Download as pdf or txt
Download as pdf or txt
You are on page 1of 49

Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 1 of 49

3 UNITED STATES DISTRICT COURT


4 DISTRICT OF NEVADA
5 ***
6 BARTELL RANCH LLC, et al., Case No. 3:21-cv-00080-MMD-CLB
7 Plaintiffs, ORDER
v.
8
ESTER M. MCCULLOUGH, et al.,
9
Defendants.
10

11 I. SUMMARY

12 Plaintiffs1 and Plaintiff-Intervenors2 challenge the Bureau of Land Management of

13 the U.S. Department of Interior’s3 approval of Intervenor-Defendant Lithium Nevada

14 Corporation’s plan to build a lithium mine near Thacker Pass, Nevada and engage in

15 further exploration for lithium (the “Project”). They ask the Court to review BLM’s Record

16 of Decision (“ROD”) under the Administrative Procedure Act, 5 U.S.C. § 701, et seq.

17 (“APA”), challenging BLM’s compliance with three federal statutes.4 While this case

18 encapsulates the tensions among competing interests and policy goals, this order does

19

20 Ranch LLC and Edward Bartell (collectively, the “Rancher Plaintiffs”), along
1Bartell
with Western Watersheds Project, Wildlands Defense, Great Basin Resource Watch, and
21 Basin and Range Watch (collectively, the “Environmental Plaintiffs”).
22 2Reno-Sparks Indian Colony (“RSIC”) and the Burns Paiute Tribe. The Court refers
to both tribes collectively as the Tribal Plaintiffs.
23
3Ester M. McCullough, the District Manager of BLM’s Winnemucca office, along
24 with the Department of the Interior, are also named Defendants. The Court refers to them
collectively as the Federal Defendants.
25
4The National Environmental Policy Act, 42 U.S.C. §§ 4321-61 (“NEPA”), the
26 Federal Land Policy and Management Act, 43 U.S.C. §§ 1701-1787 (“FLPMA”), and the
National Historic Preservation Act, 54 U.S.C. § 300101, et seq. (“NHPA”). (ECF Nos. 1,
27 46, 83.) See also Western Watersheds Project, et al. v. Bureau of Land Management of
the U.S. Department of the Interior, et al., Case No. 3:21-cv-00103-MMD-CLB, ECF No.
28 1 (D. Nev. Filed Feb. 26, 2021) (since consolidated into this case).
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 2 of 49

1 not somehow pick a winner based on policy considerations. That is not this Court’s role.

2 The Court’s role instead is to carefully apply the applicable standard of judicial review to

3 consider the decision of a federal agency that is generally entitled to deference, based

4 entirely on the contents of the records before the agency at the time of its challenged

5 decision.

6 This order addresses the parties’ dispositive motions seeking judgment on the

7 merits.5 (ECF Nos. 202, 203, 204, 205, 241, 242.) The Court explains below its resolution

8 of the pending motions, and, thus, this case. To preview, the Court finds that Ctr. for

9 Biological Diversity v. United States Fish & Wildlife Serv., 33 F.4th 1202 (9th Cir. 2022)

10 (“Rosemont”) applies. This in turn leads the Court to conclude that BLM’s approval of the

11 Project violated FLPMA as it relates to the approximately 1300 acres of land Lithium

12 Nevada intends to bury under waste rock because BLM did not first make a mining rights

13 validity determination as to those land. The Court otherwise affirms BLM’s decision,

14 rejecting arguments that the Project will cause unnecessary and undue degradation to the

15 local sage grouse population and habitat, groundwater aquifers, and air quality in violation

16 of FLPMA, that BLM failed to adequately assess the Project’s impacts on air quality,

17 wildlife, and groundwater in violation of NEPA, that BLM failed to adequately consider the

18 Project’s impacts as to the area’s contemporary cultural or religious significance to local

19 tribes also in violation of NEPA, and that BLM unreasonably or in bad faith decided not to

20 consult with Tribal Plaintiffs before approving the Project in violation of the NHPA. In sum,

21 the Court concludes that BLM’s decision as it relates to approval of land to be used for

22 waste dumps violated FLPMA (43 U.S.C. § 1732(b)) and is therefore arbitrary and

23 capricious under the APA. But the Court otherwise rejects Plaintiff and Plaintiff-

24 Intervenors’ claims.

25

26 5These motions are fully briefed, and the Court has reviewed all of the briefing the
parties submitted. In addition, the Court held an in-person hearing (“Hearing”) on the
27 pending motions on January 5, 2023. (ECF Nos. 273 (setting hearing), 277 (hearing
minutes).) The Court accordingly discusses infra some arguments and concessions the
28 parties made at the Hearing.
2
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 3 of 49

1 The Court has also determined this is the rare case where remand without vacatur

2 is appropriate primarily because the records suggest BLM could fix the error the Court

3 identifies and Plaintiffs fail in their other legal challenges to BLM’s decision to approve the

4 Project. The Court will remand for BLM to fix the error—to determine whether Lithium

5 Nevada possesses valid rights to the waste dump and mine tailings land it intends to use

6 for the Project. But the Court declines to vacate the ROD pending BLM’s review of the

7 mining plan of operations portion of the Project.

8 II. LEGAL STANDARD

9 The Court reviews BLM’s decision to issue the ROD based entirely on the contents

10 of the Administrative Record (“AR”) under the APA. “The APA does not allow the court to

11 overturn an agency decision because it disagrees with the decision or with the agency’s

12 conclusions about environmental impacts.” River Runners for Wilderness v. Martin, 593

13 F.3d 1064, 1070 (9th Cir. 2010). But “[u]nder the [APA], a reviewing court shall ‘hold

14 unlawful and set aside agency action, findings, and conclusions found to be ... arbitrary,

15 capricious, an abuse of discretion, or otherwise not in accordance with the law....”’ Nw.

16 Motorcycle Ass’n v. U.S. Dep’t of Agric., 18 F.3d 1468, 1471 (9th Cir. 1994) (quoting 5

17 U.S.C. § 706(2)(A)). An agency’s decision may be reversed as arbitrary and capricious “if

18 the agency has relied on factors which Congress has not intended it to consider, entirely

19 failed to consider an important aspect of the problem, offered an explanation for its

20 decision that runs counter to the evidence before the agency, or is so implausible that it

21 could not be ascribed to a difference in view or the product of agency expertise.” Motor

22 Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983).

23 “To make this finding, the court must consider whether the decision was based on a

24 consideration of the relevant factors and whether there has been a clear error of

25 judgment.” Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402, 416 (1971).

26 But in reviewing an agency’s decision under this standard, “the reviewing court may

27 not substitute its judgment for that of the agency.” Envtl. Def. Ctr., Inc. v. U.S. Envtl. Prot.

28 Agency, 344 F.3d 832, 858 n.36 (9th Cir. 2003); see also Rosemont, 33 F.4th at 1216

3
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 4 of 49

1 (same). And the Court’s “review is limited to ‘the grounds that the agency invoked when it

2 took the action.”’ Id. (citation omitted). Although this review is narrow, “a reviewing court

3 must conduct a searching and careful inquiry into the facts.” Nw. Motorcycle Ass’n, 18

4 F.3d at 1471. “A satisfactory explanation of agency action is essential for adequate judicial

5 review, because the focus of judicial review is not on the wisdom of the agency’s decision,

6 but on whether the process employed by the agency to reach its decision took into

7 consideration all the relevant factors.” Asarco, Inc. v. U.S. Envtl. Prot. Agency, 616 F.2d

8 1153, 1159 (1980).

9 The Court reviews for substantial evidence the agency’s factual conclusions based

10 on the administrative record. See Ctr. for Biological Diversity v. Zinke, 900 F.3d 1053,

11 1068 (9th Cir. 2018). “Where ‘evidence is susceptible of more than one rational

12 interpretation,’ [the Court upholds] the agency’s finding if a ‘reasonable mind might accept

13 [it] as adequate to support a conclusion.”’ Id. (citation omitted).

14 III. DISCUSSION

15 The Court primarily organizes this discussion by plaintiff group, first discussing

16 Environmental Plaintiffs’ claims, then Rancher Plaintiffs’ claims, and then Tribal Plaintiffs’

17 claims. However, the Court notes when two plaintiff groups have essentially the same

18 claims and considers those claims together. And the Court concludes by explaining its

19 decision to remand without vacatur.

20 A. Environmental Plaintiffs

21 Environmental Plaintiffs argue BLM’s decision to approve the Project in the ROD

22 violates FLPMA and NEPA. The Court addresses below Environmental Plaintiffs’

23 arguments under both statutes after first describing the pertinent factual background.

24 1. Factual Background

25 Lithium Nevada submitted two plans of operations (one for exploration, and the

26 other for mining and reclamation) to BLM for approval in September 2019. (TPEIS-0452

27 at AR-052517.) BLM approved both plans in the ROD. (Id.)

28 ///

4
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 5 of 49

1 The pertinent NEPA process began when BLM issued a notice of intent to prepare

2 an environmental impact statement on January 21, 2020. See Notice of Intent To Prepare

3 a Draft Environmental Impact Statement and Resource Management Plan Amendment,

4 for the Lithium Nevada Corp., Thacker Pass Project Proposed Plan of Operations and

5 Reclamation Plan Permit Application, Humboldt County, Nevada, 85 FR 3413-02, 2020

6 WL 279646 (Jan. 21, 2020). BLM then went through a scoping period where it held two

7 virtual public meetings in Winnemucca and Orovada, Nevada on February 5 and 6, 2020,

8 and received 26 comment letters. (ECF No. 237 at 11-12.)

9 BLM provided a draft environmental impact statement with underlying data and

10 analysis to stakeholders including the Nevada Department of Wildlife (“NDOW”) in the

11 spring of 2020, and made the draft environmental impact statement available for public

12 comment on July 29, 2020. See Notice of Availability of the Draft Environmental Impact

13 Statement, 85 FR 45651-01, 2020 WL 4340040 (Jul. 29, 2020). BLM held two additional

14 public meetings in August 2020 and received 63 letters commenting on the draft

15 environmental impact statement. (ECF No. 237 at 12.)

16 BLM then issued the final environmental impact statement (“FEIS”) on December

17 4, 2020. See Notice of Availability of the Final Environmental Impact Statement for the

18 Proposed Thacker Pass Project, Two Plans of Operations Submitted by Lithium Nevada

19 Corporation for Mining and Exploration in Humboldt County, Nevada, 85 FR 78349-01,

20 2020 WL 7075441 (Dec. 4, 2020). BLM considered additional comments submitted in the

21 30 days that followed, including from Plaintiffs, NDOW, and the United States

22 Environmental Protection Agency (“EPA”). And as noted, BLM issued the ROD approving

23 the Project on January 15, 2021. (TPEIS-0452 at AR-052515.)

24 2. FLPMA

25 Environmental Plaintiffs argue BLM violated FLPMA in two different ways: (1) by

26 approving the Project, which does not comply with the Nevada and Northeastern California

27 Greater Sage-Grouse Approved 2015 RMP Amendment (“ARMPA”), the applicable,

28 regional land-use plan, based on the erroneous presumption that Lithium Nevada

5
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 6 of 49

1 possessed valid rights under the Mining Law of 1872 (codified as amended at 30 U.S.C.

2 §§ 21 to 54) (the “Mining Law”) to the land that Lithium Nevada intends to use as waste

3 dumps;6 and (2) because the Project will cause unnecessary and undue degradation

4 (“UUD”) prohibited by FLPMA in any event. (ECF No. 202 at 15-31, 43-48.) The Court

5 addresses each of Environmental Plaintiffs’ FLPMA arguments in turn.

6 a. Mining Law

7 More than a year after BLM issued the ROD, and indeed after briefing on the

8 pending motions began, the United States Court of Appeals for the Ninth Circuit issued its

9 opinion in Rosemont, 33 F.4th 1202. The Court indicated to the parties that it was

10 interested in hearing argument at the Hearing on the extent to which Rosemont controls

11 the outcome of this case. (ECF No. 276.) And, indeed, much of the argument at the

12 Hearing focused on the application of Rosemont to this case. As further explained below,

13 the Court finds that Rosemont applies, which means that BLM must have, but did not,

14 determine whether Lithium Nevada has valid rights under the Mining Law to occupy the

15 approximately 1300 acres it plans to occupy with waste rock dumps and tailings piles

16 outside the mine pit before issuing the ROD.

17 Rosemont is about a copper mine on Forest Service land, not a lithium mine on

18 BLM land. But the language of the regulations at issue in Rosemont is so similar to the

19 language of the regulations at issue here, and the reasoning of Rosemont otherwise so

20 applicable to these facts, that the Court finds Rosemont controlling. As further explained

21 below, the Rosemont court’s analysis focused on the Mining Law. The Mining Law “gives

22 to United States citizens free of charge, except for small filing and other fees, mining rights

23 upon discovery of ‘valuable minerals’ on federal land.” Rosemont, 33 F.4th at 1208. The

24

25 6Rancher Plaintiffs also make this argument so the Court’s analysis of this
argument also applies to Rancher Plaintiffs. The Court notes in its discussion any ways in
26 which Rancher Plaintiffs’ argument differs from Environmental Plaintiffs’ argument. In
addition, Rancher Plaintiffs joined Environmental Plaintiffs’ motion for summary judgment.
27 (ECF No. 212.) Thus, the Court’s discussion of Environmental Plaintiffs’ NEPA claims also
applies to Rancher Plaintiffs’ arguments that overlap with Rancher Plaintiffs’ NEPA claims
28 because Rancher Plaintiffs have joined Environmental Plaintiffs’ motion.
6
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 7 of 49

1 scope of the Mining Law has been reduced since its enactment, following withdrawals of

2 federal land from mining, later statutory declarations that some minerals are not “valuable

3 mineral deposits” within the meaning of the Mining Law, and the enactment of

4 environmental laws such as NEPA. See id. at 1208-09. The Mining Law treats exploration

5 and occupation for purposes of mining differently. See id. at 1209. To occupy federal land

6 for mining purposes, a miner must have a valid claim. See id. at 1209-10.

