+final Ukp Eto 10
+final Ukp Eto 10
1. An important quantity which is useful in circuit analysis is known as conductance G (Siemens). Which of the
B,C,D,E….T
26. Before taking insulation resistance readings of generator windings the automatic voltage regulators should be
isolated and all semiconductor short circuited or disconnect in order to:
- Prevent damage to sensitive electronic components from high voltage tester
27. Check-synchroniser is often installed to:
- Prevent manual synchronising outside permitted limits
28. Compressed air for instrument and control purposes needs to be of high quality in order to condition the air filter
modules are usually fitted to remove the contaminants. If there is evidence of oil carry over to the final elements
in the instrumentation air system what is the most likely cause?
- The coalescer module is saturated and requires renewal
29. During routine checking of alarm function of main and auxiliary equipment, some setpoints are cancelled due to a
mistake. What is the appropriate routine to ensure correct setpoints are set?
- Consult with the instruction manual for the equipment in question for correct values
30. Diodes are widely used in rectification, or the conversion of alternating current to direct current. This circuit
symbol is such example. The input voltage V(in) is sine-wave AC. Which of the shown output voltages is correct for
this circuit?
- Figure 1
31. During maintenance of a pneumatically operated, diaphragm actuated control valve the diaphragm is found to be
split. Select, from the options given, a suitable material to use to make a temporary replacement if there is no
spare diaphragm available.
- Natural rubber sheet of approximately the same thickness and elasticity as the original diaphragm material
32. During maintenance work on a compensated mechanical hydraulic governor air is drawn in to the hydraulic circuit
after draining and flushing out the unit. Which of the actions given in the options is most likely to assist in the
removal of the air from the system?
- With the governor in operation open the compensation needle valve to introduce instability and disturb the
engine load to make the governor hunt.
33. Electronic Drawing Application Software yang cocok digunakan untuk memudahkan dalam membuat gambar
rencana layout PCB di antaranya adalah …..
- Protel
34. Following replacement of a diesel alternator governor the machine is test run on load. It is found that as the load is
gradually increased the voltage and the frequency gradually fall to an unacceptable level. The governor is a
mechanical hydraulic type. Select from the options given the correct adjustment to make to correct the situation.
- The governor droop should be reduced.
35. For ideal synchronising, the phase angle difference between the incomer e.m.f. and the busbar voltage should be:
- 0°
36. For two generators running in paralel, their share of additional load (kW) will be determinated by the:
- Governor droop setting on each prime mover
37. For which of the following systems would you install a PID-controller?
- Temperature-control
38. High Voltage systems rely on the installed protective equipment being able to interrupt any fault in the system.
Throughout the system, the fault level has been calculated, and under no circumstances must the system be
modified to exceed this fault level. What is meant by fault level?
- The amount of apparent power that could flow into any fault at any point in the electrical network.
39. How would pirates attacking a ship be communicated to another ship?
- "My ship is under attack by pirates"
40. How would you report containers with dangerous goods lost overboard?
- "My vessel has lost containers with dangerous goods of IMDG Class….in position…."
41. Identify 4 of the Five Steps in Team Formation and Development
- Forming, Storming, Norming and Performing
42. If master finds reason to doubt wether the agent is giving the vessel’s interest full and proper attention he should:
- Investigate the matter carefully and report the findings to the company
43. If the A.C. line current in a generator is doubled, the heating effect in the stator windings will:
- Quadruple
44. If there are any changes in the crew in a foreign port, the changes will be made by _______
- Consul on the Shipping Articles
45. In installations of INTRINSICALLY SAFE equipment it is required that all cabling should be separated from non-
intrinsically safe equipment, and (where colour coding is relied upon) to be of a special colour. What colour is that?
- Blue
- L(S) = 4 H
78. The circuit consist of two inductors, L(1) = 6H and L(2) = 12H, connected in series. Calculate the equivalent L(S) of
two inductors.
- 18H
79. The circuit consist of two capacitors, C(1) = 6µF and C(2) = 12µF, in parallel. Calculate the equivalent C(S) of the two
capacitors.
- 18µF
80. The circuit consists of two capacitors, C(1) = 6µF and C(2) = 12µF, in series. Calculate the equivalent C(S) of the two
capacitors.
- 4µF
81. The correct time to synchronise is usually taken to be when the Synchroscope reaches the “5 to 12” position. This
allow for:
- Circuit breaker operating time
82. The earth lamps in a 3-phase system indicate as follows: Red=Bright, Yellow=Dark, Blue=Dim. Which fault
condition shown as red-yellow-blue is correct?
- No fault – Hard earth – Light earth
83. The damage to a vessel is over $25,000. Who must notify the nearest Coast Guard Marine Safety or Marine
Inspection Office as soon as possible?
- The Master of the vessel
84. The figures show a graphical symbol for a particular electronic component and a typical operating characteristic
for the same. Which component?
- Transistor
85. The figures show a graphical symbol for a particular electronic component and a typical operating characteristic
for the same component. Which component?
- Triac
86. The figure show a graphical symbol for a particular electronic component and a typical working characteristic for
the same component. Which component?
- Triac
88. The figure shows a silicon controlled rectifier with a RC circuit connected in parallel. RC circuit is often used in such
connection. For which purpose?
- Protect the SCR against damage caused by high voltage spikes
89. The circuit symbol is a widely used system for rectification of AC into DC. Which of the diagrams is the correct for
the output voltage when the input voltage is sine-shaped as shown?
- Figure 1
90. The circuit symbol is a full-wave bridge rectifier. Which electronic component will you connect between ‘a’ and ‘b’
in order to obtain reduced ripple voltage to the load RL?
- Capacitor
91. The function of the fuses in a motor starter circuit is to provide:
- Short circuit protection
92. The inductance which will induce an EMF of 1 Volt in a conductor when the current is changing at a rate of 1 Amp
per second, is defined as?
- Henry
93. The instrument most widely used for testing of semiconductor diodes is:
- Ohmmeter
94. The majority conventions adopted under the auspices of IMO fall into which of the three main categories:
- Maritime Safety, Prevention of Marine Pollution, Liability and compensation
95. The maximum current that a 15 Volt, 3 Watt Zener diode can handle without damage is?
- 0.2 A
96. The picture shows a common used 3.5 inches diskette type for storing data. What is the data storing capacity for
such diskette?
- 1.44 MB
97. The power requirements for the excitation winding/circuit for a 3-phase alternator operating at rated output
power are supplied by:
- The alternators output itself via the automatic voltage regulator and the prime mover
98. The proper way to correct a mistake in the logbook is to _________
- Draw one line through the entry, rewrite, and initial the correction
99. The physical size of a resistor is an indicator of what aspect of it's specification?
- Power dissipation capability
100. The range of a transducer is 0-200 bar. The output signal is 4-20 mA. What is the span of the output signal?
- 16 Ma
101. The range of a transducer is 0-200 bar. The standard output signal 4-20 mA. What is the output signal when
the process value is 100 bar?
- 12 mA
102. The range of a transducer is 0-200 bar. The output signal 4-20 mA. What is the span of the output signal?
- 16 mA
103. The recognised definition of High Voltage equipment is anything that operates at over which of the
following levels?
- 1000Volts ac or 1500Volts dc.
104. The refrigeration system for the ships provisions consists of a number of cold rooms served by a central
refrigeration system. The evaporator coils for the vegetable room are found to be frosting up even though the
room is down to temperature and the liquid line valve has closed. Select, from the options given, the automatic
control component which is likely to be malfunctioning and so cause this condition.
- Back pressure control valve
105. The responsible person for maintaining budget on board normally is:
- Master
106. Thermocouples are often used for measuring temperatures. Which of the following descriptions are valid
for a thermocouple?
- A junction between two dissimilar metals generates a small voltage
107. Thermistor will typically have
- Relatively nonlinear characteristic
108. Thermo-elements will typically have
- Relatively wide range of temperature measurement
109. The typical current gain of a common emitter transistor is
- 10-200
110. This is a simplified block diagram of a dc generator and its voltage regulator. Find the value of the feedback
constant H if the reference VR is a 45Volt battery and the terminal voltage Vt is to be 250 Volt.
- H = - 0.178
111. This is the graphical symbol and truth table for a logic gate. Which gate?
- NOR
112. Thermistors are temperature sensitive devices. A positive temperature coefficient thermistor will typically
have
- Relatively non linear characteristic
113. Thermocouples are often used for measuring temperatures. Which of the following descriptions explains
the principle of operation of a thermocouple?
- A junction between two dissimilar metals generates a small voltage
114. The Ziegler-Nichols method is used in control engineering when setting up the system. Which of the system
components given in the options would this method be applied to during initial set up?
