and are most likely to
be associated with low wind speeds.

131 The occurrence of Pasquill classes E and F is between the hours 1600–0800 (see Table
4.1.10 in CRR133) and therefore mainly but not exclusively outside normal office hours. Note that
weather conditions associated with the Buncefield explosion are affected by seasonal variations
and should be accounted for by the analyst.

105
Safety and environmental standards for fuel storage sites
Final report

CM 2 – Probability of ignition of a large flammable cloud


132 This conditional modifier represents the probability that the ignition of the vapour cloud from
a storage tank overflow is delayed until it is sufficiently large to cause a widespread impact.
Alternative outcomes are an earlier ignition that causes a localised flash fire, or safe dispersal of
the cloud without ignition.

133 As a general rule, as the size and duration of a Buncefield-type release increases the
probability of ignition will increase, eventually tending towards 1.0. For shorter duration large
releases, some available data has been quoted in LOPA studies by operators based on Lees’
Loss Prevention in the Process Industries66 suggesting a probability of ignition of 0.3 although this
value is based on offshore blowouts and is not directly applicable to Buncefield-type events.

134 The bulk of available literature on ignition probabilities is pre-Buncefield and is based on
scenarios and circumstances that differ significantly from the Buncefield incident. This can in many
cases make their adoption for Buncefield-type scenarios inappropriate. Therefore, a number of
factors need to be taken into consideration when determining the probability of ignition for gasoline
and other in scope substances. These include, but are not necessarily limited to the following:

■■ Size and duration of release – which may require an estimate of how long an overflow might
persist before it is discovered, how big the cloud can get and how long it might take to
disperse. In the absence of better information, the size and duration of release should be
based on the Buncefield incident.
■■ Site topography, which can lead to a flammable cloud drifting either towards or away from an
ignition source.
■■ The potential ignition sources present that could come into contact with the flammable cloud
such as a vehicle, a pump house or a generator. This assessment should include any off-site
sources within the potential flammable cloud.
■■ Immediate ignition is likely to produce a flash fire, delayed ignition may produce a flash fire or
explosion.

135 The significance of area classification in preventing ignition should be considered carefully.
While area classification will limit the likelihood of ignition of a flammable cloud in the zoned
areas, it will not stop it completely (eg see section 1.6.4.1 of Ignition probability review, model
development and look-up correlations67 and section 8.1.3 of A risk-based approach to hazardous
area classification68), and the type of release being considered in this report is outside the scope
of conventional area classification practice. ‘Classified’ hazardous areas are defined by the
probability of flammable or explosive atmospheres being present in ‘normal’ operations or when
releases smaller than those at Buncefield occur due to equipment failure. Most major hazard
releases would go beyond the ‘classified’ hazardous areas.

136 Even if a dutyholder chooses as a matter of policy to purchase Zone 2 minimum electrical
equipment throughout their facility, this may not apply to every type of equipment (for example, street-
lighting). Also, normal site layout practice may allow uncertified electrical equipment (such as electrical
switchgear and generators), ‘continuous’ sources of ignition such as boilers or fired heaters, and hot
surfaces, to be present close to Zone 2 boundaries, increasing the chance of ignition.

137 It is also possible that the operation of emergency response equipment (including switchgear
and vehicles) may act as an ignition source. The operation of such equipment may be initiated
directly or indirectly by the tank overflow and therefore cannot be assumed to be independent of
the overflow event.

138 Where a more detailed estimate of ignition probabilities is required further information is given
in the HSE’s research report CRR20369 and the Energy Institute’s Ignition probability review,
model development and look-up correlations. The assessment should take into account the
spread of the cloud over the facility and its environs and should identify all credible sources of
ignition within the area.

106
Safety and environmental standards for fuel storage sites
Final report

CM 3 – Probability of explosion after ignition


139 The reasons why the vapour cloud at Buncefield exploded as opposed to burning as a
flash fire are not fully understood. The latest understanding is contained in the report ‘Buncefield
explosion mechanism Phase 1: Volumes 1 and 2 RR718 HSE Books 2009’. Factors such as
ambient temperature; cloud size, shape, and homogeneity; congestion (including that from
vegetation); droplet size; and fuel properties may have a significant effect on the probability of an
explosion compared to a fire.

140 This conditional modifier is intended to represent such factors. However, there is insufficient
information available at present to know which of the above factors, if any, are relevant to the
probability of explosion. Nor is it clear whether commonly used generic probabilities of explosion
(typically derived from onshore and offshore process data and applied to a wide range of leak
sizes with some or no relationship to leak size) can be applied to the type of event considered in
this report.

141 Given the present state of knowledge about the Buncefield explosion mechanism this report
tentatively proposes that the value of this modifier should be taken as unity in the stable, low wind-
speed, conditions that are the basis of this hazardous scenario. A much lower, and possibly zero,
probability might be appropriate. It is possible that an improved understanding of the explosion
mechanism may allow a better basis for determining the value of this factor in the future.