7 In approving the copper mine at issue in Rosemont, the Forest Service “either

8 assumed that Rosemont’s mining claims on that land were valid or (what amounted to the

9 same thing) did not inquire into the validity of the claims.” Id. at 1212. “Based on its

10 assumption that the mining claims were valid, the Service concluded that Rosemont’s

11 permanent occupation of the claims with its waste rock was permitted under the Mining

12 Law.” Id.

13 The Rosemont court found the Forest Service erred, instead finding in pertinent

14 part that the Mining Law did not give Rosemont “the right to dump its waste rock on

15 thousands of acres of National Forest land on which it has no valid mining claims.” Id. at

16 1218. As the Forest Service abandoned its rationale based on 30 U.S.C. § 612 on appeal,

17 see id., the Rosemont court largely focused its analysis on 30 U.S.C. § 22 (“Section 22”)

18 of the Mining Law. See id. at 1218-1221. And the Rosemont court found that Section 22

19 required a discovery of valuable minerals before a project proponent could permanently

20 occupy any land, including with waste dumps or tailings piles. See id. at 1220. The

21 Rosemont court also rejected the argument that burying land with waste rock was

22 somehow not permanent. See id. at 1220-21.

23 Even more pertinent to this case, the Rosemont court went on to reject the Forest

24 Service’s argument that the Forest Service’s founding statute and its own regulations

25 created no implicit requirement that the Forest Service determine whether a proponent of

26 a mining project had discovered valuable mineral deposits in land it planned to occupy

27 with waste dumps and tailings piles before approving those uses because that statute and

28 regulation both referred back to the Mining Law itself. See id. at 1221-22. The Rosemont

7
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 8 of 49

1 court found that the Mining Law accordingly controls, not the Forest Service’s founding

2 statute or its regulation. And the Mining Law only gives a right of occupation to lands within

3 which valuable mineral deposits have been found—the question is “not whether valuable

4 minerals might be found.” Id. at 1222. Said otherwise, the Rosemont court found that it

5 was only the Mining Law that could permit the project proponent “to dump its waste rock

6 on its mining claims [but] only if those claims are valid[,]” not the Forest Service’s contrary

7 interpretation of its founding statute or its regulations. See id. at 1221.

8 More specifically, the Rosemont court interpreted the Forest Service’s founding

9 statute as generally intended to protect against depredations to National Forest lands

10 while also specifying that it permitted the continuation of mining activities authorized by

11 federal mining laws, including the Mining Law. See id. at 1210. And the Part 228A

12 regulations upon which the Forest Service also relied in Rosemont to support its view that

13 it did not have to determine mining claim validity applied to uses of National Forest lands

14 ““in connection with operations authorized by the United States mining laws[.]” Id. at 1211

15 (citation omitted, emphasis in original). Thus, both the statute and regulation upon which

16 the Forest Service relied to support its approach to approving the copper mine referred

17 back to the Mining Law.

18 Like the statute and regulation at issue in Rosemont, the statute (FLPMA) and

19 regulations that Federal Defendants and Lithium Nevada rely on to argue BLM was not

20 required to determine whether Lithium Nevada had discovered valuable mineral deposits

21 under the approximately 1300 acres of land Lithium Nevada intends to use for waste

22 dumps and tailings piles also refer back to the Mining Law. (ECF Nos. 237 at 14-16, 18-

23 31, 242 at 11-18.) Federal Defendants first rely on FLPMA itself, specifically 43 U.S.C. §

24 1732(b). (ECF No. 237 at 27.) The pertinent portion of this section of FLPMA is:

25
Except as provided in section 1744, section 1782, and subsection (f) of
26 section 1781 of this title and in the last sentence of this paragraph, no
27 provision of this section or any other section of this Act shall in any way
amend the Mining Law of 1872 or impair the rights of any locators or claims
28 under that Act, including, but not limited to, rights of ingress and egress. In

8
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 9 of 49

managing the public lands the Secretary shall, by regulation or otherwise,


1 take any action necessary to prevent unnecessary or undue degradation of
2 the lands.

3 43 U.S.C. § 1732(b). As Environmental Plaintiffs argue, this refers back to the Mining
4 Law, much like the Forest Service’s founding statute at issue in Rosemont. (ECF No. 264
5 at 22-23.) Indeed, this portion of FLPMA interacts with the Mining Law in two ways. It
6 applies the prohibition on UUD even to rights of any locators or claims under the Mining
7 Law,7 but more pertinent here, it otherwise explains that interpretation of rights under the
8 Mining Law controls the analysis of whether an agency violated FLPMA in taking an action
9 not sanctioned by the Mining Law. See 43 U.S.C. § 1732(b). And the Rosemont court
10 recently provided a binding interpretation of the Mining Law, finding that its Section 22
11 requires a discovery of a valuable mineral deposit for a mining project proponent to have
12 rights under Section 22 before that proponent may permanently occupy any land. See 33
13 F.4th at 1223-24. Thus, contrary to Federal Defendants’ argument, 43 U.S.C. § 1732(b)
14 requires BLM to look to Section 22 of the Mining Law, and accordingly make a
15 determination about claim validity, before authorizing a project proponent to occupy non-
16 mill site lands outside a mine pit with waste dumps and tailings piles under Rosemont.
17 (ECF No. 237 at 27-28.)
18 Federal Defendants next proffer BLM’s surface-management regulations at 43
19 C.F.R. subpart 3809 as not requiring any determination from BLM as to whether Lithium
20 Nevada located any valuable mineral deposits under the waste dump land to support
21 BLM’s decision not to make any such determination. (Id. at 28.) Federal Defendants also
22 point to a BLM handbook interpreting those regulations stating that BLM need not make
23 any validity determination when the land is open to access under the Mining Law.8 (Id. at
24

25 7Thisis why Environmental Plaintiffs have a distinct argument discussed infra that
Federal Defendants’ decision to approve the Project caused UUD under FLPMA.
26
8“Provided the subject land is open to entry under the Mining Laws, a validity
27 examination is not required to process a Plan of Operations and the NEPA analysis does
not need to address mining claim status or validity. Nor does the NEPA analysis need to
28

9
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 10 of 49

1 29.) Of course, the Rosemont court did not address these BLM regulations or its

2 handbook. And it is also true that the Rosemont court did not rule on whether the Forest

3 Service could rely on its analogous regulations to support its decision because the Forest

4 Service had not done so in the decision challenged in that case. See 33 F.4th at 1223-24.

5 Thus, Rosemont does not cleanly foreclose Federal Defendants’ argument based on its

6 own regulations and handbook in the way that it does Federal Defendants’ argument

7 based on FLPMA (43 U.S.C. § 1732(b)) itself.

8 However, Environmental Plaintiffs point to one of BLM’s surface-management

9 regulations, 43 C.F.R. § 3809.420(a)(3), which specifies that a mining plan of operations

10 must comply with applicable BLM land-use plans, “[c]onsistent with the mining laws[.]”

11 (ECF No. 264 at 13.) And the purpose of the surface-use regulations Federal Defendants

12 rely on to make their argument is to, “[p]revent unnecessary or undue degradation of public

13 lands by operations authorized by the mining laws.” 43 C.F.R. § 3809.1(a). Moreover,

14 these surface use provisions are all within a subpart titled, “Part 3800—Mining Claims

15 Under the General Mining Laws[.]” In addition, the specific excerpt of the Handbook

16 Federal Defendants rely on also includes the caveat, “[p]rovided the subject land is open

17 to entry under the Mining Laws[.]” (TPEIS-0714 at AR-067896.) So, overall, BLM’s

18 surface-management regulations refer back to the Mining Law, much like the Forest

19 Service regulations the Rosemont court discussed. See 33 F.4th at 1221 (“The regulations

20 in Part 228A apply to “operations authorized by the United States mining laws.”) (citation

21 omitted).

22 The Court accordingly finds that the appropriate analysis under Rosemont looks

23 through BLM’s surface-management regulations to the Mining Law itself, and Rosemont

24 makes clear that the approving federal agency must evaluate the mining project

25 proponent’s rights under lands they intend to use for waste dumps before they approve

26
discuss how the information gained under a Plan of Operations could support an
27 application to patent a particular mining claim. The issuance of mineral patents is a
separate nondiscretionary action not subject to NEPA review.” (TPEIS-0714 at AR-
28 067896.)
10
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 11 of 49

1 the use of that land for that purpose. See generally id. It is undisputed that Federal

2 Defendants did not do that before issuing the ROD, and indeed Federal Defendants

3 continue to argue they were not required to perform such an evaluation. But the Court

4 cannot simply ignore Rosemont even in the face of longstanding BLM policy reflected in

5 its regulations and handbook.9 Thus, the Court finds that under Rosemont, BLM was

6 required to make a validity determination as to the waste dump and mine tailings land

7 before issuing the ROD, regardless of BLM’s regulations and handbook.

8 However, the Court agrees with Federal Defendants and Lithium Nevada that this

9 case differs from Rosemont in at least one crucial way that suggests Federal Defendants

10 could cure their issue created by Rosemont on remand. In Rosemont, there was “no

11 evidence that valuable minerals have been found on Rosemont’s mining claims” covering

12 the waste dump land. Id. at 1222. “Because no valuable minerals have been found, the

13 claims are necessarily invalid.” Id. But here, as Federal Defendants and Lithium Nevada

14 point out, there is evidence in the record of lithium mineralization throughout the Project

15 area, including the area slated for burial under waste rock and mine tailings. (ECF Nos.

16 237 at 31, 31 n.52, 242 at 15-17; see also, e.g., TPEIS-0702 at AR-065693, TPEIS-0234

17 at AR-033935, TPEIS-0672 at AR-063882 (“More than 40 drill holes throughout the

18 caldera have encountered lithium-mineralized rocks in caldera-fill sedimentary rocks at

19 grades that are potentially economic (Tetra Tech, 2014). In addition, geochemical

20 anomalies and mineralogical studies reported by Glanzman and others (1977), Rytuba

21 and Glanzman (1979), and Stillings (2012) demonstrate that there are occurrences of

22 lithium-mineralized rocks throughout the caldera-fill sedimentary rocks.”).)

23 Accordingly, at least as to Federal Defendants’ decision not to analyze whether

24 Lithium Nevada had discovered valuable minerals within the land it plans to bury under

25 waste rock and tailings piles, there is “at least a serious possibility that the [agency would]

26
27 9The Rosemont court seemed poised to find invalid regulations inconsistent with its
interpretation of the Mining Law, even if it technically did not reach arguments based on
28 the Forest Service’s regulations in Rosemont. Compare id. at 1221 with id. at 1223-24.
11
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 12 of 49

1 be able to substantiate its decision on remand[.]” Pollinator Stewardship Council v. U.S.

2 E.P.A., 806 F.3d 520, 532 (9th Cir. 2015) (quoting Allied-Signal, Inc. v. U.S. Nuclear

3 Regulatory Comm’n, 988 F.2d 146, 150-51 (D.C. Cir. 1993)). Said otherwise, BLM simply

4 declined to make any determination as to whether Lithium Nevada had discovered

5 valuable minerals in the land it plans to bury under waste dumps and tailings piles. But

6 BLM could conduct such an analysis on remand, and evidence already in the record

7 suggests that BLM could permissibly allow Lithium Nevada to occupy those land under

8 Rosemont, which dealt with the admittedly different situation where no evidence of

9 valuable minerals had been found in the waste dump land.10

10 The Court also finds—based on Environmental Plaintiffs’ clarification at the Hearing

11 as to Rosemont’s application—that Environmental Plaintiffs only challenge the land

12 approved for waste dumps and tailings piles as part of the Project, not any prior

13 authorizations that Lithium Nevada is already operating under or the plan of exploration

14 also approved in the ROD. Indeed, based on Rosemont, such a challenge to approved

15 exploratory activities would be difficult because the Rosemont court found a distinction in

16 the Mining Law between exploration and occupation that formed a key plank of its analysis.

17 See Rosemont, 33 F.4th at 1209-1210, 1219-21. But the point here is that Environmental

18 Plaintiffs rely on Rosemont to only challenge—successfully, as explained herein—a

19 portion of the activities approved in the ROD, further suggesting that remand without

20 vacatur may be appropriate.

21 ///

22

23 10While it appears that BLM could fix its Rosemont issue on remand, the fix would
nonetheless further illustrate a key tension discussed in Rosemont. As the Rosemont court
24 explains, the Mining Law “allows the owner of a valid mining claim on land containing
valuable minerals to obtain possessory rights to other land for use as a ‘mill site.”’ Id. at
25 1210. And implementing regulations specify that mill sites can be used for waste dumps
and tailings piles. See id. But unfortunately for mining project proponents like Lithium
26 Nevada, the statute limits mill sites to five acres, though regulations permit the potential
authorization of the use of multiple mill sites. See id.; see also 30 U.S.C. § 42(b). This is
27 not enough land for modern mining projects like the one Lithium Nevada is pursuing here.
However, as the Rosemont court explained, that is a problem with the statute best fixed
28 by Congress. See 33 F.4th at 1224.
12
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 13 of 49

1 The Court now addresses some additional arguments it finds unpersuasive. At the

2 Hearing, Rancher Plaintiffs argued Rosemont also requires BLM to make a validity

3 determination as to all land required for the Project beyond the mine pit—and hinted at

4 this argument in a cursory way in their brief as well.11 (ECF No. 204 at 49 (“Moreover, BLM

5 failed to show that mine infrastructure cannot be located outside the PHMA and GHMAs,

6 as required by the 2015 and 2019 ARMPA.”).) The Court does not read Rosemont as

7 extending beyond land a mining project proponent intends to cover with waste rock and

8 mine tailings. Such lands were squarely Rosemont’s focus. Rosemont does not address

9 production wells, water lines, or power transmission lines. Lithium Nevada’s counsel

10 asserted at the Hearing that those facilities are covered under separate authorizations.