- PID controller for tuning
115. This block diagram illustrates an elementary control system. What is the common name for this type of
system?
- Figure 2
117. This circuit consists of two capacitors, C(1) = 6 µF and C(2) = 12 µF, in series. Calculate the equivalent C(S)
of the two capacitors.
- C(S) = 4 µF
118. This circuit consists of two resistances, R1 = 6 ohm and R2 = 12 ohm, connected in series. Calculate the
equivalent resistance R(S).
- R(S) = 18 ohm
119. This circuit consists of two resistances, R(1)= 12 ohm and R(2) = 6 ohm, connected in parallel. Calculate the
equivalent value R(S) of the two resistances.
- R(S) = 4 ohm
120. This circuit consists of a current source I, a change-over switch S, a resistor R and an inductor L. The
voltage/time figures 1 to 4 show possible changes through L if the switch S is suddenly shifted from position 1 to 2
at time t = 0. Only one of the diagrams is correct. Which?
- Figure 3
121. This circuit consists of a current source I, a change-over switch S, a resistor R and a capacitor C. The
current/time figures 1 to 4 show possible changes in the current I in case the switch S is suddenly shifted from
position 1 to 2 at time t=0. Only one of the diagrams is correct. Which?
- Figure C
122. This circuit consists of a voltage source V, a change-over switch S, a resistor R and a capacitor C. The
voltage/time figures 1 to 4 show possible changes in the voltage V© in case the switch S is suddenly shifted from
position 1 to 2 at time t=0. Only one of the diagrams is correct. Which?
- Figure 1
123. This circuit is a logic gate with two input signals, A and B, and one output signal Q. Which type of logic
function is the gate giving?
- NOR gate
124. This circuit is a logic gate with two input signals, A and B, and one output signal Q. Which type of logic
function is the gate giving?
- OR gate
125. This circuit is a flip-flop. Which type?
- Bi-stable flip-flop
126. This circuit consists of two resistances, R1 = 6 ohm and R2 = 12 ohm, connected in series. Calculate the
equivalent resistance R(S) of the two resistances?
- 18 ohm
127. This circuit consists of two resistances, R1 = 6 ohm and R2 = 12 ohm, connected in parallel. Calculate the
equivalent resistance R(S) of the two resistances?
- 4 ohm
128. This graphical symbol is a logic gate with truth table. Which gate?
- OR
129. This graphical symbol is a logic gate. Which gate?
- NOR
130. This graphical symbol is a logic gate. Which gate?
- OR
131. This graphical symbol is a logic gate. Which gate?
- NAND
132. This is a parallel L-C circuit with curve showing frequency-impedance characteristics. Which of the formulas
A to D will you utilize for determining the resonant frequency?
- fo = 1/(2sqrt (L/C))
133. This resistor has the value of 68 k ohm. Which color code should be marked on the rings (assume ring d is
the tolerance ring)?
- Blue b. Grey c. Orange
134. Total responsibility for shipping and discharging the seamen is that of the _______
- Master of the vessel
135. Transducers are devices which translate the value of one measured value into diferent measurement units
(for instance units of temperature to millivlots). What is the meant by the “Range” of a transducer?
- The difference between possible maximum and minimum measurement
136. Two reference points for pressure exist, absolute zero and atmospheric pressure. What is the common
name pressures measured relative to atmospheric pressure?
- Gauge pressure
137. Use Kirchhoff’s voltage law and Ohm's law to calculate the voltage V2 across the resistance R2.
- 4,5V
W
WHAT
138. What could be the cause of a refrigeration compressor running continuously even though normal
temperatures for the cold rooms have been reached?
- Low-pressure cut-out is stuck in closed position.
139. What is the meaning of the abbreviation of PCB?
- Printed Circuit Board
140. What is a ZENER BARRIER?
- A zener barrier is a unit made to obtain intrinsic safety in installations for instrumentation in hazardous areas.
141. What is an A/D and a D/A converter?
- A converter H at convert an analogue signal to a digital signal and vice versa
142. What is digital signal?
- A signal representing 0 = “low” and 1 = “High"
143. What is an analogous signal?
A variable electric signal
144. What is an I/P transducer?
- A transducer that converts a known electric current to a pressure proportional to the current
145. What is a typical problem when it is something wrong with the span of an instrument?
- Zero-point is accurate, but 100% input is not giving 100% output
146. What the symbol for a THYRISTOR?
- Figure 2
147. What is the definition of DEAD BAND?
- The change needed in the input signal to produce a change in the output signal
148. What is dynamic amplifying?
- Amplitude of output signal divided by amplitude of input signal
149. What is static amplifying?
- Change in output signal divided by change in input signal
150. What is the advantage of a transmitter with a narrow measurement range?
- Better linearity and increased accuracy
151. What is the meaning of instrument calibration?
- Comparing input and output values against a documented standard
152. What is the influence of the I (integration) function of a controller?
- It will try to reduce the deviation between set-point and process value
153. What is the meaning of the expression dead-band?
- The controller will not react on a process change in a specific range
154. What is the meaning of split-range?
- Several control-valves are connected to the same controller
155. What is the meaning of term “Span” of transducer?
- The difference between maximum and minimum measurement that gives a standard output signal
156. What is the meaning of "make fast"
- To secure a rope
157. What is the meaning of the medical term "Hypothermia"?
- Hypothermia is the condition when the core temperature of the body is lower than normal
158. What is the most common signal from an I/P converter?
- Pressure-reducing regulator
163. What will be the probable outcome, if the amplification is set too high on a temperature Controller?
192. What is the correct name of the part highlighted in the illustration?
- Connecting rod
a. Piston rod
193. What is the correct name of the part highlighted in the illustration?
- Camshaft
194. What is the correct name of the part highlighted in the illustration?
- Piston
195. What is the correct name of the part highlighted in the illustration?
- Crosshead
196. What is the correct name of the part highlighted in the illustration?
- Crankshaft
197. What is the correct name of the part highlighted in the illustration?
- Exhaust valve
198. What is the correct name of the part highlighted in the illustration?
- Exhaust valve
199. What is the correct name of the part highlighted in the illustration?
- Fuel injector
200. What is the correct name of the tool in the illustration?
- Monkey wrench
201. What is the correct name of the tool shown in the illustration?
- Water Pump Pliers
202. What is the correct name of the tool shown in the illustration?
Flat file
203. What is the correct name of the tool shown in the illustration?
- Adjustable wrench
204. What is "DRAUGHT", in the figure?
- Draught is indicated by D, in the figure
- Inverter
224. Which electronic component or system of components is this graphical symbol illustrating?
- Operational amplifier
227. Which electronic component is this graphical symbol illustrating?
- Zener diode
228. Which diagram is the symbol for a THYRISTOR?
- Figure 2
- Ionization type
247. Which alternative is correct for measuring current over the load L?
- Figure 3
- Pressure-reducing regulator
251. Which component does this graphical symbol illustrate?-
- LIC
254. Which of the following parameters will result in oscillation?
- Too high amplification
255. Which of the following parameters will not result in oscillation?
- Too long I-time
256. Which of the 3 alternatives given is correct for a NOT-gate?
- Figure 1
257. Which of the 3 alternatives given is correct for an AND-gate?
- Figure 3
258. Which of the 3 alternatives given is correct for an OR-function?
- Figure 2
259. Which of the following alternatives summarise the benefits of using high voltage on ships?
- Smaller conductors, machines and switchgear
260. Which of the Following is not a Type of Team?
- Individual
261. Which function is this operational amplifier circuit performing?
- Inverting amplifier
262. Which function is this operational amplifier circuit performing?
- Non-inverting amplifier
263. Which function is this operational amplifier circuit performing?
- Differentiator
264. Which function is this operational amplifier circuit performing?
- Integrator
265. Which function is this circuit performing?
- Differentiating
266. Which of the following options may be used as a brief summary of how to safely make high voltage
equipment accessible?
- Disconnect, isolate, earth (ground)
267. Which of the methods given in the options will give the most accurate test of the accuracy of a bourdon
tube type pressure gauge with a range of 0 to 20 bar?
- Check the gauge on a deadweight tester
268. Which one of these is a Disadvantage of Teamwork?
- More ideas may be generated
269. With regard to radar, what would be a correct form of response to the question: What range scale are you
using?
- The correct form of response would be: "I am using the 12 mile range scale"
270. With reference to the installation of pressure gauges for steam systems. Complete the following statement
from the options given. To protect a bourdon tube type pressure gauge which is to be fitted to a steam line it
should ….
- ..be fitted with a siphon loop between it and the steam pipe.
271. With the set point at the actual desired value, a temperature control system is giving an unacceptably large
offset (difference between set point and measured value) on high load resulting in a low system temperature.
