Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

GOVERNMENT OF KERLA

DEPARTMENT OF TECHNICAL
EDUCATION
GOVERNMENT POLYTECHNIC COLLEGE
MEENANGADI – WAYANAD
[DEPARTMENT OF CIVIL ENGINEERING]

PROJECT REPORT ON
PLANNING AND ESTIMATION OF
RESIDENTIAL BUILDING
2021-2022
PRESENTED BY
SULFEECKER PN
GOVERNMENT POLYTECHNIC COLLAGE
MEENANGADI WAYANAD
[DEPARTMENT OF CIVIL ENGINEERING]

This is to certify that the seminar report titled as ‘RESIDENTIAL BUILDING’


has done by SULFEECKER PNwith Reg no : 20013326of 2nd year student of
CIVIL ENGINEERING under the DIRECTORATE OF TECHNICAL
EDUCATION, Government of kerala during the accademic year 2022-2023 under
the guidance at Govt. polytechnic collage Meenanghadi.

Staff in charge Head of the department

External examiner Internal Examiner


MINI PROJECT 2021-22

ACKNOWLEDGEMENT

I acknowledge my deep sincere gratitude with plesure to my


guide VEENA madam for her help and guidance her valuble
guidance and encouragement has accomplished to achieve the
knowledge of this miniproject turned to unforgettable educational
experience for me are concered.
I express our sincere gratitude to all other teaching and non –
teaching staff of Civil Engineering Department with pleasure for
whole hearted co-operations.

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

SULFEECKER 20013326
PN

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

to

TABLE OF CONTENTS

1.INTRODUCTION…………………………………………………………….

2.NEED.AND SCOPE…………………………………………………………..
3SITE DETAILS ………………………………………………………………..
4. TERMS………………………………………………………………………
5. DATA OBTAINED FROM KPBR 2019……………………………………
7.COMPARISON OF RESIDENCE WITH KPBR 2019………………………
8. ESTIMATON
a.QUANTITY ESTIMATION……………………………………………….
b.ABSTRACT ESTIMATION……………………………………………….
9.CONCLUSION…………………………………………………………………
10. REFERENCES………………………………………………………………
11.DRAWINGS

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

INTODUCTION
The mini project work is entrusted to us as 2nd year diploma
student of Civil engineering with an attitude of developing
various aspects of construction in the days to come
The mini project’s goal was to draw and estimate of residential
building.The floorplan and building layout were desighned in
accordance with Kerala Panchayat Building Rule and National
Building Code.
The project has been prepared in partial fullfillment of the course
of the student in 2nd year Civil Engineering during the year 2021-
2022

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

NEED AND SCOPE

The object of the project work is to get a practical knowledge in


design, drawing and in preparation of detailed estimate

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

SITE DETAILS
The site for proposed construction of residential building is
beside NEAR PARAKKUNNU MADRASA JUNCTION. This
site is located in kizhakoth panchayath , koduvally town.

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

TERMS
Building Line:
A line which is away from the street boundary and upto which the main
wall of the building facing that street may lawfully extent , no portion of
the building may extend beyond as prescribed in these rules.

Carpet Area:
The usable floor area excluding the area of staircase, lift wells, escalator,
ducts, toilets, air condition plant room and electrical control room.
Dwelling:
A Building or aportion there of which is designed or use wholly of
principally for residerntial purpose.
Dwelling unit:
A room or suits of rooms designed and intended for habitation by an
individual or household in which fascllities for cooking may or may not
be provided.
External wall:
An outer wall of a Building eventhough adjoining a wall of another
building. It also means a wall abutting of an interior open space of any
building.
Floor area:
The built up area of a building at any floor level.
Varantha:
A covered area with atleast one side open to the out side with the
expectation of parapette trellies, Jally or grill work on the open side.

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

Plinth:
A portion of a structure between thesurface of the surrounding ground
and surface of the floor, first above the ground.
Height of the room:
The vertical distance between the floor and the lowest point of the
ceiling.
Frontage:
The side or part of the side of a plot which abuts on a street.

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

DATA OBTAINED FROM KPBR 2019

OCCUPANCIES
GROUP A-RESIDENTIAL BUILDING

YARD
FRONT-1.8m
SIDE-1m
REAR-1m

HEIGHT OF ROOM
MINIMUM HEIGHT=2.75m

SIZE OF BATHROOM AND LATERINE


AREA OF COMBINED BATHROOM AND LATERINE SHALL BE NOT LESS THAN 2.2m^2 WITH
ONE SIDE NOT LESS THAN 1.1m

VERANDAH
WIDTH SHOULD BE NOT LESS THAN 1m

COVERAGE AND F.S.I


MAXIMUM PERMISSIBLE COVERAGE=20%
MAXIMUM PERMISSIBLE F.S.I=3.25

DISTANCE BETWEEN WELL AND SEPTIC TANK


MINIMUM DISTANCE BETWEEN WELL AND SEPTIC TANK=15m

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

COMPARISON OF RESIDENCE WITH DATAS FROM KPBR


2019

1. FRONT =10.47>1.8m
2. REAR= 1.5m>1m
3. RIGHT SIDE=1.21m>1m
4. LEFT SIDE4.930.5m>1m
5. HEIGHT OF ROOM=3m>2.75m
6. SIZE OF a)BATHROOM-1 =3.4m^2>1.1m^2 b)BATHROOM-2=2.8m^2>1.1m^2
7. WIDTH OF VERANDAH=1.8m>1m
8. AREA CALCULATION
COVERAGE AREA=107.31m^2
PLOT AREA=324m^2

