Hadeed JSA Shearing Machine Installation
Hadeed JSA Shearing Machine Installation
L4 C5 4 Work in safe manner and materials shall be L5 C5 4 Worker, site supervisor and
Tripping and slipping hazard. arranged to avoid tripping and slipping safety officer and permit
hazard. receiver.
Must be housekeeping.
Risk of injury due to low awareness of L4 C5 4 All employees must have attended basic L5 C5 4 Worker, site supervisor and
work activities Safety orientation / Awareness. safety officer and permit
TBT shall be conducted with Working crew receiver.
prior for job execution every day.
Classification: Internal Use
Jacking Up / Down L4 C5 4 Jacks to be inspected for any deformation L5 C5 4 Rigging crew, site supervisor
before use and safety officer and permit
(Uncontrolled motion) Selected jacks must be with safe margin receiver.
from its maximum capacity (50-70%)
Safety gripping should not be kept with
maximum gape of 15 cm
Continues monitoring of line pressure
Jacking Up / Down L4 C5 4 PPE is require as per job condition. L5 C5 4 Rigging crew, site supervisor
and safety officer and permit
(Pinch point) Proper focus on the job receiver.
Use long stick for adjusting rollers
Use leather gloves.
Proper communication with concerned
person.
Skidding, turning the load and Sliding on L4 C5 4 Assure the proper leveling of sliding system L5 C5 4 Rigging crew, site supervisor
steel plate Place support under weak points and safety officer and permit
Place rubber / plywood between load and receiver.
(Uncontrolled motion) roller
Use chain blocks with long web sling for
holding and pulling the load
Use wedge for stopping the load
3 Lifting, rigging and loading on trailer.
Classification: Internal Use
L4 C5 4 Must be inspect before start the work. L5 C5 4 Operator, site supervisor and
Crane, fork lift, Telehandler failure safety officer and permit
Third party and Hadeed inspection sticker receiver.
must be required.
Set the crane, Fork lift, Telehandler on firm,
uniform and level ground, close to the load.
Assign flagman for any movement of the
equipment
Crane, Forklift and telehandler must not
exceed the rated capacity
4 Loading and unloading the equipment
from the Trailer with crane
A defective lifting device or crane L4 C5 4 Inspection of equipment must be done by client L5 C5 4 Site Engineer Supervisor
Crane Inspection Unit every ninety (90) days or Permit Receiver
after major repairs. Crane shall have valid test Safety Officer
stickers. CRANE operator
Rebar cutting sparks L3 C4 3 PPE must be complied before starting the L4 C5 4 Site supervisor and safety officer
work and permit receiver.
Enclose the work location with wet fire
blankets and observe hot work permit
requirements.
Assign authorized fire watchman to monitor
the hot work and follow the procedure.
Placement Procedure L3 C4 3 Mixer equipped with 0.75 cm. or larger L4 C5 4 Site Engineer Supervisor
loading skips shall be equipped with Permit Receiver
Erection of form work Safety Officer
mechanical device to clear the skip of
Worker
Removal of form work concrete.
Skin and Eye irritation L4 C5 4 Use of hand, ear and eye protection devices. L5 C5 4 Worker, site supervisor and
Use of boots to protect feet. safety officer and permit
Use of warning signs at fresh placed receiver.
concrete.
Proper handling of concrete and avoiding
random application.
Removal of spilled concrete
9 Scaffolding erection for Jib crane
Falling hazards (Personnel and L3 C4 3 Full body harness shall be used and 100% L4 C5 4 Worker, scaffolding supervisor
materials) tie off and area to be barricaded with caution and safety officer and permit
sign. receiver.
Scaffold materials and tools to be secured
with lanyards.
Ensure proper Guard rail system should be
installed.
Materials to be elevated by bucket and
manila rope.
Ensure 3-point contact while accessing
ladder
Unauthorized erection of scaffold L3 C4 3 General work permit shall be obtained prior L4 C4 4 Scaffolding supervisor and
to work. safety officer and permit
Scaffolding erection shall be done by receiver.
competent erector, supervisor and inspector
with valid 3rd party certificate and approved
by HADEED.
Scaffolding collapse L3 C4 3 Scaffolding materials to be inspected by L4 C4 4 Scaffolding supervisor and
competent person and approved by safety officer and permit
HADEED. receiver.
Scaffolding plan to be prepared by
competent person and approved by
HADEED prior to use.
Scaffolding shall not be overloaded and shall
follow the rated load duty as per scaffold tag.