11 And Rancher Plaintiffs have not proffered a case to support their argument that Rosemont

12 extends beyond land for proposed burial under waste dumps and mine tailings for which

13 no validity determination has first been completed as to the discovery of valuable minerals.

14 That brings the Court to two of Lithium Nevada’s arguments based on other Ninth

15 Circuit opinions, neither of which the Court finds ultimately persuasive. At the Hearing,

16 Lithium Nevada’s counsel argued the outcome of this case is controlled by United States

17 v. Richardson, 599 F.2d 290 (9th Cir. 1979), not Rosemont. Lithium Nevada relies on

18 Richardson because it draws a distinction between BLM and Forest Service regulations

19 when it comes to interpretation of the Mining Law. See id. at 294 (stating that BLM

20 “regulations do not, however, apply to national forest lands under the jurisdiction of the

21 Secretary of Agriculture”). This aspect of Richardson no doubt supports Lithium Nevada’s

22 argument that Rosemont is distinguishable. But it would be quite a leap to simply ignore

23 Rosemont, binding precedent from this past year—and where the Rosemont court’s

24 reasoning clearly applies to the facts of this case—because of a single point in an opinion

25
11Environmental Plaintiffs’ counsel walked a line at the Hearing, agreeing he joined
26 Rancher Plaintiffs’ counsel’s argument on this point, but consistently reiterating that
Environmental Plaintiffs’ argument focused on the waste dump and mine tailings land. And
27 indeed, the Court understands Environmental Plaintiffs’ argument based on Rosemont as
limited to the approximately 1300 acres of waste dump land, and the plan of operations
28 approved in the ROD.
13
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 14 of 49

1 from 1979.12 Moreover, the difference between the facts of this case and Richardson is

2 much deeper than the difference between the facts of this case and Rosemont.

3 The Richardson court affirmed the decision of a district court entering an injunction

4 against a couple who was attempting to prospect for minerals on their mining claims on

5 National Forest land using a bulldozer and a backhoe, prohibiting them from continuing to

6 prospect that way, and requiring that they restore the land they had torn up. See generally

7 id. In the key portion of its analysis, the Richardson court held that the Forest Service had

8 the power under 30 U.S.C. § 612 to prohibit and enjoin ‘excessive bulldozing’ by looking

9 to the legislative history of that statute. See id. at 294-25. “In summary,” the Richardson

10 court concluded, “we suggest that each case of this kind is controlled by the facts of each

11 particular case.” Id. at 295.

12 Thus, the facts of and analysis in Richardson—an opinion explicitly limited to its

13 facts from 1979—are very different from the facts pertinent to this case and the analysis

14 the Court conducted comparing these facts to Rosemont, supra. For the reasons provided

15 supra, Rosemont is a much better fit to the facts of this case, and issued this past year.

16 The Court declines to entirely discount the applicability of Rosemont because the

17 Richardson court stated that BLM regulations do not apply to analysis of Forest Service

18 actions.

19 Lithium Nevada also relies on Grand Canyon Trust v. Provencio, 26 F.4th 815, 824

20 (9th Cir. 2022) to support its argument that, “[b]ecause the Mining Law does not expressly

21 address whether a validity determination is required prior to authorization of a mine plan

22 BLM’s interpretation is entitled to deference.” (ECF No. 242 at 12.) That is an accurate

23 citation to Provencio, but the Court views this as a different situation. The Provencio court

24 held that the Department of the Interior’s interpretation of “valuable mineral deposit” was

25 entitled to Chevron deference, and was neither arbitrary nor capricious, but the Provencio

26 court did not face a situation where the Ninth Circuit had recently offered a conflicting

27
12Incidentally,
Richardson was authored by the namesake of the Reno Courthouse,
28 Bruce R. Thompson, sitting by designation.
14
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 15 of 49

1 interpretation of “valuable mineral deposit.” See generally 26 F.4th 815. Here, and as

2 discussed supra, the Rosemont court recently held that the Mining Law requires the

3 approving agency to determine whether a mining project proponent has discovered

4 ‘valuable mineral deposits’ before permitting that proponent to permanently occupy those

5 federal lands with waste dumps and tailings piles. Thus, the Court cannot evaluate BLM’s

6 regulations not requiring such a validity determination in a vacuum. And the Court is of

7 course bound by the published opinions of the Ninth Circuit. Said otherwise, the Court

8 must conduct a somewhat different analysis than the Provencio court because of

9 Rosemont. And the conclusion the Court draws from its analysis is that BLM’s regulations

10 requiring no validity determination are invalid because they conflict with Rosemont. The

11 Court accordingly follows Rosemont, not BLM’s regulations written before Rosemont

12 issued, and does not defer to BLM’s regulations as Provencio may otherwise suggest.

13 In sum, BLM’s approval of the plan of operations portion of the Project specifically

14 regarding the approximately 1300 acres Lithium Nevada intends to occupy with waste

15 dumps and mine tailings—and that land only—was arbitrary and capricious under the APA

16 and violated FLPMA (43 U.S.C. § 1732(b)) because BLM did not first determine whether

17 Lithium Nevada had discovered valuable mineral deposits within those lands—a violation

18 of the Mining Law as interpreted in Rosemont.13 But for clarity, and in line with the

19 allegations in this case, the violation is of FLPMA, not the Mining Law directly, 14 because

20 43 U.S.C. § 1732(b) does not, in pertinent part, “amend the Mining Law of 1872 or impair

21 the rights of any locators or claims under that Act[.]” Id. So as described supra, the Court

22 essentially looks through FLPMA to the Mining Law, and finds Federal Defendants violated

23

24
13For this reason, the Court need not—and does not—address Lithium Nevada’s
25 alternative argument forcefully pressed at the Hearing that the Project complies with the
ARMPA in any event. (See also ECF Nos. 278, 278-1 (additional AR citations generally
26 offered in support of that argument).)
27 14As Federal Defendants and Lithium Nevada point out, no Plaintiffs or Plaintiff-
Intervenors have brought a claim under the Mining Law directly. Environmental Plaintiffs
28 allege a violation of FLPMA as to their Rosemont argument.
15
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 16 of 49

1 FLPMA under Rosemont in issuing the ROD as it relates to the approval of the land for

2 waste dumps and mine tailings.

3 b. UUD

4 Regardless of whether Lithium Nevada has valid rights under the Mining Law,

5 Environmental Plaintiffs also argue the Project will cause UUD impermissible under

6 FLPMA in several ways. Specifically, Environmental Plaintiffs argue the Project

7 impermissibly: (1) fails to affect a net conservation gain for sage grouse or improve the

8 condition of their habitat; (2) will eventually degrade the local groundwater aquifer with

9 antimony; and (3) violates air quality standards because the Project includes a ‘black box’

10 air pollution scrubbing mechanism for compliance with those standards. (ECF No. 202 at

11 43-48.)

12 Federal Defendants counter that: (1) BLM was not required—or even permitted to—

13 require additional conservation measures for sage grouse because they are not listed as

14 a threatened or endangered species; (2) as to groundwater, the ROD does not authorize

15 any violation of groundwater contamination standards, BLM reasonably decided that

16 approving the Project would not impermissibly pollute the groundwater, and a potential,

17 future violation of groundwater standards does not constitute a violation of applicable law

18 in any event; and (3) the Project as approved does not violate any applicable federal or

19 state air quality standards. (ECF No. 237 at 31-35.)

20 Lithium Nevada echoes these arguments and further argues that this Court’s

21 decision in W. Expl., LLC v. U.S. Dep’t of the Interior, 250 F. Supp. 3d 718, 747 (D. Nev.

22 2017) (“Western Exploration”) does not support Environmental Plaintiffs’ argument that

23 BLM must require the Project to affect a “net conservation gain” on the local sage grouse

24 population, instead arguing that there, the Court merely concluded that the greater

25 protection for sage grouse included in the ARMPA was not inconsistent with FLPMA’s

26 multiple-use mandate. (ECF No. 240 at 42-44.) As to groundwater, Lithium Nevada

27 supplements Federal Defendants’ argument, insisting that the very documents

28 Environmental Plaintiffs rely on to support their argument instead show that the Project

16
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 17 of 49

1 will comply with—and even exceed—applicable water quality standards. (Id. at 44-46.) As

2 to air quality, Lithium Nevada mostly echoes Federal Defendants’ argument in urging the

3 Court to defer to BLM’s reasonable decision finding that Lithium Nevada’s proffered air

4 quality plan will not cause UUD. (Id. at 46-47.) The Court agrees with Federal Defendants

5 and Lithium Nevada in pertinent part.

6 The Court begins with Environmental Plaintiffs’ sage grouse UUD argument.

7 Federal Defendants are correct that BLM’s regulations only require Lithium Nevada to

8 “prevent adverse impacts to threatened or endangered species, and their habitat which

9 may be affected by operations.” 43 C.F.R. § 3809.420(b)(7). Sage grouse are not listed

10 as a threatened or endangered species. (ECF No. 237 at 35.) And Environmental Plaintiffs

11 do not rely on any binding authority to the contrary, instead pointing to a brief that the

12 federal government parties filed in Western Exploration and BLM’s Special Status Species

13 Management Manual.15 (ECF No. 202 at 44-45.) However, as both Federal Defendants

14 and Lithium Nevada argue, the primary source Environmental Plaintiffs rely on to support

15 this argument instead explains that the protections for sage grouse BLM included in the

16 ARMPA are more protective of sage grouse than would be required to prevent UUD. (ECF

17 Nos. 237 at 35, 240 at 42-44.) See also Western Watersheds, Case No. 3:21-cv-00103-

18 MMD-CLB, ECF No. 23-16 at 27 (“Seeking a net gain to Sage-Grouse habitat is fully

19 consistent with FLPMA’s guiding principles. The unnecessary or undue degradation

20 standard is a minimum standard for BLM’s land management policy, but it does not

21 restrain BLM’s discretion to implement a mitigation standard that calls for improvements

22 in land conditions beyond the status quo.”). Thus, Environmental Plaintiffs’ sage grouse

23 UUD argument is insufficiently supported to be persuasive.

24 And the Court’s ruling in Western Exploration, where the Court found that BLM

25 could go further than strictly necessary to prevent UUD to protect the sage grouse, further

26
15As to the Special Status Species Management Manual, being listed as a special
27 status species is not the same as being listed as a threatened or endangered species
under the federal regulations. Federal Defendants do not dispute that the greater sage
28 grouse is a special status species. (ECF No. 237 at 35.)
17
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 18 of 49

1 supports Federal Defendants’ and Lithium Nevada’s arguments. Indeed, there, the Court

2 indicated it was persuaded by the federal defendants’ argument that, “the ‘unnecessary or

3 undue degradation’ standard in the statute does not preclude the agency from establishing

4 a more protective standard that seeks improvements in land conditions that ‘go beyond

5 the status quo.”’ Western Exploration, 250 F. Supp. 3d at 747. Thus, failure to require

6 compliance with the ARMPA does not necessarily constitute UUD. And in any event,

7 “FLPMA prohibits only unnecessary or undue degradation, not all degradation.” Theodore

8 Roosevelt Conservation P’ship v. Salazar, 661 F.3d 66, 78 (D.C. Cir. 2011) (emphasis in

9 original). The Court accordingly rejects Environmental Plaintiffs’ argument that Federal

10 Defendants caused impermissible UUD to the pertinent sage grouse population by

11 approving the Project.

12 As to groundwater, the Court agrees with Federal Defendants and Lithium Nevada

13 that the ROD does not authorize violation of any state water quality standard, and

14 Environmental Plaintiffs do not identify any federal water quality standards that the Project

15 violates. (ECF Nos. 237 at 31-34, 240 at 44-46, 267 at 16-17.) Indeed, the ROD requires

16 Lithium Nevada to maintain water quality and quantity to State of Nevada standards.

17 (TPEIS-0452 at AR-052527.16) Thus, regardless of any concerns expressed about

18 potential water pollution by a BLM employee during the process that ultimately culminated

19 in the ROD (ECF No. 202 at 13 (citing TPEIS-1061 at AR-095381)), Federal Defendants

20 did not authorize UUD to water quality in approving the Project because, as noted, the

21 ROD does not authorize Lithium Nevada to violate state water quality standards. (TPEIS-

22 0452 at AR-052527.)

23 A similar analysis applies to Environmental Plaintiffs’ UUD argument regarding air

24 quality because they have not identified a federal or state air quality standard that the

25 Project violates, and BLM’s own applicable regulations require compliance with federal

26
27 16EnvironmentalPlaintiffs refer to another condition of approval included in the ROD
in their argument (no. 4), but decline to mention this condition of approval (no. 3).
28 (Compare ECF No. 202 at 41 with TPEIS-0452 at AR-052527.)
18
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 19 of 49

1 and state air quality standards. (ECF No. 237 at 34 (making this argument).) See also 43

2 C.F.R. § 3809.420(b)(4) (“All operators shall comply with applicable Federal and state air

3 quality standards, including the Clean Air Act”). Thus, Environmental Plaintiffs have not

4 shown that Federal Defendants’ approval of the Project will cause UUD as to air quality.