CM 4 – Probability that a person is present within the hazard zone


142 This conditional modifier can be used to represent the probability of a person being present
in the hazardous area at the time of a tank overflow. Care should be taken with this conditional
modifier to avoid double-counting factors which have already been taken into account elsewhere
(eg in other protection layers or in the calculation of the consequence) and in particular to
avoid double-counting any credit taken for evacuation (see paragraphs 118–122). The following
occupancy factors may be appropriate for a given scenario:

■■ For workers at the facility (including contractors and visitors), it is legitimate to take credit
if the normal pattern of work associated with the job role means that they would only
reasonably be expected to be in the hazardous area for part of their time at work. For
example, a worker may have a patrol route that means that they are outside the predicted
hazardous area for part of their shift. Maintenance crews may work over a whole facility and
may only be present in the hazardous area for a portion of the time they spend at work.
■■ Outside the facility, residential accommodation should be assumed to be fully occupied given
that the hazardous scenario is assumed to happen during night-time conditions. Industrial
and office facilities may only be occupied for a portion of the time, but care should be taken
to include security, janitorial and cleaning staff who may be present outside normal hours.

143 Where individual risk is being considered, an additional factor can be applied to the
occupancy to take account of the fact that the individual only spends part of the year in the work
place and therefore there is a chance that if the hazardous event occurs the individual may not
be at work and therefore is not exposed to harm. The equivalent factor for a scenario-based
assessment would be if the job role being considered is only required on site for part of the year
and at other times is not required.

144 Care needs to be taken in using this conditional modifier that it is truly independent of the
initiating event, any enabling event or condition, or any protection layer. If normal tank-filling
operations require the presence of an operator, or if part of the emergency response to an overflow
event requires operators to investigate the incident, this conditional modifier will not be independent.

145 If night-time occupancy is used in the LOPA (see conditional modifier on stable weather),
then a sensitivity analysis should be performed for daytime occupancy combined with the low
probability of stable, low wind speed, conditions occurring during the daytime. Such an analysis
would need to balance the factors such as increased exposed population and the higher
probability that an overflow would be seen and remedial action taken to prevent an explosion.

107
Safety and environmental standards for fuel storage sites
Final report

CM 5 – Probability of fatality
146 This conditional modifier is often referred to as ‘vulnerability’.

147 This conditional modifier may only be used if a single value can be specified for the hazardous
scenario – most likely in an Individual Risk calculation. Otherwise it should be incorporated in the
calculation of the consequence. The value to be used will have to be determined on a case-by-
case basis.

CM6 – Probability of the environmental consequence


148 This conditional modifier is included to account for any factors additional to those considered
elsewhere in the LOPA (eg seasonal factors, if not implicitly included in other factors within the
LOPA) that may influence whether the hazardous scenario can cause the defined environmental
consequence.

Completing the study of the scenario

149 The process should be repeated for the other scenarios as shown in Figure 22. It must
be remembered that the resulting predicted unmitigated frequency of the overflow event is
aggregated over all relevant initiating events. This sum, combined with existing control, protection
and mitigation risk reduction factors applicable to each initiating event must be compared with
the target frequency for the specified consequence defined in the risk tolerance criteria (see
paragraphs 36–53).

150 It is important that a sensitivity analysis should be carried out to explore the sensitivity
of the predicted risk levels to the assumptions made. It is important to be able to identify the
key assumptions and to provide justification that the analysis is based on either realistic or
conservative assumptions. Sensitivity of assumptions on initiating events and consequence side of
a risk assessment are also required.

Concluding the LOPA

151 The conclusions of the LOPA should be recorded. The record should include sufficient
information to allow a third-party to understand the analysis and should justify the assumptions
made and the choice of values for parameters such as human reliability, equipment failure
rates and conditional modifiers. Where assumptions are made about the mode of operation of
the facility (such as the proportion of the time tanks are being filled, or the number of tanks on
gasoline duty) these should be documented so that their continuing validity can be checked.

152 The LOPA should provide the basis for the safety requirements specification of the SIS
(where required). This should include:

■■ clear definition of the SIL required for the safety instrumented system in terms of reliability
level, eg PFD;
■■ it should also provide the basis of the functional specification of the SIS.

108
Safety and environmental standards for fuel storage sites
Final report

Annex 1 Summary of common failings in LOPA assessments for bulk tank


overflow protection systems

153 HSE reviewed a number of early LOPA studies of overfill protection completed following the
Buncefield incident (see RR71670). A number of errors and problems, listed below, were identified:

■■ human error probability too optimistic;


■■ independence of human operators (double counting of benefit from human tasks);
■■ risk factors due to the number of tanks on any particular site;
■■ little available data on ATG errors and failures;
■■ incorrect logic used to combine various factors;
■■ incorrect handling of number of filling operations;
■■ difficulty in analysing time at risk ie filling duration;
■■ uncertainty of ignition probability;
■■ uncertainty of probability of fatal injury;
■■ uncertainty of occupancy probability;
■■ uncertainty of probability of human detection of overflow;
■■ unjustified valve reliability;
■■ data not justified by site experience;
■■ no consideration of common cause failures of equipment;
■■ inappropriate risk targets;
■■ all hazard risk targets applied to single events;
■■ incorrect handling of risk targets eg sharing between tanks;
■■ difficulty in estimating probability of vapour cloud explosion; and
■■ difficulty in establishing and verifying all initiating events (causes).

