ID Task Task Name Duration Start Finish Predecessors December 2022 January 2023 February 2023

Mode 03 08 13 18 23 28 02 07 12 17 22 27 01
1 HIRANANDANI WAREHOUSE BUILDING 48 days Fri 16-12-22 Fri 27-01-23
2 MAIN BUILDING 24 days Fri 16-12-22 Fri 06-01-23
3 BASEBUILD 12 days Fri 16-12-22 Mon 26-12-22
4 BASE PREPARATION 3 days Fri 16-12-22 Sun 18-12-22
5 FLOORING 12 days Fri 16-12-22 Mon 26-12-22 4FF+7 days
6 HARD FINISH 24 days Fri 16-12-22 Fri 06-01-23
7 GIRT CLIP FIXING 1 day Fri 16-12-22 Sat 17-12-22 5SS+1 day
8 WALL CLADDING 8 days Sat 17-12-22 Sat 24-12-22 7FF+8 days
9 ROOF PANEL INSTALLATION 3 days Fri 16-12-22 Sun 18-12-22
10 RIDGE WALL CLADDING & CAP FIXING 2 days Sun 18-12-22 Tue 20-12-22 9

11 RIDGE VENTILATOR INSTALLATION 2 days Fri 23-12-22 Sat 24-12-22 10FF+5 days
12 SKY LIGHT FIXING 1 day Sat 24-12-22 Sun 25-12-22 11FF+1 day
13 LOUVERS INSTALLATION 4 days Sat 24-12-22 Wed 28-12-22 8FF+4 days
14 ROLLING SHUTTER INSTALLATION 2 days Fri 30-12-22 Sat 31-12-22 8FF+4 days,5FF+6 days
15 DOOR FIXING 2 days Mon 02-01-23 Wed 04-01-23 14FF+4 days
16 DOOR CANOPY FIXING 1 day Thu 05-01-23 Fri 06-01-23 15FF+2 days
17 FASCIA WORK 6 days Sat 24-12-22 Fri 30-12-22 8FF+6 days,9FF+7 days
18 GUTTER & DOWNSPOUT FIXING 4 days Sat 31-12-22 Tue 03-01-23 17FF+5 days,8FF+6 days
19 SOFT FINISH 13 days Sun 18-12-22 Fri 30-12-22
20 POP 1 day Sun 18-12-22 Mon 19-12-22 9FF+1 day
21 FIREFIGHTING FIXTURE INSTALLATION 3 days Sun 18-12-22 Wed 21-12-22 20FF+2 days

22 ELECTRICAL 2ND FIX 3 days Mon 19-12-22 Thu 22-12-22 21FF+1 day
23 PLUMBING 2ND FIX 1 day Tue 27-12-22 Wed 28-12-22 5FF+2 days
24 PAINT 1ST COAT 3 days Wed 21-12-22 Fri 23-12-22 21
25 PAINT 2ND COAT 3 days Thu 22-12-22 Sat 24-12-22 24FF+1 day
26 PAINT FINAL COAT 4 days Fri 23-12-22 Mon 26-12-22 25FF+2 days
27 PLUMBING FIXTURE INSTALLATION 1 day Thu 29-12-22 Fri 30-12-22 23FF+2 days
28 ELECTRICAL FIXTURE INSTALLATION 2 days Sat 24-12-22 Sun 25-12-22 22FF+4 days

29 LT PANEL ROOM 19 days Thu 22-12-22 Sun 08-01-23


30 BASEBUILD 4 days Thu 22-12-22 Sun 25-12-22
31 BASE PREPARATION 1 day Thu 22-12-22 Fri 23-12-22 22
32 FLOORING 2 days Sat 24-12-22 Sun 25-12-22 31FF+3 days
33 HARD FINISH 5 days Mon 26-12-22 Sat 31-12-22
34 ELECTRICAL 1ST FIX 2 days Mon 26-12-22 Wed 28-12-22 32SS+3 days
35 DOOR & WINDOW FRAME FIXING 1 day Thu 29-12-22 Fri 30-12-22 34FF+2 days
36 DOOR & WINDOW SHUTTER 1 day Fri 30-12-22 Sat 31-12-22 35FF+1 day
INSTALLATION
37 SOFT FINISH 7 days Sat 31-12-22 Fri 06-01-23
38 POP 2 days Sat 31-12-22 Sun 01-01-23 36