5 In sum, the Court rejects Environmental Plaintiffs’ UUD arguments. Federal

6 Defendants did not violate FLPMA’s UUD requirements in approving the Project.

7 3. NEPA

8 NEPA is a procedural statute that requires federal agencies to “assess the

9 environmental consequences of their actions before those actions are undertaken.”

10 Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 387 F.3d 989, 993 (9th Cir.

11 2004). NEPA provides for public participation in assessing a proposed action’s

12 environmental consequences, enabling the public to “play a role in both the

13 decisionmaking process and the implementation of that decision.” Robertson v. Methow

14 Valley Citizens Council, 490 U.S. 332, 349 (1989). Although NEPA lacks a substantive

15 mandate, its “action-forcing” procedural requirements help carry out a “national

16 commitment to protecting and promoting environmental quality.” Id. at 348. As part of

17 these action-forcing requirements, NEPA mandates that agencies considering “major

18 Federal actions significantly affecting the quality of the human environment” must, to the

19 fullest extent possible, prepare an environmental impact statement. See 42 U.S.C. §

20 4332(C).

21 “NEPA [further] imposes a procedural requirement on federal agencies to “take [ ]

22 a ‘hard look’ at the potential environmental consequences of the proposed action.”’ N.

23 Plains Res. Council, Inc. v. Surface Transp. Bd., 668 F.3d 1067, 1075 (9th Cir. 2011)

24 (citation omitted). To take a sufficiently hard look, federal agencies must have available

25 and carefully consider detailed information concerning significant environmental impacts,

26 and make relevant information available to the wider public. See id.

27 That said, in its NEPA review, the Court must employ “a ‘rule of reason’ that asks

28 whether an EIS contains a reasonably thorough discussion of the significant aspects of

19
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 20 of 49

1 the probable environmental consequences.” Great Basin Res. Watch v. Bureau of Land

2 Mgmt., 844 F.3d 1095, 1101 (9th Cir. 2016) (citation omitted). “Under this standard, once

3 satisfied that a proposing agency has taken a ‘hard look’ at a decision’s environmental

4 consequences, the review is at an end.” Id. (citation omitted).

5 Environmental Plaintiffs argue Federal Defendants violated NEPA in several

6 distinct ways. They first argue the FEIS included claims that the Project’s sulfuric acid

7 processing plant would meet air quality standards based on impossible assumptions

8 regarding an unspecified scrubbing system. (ECF No. 202 at 31-33.) Environmental

9 Plaintiffs next argue Federal Defendants failed to adequately analyze baseline wildlife

10 conditions for sage grouse, pronghorn, and springsnails. (Id. at 33-35.) They then argue

11 Federal Defendants failed to adequately analyze the Project’s potential impacts on these

12 wildlife species. (Id. at 35-38.) Environmental Plaintiffs next argue Federal Defendants

13 inadequately analyzed the Project’s cumulative impacts on local wildlife considering other

14 proposed activities within the cumulative effects study area. (Id. at 38-40.) Finally, they

15 argue Federal Defendants failed to adequately analyze mitigation measures in the NEPA

16 review documents, specifically regarding groundwater and wildlife impacts from the

17 Project. (Id. at 40-43.) The Court addresses each of these contentions, in turn, grouped

18 below by air quality, wildlife, and groundwater.

19 a. Air Quality

20 First as to the FEIS’ alleged assumptions about a tail gas scrubbing system,

21 Federal Defendants respond that they were not required to thoroughly consider the

22 effectiveness of the scrubber because they otherwise reasonably concluded the Project

23 would meet air quality standards even without the scrubber. (ECF No. 237 at 47-48.)

24 Lithium Nevada adds that the FEIS actually did describe the tail gas scrubber, and that

25 emissions limits will be enforced through a state air quality permit that Federal Defendants

26 required Lithium Nevada to obtain as well. (ECF No. 240 at 24-27.) The Court agrees with

27 Federal Defendants.

28 ///

20
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 21 of 49

1 Environmental Plaintiffs’ primary argument is that BLM did not understand how the

2 tail gas scrubber on the sulfur-burning plant would work—but BLM legally had to

3 understand. They make much of a quote from Ken Loda, the BLM Project lead, but

4 selectively quote the email that it comes from. (ECF No. 202 at 32 (quoting Mr. Loda as

5 saying “[T]he process plant is pretty much a black box.”).) However, the full sentence

6 reveals a different meaning and is consistent with Federal Defendants’ responsive

7 argument. The full sentence from the email is, “For our regulations, the process plant is

8 pretty much a black box.” (TPEIS-0981 at AR-093830.) And Mr. Loda goes on to build on

9 this understanding in the rest of the email that the regulations applying to BLM’s

10 environmental review do not require him, or BLM, to know exactly how the scrubber

11 system works. (Id.) This is very different than saying you do not understand something.

12 And indeed, Mr. Loda’s understanding of the applicable regulations is consistent with

13 Federal Defendants’ argument: “[b]ecause BLM reasonably determined that the Project

14 would not cause any exceedance of the NAAQS, and thus would not have significant air

15 quality impacts, BLM was not required to thoroughly examine the effectiveness of Lithium

16 Nevada’s additional mitigation plans.” (ECF No. 237 at 47.)

17 And Federal Defendants’ argument is also consistent with the FEIS, in which BLM

18 stated no mitigation was required because its air quality analysis demonstrated that all

19 pollutant concentrations with the Project would be less than the NAAQS and Nevada

20 standards, with negligible effects on AQRVs in Class I areas. (TPEIS-0384 at AR-045630.)

21 This is the sort of scientific determination on which the Court must defer to BLM. See

22 Klamath-Siskiyou Wildlands Ctr., 387 F.3d at 993; see also N. Plains Res. Council, Inc.,

23 668 F.3d at 1075 (“A court generally must be ‘at its most deferential’ when reviewing

24 scientific judgments and technical analyses within the agency’s expertise.”) (citation

25 omitted). Under this highly deferential standard of review, BLM’s determination in the FEIS

26 was reasonable. See Edwardsen v. U.S. Dep’t of Interior, 268 F.3d 781, 789 (9th Cir.

27 2001) (finding agency’s determination that a project would have a negligible to minor

28 impact on air quality reasonable where the analysis was based in part on the fact that the

21
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 22 of 49

1 area will remain in compliance with NAAQS). And because BLM determined that no

2 mitigation was required, it is immaterial how well the tail gas scrubber works, as

3 information about the tail gas scrubber is not essential to a reasoned choice among

4 alternatives. See Native Vill. of Point Hope v. Jewell, 740 F.3d 489, 496 (9th Cir. 2014) (“If

5 the missing information is ‘relevant to reasonably foreseeable significant adverse impacts’

6 and is ‘essential to a reasoned choice among alternatives and the overall costs of

7 obtaining it are not exorbitant,’ the agency must include that information in the EIS.”). Said

8 otherwise, this is not the situation described in the quote from Native Vill. of Point Hope.

9 That said, and as Lithium Nevada points out (ECF No. 242 at 24), Appendix K of

10 the FEIS does identify that the sulfur-burning plan will use a tail gas scrubber and that

11 Lithium Nevada has committed “to installing a state-of-the-art scrubbing control, which is

12 above customary industry standard.” (TPEIS-0706 at AR-065829.) “While the exact

13 scrubbing system has not yet been determined, LNC has committed to installing a control

14 that, at the minimum, meets the emission levels used in this analysis.” (Id. at AR-065829-

15 30.) Again, Environmental Plaintiffs rely on this quote for their argument but omit the

16 second two clauses. (ECF No. 202 at 32.) The full quote further supports the point that it

17 does not matter exactly how the tail gas scrubber works because Lithium Nevada has

18 committed to installing a control system that meets the specified emissions level. See

19 Great Basin Res. Watch, 844 F.3d at 1106 (describing “applicant committed practices” as

20 measures that the project proponent “promised to take and that are ‘considered part of the

21 operating procedures”’ and crediting them in rejecting a NEPA challenge). In addition, the

22 comment responses included as Appendix R to the FEIS indicate that Lithium Nevada had

23 selected a scrubber system by the time the FEIS issued. (TPEIS-0384 at AR-048044.)

24 In sum, the Court finds Environmental Plaintiffs’ air quality NEPA argument

25 unpersuasive.

26 b. Wildlife

27 When it comes to wildlife, Environmental Plaintiffs argue that Federal Defendants

28 got multiple steps of the NEPA analysis wrong—that Federal Defendants used inadequate

22
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 23 of 49

1 baselines, misjudged the impacts of the Project on wildlife, inadequately considered the

2 cumulative impact of this Project along with other approved projects in the geographic

3 area Federal Defendants should have used, and inadequately explained how Lithium

4 Nevada could sufficiently mitigate noise impacts from the Project on sage grouse. (ECF

5 No. 202 at 33-43.)

6 Beginning with the baseline portion of Environmental Plaintiffs’ argument, and as

7 noted, they argue that the FEIS contains no information about how sage grouse use the

8 Project area, similarly lacks information about how pronghorn use the area, does not

9 mention the King’s River Pyrg’s risk of extinction, and more generally does not provide

10 sufficient information about springsnails, including which springs they were found in and

11 how predicted groundwater drawdown will affect them. (Id. at 33-34.) Environmental

12 Plaintiffs’ inadequate baseline argument is grounded in precedential NEPA cases.

13 ‘“Without establishing the baseline conditions which exist ... before [a project] begins, there

14 is simply no way to determine what effect the [project] will have on the environment and,

15 consequently, no way to comply with NEPA.”’ Great Basin Res. Watch, 844 F.3d at 1101

16 (citation omitted). While an agency need not conduct actual baseline measurements, the

17 agency must assess baseline conditions based on accurate and defensible reasoning.

18 See id.

19 However, as to the sage grouse baseline, Federal Defendants persuasively counter

20 that Environmental Plaintiffs appear to have overlooked Appendix G of the FEIS, which

21 explains that baseline surveys were conducted for sage grouse, along with the results of

22 those surveys. (ECF No. 237 at 37; see also TPEIS-0702 at AR-065647.) Thus,

23 Environmental Plaintiffs’ statement that “there are no details about sage-grouse use of the

24 area” in the FEIS is simply inaccurate. (ECF No. 202 at 33.) And Federal Defendants’

25 response is similar—and similarly persuasive—as to pronghorn, where Federal

26 Defendants point out that the FEIS included discussion about how pronghorn use the

27 Project area, and explained that the Project will have an adverse impact on local

28 pronghorn. (ECF No. 237 at 37-39.) The Court agrees the FEIS included a sufficient, but

23
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 24 of 49

1 succinct, baseline for pronghorn. (TPEIS-0384 at AR-045586-87; see also TPEIS-0696 at

2 AR-065508 (showing how the Project is basically located at a connection point between

3 summer and winter pronghorn range).)

4 The same goes for springsnails. In response to Environmental Plaintiffs’ argument

5 that Federal Defendants’ springsnails baseline was deficient because it did not mention

6 their high risk of extinction and did not list the number of springsnails found in each spring

7 surveyed (ECF No. 202 at 34-35), Federal Defendants counter that they sufficiently

8 described a baseline for springsnails. (ECF No. 237 at 39, 39 n.84, 39 n.85.) The Court

9 agrees. The AR indicates both that BLM had baseline surveys conducted, and springsnails

10 were found in the springs surveyed. (TPEIS-0702 at AR-065642 (“Springsnails common

11 to the region were collected from some of the seeps, springs and wetlands in and around

12 the Project area (WRC 2018a; 2019a).”), id. at AR-065646 (describing springsnails

13 surveys conducted).) Environmental Plaintiffs argue for a more detailed baseline, but

14 proffer no pertinent caselaw in support of that argument, and fail to persuasively explain

15 how the springsnails baseline Federal Defendants constructed was statutorily deficient.

16 And here, unlike Great Basin Res. Watch, 844 F.3d at 1101, BLM used actual baseline

17 surveys. The Court accordingly finds Environmental Plaintiffs’ wildlife baseline NEPA

18 argument unpersuasive.

19 That brings the Court to Environmental Plaintiffs’ related argument that the FEIS

20 did not adequately analyze and disclose the Project’s long-term impact on wildlife. (ECF

21 No. 202 at 35-38.) But Environmental Plaintiffs argument here is not that the FEIS did not

22 discuss the Project’s potential impacts on wildlife—it did. (Id.) Indeed, Federal Defendants

23 point to that discussion—in the FEIS and its Appendix G—in their response. (ECF No. 237

24 at 39-40, 40 at n.86 (first citing TPEIS-0384 at AR-045581-614, then citing TPEIS-0702 at

25 AR-065641-49).) The Court overall agrees with Federal Defendants that their cited

26 portions of the FEIS contain a “a reasonably thorough discussion of the significant aspects

27 of the probable environmental consequences[,]” Half Moon Bay Fishermans’ Mktg. Ass’n

28 v. Carlucci, 857 F.2d 505, 508 (9th Cir. 1988), and are thus sufficient under NEPA.