COVERAGE=(COVERAGE AREA/PLOT AREA)*100


=(107.31/324)*100
=33.11%<20%

F.F.I=FLOOR AREA/PLOT AREA


=107.31/324
=0.33<3.25
9.DISTANCE BETWEEN WELL AND SEPTIC TANK=22.5>15m

FROM ABOVE DATAS IT IS CLEAR THAT THE RESIDENCE SATISFIED THE ALL
KMBR RULES

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

ESTIMATION

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

QUANTITY ESTIMATION
ITE
PARTICULA LENGTH(m BREADTH(m HEIGHT(m QUANTIT
M NO ) ) ) Y
NO R
EARTHWORK
1 EXCAVATION IN 1 114.4 0.9 1.25 128.7m^3
FOUNDATION
EARTHWORK
EXCAVATION IN
1 5.9 0.65 0.15 0.575m^3
2 STEPS
a)FRONT STEP
b)BACK STEP 1 1.1 0.65 0.15 0.107m^3

TOTAL QUANTITY OF EARTWORK EXCAVATION=129.38m^3

PCC IN
3 FOUNDATION IN 1 114.4 0.9 0.2 20.592m^3
1:4:8 MORTAR
PCC IN STEP IN 1:6
4 IMORTAR
a)FRONT STEP 1 5.9 0.65 0.1 0.38m^3
b)BACK STEP 1 1.1 0.65 0.15 0.07m^3

TOTAL QUANTITY OF PLANE CONCRETE IN 1:4:8=21.042m^3

DR MASONRY IN
1 115.6 0.6 0.6 41.62m^3
5 FOUNDATION
RR MASONRY IN
1 116.4 0.4 0.45 20.95m^3
6 1:6 IN BASEMENT

2.5 cm THICK
7 DAMP PROOF 1 116.4 0.4 _ 46.53m^2
COURSE
DEDUCTION:
D1 2 1 0.4 _ 0.8m^2
D2 5 0.9 0.4 _ 1.8m^2
D3 2 0.8 0.4 _ 0.64m^2

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

FRONT OPENING 1 5.8 0.4 _ 2.32m^2

TOTAL DEDUCTION= 5.56m^2


TOTAL QUANTITY OF DAMP PROOF
COURSE=41m^2
EARTHWORK
20
FILLING
a)VERANDAH 1 5.6 3.6 0.45 9.072m^3
b)BEDROOM 4 3.6 4.6 0.45 29.808m^3
c)LIVING ROOM 1 5.6 7.6 0.45 19.152m^3
d)TOILET-1 1 3.6 2.6 0.45 4.212m^3
e)TOILET-2 1 2.6 4.6 0.45 5.382m^3
f)KITCHEN 1 3.6 5.6 0.45 9.072m^3

TOTAL QUANTITY OF EARTHWORK FILLING=76.698m^3

FIRST CLASS
8 BRICKWORK IN 1 117.2 0.2 3 70.32m^3
WALLS
DEDUCTION:
a)D1 2 1 0.2 2.1 0.84m^3
b)D2 5 0.9 0.2 2.1 1.89m^3
c)D3 2 0.8 0.2 2.1 0.672m^3
d)W1 4 1.5 0.2 1.5 1.8m^3
e)W2 4 1 0.2 1.5 1.2m^3
f)V 2 0.6 0.2 0.6 0.144m^3
g)S 6 1.5 0.15 1.5 2.025m^3
h)FRONT OPENING 1 5.8 0.2 3 3.48m^3
i)OVER ALL
LINTEL 1 117.2 0.2 0.1 2.344m^3
TOTAL DEDUCTION= 14.395m^3
TOTAL= 55.92m^3

FIRST CLASS
9 BRICKWORK IN 1 60 0.1 0.6 3.6m^3
PARAPET
FIRST CLASS
10 BRICKWORK IN
STEPS

a)FRONT STEP
a) 1 5.8 0.6 0.2 0.696m^3
b) 1 508 0.3 0.15 0.261m^3
b)BACK
STEP

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

a) 1 1 0.6 0.2 0.12m^3


b) 1 1 0.3 0.15 0.045m^3
TOTAL= 60.64M^3

TOTAL QUANTITY OF FIRST CLASS BRICKWORK=120.16


RCC WORK FOR
11 1 117.2 0.2 0.1 2.344m^3
LINTEL
RCC WORK FOR
12 1 67.2 0.6 0.1 4.032m^3
SUNSHADE
RCC WORK FOR
13 1 AREA OF ROOF SLAB=233.8 0.1 23.38m^3
ROOF SLAB
T
OTAL QUANTITY OF RCC WORK=29.75