Which of the actions given in the options should be taken to reduce this effect and therefore achieve closer control
of the temperature?
- Reduce the width of the proportional band for the controller
272. Why did he study the contract in detail before signing it? Why did he study the contract in detail before
signing it?
- He studied the contract in detail before signing it because he wanted to know his duties
273. Why did the new Cadet want to go to the messroom?
- The new Cadet wanted to go to the messroom to become acquainted with the officers
274. Why did the Second Engineer wish to make a monthly allotment?
- The Second Engineer wished to make an allotment because he was married
275. Why is it important that a transmitter has been correctly installed at the correct place?
- The control system is depending on the best possible process signal
276. Why is it important that a transmitter has been correctly installed at the correct location
- The control system is depending on the best possible process signal
277. Where will you normally find the ship’s documents including Crew Passports and CDC on board a vessel?
- Ship’s office
278. When calibrating a pressure transducer we have to adjust both SPAN and ZERO. Please indicate in which
order these adjustments should be done.
- First Zero adjustment and then Span adjustment. Then Zero should be rechecked
279. When unloading a generator, it is necessary to gradually decrease the load in order to avoid:
- Undue overspeeding
280. When a blackout occurs: what should be your first reaction?
- Inform the bridge about the reason for blackout, and expected time to restarts
281. When we are measuring temperature with a thermistor, the name of the sensing device is:
- Temp sensitive semi-conductor
282. When we are measuring level of liquids with a conductivity level indicator, the name of the sensing device
is?
- Electrodes
283. When we are measuring salinity with a salinometer, the sensing device is?
- Electrodes
284. When we are using a diode to convert AC to DC, it is usually referred to as a
- Rectifier
285. When we are measuring viscosity with a restricted flow viscometer, the name of the sensing device is?
- Capillary tube
286. When we are measuring level of liquids with a conductivity level indicator, the name of the sensing device
is?
- Capacitance probe
287. When selecting switchgear to work with High Voltage it is important to use an appropriate arcing medium.
What is meant by arcing medium?
- The gas or vapour which will minimise creation of an electric arc as contacts open.
288. When should the watch-keeping engineer inform the bridge that the main engine is ready for
manoeuvring?
- Once the engine is properly prepared and tested and the engine room is correctly manned
289. When starting three phase induction motors which of the following starting methods will immediately
apply rated voltage to the machine?
- Direct on Line
290. When would gassing-up of cargo tanks on an LNG carrier normally be necessary?
- Pass fresh air through the sample chamber
291. When 3 phase alternators are operating in parallel, it is very important that the reactive load is evenly
shared so that the total alternator loads are evenly shared. If the total alternator load is the vector sum of active
and reactive loads, which side of the vector diagram shown represents the reactive load?
- (Y)
292. When a large motor load suddenly is disconnected from the switchboard and the generator is AVR
controlled, the voltage will?
- Initially rise, then reset to the set value
293. When maintenance work is to be carried out on an electric motor driving a centrifugal water pump with
automatic start, should you;
- In conjunction with the senior watchkeeper and electrician, isolate valves, electrical supply, automatics and post
‘Do not operate’ signs before commencing work.
294. When we are measuring flow of fluids with a fixed area flow meter, the name of the sensing device is:
- Orifice plate
295. When we are measuring level of liquids with a differential pressure meter, the name of the sensing device
is?
- Pressure diaphragm
296. When you are calibrating an instrument what is the most common second step in the procedure (consult
the manual)?
- Check linearity
297. When you are calibrating an instrument what is the most common first step in the procedure (consult the
manual)?
- Adjustment of Zero-point and span
298. When calibrating a pressure transducer we have to adjust both SPAN and ZERO. Please indicate in which
order these adjustments should be done.
- First Zero adjustment and the Span adjustment. Then Zero should be rechecked.
299. While a vessel is in a foreign port where there is no American Consul, a seaman becomes violent prior to
sailing. The Master should _______
- Pay off the seaman and make arrangements with the agent to return him to the original port of signing on in the
U.S.
300. Who is responsible for the safe keeping of the ship’s documents?
- Master
301. Who is responsible for providing urine specimen collection kits to be used following a serious marine
incident?
- Qualified medical personnel
302. Why is it important to make weekly/routine rounds in the accomodation areas?
- To ensure that cabins and common spaces are maintained in a clean, safe and hygienic condition
303. Will it matter to the accuracy of the measurement how you are installing a resistance element in a thermo-
well?
- Wrong installation will result in a major deviation in measurement
304. Select the option which best describes the primary duty of a watch-keeping engineer?
- The primary duty of a watch-keeping engineer is to maintain constant surveillance of the main engine and
auxiliary machinery
305. Select from the options given the statement that best describes the main duties of an engine room rating
who is part of an engine room watch?
- Engine room ratings forming part of an engine room watch should assist in efficient and safe watch-keeping
routines.
306. Some equipment may be marked with the following symbol: What does that mean?
- Intrinsically safe
307. Under what circumstances may a watch-keeping engineer normally undertake other, non-watchkeeping
duties?
- When they have been properly relieved of their watch-keeping duties.
308. Use Kirchhoff’s voltage law and Ohm’s law to calculate the voltage V(2) across the resistance R(2).
- 4.5 V
309. Read this text and answer the question: To whom should training in personal survival techniques be
given?
- To all seafarers.
310. How would you alert others onboard if you saw a person falling overboard?
- If I saw a person falling overboard I would shout repeatedly, "Man overboard"
311. With reference to engine room operations, what does the term "Stand By" mean?
- "Stand By" means that the engineers should be ready to respond to bridge requirements.
312. With no.1 and no.2 alternators running in parallel and the kW loads equally shared, one alternator is
drawing much higher current than the other. What does this indicate?
- The alternators are not generating the same voltages and should be adjusted on automatic voltage regulator
rheostats
313. Vibration analysis is often used as a conditioning monitoring tool onboard ship as part of the approved
planned maintenance system. Many vibration measuring instruments are fitted with a harmonic filter/analyser.
How would these filters normally be used during vibration measurement on a centrifugal pump?
- To isolate a single frequency of vibration associated with one of the pumps components
314. P = U x I x Root of 3 cos (fi). What is the formula for I?
- Formula 1
315. You have to choose one of the following instruments for measuring pressure in an air bottle in measuring
range 0-35 BAR. Which instrument will you install?
- Bourdon Tube manometer
316. You enter a hight voltage switchroom and smell rotten eggs. What may this indicate?
- Problem with a gas (SF6) circuit breaker.
317. Your vessel is in a foreign port and you find that one of the crew members has been incarcerated for
drunkenness. The official Logbook shows that the seaman doesn’t have funds to cover the costs of the fine. Which
action should the master take?
- Pay the seaman’s fine
318. Your vessel is on an extended foreign voyage. Several vacancies have occurred in your unlicensed crew
through sickness and repatriation. Which statement is correct?
- Qualified aliens may be employed to fill the vacancies.
319. To maintain good relationship among the crew on board a vessel, one must be:
- Understanding, Co-operative, and have respect from both sides.
320. Untuk menyimpan atau membuka file dokumen gambar skema elektronika, dapat dipilih file yang memiliki
ekstensi:
- File.sch
321. Untuk menggambar symbol-symbol komponen di Or-Cad dilakukan dengan cara:
- Klik PLACE – Part
6. Elektronika (electronic)
15. The figures show a graphical symbol for a particular electronic component
and a typical operating characteristic for the same component. Which
component?
a. Triac
b. Zener diode
c. Tunnel diode
d. Field effect transistor
16. The physical size of a resistor is an indicator of what aspect of it's
specification?
a. Power dissipation capability
b. Total resistance
c. Resistivity
d. Tolerance
17. The range of a transducer is 0-200 bar. The output signal is 4-20 mA. What
is the span of the output signal?
a. 16 mA
b. 20 mA
c. 24 mA
d. 4 mA
18. This circuit is widely used for rectification of AC into DC. Which of the
diagrams is correct for the out- put voltage when the input voltage is sine-
shaped as shown?
a. Figure 1
b. Figure 2
c. Figure 3
d. Figure 4
19. This circuit consists of two capacitors, C(1) = 6 µF and C(2) = 12 µF, in
series. Calculate the equivalent C(S) of the two capacitors.
a. C(S) = 4 µF
b. C(S) =2µF
c. C(S)=1,5µF
d. C(S) =18µF
20. This resistor has the value of 68 k ohm. Which colour code should be
marked on the rings (assume ring d is the tolerance ring)?
a. a. blue b. grey c. orange
b. a. black b. red c. orange
c. a. violet b. green c. yellow
d. a. red b. black c. yellow
21. What function is this operational amplifier circuit performing?
a. Inverting amplifier
b. Non-inverting amplifier
c. Integrator
d. Differentiator
22. When a diode is used to convert AC to DC, it is usually referred to as
which of the following?
a. Rectifier
b. Controller
c. Alternator
d. Regulator
23. Which diagram is the symbol for a THYRISTOR?
a. Figure 2.
b. Figure 1.
c. Figure 3:
d. Figure 4.