24
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 25 of 49

1 Moreover, this portion of Environmental Plaintiffs’ argument is primarily based on

2 comments from NDOW on a preliminary version of the draft environmental impact

3 statement. (ECF No. 202 at 35 (relying on TPEIS-1114 at AR-097080 (though the correct

4 citation would be to AR-097079) and AR-097082-83; TPEIS-1493 at AR-108859).) But as

5 Federal Defendants also point out in response (ECF No. 237 at 40-41), BLM addressed

6 some of these comments during the environmental review process, which NDOW

7 acknowledged in subsequent comments submitted in response to the FEIS. (See, e.g.,

8 TEPIS-0384 at AR-048176 (“We appreciate the incorporation of our previous comments

9 and applaud the BLM for recognizing that the direct disturbance will result in loss of habitat,

10 displacement, and indirect effects to wildlife resulting from displacement.”).) Thus,

11 Environmental Plaintiffs’ argument based on NDOW’s comments is somewhat inflated

12 because it relies on comments submitted in response to preliminary documents that

13 NDOW even acknowledged were later (at least partially) addressed.

14 In addition, to the extent Environmental Plaintiffs and NDOW disagree with BLM’s

15 analysis of the longer term impacts of the Project on wildlife, that disagreement does not

16 necessarily constitute a NEPA violation. The Court “must also be mindful to defer to

17 agency expertise, particularly with respect to scientific matters within the purview of the

18 agency.” Klamath-Siskiyou Wildlands Ctr., 387 F.3d at 993. Analysis of impact of the

19 Project on wildlife over the longer term is also the sort of scientific matter on which the

20 Court must defer to BLM.

21 Turning to cumulative impacts, Federal Defendants counter that they satisfied their

22 obligations to conduct a cumulative-impacts analysis by identifying, describing, and

23 mapping the cumulative effects study area for each resource, identifying past, present,

24 and reasonably foreseeable future actions, and then describing the impacts of these other

25 projects in its detailed analyses of the Project’s cumulative impacts on various resources.

26 (ECF No. 237 at 43-44 (citing TPEIS-0384 at AR-045671-90).) The Court agrees with

27 Federal Defendants that the cumulative impacts analysis BLM provided in the FEIS was

28 sufficient, as BLM provided more thorough analysis in the pertinent portion of the FEIS

25
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 26 of 49

1 than the agencies provided in the decisions reviewed in the two primary cases upon which

2 Plaintiffs rely. (TPEIS-0384 at AR-045671-90; see also ECF No. 202 at 39-40 (relying on

3 Great Basin Mine Watch v. Hankins, 456 F.3d 955, 973 (9th Cir. 2006) and Great Basin

4 Res. Watch, 844 F.3d at 1104).)

5 For example, the Great Basin Mine Watch court found that a handful of “vague and

6 conclusory statements, without any supporting data” in the cumulative impacts section of

7 a final EIS did not constitute the requisite hard look under NEPA. 456 F.3d at 973. But

8 here, BLM provided pages of analysis of the cumulative impacts of the Project on various

9 resources supported by data, and at least did more than BLM did in Great Basin Mine

10 Watch. (TPEIS-0384 at AR-045671-90.) Similarly, the Great Basin Res. Watch court found

11 BLM erred because it “made no attempt to quantify the cumulative air impacts of the

12 Project together with the Ruby Hill Mine and vehicle emissions[,]” did not “attempt to

13 quantify or discuss in any detail the effects of other activities” affecting air quality, and

14 chose a baseline value of zero for certain pollutants without justification. 844 F.3d 1104-

15 06. In contrast, here, BLM attempted to quantify the air quality impacts of the Project

16 together with estimated emissions from all sources in Humboldt County.17 (TPEIS-0384 at

17 AR-045682-84 (incorporating by reference discussion and analysis of air quality impacts

18 of the Project (Section 4.9.1.1, Appendix K, and Table 4.12) into the broader discussion).)

19 BLM also did not use baseline pollutant levels of zero without justification. (TPEIS-0384 at

20 AR-045683 (“The resulting pollutant concentrations are reflected in the measured ambient

21 data which support the background concentrations used in the analysis (Section 4.9.1.1

22 and Appendix K.). Accordingly, the air quality effects of these past and present activities

23 are considered to be captured in the background concentrations.”).) Thus, the cumulative

24

25

26 17This discussion may fit more logically under the ‘air quality’ subheading because
of the Great Basin Res. Watch court’s focus on BLM’s air quality analysis but the Court
27 addresses and distinguishes Great Basin Res. Watch here because Environmental
Plaintiffs generally rely on this case in the cumulative impacts portion of their argument—
28 as to “wildlife, air quality, and other potentially affected resources.” (ECF No. 202 at 39.)
26
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 27 of 49

1 impacts analysis as to air quality in the FEIS was more detailed that the analysis found

2 insufficient in Great Basin Res. Watch.

3 As to the wildlife portion of Environmental Plaintiffs’ mitigation argument,

4 Environmental Plaintiffs argue that BLM ignored input from EPA and NDOW regarding the

5 purported lack of wildlife mitigation measures and noise impacts to sage grouse. (ECF No.

6 202 at 42-43.) Federal Defendants generally counter that BLM considered and responded

7 to the pertinent comments from both agencies, but was not required to agree with them,

8 and specifically counter that the comments upon which Environmental Plaintiffs rely for

9 this argument were made on the FEIS—so BLM did not have to consider them at all. (ECF

10 No. 237 at 48-49.) The Court again agrees with Federal Defendants. To the general point,

11 NEPA only requires that BLM consider and respond to criticisms and concerns raised by

12 other agencies during the environmental review process, as well as those from the general

13 public—but BLM is not required to agree with other agencies. See Ctr. for Biological

14 Diversity v. Bureau of Land Mgmt., 833 F.3d 1136, 1150 (9th Cir. 2016). And to the specific

15 point, Federal Defendants are correct that both parties’ comments on which Environmental

16 Plaintiffs rely post-date the FEIS, so BLM was not required to consider them.18 See

17 Japanese Vill., LLC v. Fed. Transit Admin., 843 F.3d 445, 467 (9th Cir. 2016) (“Appellees

18 were not required to accept public comments after publishing the FEIS.”) (citing 40 C.F.R.

19 § 1503.1(b)). (See also TPEIS-0695 at 1 (“EPA Comments on the Final Environmental

20 Impact Statement for the Thacker Pass Lithium Mine Project, Humboldt County, Nevada”),

21 TPEIS-0446 at AR-052420 (providing comments on FEIS and noting that they have

22 worked with BLM since 2018 on the planning process for the Project).)

23 In sum, the Court is unpersuaded by Environmental Plaintiffs’ NEPA arguments

24 regarding wildlife.

25 ///

26
27 18Moreover,the Court further addresses BLM’s engagement with EPA and NDOW
during the planning process in other portions of this order, finding BLM adequately
28 engaged with EPA and NDOW’s comments.
27
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 28 of 49

1 c. Groundwater

2 Environmental Plaintiffs also attack the adequacy of Federal Defendants’ analysis

3 as to the impact of the Project on groundwater, both to the extent that they did not

4 adequately consider the impacts of dewatering on local wildlife, and because Federal

5 Defendants adopted what Environmental Plaintiffs characterize as a ‘wait and see’

6 approach to mitigation of potential groundwater pollution. (ECF No. 202 at 35-37, 40-42.)

7 Environmental Plaintiffs further argue that Federal Defendants essentially ignored

8 comments from EPA regarding the insufficiency of the groundwater monitoring plan in the

9 FEIS. (Id. at 41-43.) Federal Defendants counter that they—contrary to Environmental

10 Plaintiffs’ argument—included a plan for monitoring potential contamination of

11 groundwater resources as an appendix to the FEIS, which also contemplated additional

12 monitoring and mitigation before mining operations could start. (ECF No. 237 at 45-47.)

13 As to the EPA’s comments, Federal Defendants argue that they adequately responded to

14 them, because they had no obligation to accept or adopt EPA’s comments. (Id. at 48-49.)

15 Lithium Nevada goes a bit farther, arguing that the adaptive management approach

16 Federal Defendants blessed in the FEIS is environmentally preferable. (ECF No. 240 at

17 37.) Indeed, Lithium Nevada argues, this approach makes sense because any impacts on

18 groundwater are speculative and will not occur for years, if at all. (Id. at 37-38.) The Court

19 again agrees with Federal Defendants.

20 Setting aside BLM’s responses to NDOW’s comments—addressed supra—the

21 Court construes Environmental Plaintiffs’ pertinent arguments as having two remaining

22 components. First, that the groundwater monitoring and mitigation plan BLM included in

23 the FEIS is inadequate, and second, that BLM did not sufficiently respond to EPA’s

24 comments.

25 Beginning with the groundwater monitoring and mitigation plan, the Court cannot

26 say that it is so inadequate as to violate NEPA under the governing deferential standard

27 of review. See Klamath-Siskiyou Wildlands Ctr., 387 F.3d at 993. And contrary to

28 Environmental Plaintiffs’ argument, the FEIS does contain a groundwater quality

28
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 29 of 49

1 monitoring and mitigation plan. (TPEIS-0384 at AR-045572-76; see also TPEIS-0711

2 (Appendix P).) Indeed, as Federal Defendants point out (ECF No. 237 at 46),

3 Environmental Plaintiffs appear to overlook the existence of the primary groundwater

4 quality mitigation and monitoring plan and instead challenge an additional groundwater

5 quality monitoring plan also described in the FEIS. (Compare TPEIS-0384 at AR-045572-

6 76 (describing various groundwater quality monitoring and mitigation requirements

7 imposed on Lithium Nevada) with TPEIS-0384 at AR-045574-75 (describing an additional

8 groundwater quality monitoring and mitigation plan that Lithium Nevada would prepare

9 “[i]n the event that constituent concentrations exceed established regulatory thresholds at

10 one or more established compliance monitoring points, and the exceedance is attributable

11 to contamination originating from mine facilities or operations.”).) Environmental Plaintiffs’

12 argument thus appears to miss that there are two groundwater quality monitoring and

13 mitigation plans described in the FEIS, not one—and that omission undermines their

14 argument. Moreover, the Ninth Circuit has upheld a “wait and see” approach to

15 groundwater quality monitoring “given the relatively low probability and temporal

16 remoteness of adverse impacts to ground water.” Great Basin Res. Watch, 844 F.3d at

17 1107. And according to the Water Quantity and Quality Impacts Assessment Report

18 attached as Appendix P to the FEIS, “[b]ecause the projected timeline is long, it is

19 anticipated that any mitigation action, if necessary, would not occur for years to decades

20 after closure.” (TPEIS-0711 at AR-066297.) Thus, Great Basin Res. Watch, 844 F.3d at

21 1107, applies here.

22 As to BLM’s responses to EPA’s comments, the Court concludes they were

23 sufficient. While Environmental Plaintiffs are correct that an agency may not simply ignore

24 comments from a cooperating agency, see W. Watersheds Project v. Kraayenbrink, 632

25 F.3d 472, 492-93 (9th Cir. 2011), an agency’s responses to a cooperating agency’s

26 comments are sufficient when, “the record indicates that BLM did indeed consider and

27 respond to criticisms and concerns raised by other agencies[.]” Ctr. for Biological Diversity,

28 833 F.3d at 1150. And the record here indicates that BLM considered EPA’s comments.

29
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 30 of 49

1 (See, e.g., TPEIS-0384 at AR-048166-68 (responding to EPA’s comments on the draft

2 environmental impact statement in an appendix of comments included as part of the

3 FEIS).) Environmental Plaintiffs’ citation of a letter EPA sent after BLM issued the FEIS

4 (TPEIS-0695) certainly indicates that EPA did not agree with some of BLM’s conclusions

5 and perhaps BLM’s decision to approve the Project, but BLM is not required to agree with

6 EPA, see Ctr. for Biological Diversity, 833 F.3d at 1150, and Environmental Plaintiffs’ focus

7 on EPA’s post-FEIS letter does not capture the full scope of the back-and-forth between

8 BLM and EPA throughout the environmental review process. (ECF No. 202 at 41-43

9 (making the argument).)

10 The Court is accordingly unpersuaded by Environmental Plaintiffs’ NEPA argument

11 regarding groundwater.

12 4. Summary as to Environmental Plaintiffs’ Claims

13 Environmental and Rancher Plaintiffs19 are entitled to summary judgment that

14 Federal Defendants violated FLPMA because BLM failed to first make a validity

15 determination under Rosemont before approving Lithium Nevada’s use of some 1300

16 acres of public land for waste dumps and tailings piles. Their motions for summary

17 judgment are accordingly granted on that issue, and Federal Defendants’ and Lithium

18 Nevada’s corresponding cross motions are accordingly denied. Environmental Plaintiffs’

19 motion for summary judgment is otherwise denied, and Federal Defendants’ and Lithium

20 Nevada’s cross motions are otherwise granted except as to the Rosemont issue.

21 B. Rancher Plaintiffs

22 Having already addressed Rancher Plaintiffs’ FLPMA claim in the section

23 addressing Environmental Plaintiffs’ FLPMA claims, along with Rancher Plaintiffs’ NEPA

24

25

26
27
of Rancher Plaintiffs’ joinder and because they make substantially the
19Because
28 same argument based on Rosemont.
30
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 31 of 49

1 claims to the extent they reflect their joinder of Environmental Plaintiffs’ claims,20 the Court

2 now addresses Rancher Plaintiffs’ remaining NEPA claim.21

3 Rancher Plaintiffs make several NEPA arguments that all turn on one core

4 contention—that the water resource baselines prepared by a contractor were inadequate,

5 failing to capture the true impact of the Project on nearby streams, springs, groundwater,

6 and the Lahontan Cutthroat Trout (“LCT”). (ECF No. 204 at 22-48.) Federal Defendants

7 essentially respond that Rancher Plaintiffs are asking the Court to impermissibly flyspeck

8 BLM’s environmental analysis, and Rancher Plaintiffs’ arguments as to data collection

9 methodologies and purported errors in data collection “do not demonstrate a NEPA

10 violation because the agency is entitled to heightened deference on matters of scientific

11 expertise and reasonably relied on the contractor’s analysis.” (ECF No. 238 at 13-14.)

12 Lithium Nevada echoes Federal Defendants’ basic argument. (ECF No. 241 at 7-9.) As

13 further explained below, the Court agrees with Federal Defendants in pertinent part.