109
110
Final report

Critical factor Critical factor Critical factor Critical factor Critical factor Critical factor
- 2 3 4 5 6
Bund floor falls Spill ignites Firewater applied Release or Release or Off-site
AND pathway to (also includes transfer from transfer from mitigation
ground water protective foam Secondary Tertiary failure
blanket circling containment containment
water)
YES
Spill and fire water goes off site unmitigated and ground water affected

YES

YES NO Spill and fire water goes off site and mitigated but ground water affected

YES NO
Spill and fire water contained on site but ground water affected

NO
Spill and fire water contained in bund walls but ground water affected

YES YES
Spill goes off site unmitigated and ground water affected
Safety and environmental standards for fuel storage sites

YES

YES NO
Spill goes off site and mitigated but ground water affected

NO NO
Spill contained on site but ground water affected

NO
Spill contained in bund walls but ground water affected

Liquid
release YES
Spill and fire water goes off site unmitigated and but ground water affected
from tank
YES

YES NO
Spill and fire water goes off site and mitigated and but ground water affected

YES NO
Spill and fire water contained on site but ground water affected

NO
Spill and fire water contained in bund walls but ground water affected

NO YES
Spill goes off site unmitigated and ground water affected

YES
Annex 2 Critical factors for environmental damage from a tank overflow

YES NO
Spill goes off site and mitigated but ground water affected

NO NO
Spill contained in bund walls but ground water affected

NO
Spill and fire water goes off site unmitigated
Critical factor Critical factor Critical factor Critical factor Critical factor Critical factor
- 2 3 4 5 6
Bund floor falls Spill ignites Firewater applied Release or Release or Off-site
AND pathway to (also includes transfer from transfer from mitigation
ground water protective foam Secondary Tertiary failure
blanket circling containment containment
water)
YES
Spill and fire water goes off site and mitigated

YES

YES NO Spill and fire water contained on site

YES NO
Spill contained in bund

NO
Spill goes off site unmitigated

YES YES
Spill goes off site and mitigated

YES

YES NO Spill contained on site

NO NO
Spill contained in bund walls

NO

No liquid
release YES
Spill and fire water goes off site unmitigated
from tank
YES

YES NO
Spill and fire water goes off site and mitigated

YES NO
Spill and fire water contained on site

NO
Spill contained in bund

NO YES
Spill goes off site unmitigated

YES

YES NO
Spill goes off site and mitigated

NO NO
Spill contained on site

NO
Spill contained in bund

111
Final report
Safety and environmental standards for fuel storage sites
Safety and environmental standards for fuel storage sites
Final report

Annex 3 Demand tree methodology for systematic identification of initiating causes

154 The purpose of this annex is to provide an example of an outline methodology for the
systematic identification of initiating events that can lead to hazardous events. This methodology
can be used with any SIL determination (such as LOPA, fault tree analysis) or other techniques
used for identification of the initiating events leading to a specific hazardous event.

Description of process example


155 Figure 24 shows the simplified schematic for part of a process sector plant. It has the incoming
flow from the left, with a flow controller (FIC210) setting the flow rate into the separator vessel shown.

Flare

PIC
214

Lights
PCV
HH 214
LZ
247

Separator

FT FIC
210 210

XZV FCV
247 210
LT
245
LZ
246
LL

LICA
XZV 245
246

Liquid
LCV
245

Figure 24 Simplified process schematic

156 The incoming flow is separated in the vessel into two streams: a light vapour phase, which
exits the top of the vessel, and a liquid phase, which exits the bottom of the vessel. The liquid
level in the vessel is maintained by the level controller (LICA245) that adjusts the liquid flow out
of the vessel. The pressure in the vessel is maintained by a pressure controller (PIC214) in the
vapour line. Over-pressure protection is provided by a pressure relief valve on the top outlet from
the vessel.

157 Two instrumented protective measures are shown: (a) a low level trip (LZ246) protects against
loss of level in the vessel and vapour entering the liquid line and (b) a high level trip (LZ247) which
protects against liquid entering the vapour line.

158 The specific process concern in this example is associated with an uncontrolled high level in
the vessel and the consequences that would result from that. Detailed consequence analysis is
not necessary for illustration of the method for demand identification and so for the illustration the
hazardous event will be taken as ‘high level in the separator with flow into the vapour line’.

112
Safety and environmental standards for fuel storage sites
Final report

Methodology ‘rules’
159 The use of this methodology requires the application of some simple rules:

■■ No protective measures, which would protect against the hazardous event of concern, are
considered at this stage. That is to say in this example, no alarms, trips or interlocks or
actions protecting against high level.
■■ Thinking is not limited to the diagram boundary but is extended as required beyond what is
on the diagram.
■■ All modes of operation are considered: (a) normal operation, (b) start-up, (c) shutdown, etc.

160 The hazardous event is put at the top of a page and the initiating events (demands) are then
developed in a systematic manner by asking the question ‘how?’ at each level of detail.

Mode of operation
161 When developing the demand tree and considering the question ‘how?’ it is important that
the different modes of operation are reviewed for failures that could lead to the hazardous event.
Table 11 may be used as a prompt to assist the systematic process.

Table 11 Modes of operation and initiating events


Mode of Class of initiating event
operation
Equipment Failure of Human failure External events
failure services
Normal operation

Start-up

Shutdown

Abnormal modes

Maintenance

162 In Table 11 services could include any or all of the following:

■■ Loss of electrical power.


■■ Loss of steam.
■■ Loss of instrument air.
■■ Loss of cooling water.
■■ Other.

Example demand tree


163 Figure 25 shows an example demand tree. The top of the demand tree is the hazardous
event of concern. This is expressed as clearly and precisely as possible to assist with
development of the rest of the tree.

164 The next level down may relate to modes of operation (eg start-up, shutdown, normal,
catalyst regeneration etc) or composition ranges (eg ‘high’ ethylene, ‘high’ methane, ‘high’
hydrogen concentration etc). The important requirement at this level is to keep the description as
generic as possible so that it can be developed in more detail further down the tree.