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors December 2022 January 2023 February 2023
Mode 03 08 13 18 23 28 02 07 12 17 22 27 01
39 ELECTRICAL 2ND FIX 1 day Mon 02-01-23 Tue 03-01-23 38FF+2 days
40 PAINT 1ST COAT 2 days Tue 03-01-23 Thu 05-01-23 39
41 PAINT FINAL COAT 2 days Wed 04-01-23 Fri 06-01-23 40FF+1 day
42 LT PANEL EQIPMENT INSTALLATION 2 days Fri 06-01-23 Sun 08-01-23 41
43 GUARD ROOM 11 days Mon 19-12-22 Thu 29-12-22
44 BASEBUILD 2 days Mon 19-12-22 Wed 21-12-22
45 BASE PREPARATION 1 day Mon 19-12-22 Tue 20-12-22 20
46 FLOORING 1 day Tue 20-12-22 Wed 21-12-22 45FF+1 day
47 HARD FINISH 5 days Wed 21-12-22 Sun 25-12-22
48 ELECTRICAL 1ST FIX 1 day Thu 22-12-22 Fri 23-12-22 46FF+2 days
49 PLUMBING 1ST FIX 2 days Wed 21-12-22 Fri 23-12-22 48FF
50 DOOR & WINDOW FRAME FIXING 1 day Sat 24-12-22 Sat 24-12-22 49FF+2 days
51 DOOR & WINDOW SHUTTER 1 day Sat 24-12-22 Sun 25-12-22 50FF+1 day
INSTALLATION
52 SOFT FINISH 4 days Sun 25-12-22 Thu 29-12-22
53 ELECTRICAL 2ND FIX 1 day Sun 25-12-22 Mon 26-12-22 51
54 PLUMBING 2ND FIX 1 day Sun 25-12-22 Mon 26-12-22 53FF
55 PAINT 1ST COAT 2 days Sun 25-12-22 Tue 27-12-22 54FF+1 day
56 PAINT FINAL COAT 2 days Mon 26-12-22 Wed 28-12-22 55FF+1 day
57 ELCTRICAL FIXTURE INSTALLATION 1 day Wed 28-12-22 Thu 29-12-22 56
58 PLUMBING FIXTURE INSTALLATION 1 day Wed 28-12-22 Thu 29-12-22 57FF
59 OFFICE ROOM 25 days Thu 22-12-22 Fri 13-01-23
60 BASEBUILD 9 days Thu 22-12-22 Fri 30-12-22
61 BRICKWORK 4 days Thu 22-12-22 Sun 25-12-22 45FS+2 days
62 INTERNAL PLASTER 2 days Sat 24-12-22 Mon 26-12-22 61FF+1 day
63 EXTERNAL PLASTER 2 days Sun 25-12-22 Tue 27-12-22 62FF+1 day
64 BASE PREPARATION 1 day Wed 28-12-22 Thu 29-12-22 63FF+2 days
65 FLOORING 1 day Thu 29-12-22 Fri 30-12-22 64
66 HARD FINISH 9 days Mon 26-12-22 Tue 03-01-23
67 ELECTRICAL 1ST FIX 2 days Mon 26-12-22 Wed 28-12-22 62
68 PLUMBING 1ST FIX 2 days Tue 27-12-22 Thu 29-12-22 67FF+1 day
69 FIREFIGHTING 1ST FIX 1 day Fri 30-12-22 Sat 31-12-22 68FF+2 days
70 HVAC 1ST FIX 1 day Fri 30-12-22 Sat 31-12-22 69FF
71 ELV 1ST FIX 1 day Sun 01-01-23 Sun 01-01-23 70FF+2 days
72 DOOR WINDOW FRAME FIXING 2 days Fri 30-12-22 Sat 31-12-22 65
73 DOOR WINDOW PANEL 1 day Sun 01-01-23 Sun 01-01-23 72FF+1 day
INSTALLATION
74 FALSE CEILING FRAME & BOARD 2 days Sun 01-01-23 Tue 03-01-23 73FF+2 days
FIXING
75 SOFT FINISH 13 days Sun 01-01-23 Fri 13-01-23
76 POP 2 days Sun 01-01-23 Tue 03-01-23 73
77 ELECTRICAL 2ND FIX 2 days Mon 02-01-23 Wed 04-01-23 76FF+1 day