14 In addition, at the Hearing, Rancher Plaintiffs argued this case is analogous to

15 Oregon Nat. Desert Ass’n v. Jewell, 840 F.3d 562 (9th Cir. 2016), and the FEIS and ROD

16 should be vacated and remanded based on Jewell’s application to this case. The Court

17 disagrees. At the outset, the Court notes that this is not a case like Jewell where the

18 pertinent FEIS relied on an assumption that was contradicted by a baseline survey. See

19 id. at 568-71. In Jewell, the FEIS assumed that no sage grouse were present at the site

20 of a wind farm when in fact that assumption overlooked a survey showing that some sage

21 grouse spent the winter there. See id. at 569. The Ninth Circuit accordingly found that

22

23 20That
said, Environmental Plaintiffs also joined Rancher Plaintiffs’ motion. (ECF
No. 211.) Thus, this discussion of Rancher Plaintiffs’ NEPA claim also applies to
24 Environmental Plaintiffs’ claim to the extent necessary to reflect that joinder.
25 21The APA and NEPA legal standards summarized supra apply to the discussion
of Rancher Plaintiffs’ NEPA claim infra as well. In addition, the factual background
26 pertinent to Rancher Plaintiffs’ motion is also the same as the factual background provided
towards the beginning of the Court’s discussion of Environmental Plaintiffs’ claims, with
27 the additional note that Rancher Plaintiffs actively participated in the Project’s
environmental review process, submitting comments on both the draft environmental
28 impact statement and the FEIS. (TPEIS-0388, TPEIS-0516, TPEIS-1499, TPEIS-0448.)
31
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 32 of 49

1 BLM’s assumption of no sage grouse present was arbitrary and capricious, and neither a

2 harmless error nor saved by the mitigation measures also adopted by the pertinent FEIS.

3 See id. at 569-71.

4 Here, in contrast, Rancher Plaintiffs do not argue that the water resource portions

5 of the environmental impact statements and ROD contradict the results of a baseline

6 study, instead arguing that the water resource baseline studies are wrong. (ECF No. 204

7 at 22-48.) This is also not a case where BLM failed to conduct a baseline study as to water

8 resources, as BLM did (see TPEIS-0384 at AR-046513 - AR-047130, TPEIS-0711 at AR-

9 066146-47, AR-067399-401, and TPEIS-081), and Lithium Nevada even had the water

10 resources contractor prepare memoranda specifically responding to concerns Rancher

11 Plaintiffs raised during the environmental review process similar to the arguments they

12 make now (see TPEIS-0403, TPEIS-0406). Moreover, this is not a case where BLM

13 concluded—like in Jewell—that there would be no impact to an important resource without

14 any basis. Indeed, BLM concluded there will be some impact on groundwater resources

15 (and the wildlife that depends on it) from the Project, both explaining those predicted

16 impacts and including mitigation measures intended to remedy them. (TPEIS-0384 at AR-

17 045554 - AR-045581.) The Court accordingly does not find that Jewell requires remand

18 and vacatur.

19 Turning to some of Rancher Plaintiffs’ more specific arguments, Rancher Plaintiffs

20 argue that the baseline seep and spring data lacks scientific and professional integrity

21 because the contractor who collected the data did not adhere to something called the

22 Stevens Protocol.22 (ECF No. 204 at 23, 25-30.) But the contractor, Piteau and Associates,

23 did not state it would follow the entire Stevens Protocol, instead specifying in its work plan

24 that its spring and seep inventory would use certain elements of Level 1 of the Stevens

25 Protocol. (TPEIS-0054 at AR-005702-03.) Thus, Rancher Plaintiffs’ argument that the

26 spring surveys did not follow the Stevens Protocol does not really apply and is

27
22The parties agree what the Stevens Protocol is and further explanation of it is not
28 strictly necessary for the Court’s analysis.
32
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 33 of 49

1 inconsequential. (ECF No. 204 at 36-40.) The same goes for Rancher Plaintiffs’ argument

2 that Piteau should have followed Levels 2 and 3 of the Stevens Protocol (id. at 35-36);

3 Piteau never said it was going to (TPEIS-0054 at AR-005702-03).23 Moreover, Federal

4 Defendants were not required to follow the Stevens Protocol in any event because NEPA,

5 “does not require adherence to a particular analytic protocol.” Oregon Nat. Desert Ass’n

6 v. Rose, 921 F.3d 1185, 1191 (9th Cir. 2019) (citation omitted).24

7 Rancher Plaintiffs otherwise argue that the baseline surveys regarding springs,

8 seeps, groundwater, and Pole Creek contain various inaccuracies such that Federal

9 Defendants’ environmental review lacks an adequate baseline—and accordingly the FEIS

10 underestimates the negative impact of the Project on local water resources. (ECF No. 204

11 at 40-46.) The Court finds that—at most—these arguments reflect a technical or scientific

12 disagreement on which the Court must defer to BLM. Indeed, Rancher Plaintiffs largely

13 rely on comments they submitted during the environmental review process, which in turn

14 rely on the comments of their expert, Dr. Erick Powell. (See, e.g., id. at 46 n.29 (citing

15 TPEIS-0516 at AR-056387).) Dr. Powell raised substantially the same points in comments

16 submitted to BLM during the environmental review process that Rancher Plaintiffs now

17 proffer, and BLM substantively responded to Dr. Powell’s comments, further suggesting

18

19 23Rancher Plaintiffs’ argument about trespass similarly is based on a principle from


the Stevens Protocol—consultation with pertinent private property owners before
20 conducting spring surveys (ECF No. 204 at 36-38)—that Piteau did not state it would follow
(TPEIS-0054 at AR-005702-03). And in any event, as Federal Defendants point out,
21 Rancher Plaintiffs have not shown, “how any alleged trespass affects the sufficiency or
accuracy of the baseline data or rises to the level of a NEPA violation, even if BLM were
22 aware of it—which [Rancher Plaintiffs have] not established.” (ECF No. 238 at 24.) There
is at most a dispute about whether Piteau trespassed, but even if that were the case, it is
23 unclear to the Court how that necessarily means the measurements collected at the two
springs subject to the trespass dispute are inaccurate or unreliable. That said, while
24 trespass is not an issue relevant to the Court’s review of BLM’s decision in this APA case,
the Court of course does not sanction trespass.
25
24Rancher Plaintiffs rely on this case to support their argument that Federal
26 Defendants violated NEPA by failing to comply with the Stevens Protocol (ECF No. 204 at
39-40), but the portion of Rose upon which they rely describes a situation where BLM said
27 it would do something—complete a prompt on Route Analysis Forms—but did not. See
Rose, 921 F.3d at 1192. In contrast, and as noted, Piteau never wrote it would entirely
28 follow the Stevens Protocol.
33
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 34 of 49

1 that Rancher Plaintiffs’ argument primarily reflects scientific or technical disagreement on

2 which the Court must defer to BLM. (TPEIS-0713 at AR-067655 - AR-067668.) Indeed,

3 the Court does not sit as a referee on a professional, scientific journal, but as a generalist

4 judge acting pursuant to congressionally delegated authority. See San Luis & Delta-

5 Mendota Water Auth. v. Jewell, 747 F.3d 581, 621 (9th Cir. 2014).

6 An unreported district court case upon which Rancher Plaintiffs rely illustrates why

7 their core NEPA arguments about the unreliability of the water baseline surveys are

8 ultimately unpersuasive, despite the italicization and overheated rhetoric throughout their

9 briefs. (ECF No. 204 at 38, 42 (citing League of Wilderness Defs./Blue Mountains

10 Biodiversity Project v. Connaughton, Case No. 3:12-CV-02271-HZ, 2014 WL 6977611, at

11 *21 (D. Or. Dec. 9, 2014) (“Blue Mountains”)).) The Blue Mountains court found that a

12 dispute about the agency’s estimated age of implicated Grand Fir trees was, “a situation

13 where experts differ in their testimony and the Court is being asked to guess if public

14 opinion would change based on adding several years to the average age of grand firs. In

15 such a situation, the Court defers to the agency and, therefore, there is no NEPA violation.”

16 Id. at *23; see also id. at *21-*23 (containing the rest of that court’s analysis). Similarly,

17 here, the Court can discern nothing more from Rancher Plaintiffs’ NEPA arguments than

18 a situation where they and their expert substantively disagree with BLM’s scientific and

19 technical conclusions regarding the water resource baselines and the predicted impacts

20 of the Project that flow from those baselines. This does not constitute a NEPA violation.

21 And to the extent Rancher Plaintiffs argue the ROD must be vacated because BLM

22 did not independently evaluate the data that Piteau collected and analyzed, the Court is

23 unconvinced. (ECF No. 204 at 25-28.) To the contrary, the AR shows that BLM

24 independently evaluated Piteau’s work and engaged in an iterative process to improve it.

25 (TPEIS-1022 (requesting underlying model dataset Piteau prepared for review), TPEIS-

26 1205 (providing comments on Piteau report), TPEIS-1131 at AR-097595-96 (“Dan Erbes

27 (BLM geohydrologist) and Patrick Plumlee (hydrology/geochemistry subcontractor to ICF)

28 have been working with Piteau and LNC with regard to these baselines as well as the

34
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 35 of 49

1 issues with the modeled effects on water quality and quantity…”), TPEIS-0986 (organizing

2 in-person meeting between Piteau and BLM employees), TPEIS-1013 (following up on in-

3 person meeting), TPEIS-1072 (passing comments back to Piteau), TPEIS-1330 (“The

4 revised water resources section in the 6/19/2020 Thacker Pass ADEIS constitutes a vast

5 improvement over the previous version and I only have a few comments (included

6 below).”), TPEIS-1411 (describing comments from Rancher Plaintiffs similar to the

7 arguments raised in their briefs, agreeing with Rancher Plaintiffs that some spring data

8 may have been collected from incorrect locations, but providing the opinion that the model

9 Piteau prepared is still useful, though could use some tweaking).)

10 Rancher Plaintiffs finally argue that BLM did not provide them with sufficient

11 information to engage in meaningful public comment (ECF No. 204 at 28-32), but as

12 Federal Defendants and Lithium Nevada detail in their responses, BLM engaged

13 extensively with Rancher Plaintiffs throughout all stages of the environmental review

14 process, and even after the FEIS issued (ECF Nos. 238 at 36-39, 241 at 16-22). And as

15 for Rancher Plaintiffs’ argument regarding the Biological Assessment about LCT (ECF No.

16 204 at 28-32), the Court agrees with Federal Defendants that the FEIS discussed the

17 potential impacts of the Project on LCT (FEIS-0384 at AR-045595), concluding the Project

18 would not affect nearby LCT, a conclusion consistent with the conclusion reached and

19 discussed in the Biological Assessment BLM shared with the United States Fish and

20 Wildlife Service (TPEIS-0480). The Court accordingly finds that the FEIS sufficiently

21 discussed the Project’s impacts on LCT such that BLM was not required to provide for

22 public comment on the Biological Assessment as to LCT. See Cascadia Wildlands v. U.S.

23 Forest Serv., 937 F. Supp. 2d 1271, 1278 (D. Or. 2013) (reaching analogous conclusion).

24 Moreover, the AR indicates that Rancher Plaintiffs made their view that the Project would

25 negatively impact LCT clear to BLM (see, e.g., TPEIS-1489 at AR-106684-85), reducing

26 the persuasiveness of Rancher Plaintiffs’ suggestion that they were unable to provide

27 comments to the effect that they believe the Project will have a negative impact on nearby

28 LCT because BLM did not permit them to comment on the Biological Assessment.

35
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 36 of 49

1 In sum, the Court may not “‘fly speck’ an EIS and hold it insufficient on the basis of

2 inconsequential, technical deficiencies[,]” Ass’n of Pub. Agency Customers, Inc. v.

3 Bonneville Power Admin., 126 F.3d 1158, 1184 (9th Cir. 1997) (citation omitted), despite

4 Rancher Plaintiffs’ vigorous invitation to do so. Rancher Plaintiffs’ motion for summary

5 judgment is denied to the extent based on its NEPA arguments, and Federal Defendants

6 and Lithium Nevada’s corresponding counter and cross motions are granted. However, as

7 noted, Rancher Plaintiffs’ motion is granted to the extent necessary to reflect that the Court

8 agrees with the FLPMA argument based on Rosemont, and as provided supra as to

9 Environmental Plaintiffs’ motion, Federal Defendants’ and Lithium Nevada’s motions are

10 denied to the extent they resist application of Rosemont.

11 C. Tribal Plaintiffs

12 RSIC and Burns Paiute Tribe bring essentially the same claim under the NHPA—

13 arguing that BLM should have consulted them before issuing the ROD, but did not—but

14 only Burns Paiute Tribe also brings a NEPA claim, arguing that BLM did not take the

15 requisite “hard look” at the impacts of the Project in terms of whether the Project area is

16 an area of contemporary cultural or religious significance to local tribes. The Court

17 accordingly discusses Tribal Plaintiffs’ NHPA claims together, and then addresses Burns

18 Paiute Tribe’s NEPA claim.25 In addition, the Court incorporates by reference its orders

19 denying Tribal Plaintiffs’ motions for preliminary injunction and denying reconsideration of

20 that decision because Tribal Plaintiffs’ pending motions focus on NHPA arguments the

21 Court has already addressed twice in the context of its likelihood of success on the merits

22 analysis—and Tribal Plaintiffs rely on the same evidence already addressed in these prior

23 orders to support their NHPA arguments.26 (ECF Nos. 92, 117.)