113
Safety and environmental standards for fuel storage sites
Final report

High liquid level


in the separator
allowing flow into
the vapour line

Start-up Normal operation Shut down

Develop further Develop further

Closure of valve of Failure of level Closure of trip valve


other stoppage of control loop XV246
flow downstream LC245 causing
from LCV245 the control valve
LCV245 to close

Develop further

Failure of level sensor Failure of level Failure of control Manual


LT245 reading low controller LICA245 valve LCV245 closed operation
with low output

Frequency of manual Other loss of control


control and loss from manual
of attention intervention

Spurious operation Real demand on trip,


of low-level trip causing closure of
trip valve

Develop further
looking at sources
of demand on this
function

Figure 25 Demand tree illustration

165 The tree is developed to a level of detail at which the initiating events (demand failures) can
have some frequency assigned to them.

166 It is very important that protective measures do not appear on the demand tree. This has at
least three benefits: (a) there is clarity of thinking without the complication of worrying about the
protective measures, (b) you get a smaller diagram and (c) it helps you to consider the causal
failures on a wider basis and may include some for which there are no protective measures.

Next stages
167 Having identified a number of initiating events, the demand tree can be used as an input to
other analysis techniques to carry out a more detailed risk assessment. This further stage would
typically use either a fault-tree analysis or a layer of protection analysis (so long as the LOPA
methodology used has sufficient flexibility to treat each cause separately and then combine them
when assessing the frequency of the hazardous event).

Annex 4 Discussion of ‘time at risk’

168 The concept of ‘time at risk’ is used to account for periodic, discontinuous, operations. Where
operations are essentially continuous, the hazards associated with the operation will be present
continuously. In contrast, where operations are carried out as batch operations, the hazards
associated with the batch operation will only be present while the batch is being carried out.

114
Safety and environmental standards for fuel storage sites
Final report

169 This discussion of time at risk relates to the context of tank filling operations. The context
assumes that the storage facility is operational throughout the year and that periodically during the
year tank filling occurs.

Failure of equipment
170 During the tank filling operation, there is reliance on items of equipment such as a tank level
measurement gauge. Failure of the gauge is one of the potential initiating causes of over filling.

171 For the purpose of this example, failure of the gauge is assumed to be possible at any
time, whether the tank is being filled or not. It is also assumed that the fail-to-danger rate of
the gauge is a constant, whether the tank is being filled or not (and therefore that failures of the
transmitter head or servo-mechanisms may occur with equal likelihood at any time). Note that
this assumption may not be true for all failure modes and would need consideration on a
case-by-case basis.

172 Figure 26 shows the storage facility as operational throughout the year. It also shows one
period of tank filling. This is to make the diagram easier to follow. However, the line of argument
will still apply to the situation of multiple tank filling periods during the year.

January December
Plant operational
Tank filling

B C A

Figure 26 Equipment item failure

173 It is assumed that failure of the level gauge can occur at any time. If it occurs at time A, then
it can clearly affect the control of the filling operation. If it occurs at time B then it can only affect
the filling operation if it is not detected before tank filling starts at time C and the filling operation
proceeds with a faulty gauge.

174 If detection at time C is carried out with a high degree of reliability by some form of checking
operation (eg independent gauging or stock checks) then it can be assumed that only gauge
failures that occur during tank filling can affect the filling operation. The checking activity fulfils a
similar function in this case to a trip system proof-test.

175 If the failure rate of the level gauge is λ per year and the total duration of filling during a
calendar year is t hours, then the proportion of time (there being 8760 hours in a year) for which
failures are significant is t/8760. This proportion of time may be used with the failure rate to
calculate the rate at which failures occur during the tank filling operation. This is then λ x t/8760 in
units of per year.

Human failure
176 Another potential cause of over filling is some form of human failure. This can be associated
with a failure to control the filling operation or failure to select the correct tank or one of a number
of other possibilities, depending on the details of the operation and what tasks people are involved
in carrying out.

115
Safety and environmental standards for fuel storage sites
Final report

January December
Plant operational
Tank filling

Figure 27 Human action

177 The human task of controlling the filling operation to stop at the intended level is represented
in Figure 27 by the letter ‘H’. This task by definition only occurs when the tank is being filled.
Therefore, the opportunity for the error of allowing the tank to overflow can only occur while
the tank is filling. This means that as the task is directly associated with the time when the
filling operation occurs, the concept of time at risk does not apply. The occurrence of the filling
operation and the possibility of error are not independent but are linked.

178 Note that an important distinction between human failure in carrying out a task and the
failure of equipment described is that human failure is characterised by a probability per event
(and is therefore dimensionless). Equipment failure is characterised by a failure rate (typically with
dimensions of (per year)).

Conclusion
179 Thus there is the generalisation, that ‘time at risk’ (the proportion of the year for which the filling
operation is happening) is relevant to equipment failure that can occur at any time during the year
– subject to the caveat of detection of any failure that occurs prior to the filling operation before it
causes over filling. Conversely, for any failure such as human error that is directly related to a task that
only occurs in relation to the tank filling operation, then the ‘time at risk’ factor should not be used.