24. Which electronic component does this graphical symbol illustrate?
a. Bipolar transistor
b. Silicon controlled rectifier
c. Diode
d. Field Effect Transistor
25. Which electronic component does this graphical symbol represent:
a. Resistor, 3300 ohms
b. Electric heater, 3.3 kilowatts
c. Capacitor, 3.3 Uf
d. Inductive reactor, 3.3 kH
34. For two generators running in parallel, their share of additional load (kW)
will be determined by the:
a. Governor droop settings on each prime mover
b. Voltage droop setting on each AVR
c. The power factor of the additional load
d. The temperature difference between the generator rotors
35. Resistance thermometers are often installed in a thermo-well. Will it matter
to the accuracy of the measurement how you install a resistance element in a
thermo-well?
a. Wrong installation will result in a major deviation in measurement
b. Will have a minor influence on the measurement
c. Will only result in mechanical problems
d. No influence at all
36. Salinometers are often used to monitor water supplies.The most common
type of sensing device they use is:
a. Electrodes
b. Strain gauge
c. Capacitance probe
d. Inductor capsule
37. A 450 volt 3 phase brushless alternator will have the following combination
of items mounted on the rotor:
a. 3 phase excitation winding/rectifier bank/main field winding
b. 3 phase excitation winding/ main field winding
c. 1 phase excitation field winding/rectifier bank/main field winding
d. Excitation field winding/main field winding
38. A second alternator has just been synchronized onto the main switchboard,
and it is necessary to equally share the load between the "running" and
incoming alternators. What should be done first?
a. Raise the governor speed controller of the incoming alternator and
reduce the governor speed controller of the alternator already on the
switchboard
b. Adjust voltage rheostat for the incoming alternator on the front of
the switchboard
c. Lower the governor speed controller of the incoming alternator and
increase the governor speed controller of the alternator already on
the switchboard
d. Trip the circuit breaker of the incoming alternator and check the
voltage and speed adjustments before trying again
39. After successful synchronising an incoming machine the kW and kVar
loading are respectively transferred by the following controls:
a. Speed governor and voltage regulator
b. Current regulator and voltage regulator
c. Voltage regulator and synchroscope
d. Speed governor and load power factor
40. Alteration of the excitation voltage (or field current) of one alternator
operating in parallel, will cause which change in that alternators output:
a. Reactive load (kVAR)
b. Active load (kW)
c. Frequency
d. None of the mentioned alternatives
41. Consider a 450 volt, 859 kW rated generator has not been in operation for
several weeks. Prior to starting, insulation resistance readings are taken. The
minimum acceptable insulation resistance reading on the main stator
winding to allow you to proceed with running the generator is:
a. 1 000 000 Ohms
b. 10 Ohms
c. 1000 Ohms
d. 10 000 Ohms
42. Consider generator 1 and 2 to be initially working in parallel. If prime-
mover 2 suffers a total fuel loss what is the likely outcome?
a. No.2 generator trips on reverse power
b. Generator set 2 trips on reverse speed
c. No.1 machine overloads and trips out on overspeed
d. No.1 machine overspeeds and trips out on overload
43. Due to failure of one of the carbon brushes the excitation voltage is lost on
one alternator that is operating in parallel. Will that alternator then:
a. Completely lose its share of the load causing the auxiliary engine to
speed up
b. Overload due to reduced voltage output and increased current
c. Continue to share the active load (kW) but have very high reactive
load (kVAR)
d. Try to take all the load and so trip the main circuit breaker
44. During regular inspection of alternator windings it is found that windings
are always covered with a heavy oil film coming from the atmosphere
surrounding the auxiliary engine. After cleaning with an approved solvent,
what should be done?
a. Improve material of intake air filters
b. Take no additional action
c. Blank off intake air filters
d. Reinsulate the windings after each cleaning
52. Regular (at least weekly) testing of the emergency generator must be
performed to check:
a. Its readiness to perform as specified.
b. Its environmental noise factor during emergency fire-drills.
c. Its voltage/current and prime mover characteristics.
d. Its compliance with the shipbuilder's recommendations.
53. Ship's generators must be synchronised before they can be connected to the
same supply network. Prior to synchronising, the generator voltage and
frequency are respectively adjusted by:
a. AVR and speed governor
b. Voltmeter and frequency meter
c. Speed governor and load power factor controller
d. Synchroscope and speed governor
54. The internal e.m.f. generated in the phase windings of a lightly loaded a.c.
generator is controlled by:
a. The prime mover speed and excitation current.
b. The internal volt drop and the load current.
c. The prime mover and load current.
d. The internal volt drop and the residual magnetism.
55. The power requirements for the excitation winding/circuit for a 3-phase
alternator operating at rated output power are supplied by:
a. The alternators output itself via the automatic voltage regulator and
the prime mover
b. Independent battery supply with the AVR
c. Independent power supply and rectifier unit
d. The main switchboard via a three phase rectifier
56. The speed of ship's generator is regulated by the governor. A 10% reduction
in generator speed occurs due to a faulty governor. The likely consequence
for all motors powered from this generator is to:
a. Reduce motor speed by about 10%’
b. Increase motor power by about 10%
c. Increase motor speed by about 10%
d. Reduce motor volt drop by about 10%
57. The two instruments necessary for generator synchronising are:
a. Voltmeter and synchroscope
b. kW meter and frequency meter
c. Amp-meter and volt-meter
d. Synchroscope and kVar-meter
58. Two alternators are operating in parallel at 75% load capacity, but then one
of them trips without any warning. What is the first action that should be
taken?
a. Trip/stop all nonessential loads that are connected to the switchboard
b. Check the circuit breaker of the tripped alternator
c. Restart and connect the tripped alternator immediately
d. Start and connect the emergency alternator
59. Under normal conditions, the electric power for services supplied from the
emergency switchboard is supplied from:
a. The main generating plant.
b. Emergency batteries
c. An emergency battery charger.
d. A compressed air driven generator.
60. What determines the power factor of an alternator when it is connected
singularly to the switchboard?
a. The load connected to the switchboard
b. The generated voltage and AVR setting
c. The excitation voltage
d. Number of pairs of pole coils in the excitation winding
61. What is the purpose of the alternator reverse power trip?
a. To prevent the alternator from "motoring" by being supplied power
from other parallel alternator and thus being damaged
b. To prevent parallel operation if the excitation field voltage is
reversed
c. To prevent the alternator from being paralleled if it is out of phase
with the main switchboard
d. To give automatic disconnection of the circuit breaker when you are
taking the alternator off the switchboard
62. When 3 phase alternators are operating in parallel, it is very important that
the reactive load is evenly shared so that the total alternator loads are evenly
shared. If the total alternator load is the vector sum of active and reactive
loads, which side of the vector diagram (power triangle) shown represents
the reactive load?
a. (Y)
b. (X)
c. Either (X) or (Y)
d. None of the mentioned alternatives
63. When a large motor load suddenly is disconnected from the switchboard
and the generator is AVR controlled, what will the output voltage do?
a. Initially rise, then reset to the set value.
b. Remain approximately constant, due to AVR action.
c. Initially fall, then reset to the set value.
d. Remain approximately constant, due to governor action.
64. When manually paralleling two alternators the pointer of the synchroscope
may slowly stop rotating and remain stopped in one position before the
circuit breaker is closed. This would indicate:
a. The frequency of the incoming alternator is the same as that of the
main switchboard
b. The synchroscope is not functioning properly and should be checked
c. The voltage of the incoming alternator is the same as that of the
main switchboard
d. The incoming alternator is in phase with the switchboard, but the
frequency is not the same
65. When paralleling two alternators they must have:
a. Equal number of phases, phase sequence and frequency
b. Same number of phases, phase rotation and power rating
c. Same phase rotation and voltage rating
d. Same frequency, voltage and power factor
66. When unloading a generator, it is necessary to gradually decrease the load
in order to avoid:
a. Undue overspeeding.
b. Undue overload on the switchboard.
c. Undue overcurrent
d. Undue temperature rise.
