Pump Room Intake Facilities
Pump Room Intake Facilities
Amount (US
Bill No Description
DOLLARS)
.............................................................. ..............................................................
Mr. Vann Sophal
Managing Director
NORAK Engineering Co., Ltd. OBAYASHI Corporation
PRIMARY COST
TOTAL 460,030.0
Project For The Expansion Of Water Supply System In Pursat
Date: June 9, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
INTAKE FACILITY
3 Embankment for slope Protection m3 6,386.00 6.50 41,509.00 7.50 47,895.00 89,404.00
6 m2 540.80
Retaining Sheet 11.00 5,948.80 2.50 1,352.00 7,300.80
7 pcs 270.00
Gabion Works 75.00 20,250.00 25.00 6,750.00 27,000.00
8 m
Boundary Curb W=0.2m,H=0.25m 44.30 8.50 376.55 3.50 155.05 531.60
9 m
Retaining Wall H=0.6m 21.80 57.00 1,242.60 32.00 697.60 1,940.20
10 m
Steel Fence H=1.8m 58.90 60.00 3,534.00 15.00 883.50 4,417.50
11 set
Steel Gate W=3.0m,H=1.8m 1.00 860.00 860.00 300.00 300.00 1,160.00
12 m2
Crushed Stone Pavement t=0.2m 129.20 10.00 1,292.00 7.50 969.00 2,261.00
13 m2
Sodding 8.90 4.00 35.60 2.00 17.80 53.40
I Piping Work including Installation and all contingencies related to the Works . LS 1 0.00 0.00 0.00
Project For The Expansion Of Water Supply System In Pursat
Date: June 9, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
INTAKE FACILITY
Administration Office 18,539.79 9,648.55 28,188.34
1
Excavation for construction of foundation m3 44.80 - - 6.50 291.20 291.20
2
Soil backfilling and compacting m3 8.80 6.50 57.20 7.50 66.00 123.20
3
Crushed stone compacted ( C-30 , 150mm Thk. ) m3 1.08 24.00 25.92 12.00 12.96 38.88
4
Crushed Stone t=150 for Ground Slab m3 5.40 24.00 129.60 12.00 64.80 194.40
Construction of the Pump House Foundation slab complete and including
B lean concrete, concrete pouring, curing and all contingencies related to LS 1.00 15,262.75 7,433.03 22,695.78
construction
1 Formwork for Lean Concrete m2 1.78 14.00 24.89 12.00 21.33 46.22
2 Lean concrete (50mm thick ) m3 4.24 86.00 364.83 28.00 118.78 483.61
3 Steel bars Beam FG2 kg 1,498.00 0.88 1,318.24 0.28 419.44 1,737.68
4 Formwork Beam FG2 m2 27.00 14.00 378.00 12.00 324.00 702.00
5 Concrete Beam FG2 (600 x 1200) m3 5.40 90.00 486.00 28.00 151.20 637.20
6 Concrete curing m3 5.40 2.50 13.50 2.00 10.80 24.30
7 Steel bars Beam FG1 kg 214.00 0.88 188.32 0.28 59.92 248.24
8 Formwork Beam FG1 m2 18.00 14.00 252.00 12.00 216.00 468.00
9 Concrete Beam FG1 m3 2.70 90.00 243.00 28.00 75.60 318.60
10 Concrete curing m3 2.70 2.50 6.75 2.00 5.40 12.15
11 Steel bars Beam FB1 kg 91.00 0.88 80.08 0.28 25.48 105.56
12 Formwork Beam FB1 m2 6.00 14.00 84.00 12.00 72.00 156.00
13 Concrete Beam FB1 m3 0.75 90.00 67.50 28.00 21.00 88.50
14 Concrete curing m3 0.75 2.50 1.88 2.00 1.50 3.38
15 Lean Concrete for Ground Slab m3 9.00 86.00 774.00 28.00 252.00 1,026.00
16 Steel Bar for Ground Slab kg 937.80 0.88 825.26 0.28 262.58 1,087.85
17 Pour Concrete for Ground Slab m3 9.00 90.00 810.00 28.00 252.00 1,062.00
18 Curing Concrete for Ground Slab m3 9.00 2.50 22.50 2.00 18.00 40.50