Annex 5 The BPCS as an initiating event and as a protection layer

180 The authoritative requirements and guidance on initiating events and the independence
of BPCS-based layers of protection are given in BS EN 61511. The CCPS guidance on
LOPA presents two approaches for the application of LOPA. Approach ‘A’ generally meets
the requirements of BS EN 61511. The following guidance emphasises that the normative
requirements for assessing independence are those described in BS EN 61511 and that this
guidance is intended to indicate the issues involved in making such an assessment.

181 In a simple LOPA using a conservative approach, unless there is complete independence in
how basic process control functions are implemented through the BPCS, no credit can be taken
for any risk reduction provided by a control or alarm function implemented through the BPCS as a
protection layer if a BPCS failure also forms part of an initiating event. However, this conservative
approach may be relaxed if it can be demonstrated that there is sufficient independence to allow
credit to be taken for both. This issue is discussed in Sections 9.4 and 9.5 of BS EN 61511-1 and
BS EN 61511-2. The reader is referred to these sources for a more detailed discussion. Systematic
factors such as security, software, design errors and human factors should also be considered.

Programmable electronic systems


182 Credit can be given to more than one control function implemented through the BPCS where
there is sufficient rather than complete independence between each function. With regard to any
programmable electronic systems that are part of the BPCS the following requirements, which
may not be exhaustive, should be met.

■■ There should be formal access control and security procedures for modifying the BPCS. The
access control procedures should ensure that programming changes are only made by trained
and competent personnel. The security procedures should prevent unauthorised changes and
should also ensure software security, in particular by minimising the potential to introduce a virus
to infect the BPCS.
116
Safety and environmental standards for fuel storage sites
Final report

■■ There should be an operating procedure which clearly defines the action to be taken if
the control screen goes blank, a workstation ‘freezes’, or there are other signs that the
programmable device has stopped working correctly during a filling operation.
■■ A back-up power supply should be available in case the main power supply is lost. The back-
up system should give a clear indication when it is being used. The capacity of the back-up
supply should be sufficient to allow emergency actions to be taken and these actions should
be specified in a written procedure. The back-up power supply must be regularly maintained
in accordance with a written procedure to demonstrate its continuing effectiveness.
■■ The sensors and final elements should be independent for credit to be given to more than
one control function. This is because operating experience shows that sensors and final
elements typically make the biggest contribution to the failure rate of a BPCS.
■■ BPCS I/O cards should be independent for credit to be given to more than one control
function unless sufficient reliability can be demonstrated by analysis.
■■ The credit taken for control and protection functions implemented through the BPCS should
be limited to no more than two such functions. The following options could be permitted:
–– If the initiating event involves a BPCS failure, the BPCS may only then appear once as a
protection layer – either as a control function or as an alarm function, and only if there is
sufficient independence between the relevant failed BPCS control or protection functions.
–– If the initiating event does not involve a BPCS failure, the BPCS may perform up to two
functions as protection layers (eg a control function and an alarm function) so long as other
requirements on independence are met.
■■ Claims for risk reduction achieved by the BPCS should meet the requirements of
BS EN 61511-1 and 61511-2 (eg clauses 9.4, 9.5 and 11.2).

183 Figure 28 illustrates what the application of these principles could require in practice.

Sensor 1 Input card 1 BPCS Output card 1 Final element


logic
solver
Sensor 2 Input card 2 (common) Output card 2 Final element

Figure 28 Possible structure of sufficient independent control functions within the BPCS

184 Where credit is taken for more than one function being implemented through the BPCS,
this should be supported by a detailed analysis and the analysis should form part of the LOPA
records. Determination of the degree of independence between two functions that share a common
logic solver, as depicted in Figure 28, is not a trivial task and great care should be taken not to
underestimate the level of common cause, common mode and dependent failures. Where an
operating company considers that they cannot support the level of analysis required, the BPCS
should be limited to a single function in the LOPA. It should be noted that some operating companies
preclude taking credit for more than one function from the same logic solver as a matter of policy.

185 Where the implementation of two functions involves a human operator there is evident
potential for a common cause failure due to human error affecting the performance of both
functions. This may have an impact on whether any credit can be taken for any protection layer
involving the operator if an error by the same operator is the initiating event.

186 The simplest and most conservative approach is to assume that if an error made by an individual
is the initiating event, the same individual cannot be assumed to function correctly in responding to a
subsequent alarm. Therefore, if human error is the cause of failure of a BPCS credit cannot then be
taken for the same individual responding correctly to an alarm. This approach is equivalent to taking
no credit for error-recovery even if suitable means of error recovery can be identified.

187 A more complex approach would attempt to identify and quantify the possibility of error
recovery. This approach would need to consider the type of error causing the initiating event, the
information and systems available to warn of the error, the effectiveness of the warning systems in

117
Safety and environmental standards for fuel storage sites
Final report

helping the diagnosis of the error and the time available for diagnosis and recovery before effective
recovery is impossible. Where credit is taken for error recovery, this should be supported by detailed
analysis by a person competent in appropriate human reliability assessment techniques.

Annex 6 Cross-checking

Discussion
188 Many tank-filling operations include a number of cross-checking activities as part of the
operation. These may include checks before the transfer starts (eg routing valve line-up, tank dips,
available ullage) and periodic checks during the filling operation (filling rate, tank dips, unusual
behaviour of instruments).

189 The risk reduction that can be claimed for checking activities varies greatly with the kind of
check being carried out. Experience shows that the risk reduction due to checking is frequently
not as great as might be expected. Operators asked to ‘check’ each other may be reluctant to
do so, or the checker may be inclined to believe that the first operator has done the task correctly
because they are known to be experienced. Therefore the intended independence of the checking
process may not in fact be achieved.