Classification: Internal Use Tagging system for scaffolding to be
implemented (Red, yellow, and green).
Scaffolding shall be erected in even and
leveled ground and to be provided with base
plate if erected in soil.
Manual handling L4 C5 4 Hand gloves to be use as per the job L5 C5 4 Worker, site supervisor and
condition. safety officer and permit
Manual handling shall be limited to 23 kg receiver.
and use of third party certified mechanical
aid shall be used above 23 kg.
Never bend at the waist instead bend the
knees, grip the load with both hands.
While manual handling, keep the load close
to your body.
Overhead Utilities L3 C4 3 Scaffolding shall maintain safe distance to L3 C5 4 Site supervisor and safety officer
overhead utilities. and permit receiver.
10 Jib crane dismantle and assemble.
Physical injury L4 C5 4 Use appropriate personnel protective L5 C5 4 Worker, site supervisor and
equipment’s such as safety helmet, Safety safety officer and permit
glass, safety shoes, Coverall and Leather receiver.
gloves.
Provide proper walk way and material
storage area
All floor are in dry condition and uniform.
L4 C5 4 Work in safe manner and materials shall be L5 C5 4 Worker, site supervisor and
Tripping and slipping hazard. arranged to avoid tripping and slipping safety officer and permit
hazard. Must be housekeeping. receiver.
Lack of training, uncertified and L4 C5 4 All the Operators must trained and L5 C5 4 Site supervisor and safety officer
Incompetency experienced. and permit receiver.
In case of Boom truck, Forklift or crane
utilization, third party certified and competent
operator must execute the operations.
All Loading and unloading operations shall
be supervise by a certified riggers.
All the crew members shall be aware about
the task and Hazards.
All the activities shall be executed under the
supervision of an experienced and
competent Supervisor.
The supervisor must check all the required
documents together with HSE officer
assigned prior to start the any activities.
L4 C5 4 Must be inspect before start the work. L5 C5 4 Operator, site supervisor and
Fork lift, Telehandler failure safety officer and permit
Third party and Hadeed inspection sticker receiver.
must be required.
Set the crane, Fork lift, Telehandler on firm,
uniform and level ground, close to the load.
Manual handling L4 C5 4 Hand gloves to be use as per the job L5 C5 4 Worker, site supervisor and
condition. safety officer and permit
Manual handling shall be limited to 23 kg receiver.
and use of third party certified mechanical
aid shall be used above 23 kg.
Never bend at the waist instead bend the
Classification: Internal Use knees, grip the load with both hands.
While manual handling, keep the load close
to your body.
11 Installation of equipment
12 House keeping
Physical injury L4 C5 4 Use appropriate personnel protective L5 C5 4 Worker, site supervisor and
equipment’s such as safety helmet, Safety safety officer and permit
glass, safety shoes, Coverall and Leather receiver.
gloves.
Provide proper walk way and material
storage area
All floor are in dry condition and uniform.
Tripping and slipping hazard. L4 C5 4 Work in safe manner and materials shall be L5 C5 4 Site supervisor and safety officer
arranged to avoid tripping and slipping and permit receiver.
hazard.
Prior to unload the materials & tools,
Supervisor shall assign storage area.
All the materials must be stack and store
properly.
Do not store in any unauthorized area.
Hard barricade and place signage.
Manual handling L4 C5 4 Hand gloves to be use as per the job L5 C5 4 Worker, site supervisor and
condition. safety officer and permit
Manual handling shall be limited to 23 kg receiver.
and use of third party certified mechanical
aid shall be used above 23 kg.
Never bend at the waist instead bend the
knees, grip the load with both hands.
While manual handling, keep the load close
to your body.
L4 C5 4 Must be inspect before start the work. L5 C5 4 Operator, site supervisor and
Fork lift, Telehandler failure safety officer and permit
Third party and Hadeed inspection sticker receiver.
must be required.
Set the crane, Fork lift, Telehandler on firm,
uniform and level ground, close to the load.
Classification: Internal Use
Note: For risks cannot be reduced or mitigate after formal JSA study,
then approval shall be obtained as per SHEM-02 SAFER requirement.
Approved by Unit Owner/Operation Manager:
Approved By
SN Area Owner Sr.Manager (Minor Residual Risk) Department Signature Date
01
Note: If Residual Risk is, Significant and above SAFER Approval Required.
ENDORSEMENT SECTION (This section shall be filled incase this document use for same scope of work in future)
SFM-08.10-SHEM-009
Classification: Internal Use