19 Concrete Steel Trowel finish m2 36.00 - - 3.00 108.00 108.00
20 Steel bars Column kg 131.81 0.88 116.00 0.28 36.91 152.90
21 Formwork Column m2 11.52 14.00 161.28 12.00 138.24 299.52
22 Concrete Column m3 1.17 90.00 105.30 28.00 32.76 138.06
23 Concrete curing m3 1.17 2.50 2.93 2.00 2.34 5.27
24 Steel Bar for Concrete Wall kg 222.24 0.88 195.57 0.28 62.23 257.80
25 Formwork for concrete wall m2 16.80 14.00 235.20 12.00 201.60 436.80
26 Pour Concrete for wall m3 1.44 90.00 129.60 28.00 40.32 169.92
27 Curing concrete for wall m3 1.44 2.50 3.60 2.00 2.88 6.48
28 Steel bars Beam Roof Beam kg 1,012.65 0.88 891.13 0.28 283.54 1,174.68
29 Formwork Roof Beam m2 57.40 14.00 803.60 12.00 688.80 1,492.40
30 Concrete Roof Beam m3 7.20 90.00 648.00 28.00 201.60 849.60
31 Concrete curing m3 7.20 2.50 18.00 2.00 14.40 32.40
32 Support m3 23.52 1.50 35.28 2.50 58.80 94.08
33 Scaffolding m2 81.60 1.50 122.40 2.50 204.00 326.40
34 Steel bar for Gutter kg 286.40 0.88 252.03 0.28 80.19 332.22
35 Formwork for Gutter m2 33.60 14.00 470.40 12.00 403.20 873.60
36 Pour Concrete for Gutter m3 4.32 90.00 388.80 28.00 120.96 509.76
37 Curing concrete for Gutter m3 4.32 2.50 10.80 2.00 8.64 19.44
38 Support m2 68.40 1.50 102.60 2.50 171.00 273.60
39 Cement waterproof mortar for gutter m2 40.80 12.50 510.00 5.00 204.00 714.00
40 Steel bar roof slab kg 871.20 0.88 766.66 0.28 243.94 1,010.59
41 formwork roof slab m2 62.40 14.00 873.60 12.00 748.80 1,622.40
42 pour concrete roof slab m3 6.84 90.00 615.60 28.00 191.52 807.12
43 curing concrete roof slab m3 6.84 2.50 17.10 2.00 13.68 30.78
44 Support m3 125.00 1.50 187.50 2.50 312.50 500.00
45 Monier Roft tiles m2 56.23 17.50 984.03 5.00 281.15 1,265.18
46 Asphalts Waterproof for Roof m2 54.00 12.50 675.00 5.00 270.00 945.00
C Masonery Work 2,452.32 1,612.56 4,064.88
1 Concrete Block t=150 m3 55.92 18.00 1,006.56 7.00 391.44 1,398.00
2 Plaster t25 on CB m3 111.84 4.50 503.28 5.00 559.20 1,062.48
3 Plaster t25 on Concrete m2 16.80 4.50 75.60 5.00 84.00 159.60
4 Ceiling m2 24.00 12.00 288.00 8.00 192.00 480.00
5 Painting m3 128.64 4.50 578.88 3.00 385.92 964.80
D Door and Window Work 612.00 168.00 780.00
1 Aluminium Door (Size 2m x 0.7m) ea 1.00 200.00 200.00 50.00 50.00 250.00
2 Aluminium Door (Size 2m x 0.9m) ea 1.00 252.00 252.00 63.00 63.00 315.00
3 Aluminium Window (Size 0.6m x 0.9m) ea 1.00 50.00 50.00 15.00 15.00 65.00
4 Aluminium Window (Size 1.5m x 0.9m) ea 1.00 110.00 110.00 40.00 40.00 150.00
Project For The Expansion Of Water Supply System In Pursat
Date: June 9, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
INTAKE FACILITY
External Work 102,099.25 62,963.05 165,062.30
1 Formwork for Lean Concrete m2 0.60 14.00 8.40 12.00 7.20 15.60
2 Lean concrete (200mm thick ) m3 0.38 86.00 32.68 28.00 10.64 43.32
3 Formwork for Septic Tank Base m2 3.36 14.00 47.04 12.00 40.32 87.36
4 Concrete m3 1.92 90.00 172.80 28.00 53.76 226.56
5 Steel bars kg 147.00 0.88 129.36 0.28 41.16 170.52
6 Concrete curing m3 1.92 3.00 5.76 2.00 3.84 9.60