67. Which group of electrical services are likely to be supplied from an
emergencygenerator?
a. Steering gear and engine room alarm system
b. Engine room lighting and bow thruster
c. Galley and air conditioning
d. Sound powered telephone system
68. With two alternators running in parallel, and one is to be disconnected. The
first step is to:
a. Remove the load from the alternator to be stopped
b. Make sure the load is evenly shared
c. Trip the main circuit breaker
d. Increase the frequency on the switchboard
69. Before taking insulation resistance readings of generator windings the
automatic voltage regulators should be isolated and all semiconductor short
circuited or disconnected in order to:
a. Prevent damage to sensitive electronic components from high
voltage tester
b. Protect insulation resistance tester and leads from being damaged
c. Prevent charging of capacitive components within the automatic
voltage regulator causing false regulation when generator restarts
d. Prevent operation of automatic voltage regulator during insulation
testing
1. Why is it important that a transmitter has been correctly installed at the correct location
a. The control system is depending on the best possible process signal
b. It is important to have easy access to the transmitter for maintenance
c. It must be easy to observe for troubleshooting
d. Can be installed anywhere in the piping system
14. This graphical symbol is a logic gate with truth table. Which gate?
a. OR
b. AND
c. NOR
d. NAND
15. This is the graphical symbol and truth table for a logic gate. Which gate?
a. NOR
b. NAND
c. OR
d. AND
16. Two reference points for pressure exist, absolute zero and atmospheric pressure. What
is the common name pressures measured relative to atmospheric pressure?
a. Gauge pressure
b. Atmospheric pressure
c. Absolute pressure
d. Pressure drop
17. What can be measured by means of a manometer?
a. Pressure
b. Strain
c. Temperature
d. Motion
18. What is the difference between a PRESSURE SWITCH and a PRESSURE
TRANSMITTER, if any?
a. The pressure switch has contact(s) that will change between open and closed
position.The pressure transmitter converts a pressure signal into an electric
signal.
b. There is no difference.
c. The pressure switch gives out an analogue signal depending on the switch
setting.The pressure transmitter gives out a binary signal depending on the
pressure.
d. The pressure switch gives out a digital signal dependent on pressure and
temperature.The pressure transmitter converts a pressure signal to a digital
signal.
19. What is the main difference between a THERMOSTAT and a TEMPERATURE
TRANSMITTER, if any?
a. The thermostat has one or more contacts (open or closed) depending on the
temperature/setting. The temperature transmitter converts a temperature signal
to an electric signal.
b. There is no difference.
c. The thermostat gives out an analogue signal depending on the switch setting.
The temperature transmitter gives out a binary signal depending on the
temperature.
d. The temperature transmitter is a digital component while the thermostat is an
analogue component.
20. What type of signal output is derived from a NiCr/Ni thermocouple?
a. mV.
b. Ohm.
c. mA.
d. Watt
21. When measuring level of liquids with a differential pressure meter, the name of the
sensing device is:
a. Pressure diaphragm
b. Float
c. Capacitance probe
d. Positive displacement tube
22. When calibrating a pressure transducer we have to adjust both SPAN and ZERO.
Please indicate in which order these adjustments should be done.
a. First Zero adjustment and the Span adjustment. Then Zero should be
rechecked.
b. First Span adjustment and then Zero adjustment. After that Span setting should
be checked again.
c. First Span adjustment and then Zero adjustment. Then do not adjust anything.
d. The order of adjustment is of no importance.
23. When calibrating an instrument what is the most common first step in the procedure ?
a. Adjustment of Zero-point
b. Adjustment of span
c. Adjustment of range
d. Adjustment of linearity
24. When calibrating an instrument what is the most common second step in the
procedure?
a. Check linearity
b. Adjustment of span
c. Adjustment of range
d. Adjustment of Zero-point
25. When measuring flow of fluids with a fixed area flow meter, the name of the sensing
device is?
a. Orifice plate
b. Float
c. Turbine rotor
d. Positive displacement rotor
26. Which component does this graphical symbol illustrate?
a. Resistance temperature sensor
b. Potentiometer
c. Thermocouple
d. Triac
27. Which device does this graphical symbol illustrate?
a. Remote level controller with indicator
b. Local level controller with indicator
c. Level switch for centre-tank
d. Low carbon incinerator
28. Which of the following detectors is commonly used for sensing if a watertight steel
door is closed or open?
a. Proximity switch
b. Synchro
c. Strain gauge
d. Transducer
29. Which of the following detectors would you choose for measuring the torque of a steel
shaft?
a. Strain gauge
b. Ultrasonic gauge
c. Synchro
d. Pyrometer
30. Which of the following letter combinations represents a flow indicating controller on a
process and instrumentation diagram
a. FIC
b. LIR
c. FLO
d. FIR
31. Which of the following letter combinations represents a temperature controller on a
process and instrumentation diagram?
a. TC
b. TIC
c. PIC
d. FIC
32. Which type temperature sensors are shown on the picture?
a. Resistance sensors
b. Thermocouple sensors
c. Thermistors type NTC
d. Thermistor type PTC
33. If the outlet temperature “Tout" is kept constant at 65 degrees C and during normal sea
speed the inlet temperature “Tin” is 62 degree C, what would 'Tin" show during engine
slow down ?
a. A differentiator assembly
b. An amplifier
c. An integrator assembly
d. A nozzle/flapper assembly
38. In this nozzle/flapper assembly (part of a pneumatic control system) at what distance
away from the nozzle oes the flapper need to be mooed in order not to have any
influence on the HEW (nozzle back pressure) ?
a. h = 0.25 D
b. h = D
c. h = 0.4 D
d. h = 0.5 D
39. What is the meaning of the pressure indicated by NBP on this nozzle/flapper assembly
?
a. 3 psi
b. 0 psi
c. 20 psi
d. 15 psi
42. This characteristic shows that only linear part a-b can be used. This means that the
normal effective travel the flapper is only …… for the full measuring range.
a. 0.05 mm
b. mm
c. 0.10 mm
d. 0.005 mm
43. As we can use only the linear part of the characteristic, this shows that the flapper can
only travel 0.01 mm, therefore DELTA psi obtained can only be less than 1 psi. Can
we use the flapper nozzle system ?
a. Yes, but the readings obtained between DELTA psi need to be amplified
b. No , the flapper system will gives erratic readings
c. No, the nozzle/flapper assembly needs modification
d. Yes, but the valves need a servo booster
44. The proportional linear signal for a pneumatic nozzle/flapper assembly is only less than
1 psi for 0.01 mm flapper travel. How do we make use of this signal ?
a. A pneumatic controller
b. A pneumatic amplifier
c. A pneumatic flapper / nozzle assembly
d. A pneumatic booster aggregate
46. On which part of the Pneumatic Amplifier is the nozzle back pressure of the nozzles /
flapper (NBP) acting ?
a. On spring S
b. On valve V
c. On ball valve B
d. On membrane M
47. By what parts is the outlet pressure Pu of this pneumatic transmitter directly
controlled ?
a. spring tension in S
b. By the restriction R
c. By the stand of the valves V and B
d. By slight fluctuation of supply pressure
48. What is the function of ball value B in relation to the outlet pressure Pu of this
pneumatic amplifier?
50. What would be the result if after period of time the tension of spring S should weaken
on this pneumatic amplifier ?
53. Where is the output pressure Pu taken from this pneumatic amplifier shown here ?
a. Air passage 15
b. Air passage 13
c. Air passage 14
d. Air passage 12
54. Via which air passage is the nozzle back pressure from the nozzle/Flapper admitted
for this pneumatic amplifier ?
a. Air passage 14
b. Air passage 15
c. Air passage 13
d. Air passage 12
55. Which is the exhaust or air vent port to the atmosphere shown on this pneumatic
transmitter?
a. Air passage 13
b. Air passage 14
c. Air passage 12
d. Air passage 15
a. Nozzle flappers
b. Blade (feather) springs to load the ball and the vent valve
c. Ball valve securing blades
d. Retaining plates for the ball valve
57. Flow can the output pressure Pu of this pneumatic amplifier be initially adjusted ?
a. By screw item 10
b. By screw item 1
c. By screw item 11
d. By screw item 4
58. Which important pneumatic control accessory is shown here ?
a. A transmitter
b. An nozzle /flapper assembly
c. A pressure regulator
d. An amplifier
59. What is part No 4 shown in this drawing of a pneumatic amplifier ?
a. Diaphragma No 7 bursts
b. Valve stem No 6 defective
c. Internal passages blocked by oil mixed with dirt.
d. Gasket No 8 blown
62. This shows a pneumatic control unit which forms the basis of pneumatic control
engineering. It is.........
a. a pneumatic transmitter assembly
b. a totaliser or summator unit
c. a nozzle/flapper assembly with amplifier
d. a pneumatic basic controller unit
63. These small pneumatic pipes are connected to the different parts of pneumatic system
so they can be easily dismantled, using ............ ?