14 FLOORING

a)VERANDAH 1 5.8 3.8 _ 22.04m^2


b)LIVING ROOM 1 5.8 7.8 _ 45.24m^2
c)BEDROOM 4 3.8 4.8 _ 71.44m^2
d)TOILET-1 1 3.8 2.8 _ 10.64m^2
e)TOILET-2 1 2.8 4.8 _ 13.44m^2
f)KITCHEN 1 3.8 5.8 _ 22.01m^2
ADDITION OF
_
DOORS:
a)D1 2 1 0.2 _ 0.4m^2
b)D2 5 0.9 0.2 _ 0.9m^2
c)D3 2 0.8 0.2 _ 0.8m^2
d)FRONT OPENING 1 5.8 0.2 _ 1.16m^2

TOTAL QUANTITY OF FLOORING=188.07m^2

15
TOTAL QUANTITY OF
TILING=188.07m^2
PLASTERING IN
16
WALLS
a)OUTSIDE 1 75 _ 3 225m^2
b)INSIDE 1 133.2 _ 3 399.6m^2

DEDUCTION:
a)D1 4 1 _ 2.1 8.4m^2
b)D2 10 0.9 _ 2.1 18.9m^2
c)D3 4 0.8 _ 2.1 6.72m^2
d)W1 8 1.5 _ 1.5 18m^2
e)W2 8 1 _ 1.5 12m^2

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

f)V 4 0.6 _ 0.6 1.44m^2


g)S 6 1.5 _ 1.5 13.5m^2
TOTAL
78.96
DEDUCTION=
TOTAL= 551.64
PLASTERING IN
17
PARAPET
a)VERTICAL SIDE 2 60 _ 0.6 72m^2
b)TOP PORTIONS 1 60 0.1 _ 0.6m^2
72.6m^2
TOTAL=
PLASTERING IN
18
STEPS
a)FRONT STEP
2 5.8 0.3 _ 3.48m^2
THREAD
RISE 2 5.8 _ 0.15 1.74m^2
LOWER RISE 1 5.8 _ 0.2 1.16m^2
END PORTIONS 2 (0.3*0.15)+(0.6*0.2) 0.33m^2
b)BACK STEP
THREAD 2 1 0.3 _ 0.6m^2
RISE 2 1 _ 0.15 0.3m^2
LOWER RISE 1 1 _ 0.2 0.2m^2
END PORTIONS 2 (0.3*0.15)+(0.6*0.2) 0.33m^2
8.14m^2
TOTAL=
PLASTERING IN
19
SUNSHADE
a)HORIZONTAL
2 67.2 0.6 _ 80.64
PORTION
b)VERTICAL
1 67.2 _ 0.1 6.72
PORTION
TOTAL= 87.36

TOTAL QUANTITY OF PLASTERING=713.74

20 TOTAL QUANTITY OF WHITE WASHING=713.74

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

ABSTRACT ESTIMATION
ITE
QUANTIT AMOUN
M RATE UNIT
DESCRIBTION Y T
NO
EARTWORK IN
1 129.38m^3 298.8 cum 38658.7
EXCAVATIN
PLANE CEMENT
2 21.042m^3 8160 cum 171703
CONCRETE
3 DR MASONRY 41.62m^3 3446.6 cum 143448
4 RR MASONRY 20.95m^3 7121.6 cum 149198
DAMP PROOF
5 41m^3 95.2 sqm 3903.2
COURSE
EARTHWORK
6 76.698m^3 816 cum 62585.5
FILLING
FIRST CLASS
7 120.16m^3 7000 cum 841120
BRICKWORK
8 RCC WORK 29.75m^3 13272 cum 394842
9 FLOORING 188.07m^3 1547.5 sqm 291038
10 TILING 188.08m^3 3695.4 sqm 695031
11 PLASTERING 713.74 407.27 sqm 290685
12 WHITE WASHING 713.74 30.98 sqm 22111.6

TOTAL
3104322
=

ADD 3% FOR CONTENGENCIES 93129.6


ADD 2% FOR WORK CHARGE ESTABLISHMENT 62086.4

TOTAL AMOUNT=3259538 INR

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

CONCLUSION
The estimation of a residential building is done and the report is
supmited for valuation. This project help us to understand more
about planning and estimation. This project is done by according
to the rules in kerala panchayat building rule and national
building code.The total cost of building is RS.3259538

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

REFERENCES
1. KERALA PANCHAYATH BUILDING AMENDMENT RULE
2. NATIONAL BUILDING CODE
3. ESTIMATING AND COSTING- BN DUTTA
4. PWD SCHEDULE OF RATE

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING


MINI PROJECT 2021-22

DRAWINGS

GOVT POLYTECHNIC COLLEGE MEENANGADI DEPARTMENT OF CIVIL ENGINEERING

You might also like