190 This report distinguishes between self-checking activities and those carried out by a third party.
Self-checking activities, such as those carried out by the operator responsible for monitoring the
filling operation, should be considered as part of the basic reliability of the operator in carrying out
the filling operation and hence included in the risk reduction claimed for that activity. The extent
and nature of the self-checks may legitimately be considered a factor in the reliability claimed, but
they would not warrant separate identification, and hence a claim for risk reduction, within the study
unless an error recovery assessment is performed and fully supports any claims made.

191 Third party checks, which may offer risk reduction include: third party verification of tank dips
prior to transfer; verification of tank dips for customs purposes. Supervisor verification of valve
line-ups prior to transfer may suffer from similar dependencies to that of a second operator as
described above. The following guidance applies under these circumstances.

General requirements
192 It can be claimed that an ‘independent’ cross check will affect the frequency of the initiating
event and the demand on any layer of protection if the cross check can be shown to be a formal
requirement of a standard operating procedure and the cross-check is:

■■ independent;
■■ effective; and
■■ proper auditable records kept.

193 Note that management system and standard operating procedures cannot be claimed as
a protection layer in their own right. On their own, procedures do not meet the requirement of
effectiveness for a protection layer because they cannot identify a hazard or perform an action.
Instead, procedures are incorporated in the performance claimed for a protection layer because
they define requirements for the conduct of activities and therefore are included implicitly rather
than explicitly within the analysis.

194 An important task for a LOPA team is to distinguish between those checks that are formally
required and those that are carried out as a matter of custom and practice. Checks which are not part
of a formal procedure cannot be considered to offer significant risk reduction. For example, where field
operators carry out informal checks on tank levels from time to time, the check cannot be considered
a valid cross-check because there is no formal requirement to carry it out even though it may offer
some risk reduction. Additionally, they may vary over time without requiring any change control.

118
Safety and environmental standards for fuel storage sites
Final report

195 It will also be necessary for the LOPA team to review the checking activities in detail to confirm
exactly what is done and how, compared with the requirements of the procedure. Where the
procedure requires something to be confirmed visually, the team should verify that this actually
happens, as opposed to the checker relying on what they are told by the person carrying out the task.

196 The LOPA team need to be alert to hidden dependencies between the person carrying out
the task and the person checking. For example, the visual confirmation that a specific valve has
been closed may correctly verify that a valve has been closed, but not necessarily that the correct
valve has been closed. The checker may implicitly have relied on the person carrying out the task
to select the correct valve.

Quantifying the benefit from checking


197 The key to appropriate checking is the identification of what error is to be highlighted by the
check and the action that is taken following identification of the error. The analyst must ask the
question ‘If the person who has carried out the original action has not spotted the error, what is
the justification that the person checking will be able to spot the error?’

198 For example, when considering a check on opening a manual valve, there is a need to
consider each of the types of error separately; this is because the validity or benefit of checking is
likely to be different for each type of error.

199 The error may be:

■■ omission of valve opening;


■■ opening the wrong valve;
■■ only partially opening the correct valve;

200 For the error of omission, the LOPA team need to ask the question as to whether the checker
will even be requested to check that the valve has been opened. Review of the procedure may
reveal that the checking part may be triggered by the completion of the original action. Hence with
an omission checking may not occur and so a claim for checking would not be appropriate.

201 For the error of opening the wrong valve, the LOPA team need to ask the question as to
how the checker knows which valve is to be checked. If the actual procedure involves the person
carrying out the original action telling the checker which valve is to be checked, then again a claim
for checking would not be appropriate. Equally if the checker uses the same information source
as the person carrying out the original action and an error in that information is the cause of the
original error, then the checker can be expected to make the same error as the person carrying
out the original action; the check has no benefit.

202 For the failure to open fully the valve, then the question arises ‘what is it that will alert the
checker to the error and yet it was not able to alert the person carrying out the original action?’
Again the LOPA team needs to question whether the checker can see anything different from
the person carrying out the original action. If there is nothing that the checker will be able to see
differently, it is difficult to justify that there is any risk reduction benefit from the checker.

203 There is another aspect in which checking needs careful thought. If the person carrying out
the original action knows that there will be checking, then there is a possibility that there may be
a level of reliance on the checker: the person carrying out the original action may take less care,
secure in the belief that any errors will be detected and corrected by the checker.

204 Making risk reduction claims for checking requires clear written discussion to say what is being
checked and how the checker will be successful when the person carrying out the original action has
not been successful.

205 Table 12 suggests some levels of checking to consider. The first level of checking would give
a low level confidence in the effectiveness of the cross check and the last level of checking in

119
Safety and environmental standards for fuel storage sites
Final report

Table 12 would give a higher level of confidence in the effectiveness of the checking. No figures
for the probability of error are given because these should be determined and justified on a case-
by-case basis by a specialist in human error quantification.

Table 12 Levels of cross-checking effectiveness

Level of dependency Level of checking


Complete No justifiable reason why the checker should identify the failure when the
person carrying out the original action has not.
High The checker can determine the correct course of action independently of the
first person. However, checker either has a common link with the first person
or there is good reason to believe that the checker will make the same error as
the first person.
Moderate Checker has a weak link to the first person or there is moderate likelihood that
the checker will will make the same error as the first person.
Low Checker has sufficient independence from the person carrying out the original
action and the check is designed to highlight errors that may have occurred.