64. Which part shown here is the nozzle in this pneumatic assembly ?
a. Part No 2
b. Part No 4
c. Part No 3
d. Part No 5
65. What will be the existing pneumatic pressure in connecting pipe item 110 6 from
flapper nozzle assembly to the pneumatic amplifier ?
66. Pneumatic instruments have an air filter fitted so that any impurity present is
removed. Where is this filter fitted ?
a. 15 to 25 psi
b. 7 to 15 psi
c. 3 to 20 psi
d. 3 to 15 psi
a. Flapper nozzle
b. Connecting plug
c. Filter plug
d. Restrictor nozzle
71. What pneumatic device is shown here ?
a. A feedback controller
b. A feedback amplifier
c. A proportional controller
d. A proportional transmitter
72. What is the name of the bellow P, which indicates its purpose ?
a. Equalising bellow
b. Lifting bellow
c. Feedback bellow
d. Absorbing bellow
73. If the length of "a" is equal to the length of "b" what will be the proportional band
"PB" of this pneumatic controller ?
a. 0%
b. 50%
c. 100%
d. 25%
74. With what part is the degree of feedback controlled on this pneumatic Proportional
Controller ?
A. By lengths of arms "a" and 'b" (shifting of amplifier)
B. By "desired valve" input
C. By the spring tension
D. By the bellow
75. If Q1 is the filling volume of the tank and Q2 the outflow volume of the tank and the
level L is constant by controller output pressure Pu = 9 psi, the valve V2 will be open
for ...
a. 25%
b. 50%
c. 100%
d. 75%
76. If the input flow Q1 increases to Q1' and level L increases to L' what will initially
happen ?
a. Positive activation
b. Negative activation
c. Air to Close
d. Air to Open
78. If we shift the nozzle / flapper assembly to the left so that the length of "a" is half of
length "b", to what level will L' rise before it stabilizes ?
A. The offset
B. The range
C. The amplification
D. The span
80. This characteristic shows the output pressure of a controller effecting valve lift. If PB
= 100 % is the graph shown in "a". What is the graph of PB = 50 % ?
a. Graph b
b. Graph d
c. Graph e
d. Graph f
81. This characteristic shows output pressure of a controller effecting valve lift. If P8 =
100 % is the graph shown in "a ". What is the amplification factor and the
proportional band represented by graph "I" ?
a. 9 psi
b. 6 psi
c. 12 psi
d. 3 psi
84. If the measured value bellow is connected to the output of the jacket CW temperature
transmitter and thePu of the controller is 9 psi, and we reduce the temperature setting
from 75 to 72 degree C what happens tosigj the Pu ?
a. It will increase above 9 psi
b. It will increase to 20 psi
c. It will decrease to 0 psi
d. It will decrease below 9 psi
85. Between which values (expressed in psi) can setting of the Su (set value or desired
value) bellow of this pneumatic P controller be affected?
a. 2 psi
b. 3 psi
c. 6 psi
d. 0 psi
87. Suppose the INPUT of the pneumatic controller is 4 psi and the PB is 25 %. If
variation on the input is 1psi down, what is the variation on the output expressed in
psi ?
a. 2 psi
b. 1 psi
c. 6 psi
d. 4 psi
88. What would be the variation of output on this pneumatic controller if Proportional B
and PB = infinity, by varying the input as shown here ?
a. 5 psi
b. 0.5 psi
c. 0.2 psi
d. 1 psi
a. 500%
b. 50%
c. 100%
d. 20%
92. In this electrical amplifier drawing, what takes the place of the flapper/nozzle unit
used by the pneumatic control unit with amplifier ?
a. R2
b. U2
c. U1
d. R1
93. What takes the place of the 20 psi input used by pneumatic nozzle/flapper units in this
electrical amplifier equivalent ?
a. Resistance R2
b. Voltage U1
c. Voltage U2
d. Resistance R1
94. What takes the place of the output pressure of the pneumatic nozzle/flapper unit in
this electrical amplifier equivalent ?
a. Voltage U2
b. Voltage U1
c. Resistor R2
d. Resistor R1
96. The working pressures used by pneumatic control components are between 3 and 15
psi. What are the equivalent currents used by electric control equipment ?
a. Between 0 and 5 or 3 and 9 mA
b. Between 0 and 20 mA or 4 and 20 mA
c. Between 20 and 60 mA or 25 and 75 mA
d. Between 10 and 50 mA or 15 and 50 mA
97. What does a thick articulated line represent in automation schematic diagrams ? (the
top articulated line shown here)
a. A measuring line
b. A process line
c. An instrument line
d. A steering line
98. What does a broken or dotted line represent in automation schematic diagrams ? (the
second line from top shown here)
a. A pneumatic line
b. A steering line
c. An instrument line
d. A measuring line
99. What does a non-articulated full line indicate in an automation schematic drawing ?
(the third line from top shown here)
a. A controller
b. An indicator
c. A transmitter
d. An instrument
101. What does the symbol shown on the fifth line from the top (a circle with a horizontal
line through it of the drawing indicated an automation schematic diagram ?
a. An electronic instrument
b. An instrument fitted in a central panel
c. An instrument fitted in the main control console
d. A pneumatic instrument
102. What do the letters "PT" shown in this instrument symbol (drawn on the bottom
line) indicate if found in an automation schematic drawing
a. A thermometer
b. A temperature transmitter
c. A temperature controller
d. A manometer
104. As part of an automation schematic drawing, what kind of instrument might befitted
on the measuring line as indicated on the top centre drawing ?
For No. 74
108. The feedwater valve and the feedwater by-pass values are...........
109. This drawing shows a simple mechanical controller controlling the water level in the
tank. Level "L" is the DESIRED water level in the tank, in automation this is called
the .....
a. set point.
b. set level.
c. measured value.
d. proportional point.
110. Suppose that in the system drawn the water inflow Q1 increases so that the float is
pushed up by the water to level L'. The value of level L' is called the ......
a. increased value.
b. actual value.
c. level value.
d. measured value.
111. The difference between the desired value (level L) and the measured value(level L')
is called.........
a. a pure integrator
b. a pure differentiator
c. a proportional integrating controller
d. a proportional controller
117. Explain the function of a capacitor that loads up compared with a bellow that fills up
with air ?
a. A proportional controller
b. A proportional integrating-differential controller
c. A proportional differentiating controller
d. A proportional integrating controller
119. These graphs are, left, the step input and, right, the output response of a controller.
What characteristics are shown ?
a. The controller response
output characteristics
b. The PI characteristics
c. The integrator
characteristics
d. The integrator differential
characteristics
121. The measuring signal obtained to carry out flow measuring is a Differential pressure
signal. This is obtained by a certain medium flowing through a...........
a. oriface plate
b. a right-angled nozzle system
c. nozzle system
d. capillary tube
122. Since the output of the pressure transmitter is not linear with the flow in the pipe as
measured over the wring flange the output signal should be sent to a................
a. root extractor.
b. equaliser.
c. summator.
d. balancing valve.
123. To which channel is the nitrogen-filled thermal bellow in this pneumatic
temperature transmitter fitted ?
a. Channel 10
b. Channel 5
c. Bellow 8
d. Channel 8
a. Item No 3
b. Item no 2
c. Item No 4
d. Item No 1
126. On this pneumatic transmitter part drawing, which part is amplifying the signal ?
a. Part No 2
b. Part No 4
c. Part No 3
d. Part No 1
127. What is part 110 11 on this transmitter drawing ?
a. The feedback bellow
b. The balance arm tensioner
c. The transmitter bellow
d. The regulating bellow
128. Which part adjusts the proportional band of this pneumatic transmitter ?
a. Part No 9
b. Part No 7
c. Part No 8
d. Part No 10
129. On which part of this pneumatic transmitter does the pressure of the process
(steam,oil,water) act ?
a. Item No 1
b. Item No 3
c. Item No 2
d. Item No 4
130. The span of this pneumatic transmitter is set by adjusting or tensioning.......
a. part No 10.
b. part No 9.
c. part No 15.
d. part No 11.