24 ///

25

26 25The NEPA legal standard described elsewhere in this order applies to Burns
Paiute Tribe’s NEPA claim.
27
26These orders also describe the pertinent factual background and legal standards
28 that apply to the Court’s NHPA analysis.
36
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 37 of 49

1 Building on that point, the Court has twice ruled that Tribal Plaintiffs may not assert

2 the interests of other tribes who were consulted on the Project to support their arguments.

3 (Id.) The Court will accordingly not address any arguments Tribal Plaintiffs make in their

4 pending motions based on that twice-rejected proposition, and explicitly incorporates its

5 reasoning from those prior orders on that point by reference here. (Id.) As to Burns Paiute

6 Tribe specifically, it makes some arguments based on letters sent by the tribes who were

7 consulted on the Project after the ROD issued, and based on one letter it sent after the

8 ROD issued. (ECF No. 203 at 28-29.) In addition to violating the Court’s prior rulings on

9 asserting the interests of non-party tribes, these arguments also ignore the Court’s

10 repeated prior rulings regarding the scope of the administrative record that the Court may

11 not—and will not—consider documents that post-date the ROD. (ECF Nos. 155 at 10-11,

12 275 at 5-7.) The Court accordingly declines to further address Burns Paiute Tribe’s

13 argument based on letters that post-date the ROD, some sent by non-party tribes.

14 As mentioned, the Court first addresses Tribal Plaintiffs’ NHPA claim and then

15 Burns Paiute Tribe’s NEPA claim.

16 1. NHPA

17 As noted, and as addressed in the Court’s pertinent prior orders (ECF Nos. 92,

18 117), Tribal Plaintiffs’ primary NHPA claim is that BLM’s decision not to consult them on

19 the Project was not reasonable nor made in good faith in violation of 36 C.F.R. §

20 800.2(c)(2)(ii)(A) (“It is the responsibility of the agency official to make a reasonable and

21 good faith effort to identify Indian tribes and Native Hawaiian organizations that shall be

22 consulted in the section 106 process.”). Federal Defendants counter that BLM’s decision

23 not to consult RSIC or Burns Paiute Tribe on the Project was reasonable and made in

24 good faith by offering a chronological narrative of its interactions with both tribes, which

25 led BLM to the understanding that neither tribe would want to be consulted on the Project.

26 (ECF No. 227.) The Court is ultimately persuaded by Federal Defendants’ argument that

27 BLM’s decision not to consult Tribal Plaintiffs on the Project was reasonable and made in

28 good faith based on the information BLM had at the time it initiated consultation for the

37
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 38 of 49

1 Project. In explaining its decision that BLM’s decision not to consult Tribal Plaintiffs was

2 reasonable, the Court follows Federal Defendants’ chronology offered in their briefing and

3 at the Hearing, addressing Tribal Plaintiffs’ objections and counterarguments as they arise

4 in the context of the narrative described infra.

5 In 2005, BLM began preparing for the ARMPA, a land use plan encompassing the

6 proposed Project area. See Notice of Intent To Prepare a Resource Management Plan

7 (RMP) and Associated Environmental Impact Statement (EIS) and Initiate the Public

8 Scoping Process, 70 FR 15348-01, 2005 WL 677030 (Mar. 25, 2005). As part of this

9 process, BLM prepared a document—now part of the AR—called the Ethnographic

10 Assessment, which was finalized in April 2006. (TPNHPA-0003 (filed under seal).)27 The

11 Ethnographic Assessment describes the reprehensible history of what it describes as the

12 first Euromericans’ forays into what is now Northern Nevada, killing vital game, ruining all

13 the best grassland, and killing Native Americans without provocation. (Id. at 13-16.) These

14 initial contacts developed into a series of battles and wars between the United States

15 government and the Native Americans who lived in this region that eventually led to the

16 present-day arrangement of recognized tribes and reservations. (Id. at 16-21.) This brutal

17 history likely informs the righteous indignation with which Tribal Plaintiffs approach this

18 case.

19 However, the Ethnographic Assessment also contains information that contributed

20 more directly to BLM’s decision not to consult Tribal Plaintiffs on the Project. Specifically,

21 several tribes identified sacred and massacre sites summarized in the Ethnographic

22 Assessment, but none of the tribes who spoke to BLM’s consultant who prepared the

23 Ethnographic Assessment identified the Thacker Pass area as either sacred or a

24 massacre site. (See generally id.) RSIC’s Cultural Resource Coordinator Michon Eben

25 attended a meeting in Nixon, Nevada and offered comments and concerns on behalf of

26
27 27Apparently
Federal Defendants were unable to bates-stamp this document, so
the pages referenced are the pages in the PDF document.
28

38
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 39 of 49

1 RSIC reflected in the Ethnographic Assessment. (Id. at 95-96.) Burns Paiute Tribe

2 apparently did not respond to any letters requesting consultation on the Ethnographic

3 Assessment, but Charisse Snapp, identified in the Ethnographic Assessment as the tribe’s

4 Cultural Resource Representative, is recorded as having said on a telephone call on July

5 28, 2005, that Burns Paiute Tribe, “would defer consultation to the tribes that had

6 reservations closer to the study area.”28 (Id. at 100.) “She said that it would not be

7 necessary to keep the tribe on the mailing list for the RMP/EIS.” (Id.)

8 In 2015, RSIC sent BLM a letter explaining its official area of cultural interest, where

9 it expected to be consulted on all projects, and otherwise reserved its rights to request

10 consultation on projects falling outside that area. (TPNHPA-0034.) As the Court discussed

11 this letter and its reading of it extensively in one of its prior orders, the Court again explicitly

12 incorporates by reference that discussion here. (ECF No. 92 at 11-13.) As noted in that

13 order as well, RSIC never requested consultation on the Project until after the ROD issued,

14 so the reservation of rights to consult on other projects outside RSIC’s official area of

15 cultural interest described in the letter does not affect the Court’s analysis. (ECF No. 205

16 at 14-15, 19-21 (arguing to the contrary).) Moreover, RSIC’s argument that there is

17 insufficient evidence in the AR that a specific employee viewed the letter and made

18 decisions based on it is unpersuasive because the letter is part of the AR, and therefore

19 the Court must presume it was before BLM when BLM decided not to consult RSIC. See

20 Goffney v. Becerra, 995 F.3d 737, 748 (9th Cir.), cert. denied, 142 S. Ct. 589 (2021) (“[A]n

21 agency’s statement of what is in the record is subject to a presumption of regularity.”);

22 Pac. Choice Seafood Co. v. Ross, 976 F.3d 932, 942 (9th Cir. 2020) (stating that the AR

23 includes, “everything that was before the agency pertaining to the merits of its decision.”)

24 (citation omitted).

25
28Charisse Snapp submitted a declaration with Tribal Plaintiffs’ reply (ECF No. 259)
26 in which disputes that she was authorized to speak on Burns Paiute Tribe’s behalf, but the
Court cannot consider this declaration as it post-dates the ROD and is not part of the AR.
27 (ECF Nos. 155 at 10-11, 275 at 5-7.) And regardless, she does not dispute that she had
the phone conversation with BLM’s consultant who prepared the Ethnographic
28 Assessment summarized in the document.
39
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 40 of 49

1 Thus, the records before the BLM show that both Tribal Plaintiffs indicated to BLM

2 that they did not wish to be consulted on projects being considered in a geographic area

3 encompassing the Project—Burns Paiute Tribe in response to invitations to participate in

4 the Ethnographic Assessment, and RSIC in a letter it mailed to BLM. And between 2010

5 and 2017, BLM consulted with tribes (including, in one instance, RSIC) on four projects

6 implicating the Project area, but BLM did not learn from any of those consultations either

7 that Tribal Plaintiffs had a special interest in the Thacker Pass area, or that the Thacker

8 Pass area was religiously or culturally significant to them. (ECF No. 227 at 31-33 (citing

9 the AR).)

10 When it came time to initiate the NHPA process for the Project,29 and as otherwise

11 noted as to the NEPA process, BLM published a notice in the Federal Register. See Notice

12 of Intent To Prepare a Draft Environmental Impact Statement and Resource Management

13 Plan Amendment, for the Lithium Nevada Corp., Thacker Pass Project Proposed Plan of

14 Operations and Reclamation Plan Permit Application, Humboldt County, Nevada, 85 FR

15 3413-02, 2020 WL 279646 (Jan. 21, 2020) (“This notice announces the beginning of the

16 scoping process to solicit public comments and identify issues to be considered in the EIS,

17 and serves to initiate public consultation, as required under the National Historic

18 Preservation Act (NHPA).”). There is no dispute here that neither of Tribal Plaintiffs

19 requested consultation on the Project until after the ROD issued. And this publication

20 renders unpersuasive RSIC’s argument that BLM provided insufficient public notice of the

21 NHPA process for the Project (ECF No. 205 at 3, 8-10, 16-19), because “[p]ublication in

22 the Federal Register is legally sufficient notice to all interested or affected persons

23 regardless of actual knowledge or hardship resulting from ignorance.” Shiny Rock Min.

24 Corp. v. United States, 906 F.2d 1362, 1364 (9th Cir. 1990) (citation omitted).

25

26 29The NHPA process has several components, see WildEarth Guardians v.


Provencio, 923 F.3d 655, 676-77 (9th Cir. 2019); Montana Wilderness Ass’n v. Connell,
27 725 F.3d 988, 1005-06 (9th Cir. 2013), but, again, Tribal Plaintiffs only challenge the
decision not to consult them before issuing the ROD, and not the other steps of the NHPA
28 process.
40
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 41 of 49

1 BLM also sent consultation letters to the Fort McDermitt Paiute and Shoshone

2 Tribe, the Summit Lake Paiute Tribe, and the Winnemucca Indian Colony on December

3 12, 2019. (TPNHPA-0010, TPNHPA-0011, TPNHPA-0012.) There is also no dispute that

4 these three tribes did not respond to the consultation letters before the ROD issued.

5 In addition, BLM consulted with the Nevada State Historic Preservation Office

6 (“Nevada SHPO”), as required by NHPA. (TPNHPA-0001.) Nevada SHPO responded

7 some time later indicating that all of its concerns had been addressed, concurring that

8 BLM had initiated tribal consultation, and declining to identify any additional tribes (such

9 as Tribal Plaintiffs) with whom BLM should have consulted. (TPNHPA-0036.) This fact

10 further supports a finding that BLM’s decision not to consult with RSIC and Burns Paiute

11 Tribe before issuing the ROD was reasonable. See Ctr. for Biological Diversity v. United

12 States Army Corps of Engineers, Case No. CV 14-1667 PSG (CWX), 2015 WL 12659937,

13 at *21 (C.D. Cal. June 30, 2015), aff’d sub nom. Friends of Santa Clara River v. United

14 States Army Corps of Engineers, 887 F.3d 906 (9th Cir. 2018) (finding that the Army Corps

15 of Engineers’ decision not to consult the Santa Ynez Band was reasonable in part because

16 the California “SHPO did not advise the Corps to contact the Santa Ynez Band”).

17 At the Hearing, Federal Defendants also directed the Court’s attention to an email

18 sent by Tanner Whetstone, one of the BLM employees responsible for tribal consultation

19 on the Project, where he retroactively described the factors he considered in

20 recommending to the responsible official which tribes to consult with for the NHPA review

21 process regarding the Project. (TPNHPA-0047.)30 He describes those factors as

22

23 30The Court includes the full text of the email in this footnote, below, because it is
pertinent to the Court’s analysis.
24
David Kampwerth or I may need to be in this side-meeting that was proposed
25 in the call today. I say may because I can’t really tell if the folks are
26 concerned about reaching out to Pyramid lake Paiute Tribe about the project
or if they just want to analyze the potential impacts to PLPT, if any. If it’s the
27 latter one of us probably needs to be on the call. Not to be rude to the folks
on the call, but decisions about how the BLM consults with tribes are made
28

41
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 42 of 49

1 geographical proximity, historical ties, and whether a particular tribe had previously

2 indicated an interest in the Project area. (Id.) He also uses the phrasing reasonable and

3 good faith in several instances, suggesting he was aware of the pertinent regulation’s

4 requirements and attempted to comply with them. (Id.) The Court infers from this email—

5 part of the AR—that Whetstone decided not to consult Tribal Plaintiffs on the Project

6 because they lacked geographic proximity or historical ties to the Project area and had not

7 otherwise expressed an interest in it. And this inference is consistent with the other

8 evidence before the Court and described supra.

9 RSIC’s counsel attempted to cast doubt on the probative value of this email at the

10 Hearing by pointing out that it was sent in May 2020, or long after BLM started the

11 consultation process pertinent to the Project, but the Court’s reading of the email suggests

12 that Whetstone was describing why he did not recommend consultation with the Pyramid

13 Lake Paiute Tribe—and also described the factors that led to his recommendation about

14 which tribes to consult—at the time that he made his consultation recommendations. He

15 was not writing in the present tense. Thus, the fact that he sent the email long after

16 consultation began is immaterial. Moreover, these factors—particularly absent any

17

18
by authorized officers and tribes, not partners or BLM employees. I work with
19 our managers on a project-specific basis to help them determine which tribes
to reach out to in order to meet our reasonable and good faith effort to
20 consider tribal concerns. In this case, based on my input the HRFO Field
Manager David Kampwerth determined that the BLM would consult with Fort
21
McDermitt Paiute and Shoshone Tribe, Winnemucca Indian Colony, and
22 Summit lake Paiute Tribe. The Pyramid Lake Paiute Tribe is located 120
miles from the project area and to our knowledge has not concerned itself
23 with the Thacker Pass area before, and historically did not have ties to the
Thacker Pass area, therefore it was determined not to reach out to them. If
24 there’s a concern that traffic generated from the project may have
implications for PLPT or impact resources that are of concern to PLPT, then
25
I have no issue discussing it with our management and conducting any
26 additional outreach/consultation that they see fit, but I’ll need to know that
soon to make a meaningful effort considering the Draft EIS comes out in a
27 month.
28 (TPNHPA-0047.)
42
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 43 of 49

1 caselaw to the contrary—are reasonable factors to use in deciding which tribes to consult

2 on a particular project. And this email supports Federal Defendants’ argument that it was

3 reasonable not to consult Tribal Plaintiffs on the Project because they lacked geographical

4 proximity and historical ties to the Project area, and had never affirmatively indicated an

5 interest in the Project area. Indeed, as described supra, they effectively did the opposite

6 by opting out of consultation on projects in the geographic area of the Project.