206 If in doubt, or if a suitable justification cannot be given, no claims should be made


for risk reduction due to checking.

Annex 7 Incorporating human error in initiating events

Identification of potential human error


207 The first step is to identify which tasks are critical tasks in relation to the overflow event. In
this context, a critical task is one in which human error can trigger a sequence of events leading
to an overflow. The identification of critical tasks is best achieved during the development of a
demand tree, as described in Annex 3.

208 When doing so, there should be coverage of all modes of tank operation: filling, emptying,
maintenance, transfers, and any other abnormal modes of operation etc. A ‘critical (human) task
list’ can then be created. Table 13 shows an example.

Table 13 An example ‘critical (human) task list’

Mode of operation Task Potential adverse outcome


Transfers between tanks Opening manual routing valve Opening the wrong valve and thereby
between the transfer pump transfer to the tank under review which
discharge and a designated has too little ullage and causing the tank
receiving tank to overflow

Review of each critical task


209 For each critical task it is important to gain a good overview of the task and its context. There
are a number of task analysis techniques that can be used.

■■ Create a timeline with input from a person who does the activity.
■■ Review timeline against operating instructions and process engineering input for anomalies.
■■ Consider creating a hierarchical task analysis for the activity to identify the key tasks.

120
Safety and environmental standards for fuel storage sites
Final report

210 This is followed by a review of the key tasks to identify the potential errors within each task
that could lead to the hazardous event under consideration. Techniques for this include (among
others):

■■ Tabular Task Analysis.


■■ ‘Human HAZOP’.

The output of this can be summarised in a critical task list (Table 14):

Table 14 Critical task list


Critical activity and/or task Nature of the error leading Performance shaping
to the hazardous event of factors relating to the task
tank overflow that could influence the
probability of error
Opening manual routing valve Opening the wrong valve and –– Poor labelling of valves
between the transfer pump thereby transfer the tank under –– All communication by single
discharge and a designated review channel radio from the control
receiving tank room
–– Significant proportion of new
process operators with little
on-site experience

Human error probability assessment


211 Figure 29 illustrates the process of assessing the human error probability (HEP) for the critical
task or key step within the task.

Critical task list Select task or key step Task type Generic (random)
...................................... human error probability
......................................
......................................
......................................
......................................
...................................... Assessment of
Systematic factors human error probability
...................................... PSF or EPC
...................................... (HEP) for task

Figure 29 Process for assessing human error probability

212 The steps in the assessment process are as follows:

■■ Select an appropriate ‘generic’ human error probability, based on the task type and/or the
nature of the error.
■■ This human error probability could then be modified based on the performance shaping
factors or error producing conditions relating to the people carrying out the task and the
conditions under which they are working.

213 There are a number of standard methods such as APJ (Absolute Probability Judgment),
HEART, THERP etc to assess the potential error probability. However, these require a level of
training and specialist understanding to use and those new to the assessment of human error
probability should seek assistance.

121
Safety and environmental standards for fuel storage sites
Final report

Initiating event frequency calculation


214 The frequency for each human initiating event is based on two parameters:

■■ Task frequency (/yr).


■■ HEP – as assessed using an appropriate method or selected from a table of generic task error
probabilities, with suitable account taken for any conditions that could impact on the operator’s
ability to consistently and reliably perform their task, eg error producing conditions used in the
HEART method.

215 For each human initiating event, the initiating event frequency would be calculated by:

Initiating event frequency (/yr) = Task frequency (/yr) x HEP

For example, a task carried out once a week, with an assessed human error probability for a
specific error of 0.01; the initiating event frequency can be calculated:

Initiating event frequency (/yr) = Task frequency (/yr) x HEP


= 52 x 0.01
= 0.52 per year

Note that enabling events or conditions can be included in the task frequency (the number of
times the activity is carried out under operational conditions which could lead to the undesired
consequence) and do not require separate identification.

216 For initiating events, the error probability should be conservative.

Annex 8 Response to alarms

217 When considering the alarm function as a protection layer it is helpful to have a mental model
along the lines of that shown in Figure 30.

Alarm function Sensor


Task type Annunciator Operator Final element

Figure 30 Alarm function

218 This shows four elements: the sensor, the annunciator, the operator and the final element.
For complete independence, each of these four elements must be different from those used by
other protection layers and from the initiating event for the hazardous scenario in question. Should
any of these elements not be independent for the situation being considered then the alarm
function should not be included in a simple LOPA analysis.

219 Where there is some commonality of elements between the alarm function and the initiating
event or other protection layers, inclusion of the alarm function should be supported by a more
detailed analysis. Typically this will require that an initiating event caused by the BPCF is broken down
into individual failures of the constituent elements. Credit for the alarm function could only be claimed
if there is a means of carrying out the function which is independent of the failed component, and if
the person carrying out the function has sufficient knowledge, time and training to carry out any tasks
correctly. The factors outlined below for operator response need to be considered.

Definition of the required performance of the alarm function


220 Before proceeding with the analysis of the performance of the alarm function, the required
function should be carefully defined. It is not enough simply to identify an instrument and consider
that as a protection layer. The protection layer will need to make up a complete loop and should
therefore include:

122
Safety and environmental standards for fuel storage sites
Final report

■■ the operator who is to respond to the alarm;


■■ the means by which the alarm situation is detected and communicated to the operator; and
■■ the means of making the situation safe in the available time, given that this cannot include the
equipment which has been assumed to have failed.