131. From this drawing of a pneumatic pressure transmitter, what is the Proportional
Band setting ?
a. Proportional Band more than 100 %, amplification K less than 1
b. Proportional Band less than 100 %, amplification K more than 1
c. Proportional Band = 100 %, amplification K = 1
d. Proportional Band 0%, amplification infinitive
132. For which type of controller are these the input (left) and the response (right)
characteristics ?
a. A pneumatic integrator
b. A pressure integrating controller
c. A pneumatic inverter
d. A proportional integrating controller
133. In this drawing, the triangle marked "A" represents.......
a. an ampere-differential transmitter
b. a current converter
c. an operational amplifier
d. an analog converter
134. Which resistor determines the proportional band on this electronic proportional
integrating controller ?
a. R2
b. Rf
c. R1
d. R3
135. Fitting a restriction RI in the supply to the proportional feedback of this PID
controller ensures that for an initial small variation on the input, the initial response
on the output will be .....
a. proportional
b. zero
c. very weak
d. strong
136. For which control instrument are these the input (left) and the output or response
(right) characteristics ?
a. A pressure controlling data
register
b. A pneumatic
differentiating controller
c. A pressure differentiator
d. A proportional
differentiating controller
137. For this PID controller to act only as a P (proportional) controller, what should be
the arrangement of restricting values R1 and R2 ?
a. R1 fully open, R2
fully open
b. R1 closed, R2 fully
open
c. R1 closed, R2 closed
d. R1 fully open, R2
closed
138. which kind of controller are
the input and output characteristics shown here ?
a. A proportional indicating differentiator
b. A proportional integrating-differentiating controller
c. A pressure indicating controller
d. A pneumatic differential summator
139. In the output characteristics (right) of this controller, which response lines are
clearly shown ?
a. By C and RL
b. By C and RL
c. By C and R3
d. By C and R2
141. Where would you find this instrument on board a ship ?
a. With item No 3
b. With item No 2
c. With item No 1
d. With items 1, 2 and 3.
152. The two valves shown on the left of this picture are called flat valves and give a high
throughput for a small lift in height. They are mostly used for.......
a. self correcting flow valve, by changing pressures in the system the throughput
the same.
b. a stop (zero flow) valve.
c. open - close regulation.
d. process stability, for a certain percentage in lift changes the throughput by the
same percentage.
153. The two valves shown in the centre of the drawing are.....
a. feedback
b. separated range
c. diverted
d. split range
158. The valve positioner acts on the principle of the balance of forces. The tension of
part ..... ( .......) is to be inbalance with the force of the controller pressure which
acts on part....... (........).
a. 9 (spring), 18 (membrane)
b. 4 (relays), 12 (membrane)
c. 9 (spring), 11 (supply valve)
d. 12 (membrane), 6 (feedback lever)
159. Why does the output (instrument supply) pressure of a reducer fluctuate ?
162. This is the drawing of a Machinery Monitoring and Alarm System. What is the heart
and brain of this Scanning Unit ?
a. The LSU's
b. The CPU
c. The MAD
d. The LAD'S
163. Which port of this machinery scanning system collects the incoming data from
instruments and transducers ?
a. The CPU
b. The TWM
c. The LSU'e
d. The MAD
164. If the engine room is in UMS mode and one of the measuring points collected by a
LSU and fed into the CPU exceeds its preset value parameter, the CPU will.........
a. activate the LAD in operation and its visible and audible alarm will set off.
b. activate the MAD (main Alarm Display) and Visible and alarms will be
activated.
c. activate the TWM (Type Writer Monitor) and print out the obtained error value,
measuring point number and time.
d. activates all of these.
165. The LSU's (Local Scanning Units) have to measure temperature, pressure, flow,
level, RPM, torque, horsepower, circuit and salinity and do so via analog and digital
tranducers. What is a digital transducer ?
a. A digital transducer gives a
continue signal , example 0 - 100 mV
166. The latest obtained system values are fed into the computer and compared with
previous ones. The analysis obtained before has to be compared with the latest
analysis. This is called......
a. wear down and maintenance scheduling.
b. trend analysis and maintenance prediction.
c. material fatigue and maintenance scheduling.
d. wear down and breakdown prediction.
167. If a fault occurs in this power supply system, the best and fastest way to locate this
fault is by...........
a. With item No 7
b. With item No 5
c. With item No 1
d. With item No 2
169. How do you adjust the zero setting on this commonly used electrical pressure
transmitter?
a. By item No 5
b. By item No 7
c. By item No 2
d. By item No 1
170. In an automated engine the center from which the ship's engine room is controlled is
called:
a. the control plant station (CPS).
b. the main engine nerve and control station (MENS).
c. the power plant station control station (PPCS).
d. the engineering control room (ECR).
171. In automation, RTD & CV stands for:
a. resistance temperature drop & control event.
b. return time delay.
c. resistance temperature detector and control valve.
d. None of these.
172. The monitoring system that tests the plant for readings of the temperature, pressure
etc. is called:
a. the demand display unit.
b. the scanning unit.
c. the loop back system.
d. the comparing unit.
173. A pressostat as well as a thermostat are sources of....... type output signals ?
a. impulse
b. digital
c. analog
d. binary
174. The second potentiometer of this electric command system is located in the steering
gear. What moves this potentiometer ?
a. The telemotor
b. The rudder angle
indicator
c. The rudder position via the
trunion connection
d. The eccentric pushrod on the
HELE-SHAW pump
175. What is part No 1 ?
a. The Differentiator
b. The Pressure knob
c. The Measuring scale
d. The Adjusting knob
176. What is Part No 5 ?
a. 1
b. 0
c. 11
d. 10
178. Indicate the correct characteristic of the amplifier "A".
a. A frequency range less than 1 kHz
b. A voltage gain greater than 100,000
c. An input impedance lower than 1,000 Ohm
d. An output impedance greater than 10,000 Ohm
179. What is this symbol ?
a. A binary flip-flop
b. A binary register
c. A digital amplifier
d. A differential trigger
180. What kind of temperature control mode is fitted here ?
a. Voltage U2
b. Voltage U1
c. Resistor R1
d. Resistor R2
19. A 3-phase induction motor is rated at 200 A Full loadline current. Its initial
direct- on-line starting current will be approximately:
a. 1000 A
b. 100 A
c. 5000 A
d. 200 A
20. A delta connected 3-phase A.C. induction motor is running normally at its
rated current of 150 A when a single phasing fault (open circuit) occurs in
one line. The likely outcome will be:
a. Line currents: 0 A, 180 A, 180 A. Trip condition: trip on overload.
b. Line currents: 0 A, 150 A, 300 A. Trip condition: trip on overload.
c. Line currents: 75 A, 75 A, 75 A. Trip condition: no trip but speed
falls.
d. Line currents: 150 A,150A,150 A. Trip condition: fuses blow on
short circuit.
21. A motor is protected by a thermal overcurrent relay. After tripping on
overload it will not be possible to reset the overcurrent relay immediately
because the:
a. Bimetallic strips need time to cool down
b. Starter isolator automatically applies an interlock.
c. Oil dash-pot has to be reset.
d. Line contactor spring has to be reset
22. A ships 3 - phase a.c. electrical supply system has 440 V and 220 V
sections. The effect of a single short circuit fault to earth on a 220 V line
will cause which of the following earth lamp indications:
a. In 440 V section: all lamps equally bright. In 220 V section: Two
lamps bright one lamp dark.
b. In 440 V section: All lamps equally bright. In 220 V section: One
lamp dim.
c. In 440 V section: One lamp dim. In 220 V section: One lamp dim.
d. In 440 section: All lamps equally bright. In 220 section: All lamps
dark.
23. After main power is restored (following a blackout), a timed sequential
restart of motor-driven auxiliaries is necessary to avoid:
a. Generator overload due to many motors starting at simultaneously
b. Overloading creating earth faults
c. Overvoltage due to current surges
d. Over-frequency due to overspeed of generator
24. An earth fault exists on the blue line of a 100 A bilge pump circuit. A
second earth fault occurs on the yellow line of a 10 A ventilation fan circuit.
Both systems are supplied from the ship's 440V supply. The likely outcome
is that:
a. A short circuit occurs between earth faults and the ventilation fan
fuse blows
b. An open circuit occurs between earth fault and both motors trip out
c. Both motors trip out on overload
d. A short circuit occurs between earth fault and the bilge pump fuse
blows
25. An electrical power emergency source in a ship is required because:
a. It satisfies the SOLAS (and other) requirements for ship safety
b. The ship's total load can be shared between main and emergency
generators
c. The main diesel generator(s) can be taken out of service for overhaul
or repair
d. It satisfies the need to be environmentally "friendly"
26. Check-synchroniser equipment is often installed to:
a. Prevent manual synchronising outside permitted limits
b. Permit faster paralleling of generators
c. Allow auto-synchronising to take place
d. Ensure fair equal sharing between generators
27. In terms of electrical units, what is Hz the abbreviation for?
a. Frequency in Cycles per second
b. Revolution per minute
c. Frequency in Direct Current (DC)
d. Measure for Resistance
28. The correct time to synchronise is usually taken to be when the
synchroscope reaches the "5 to 12" position and is rotating slowly
clockwise. This to allow for:
a. Circuit breaker operating time
b. Synchroscope pointer time lag
c. Synchroscope error
d. Generator phase difference error
29. The earth lamps in a 3-phase system indicate as follows: Red= bright
Yellow= dark Blue= dim . Which fault condition shown as red - yellow -
blue is correct?
a. no fault - hard earth - light earth
b. light earth - no fault - hard earth
c. hard earth - light earth - no fault
d. light earth - hard earth - no fault
30. The function of the fuses in a motor starter circuit is to provide:
a. Short circuit protection.
b. Overload protection.
c. Undervoltage protection.
d. Over load protection.