7 More broadly, all of this evidence supports the Court’s finding that BLM’s decision

8 not to consult with Tribal Plaintiffs before issuing the ROD was reasonable and made in

9 good faith within the meaning of 36 C.F.R. § 800.2(c)(2)(ii)(A). The Court tentatively made

10 that decision in connection with Tribal Plaintiffs’ motions for preliminary injunction, and

11 makes the same decision on the merits now.

12 The Court also notes that the gist of Tribal Plaintiffs’ contrary argument has no

13 limiting principle. The gist seems to be that BLM must consult every tribe on every project.

14 But Tribal Plaintiffs do not quite argue that BLM must consult every tribe on every project,

15 and must persist in repeated contact even when faced with silence or affirmative

16 indications that a particular tribe does not wish to be consulted on projects in a particular

17 area. Tribal Plaintiffs likely do not quite make that argument because it is not the law. And

18 Tribal Plaintiffs offer no analogous caselaw (much less any binding precedent) to support

19 their argument that BLM should have consulted more tribes, including them, on this

20 Project. It is instead the law that the responsible BLM employee must make a reasonable

21 and good faith effort to identify which tribes to consult with. See 36 C.F.R. §

22 800.2(c)(2)(ii)(A). BLM made the requisite effort.

23 This distinction also applies to Tribal Plaintiffs’ more specific arguments that they

24 are both descended from Northern Paiutes forcibly dispersed from land including the

25 Project area, and that the Thacker Pass area contains features like water and rock

26 outcroppings sacred to them—so BLM should have consulted them. As Federal

27 Defendants respond, these arguments are insufficiently linked to Tribal Plaintiffs, such that

28 “BLM would have had reasonable notice that [Tribal Plaintiffs] had a relationship with

43
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 44 of 49

1 places of cultural or religious significance in the Thacker Pass area” (ECF No. 227 at 40)—

2 particularly considering the evidence to the contrary discussed supra. Or perhaps the more

3 honest answer is that the Court lacks the authority to equitably right historical wrongs

4 perpetrated against Tribal Plaintiffs in the context of the deferential review it is required to

5 conduct of a single decision BLM employees made constituting Tribal Plaintiffs’ legal claim

6 here, especially where the pertinent statute does not require any particular outcome. See

7 Connell, 725 F.3d at 1005 (“Section 106 of NHPA is a ‘stop, look, and listen’ provision that

8 requires each federal agency to consider the effects of its programs.”) (citation omitted).

9 In sum, BLM made a reasonable decision not to consult RSIC or Burns Paiute Tribe

10 on the Project before issuing the ROD. BLM did not violate NHPA in making that decision.

11 Tribal Plaintiffs’ motions are accordingly denied as to this claim, and Federal Defendants’

12 and Lithium Nevada’s cross motions are correspondingly granted.

13 2. NEPA

14 Setting aside evidence that post-dates the ROD and is thus not properly part of the

15 AR, Burns Paiute Tribe’s NEPA claim is that the FEIS did not discuss current uses of the

16 Project area by tribes or the area’s significance to local tribes.31 (ECF No. 203 at 30.)

17 However, as Federal Defendants counter (ECF No. 227 at 49, 49 n.133), the FEIS

18 incorporated by reference the Previous Cultural Resources Inventories in Appendix J

19 (TPEIS-0384 at AR-045630), which included the Class III Inventory of 12,963 Acres for

20 Lithium Nevada’s Thacker Pass Project, Humboldt County, Nevada for Lithium Nevada’s

21 Thacker Pass Project, Humboldt County, Nevada (TPEIS-0705 at AR-065807), which, in

22 turn, includes an explanation of how the area near the Project area was used by bands of

23 Northern Paiutes from around the middle of the 19th century through present (TPEIS-0269

24

25

26 31This argument accordingly also runs afoul of the Court’s ruling that the Burns
Paiute Tribe cannot assert the interests of third-party tribes based on the prudential
27 prohibition against allowing one to assert the legal interests of another known as the third
party standing doctrine, but the Court summarizes Burns Paiute Tribe’s argument here as
28 the Burns Paiute Tribe makes it in an attempt at clarity.
44
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 45 of 49

1 (filed under seal) at AR-035386-87). Thus, Burns Paiute Tribe’s NEPA argument is based

2 on either an oversight or an incorrect premise.

3 To the extent Burns Paiute Tribe more generally argues that BLM failed to take the

4 requisite hard look by failing to specifically consider the impact of the Project on historic

5 and cultural resources, the Court is unpersuaded. (ECF No. 203 at 30.) To the contrary,

6 the Court agrees with Federal Defendants that they “took the requisite hard look at the

7 potential impacts to cultural resources from the Thacker Pass Project.” (ECF No. 227 at

8 44; see also id. at 44-50 (supporting the statement).)

9 More specifically, BLM reviewed 38 cultural resource inventories conducted over

10 49 years that investigated the Project area (both mining and exploration), along with the

11 area of indirect effects. (TPEIS-0705 at AR-065805 - AR-065807.) These inventories

12 included a 2018 survey that inventoried 12,963 acres for the Project. (TPEIS-0269.) This

13 was a Class III inventory (see generally id.), meaning that it was an:

14
“[i]ntensive” survey that involve[d] “a professionally conducted, thorough
15 pedestrian survey of an entire target area ... intended to locate and record
16 all historic properties” and that “provides managers and cultural resource
specialists with a complete record of cultural properties.” BLM Manual
17 8110.2.21.C.1, C.3. This alternative requires an on-the-ground survey of the
entire subject area. The Manual explains that an “[i]ntensive survey is most
18 useful when it is necessary to know precisely what historic properties exist
in a given area.” BLM Manual 8110.2.21.C. The Class III survey is the most
19 frequently employed method of inventory. See BLM Manual 8110.2.21.
20

21 Connell, 725 F.3d at 1006. This and the prior inventories identified that the Project would

22 negatively impact some 1000 cultural resource sites, including 56 eligible for inclusion on

23 the National Register of Historic Places. (See generally TPEIS-0269.)

24 And BLM considered all of this in the FEIS. (TPEIS-0384 at AR-045630-33.) To

25 somewhat mitigate the harm to cultural properties that BLM stated the Project would

26 cause, BLM chose “an approved Historic Properties Treatment Plan (HPTP), currently in

27 development.” (Id. at AR-045633.) BLM also noted in this portion of the FEIS that the tribal

28 consultation to which had engaged up to that point in time had not yielded any concerns,

45
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 46 of 49

1 but also stated that it would engage in more tribal consultation before issuing the final

2 HPTP, along with consulting with the Nevada SHPO. (Id.)

3 Under the deferential standard of review, see Great Basin Res. Watch, 844 F.3d at

4 1101, BLM took a hard enough look at the Project’s impacts on cultural and historical

5 resources, and the Court’s review must accordingly end, see id. The NEPA portion of

6 Burns Paiute Tribe’s motion is accordingly denied, and Federal Defendants’ and Lithium

7 Nevada’s competing motions are granted to a corresponding extent.

8 D. Remand and Vacatur

9 “The remaining issue is whether to vacate the [ROD] or remand while leaving the

10 [ROD] in place.” Pollinator, 806 F.3d at 532. While the parties did not extensively brief this

11 issue, the Court heard extensive argument on it at the Hearing after informing the parties

12 it was interested in hearing such argument in advance of the Hearing. (ECF No. 276.) The

13 Court also stated at the Hearing, primarily in response to Federal Defendants’ request,

14 that it would only permit further briefing on this question if it found it necessary. The Court

15 does not so find.

16 The Court may only order remand without vacatur in limited circumstances, and

17 only when equity so demands. See Pollinator, 806 F.3d at 532. The Court must generally

18 weigh the seriousness of the agency’s errors against the disruptive consequences of

19 vacating the ROD. See id. Examples of where it is appropriate to remand without vacatur

20 include situations where environmental harm will result from vacatur, and situations where

21 the Court reasonably expects the agency could reach the same result on remand but either

22 offer better reasoning or comply with procedural rules to essentially fix the error the Court

23 has identified in its review. See id.

24 The Court finds that this is the rare case where remand without vacatur is

25 appropriate because, as described supra in the section of the order addressing Rosemont

26 in depth, BLM could fix the error—it could find on remand that Lithium Nevada possesses

27 valid rights to the waste dump and mine tailings land it intends to use for the Project. There

28 is at least some evidence in the record of sufficient lithium mineralization in those land

46
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 47 of 49

1 such that BLM could find Lithium Nevada had discovered ‘valuable mineral deposits’ in

2 them.32 This is accordingly the rare case where BLM could fix its Rosemont issue on

3 remand and still reach the same outcome that it reached in the ROD. Said otherwise, this

4 case presents a situation like the situation where remand without vacatur was found

5 appropriate in Allied-Signal, 988 F.2d at 151 (“there is at least a serious possibility that the

6 Commission will be able to substantiate its decision on remand”), described as a situation

7 where remand without vacatur would be acceptable in Pollinator, 806 F.3d at 532.

8 Moreover, as also described supra, the Rosemont argument the Court agrees with

9 only applies to the waste dump and mine tailings land subject to the mining plan of

10 operations, and not the exploration plan of operations at all. The ROD approved both

11 plans. In addition, the Court does not find that Plaintiffs or Plaintiff-Intervenors prevail on

12 any of the several other claims they advanced in this case. Thus, BLM substantially

13 complied with the applicable legal requirements here. This too suggests remand without

14 vacatur is appropriate. See Ctr. for Food Safety v. Regan, 56 F.4th 648, 664 (9th Cir.

15 2022) (“EPA’s failure to comply with FIFRA’s notice and comment requirement also does

16 not warrant vacatur, ‘especially in light of’ EPA’s ‘substantial compliance’ with FIFRA.”)

17 (citation omitted). And Rosemont did not issue until well after the ROD issued in any event.

18 Thus, remand with vacatur would be inequitable because it would sweep in many aspects

19 of the ROD as to which the Court identified no issue, and would not acknowledge that

20 would be unfair to expect BLM to follow Rosemont—in contravention of its own

21 regulations—before Rosemont had issued.33

22

23 32As noted supra, Federal Defendants and Lithium Nevada also argue the Project
already complies with the ARMPA in any event, but the Court need not—and does not—
24 reach that argument.
25 33Lithium Nevada also argues that “the disruptive impact of vacatur would be
severe” because “there is no other U.S. alternative to the Project that provides the scale,
26 grade, or timeline to production required to keep pace with transportation electrification
and carbon reduction, in addition to providing lithium products needed for national
27 security.” (ECF No. 242 at 48.) This argument finds at least some support in binding
precedent. See California Communities Against Toxics v. U.S. E.P.A., 688 F.3d 989, 993-
28

47
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 48 of 49

1 IV. CONCLUSION

2 The Court notes that the parties made several arguments and cited to several cases

3 not discussed above. The Court has reviewed these arguments and cases and determines

4 that they do not warrant discussion as they do not affect the outcome of the motions before

5 the Court.

6 It is therefore ordered that Environmental Plaintiffs’ motion for summary judgment

7 (ECF No. 202) is granted in part, and denied in part, as specified herein.

8 It is further ordered that the Burns Paiute Tribe’s motion for summary judgment

9 (ECF No. 203) is denied as specified herein.

10 It is further ordered that Rancher Plaintiffs’ motion for summary judgment (ECF No.

11 204) is granted in part, and denied in part, as specified herein.

12 It is further ordered that RSIC’s motion for summary judgment (ECF No. 205) is

13 denied as specified herein.

14 It is further ordered that Lithium Nevada’s counter motion for summary judgment

15 (ECF No. 241) as to Rancher Plaintiffs’ claims is granted in part, and denied in part, as

16 specified herein.

17 It is further ordered that Lithium Nevada’s cross motion for summary judgment (ECF

18 No. 242) as to Environmental Plaintiffs’ claims is granted in part, and denied in part, as

19 specified herein.

20 It is further ordered that Federal Defendants’ cross motions for summary judgment

21 (ECF Nos. 227, 237, 238) are granted in part, and denied in part, as specified herein.

22 It is further ordered that Lithium Nevada’s cross motions for summary judgment as

23 to Tribal Plaintiffs’ claims (ECF No. 230) are granted as specified herein.

24 It is further ordered that this case is remanded—but without vacatur of the Record

25 of Decision—to BLM to determine whether Lithium Nevada possesses valid rights to the

26
27 94 (9th Cir. 2012). However, the Court declines to reach this argument because it does
not need to in order to adequately support its decision that remand without vacatur is
28 appropriate here.
48
Case 3:21-cv-00080-MMD-CLB Document 279 Filed 02/06/23 Page 49 of 49

1 waste dump and mine tailings land it intends to use for the Project to support BLM’s

2 decision to issue the ROD described herein.

3 The Clerk of Court is directed to enter judgment accordingly and close this case.

4 DATED THIS 6th Day of February 2023.

6
MIRANDA M. DU
7 CHIEF UNITED STATES DISTRICT JUDGE
8

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26
27

28

49

You might also like