Operator response
221 Operator response to an alarm contains four sub-tasks as illustrated in Figure 31.

Alarm
Observe
layer
Task type Diagnose Plan Action

Figure 31 Sequence of operator sub-tasks

■■ Observe: The first of these sub-tasks, observing the indication, is relatively quick to do, so
long as an operator is present to hear or observe the indication. However, it does rely on the
indication of the alarm being clear and not being hidden by other alarms or information being
communicated at the same time. Any assessment of reliability of this sub-task depends on
a review of the human-instrumentation interface and the potential for confusion or masking
of the key information. It also needs to consider how the alarm is prioritised because this will
influence the importance that the operator attaches to the response.
■■ Diagnose and plan: Diagnosis of the problem and planning what to do are two closely
coupled sub-tasks. The time required for these sub-tasks will depend on the situation, the
clarity of any procedures or instructions given on the correct response, the training of the
operator, and how well practised and easy the required response is within the time available.
If the operator has not met the situation before – and this may be the case on a well-run
facility – it is possible that the operator will not be familiar with the correct response unless
the scenario is covered by regular training or by periodic drills or exercises. Where the
operator may not be able to make a decision on the correct course of action without referring
to a supervisor, caution should be taken before claiming any credit for the alarm function.
■■ Action: Carrying out the necessary action could be a relatively quick thing to do (such as
closing a remotely operated valve) or it could require the use of a radio to reach another
operator who is then required to go to a specific part of the plant to operate a manual valve.

Time for response


222 The key consideration relating to ‘time for response’ is an understanding of the actual time
available from when the alarm is activated until the process goes ‘beyond the point of no return’.
This is illustrated in Figure 32.

Alarm Process goes


activated ‘beyond point of no return’

Actual available time for response

Alarm Diagnosis and Action


observed planning
Time

Figure 32 Time for response to alarm

223 All four sub-tasks must be able to be completed effectively within this time. Shortage of time
available is one of the key factors that influence the probability of failure for operator response.
(See HEART methodology.)

224 The actual total time available for response (see Figure 32) should be evaluated on a case
by case basis taking into account all the relevant circumstances of the installation, for example
distances, means of taking action and operator experience.

123
Safety and environmental standards for fuel storage sites
Final report

225 It is important that the issue of worst-case time needed is considered. In many instances,
the LOPA team will consider it obvious what the response should be and feel that minimal time is
required for successful action. However, thinking about the less experienced operators, those new to
the operation, and even the experienced operators who have not seen this particular alarm before,
should trigger a more considered view of what length of time could be required for overall success.

Probability of failure
226 For a non-SIL alarm function (in this context, a function that does not conform to the
requirements of BS EN 61511-1 for a safety instrumented function) an overall PFDavg of no less
than 0.1 (see BS EN 61511-1 Table 9) may be used. If, however, there is a view that there could
be some increased time pressure on the operators, or other factor making the task conditions less
favourable then a higher overall probability of failure may be considered. Note that a component
of the protection layer may have a PFD lower than 0.1, but when combined with the rest of the
system, it cannot result in an overall PFD lower than 0.1.

227 Any claim for a PFDavg less than 0.1 for an alarm function would by definition mean that it
is a SIF and must meet the requirements of BS EN 61511. This would require formal assessment
to demonstrate conformance to the requirements of BS EN 61511-1 for SIL 1. The human
component of that SIF would need to be included within the assessment using a recognised
method for human error probability prediction covering each of the four sub-task elements:
‘Observation’, ‘Diagnosis’, ‘Planning’, and ‘Action’; this is a specialist activity.

228 One method for calculating the overall PFDavg for the Alarm Function is as follows:

For each hardware assessment of PFDavg, there should be some consideration of dependent
failure (ie common cause or common mode types of dependent failure) with other layers. For
each of the human error probability assessments there should again be some consideration
of dependent failure. Further guidance on this may be found in Handbook of Human Reliability
Analysis with Emphasis on Nuclear Power Plant Applications NUREG/CR-1278.71

Additional notes
229 PSLG support the recommendation of EEMUA 19172 in that it considers that SIL 2 or higher
cannot be claimed for a SIF that includes operator response. (EEMUA 191 table 5, p14.)

230 If an alarm protection layer is not a complete (ie having all four elements shown in Figure 31) and
fully independent layer (satisfying the requirements of not sharing elements with the initiating event or
other protection layers), the simplest approach is to be conservative and not to claim any risk reduction
for the alarm layer. If the analyst wishes to include partial sharing between protection layers, this should
be carefully substantiated (eg by using fault tree analysis to model the actual arrangement).

231 For any alarm function, the following factors should be addressed:

■■ the correct response is documented in operating instructions;


■■ the response is well-practised by operators;
■■ the alarm sensor is independent from the initiating event and other protection layers;
■■ the operator uses action independent from initiating event and from other protection layers;
■■ an operator is always present and available to respond to the alarm;
■■ the alarm is allocated a high priority and gives a clear indication of hazard;
■■ the alarm system and interface is well designed, managed and maintained so that it enables
the operator to detect a critical alarm among potentially many other alarms;
■■ any analysis should bear in mind that under emergency conditions, the probability of failure
could foreseeably deteriorate further.

232 Further guidance may be found in EEMUA 191.


124

You might also like