31. The insulation resistance (IR) to earth of a new galley hot-plate is measured
to be 30 Mohm. When three identical hot-plates on the same supply are
tested together their combined IR will be:
a. 10 Mohm
b. 30 Mohm
c. 3 Mohm
d. 90 Mohm
32. When maintenance work is to be carried out on an electric motor driving a
centrifugal water pump with automatic start, should you;
a. In conjunction with the senior watchkeeper and electrician, isolate
valves, electrical supply, automatics and post 'Do not operate' signs
before commencing work.
b. Set in local control, isolate the suction and delivery valves then
commence work.
c. Isolate the suction and delivery valves then inform the electrician
that you are starting work.
d. Ascertain from the senior watchkeeper if it is okay to startwork,
isolate the valves then commence work.
33. A 450 volt 3 phase brushless alternator will have the following combination
of items mounted on the rotor:
e. 3 phase excitation winding/rectifier bank/main field winding
f. 3 phase excitation winding/ main field winding
g. 1 phase excitation field winding/rectifier bank/main field winding
h. Excitation field winding/main field winding
34. A second alternator has just been synchronized onto the main switchboard,
and it is necessary to equally share the load between the "running" and
incoming alternators. What should be done first?
e. Raise the governor speed controller of the incoming alternator and
reduce the governor speed controller of the alternator already on the
switchboard
f. Adjust voltage rheostat for the incoming alternator on the front of
the switchboard
g. Lower the governor speed controller of the incoming alternator and
increase the governor speed controller of the alternator already on
the switchboard
h. Trip the circuit breaker of the incoming alternator and check the
voltage and speed adjustments before trying again
35. After successful synchronising an incoming machine the kW and kVar
loading are respectively transferred by the following controls:
e. Speed governor and voltage regulator
f. Current regulator and voltage regulator
g. Voltage regulator and synchroscope
h. Speed governor and load power factor
36. Alteration of the excitation voltage (or field current) of one alternator
operating in parallel, will cause which change in that alternators output:
e. Reactive load (kVAR)
f. Active load (kW)
g. Frequency
h. None of the mentioned alternatives
37. Before taking insulation resistance readings of generator windings the
automatic voltage regulators should be isolated and all semiconductor short
circuited or disconnected in order to:
e. Prevent damage to sensitive electronic components from high
voltage tester
f. Protect insulation resistance tester and leads from being damaged
g. Prevent charging of capacitive components within the automatic
voltage regulator causing false regulation when generator restarts
h. Prevent operation of automatic voltage regulator during insulation
testing
38. Consider a 450 volt, 859 kW rated generator has not been in operation for
several weeks. Prior to starting, insulation resistance readings are taken. The
minimum acceptable insulation resistance reading on the main stator
winding to allow you to proceed with running the generator is:
e. 1 000 000 Ohms
f. 10 Ohms
g. 1000 Ohms
h. 10 000 Ohms
39. Consider generator 1 and 2 to be initially working in parallel. If prime-
mover 2 suffers a total fuel loss what is the likely outcome?
e. No.2 generator trips on reverse power
f. Generator set 2 trips on reverse speed
g. No.1 machine overloads and trips out on overspeed
h. No.1 machine overspeeds and trips out on overload
40. Due to failure of one of the carbon brushes the excitation voltage is lost on
one alternator that is operating in parallel. Will that alternator then:
e. Completely lose its share of the load causing the auxiliary engine to
speed up
f. Overload due to reduced voltage output and increased current
g. Continue to share the active load (kW) but have very high reactive
load (kVAR)
h. Try to take all the load and so trip the main circuit breaker
49. Regular (at least weekly) testing of the emergency generator must be
performed to check:
e. Its readiness to perform as specified.
f. Its environmental noise factor during emergency fire-drills.
g. Its voltage/current and prime mover characteristics.
h. Its compliance with the shipbuilder's recommendations.
50. Ship's generators must be synchronised before they can be connected to the
same supply network. Prior to synchronising, the generator voltage and
frequency are respectively adjusted by:
e. AVR and speed governor
f. Voltmeter and frequency meter
g. Speed governor and load power factor controller
h. Synchroscope and speed governor
51. The internal e.m.f. generated in the phase windings of a lightly loaded a.c.
generator is controlled by:
e. The prime mover speed and excitation current.
f. The internal volt drop and the load current.
g. The prime mover and load current.
h. The internal volt drop and the residual magnetism.
52. The power requirements for the excitation winding/circuit for a 3-phase
alternator operating at rated output power are supplied by:
e. The alternators output itself via the automatic voltage regulator and
the prime mover
f. Independent battery supply with the AVR
g. Independent power supply and rectifier unit
h. The main switchboard via a three phase rectifier
53. The speed of ship's generator is regulated by the governor. A 10% reduction
in generator speed occurs due to a faulty governor. The likely consequence
for all motors powered from this generator is to:
e. Reduce motor speed by about 10%’
f. Increase motor power by about 10%
g. Increase motor speed by about 10%
h. Reduce motor volt drop by about 10%
54. The two instruments necessary for generator synchronising are:
e. Voltmeter and synchroscope
f. kW meter and frequency meter
g. Amp-meter and volt-meter
h. Synchroscope and kVar-meter
55. Two alternators are operating in parallel at 75% load capacity, but then one
of them trips without any warning. What is the first action that should be
taken?
e. Trip/stop all nonessential loads that are connected to the switchboard
f. Check the circuit breaker of the tripped alternator
g. Restart and connect the tripped alternator immediately
h. Start and connect the emergency alternator
56. Under normal conditions, the electric power for services supplied from the
emergency switchboard is supplied from:
e. The main generating plant.
f. Emergency batteries
g. An emergency battery charger.
h. A compressed air driven generator.
57. What determines the power factor of an alternator when it is connected
singularly to the switchboard?
e. The load connected to the switchboard
f. The generated voltage and AVR setting
g. The excitation voltage
h. Number of pairs of pole coils in the excitation winding
58. What is the purpose of the alternator reverse power trip?
e. To prevent the alternator from "motoring" by being supplied power
from other parallel alternator and thus being damaged
f. To prevent parallel operation if the excitation field voltage is
reversed
g. To prevent the alternator from being paralleled if it is out of phase
with the main switchboard
h. To give automatic disconnection of the circuit breaker when you are
taking the alternator off the switchboard
59. When 3 phase alternators are operating in parallel, it is very important that
the reactive load is evenly shared so that the total alternator loads are evenly
shared. If the total alternator load is the vector sum of active and reactive
loads, which side of the vector diagram (power triangle) shown represents
the reactive load?
e. (Y)
f. (X)
g. Either (X) or (Y)
h. None of the mentioned alternatives
60. When a large motor load suddenly is disconnected from the switchboard
and the generator is AVR controlled, what will the output voltage do?
e. Initially rise, then reset to the set value.
f. Remain approximately constant, due to AVR action.
g. Initially fall, then reset to the set value.
h. Remain approximately constant, due to governor action.
61. When manually paralleling two alternators the pointer of the synchroscope
may slowly stop rotating and remain stopped in one position before the
circuit breaker is closed. This would indicate:
e. The frequency of the incoming alternator is the same as that of the
main switchboard
f. The synchroscope is not functioning properly and should be checked
g. The voltage of the incoming alternator is the same as that of the
main switchboard
h. The incoming alternator is in phase with the switchboard, but the
frequency is not the same
62. When paralleling two alternators they must have:
e. Equal number of phases, phase sequence and frequency
f. Same number of phases, phase rotation and power rating
g. Same phase rotation and voltage rating
h. Same frequency, voltage and power factor
63. When unloading a generator, it is necessary to gradually decrease the load
in order to avoid:
e. Undue overspeeding.
f. Undue overload on the switchboard.
g. Undue overcurrent
h. Undue temperature rise.
64. Which group of electrical services are likely to be supplied from an
emergencygenerator?
e. Steering gear and engine room alarm system
f. Engine room lighting and bow thruster
g. Galley and air conditioning
h. Sound powered telephone system
65. With two alternators running in parallel, and one is to be disconnected. The
first step is to:
e. Remove the load from the alternator to be stopped
f. Make sure the load is evenly shared
g. Trip the main circuit breaker