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Predecessors December 2022 January 2023 February 2023
Mode 03 08 13 18 23 28 02 07 12 17 22 27 01
78 PLUMBING 2ND FIX 2 days Mon 02-01-23 Wed 04-01-23 77FF
79 FIREFIGHTING 2ND FIX 2 days Tue 03-01-23 Thu 05-01-23 78FF+1 day
80 HVAC 2ND FIX 1 day Thu 05-01-23 Fri 06-01-23 79
81 ELV 2ND FIX 1 day Fri 06-01-23 Sat 07-01-23 80FF+1 day
82 FALSE CEILING FINISH 2 days Thu 05-01-23 Sat 07-01-23 74FF+2 days,79FF+2 days
83 PAINT 1ST COAT 1 day Thu 05-01-23 Fri 06-01-23 82SS
84 PAINT 2ND COAT 1 day Fri 06-01-23 Sat 07-01-23 83FF+1 day
85 PAINT FINAL COAT 2 days Sat 07-01-23 Sun 08-01-23 84
86 ELECTRICAL FIXTURE INSTALLATION 1 day Mon 09-01-23 Mon 09-01-23 85FF+1 day,77

87 PLUMBING FIXTURE INSTALLATION 1 day Mon 09-01-23 Mon 09-01-23 78,86FF


88 FIRE FIGHTING FIXTURE 2 days Mon 09-01-23 Wed 11-01-23 79,87FF+2 days
INSTALLATION
89 HVAC FIXTURE INSTALLATION 1 day Thu 12-01-23 Fri 13-01-23 80,88FF+2 days
90 ELV FIXTURE INSTALLATION 1 day Thu 12-01-23 Fri 13-01-23 81,89FF
91 EXTERNAL DEVELOPMENT 24 days Sun 18-12-22 Sun 08-01-23
92 HARDSCAPE 24 days Sun 18-12-22 Sun 08-01-23
93 ROAD CONSTRUCTION 24 days Sun 18-12-22 Sun 08-01-23
94 SUBGRADE GRADING 7 days Sun 18-12-22 Sat 24-12-22 20SS
95 COMPACTION OF SUBGRADE 5 days Fri 23-12-22 Tue 27-12-22 94FF+3 days
96 PCC 6 days Sat 24-12-22 Fri 30-12-22 95FF+3 days
97 PAVER BLOCK INSTALLATION 12 days Thu 29-12-22 Sun 08-01-23 96FF+11 days
98 KERB INSTALLATION 8 days Thu 29-12-22 Thu 05-01-23 97SS
99 ELECTRIC POLE INSTALLATION 5 days Thu 22-12-22 Mon 26-12-22 94SS+4 days
100 DRAINAGE CONSTRUCTION 14 days Sun 18-12-22 Sat 31-12-22
101 EXCAVATION 4 days Sun 18-12-22 Thu 22-12-22 94SS
102 PCC 4 days Mon 19-12-22 Fri 23-12-22 101FF+1 day
103 REINFORCEMENT BINDING 8 days Wed 21-12-22 Wed 28-12-22 102FF+6 days
104 SHUTTERING 6 days Sat 24-12-22 Thu 29-12-22 103SS+3 days
105 CASTING 5 days Mon 26-12-22 Sat 31-12-22 104FF+2 days
106 SOFTSCAPE 10 days Sat 24-12-22 Mon 02-01-23
107 PLANTER INSTALLATION 5 days Sat 24-12-22 Thu 29-12-22 95FF+2 days
108 GRASS PAVER INSTALLTION 5 days Tue 27-12-22 Sat 31-12-22 107FF+3 days
109 SHURBS & TREES 4 days Fri 30-12-22 Mon 02-01-23 108FF+2 days
110 TESTING & COMMISSIONING 9 days Fri 13-01-23 Sat 21-01-23
111 ELECTRICAL COMMISSIONING 3 days Fri 13-01-23 Mon 16-01-23 90
112 PLUMBING COMMISSIONING 2 days Tue 17-01-23 Wed 18-01-23 111FF+3 days
113 FIRE FIGHTING COMMISSIONING 5 days Mon 16-01-23 Fri 20-01-23 112FF+2 days
114 HVAC COMMISSIONING 1 day Fri 20-01-23 Sat 21-01-23 112FF+3 days
115 DESNAGGING 2 days Mon 02-01-23 Wed 04-01-23 109
116 HANDING OVER 4 days Tue 24-01-23 Fri 27-01-23 115FF+1 day,114FS+3 days
117 FINSH 0 days Fri 27-01-23 Fri 27-01-23 116 27-01

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16

27-01

Task Project Summary Manual Task Start-only Deadline

Project: HIRANANDANI WAREH Split Inactive Task Duration-only Finish-only Progress


Date: Sat 17-12-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress