IKDC-BINKEI-FP-SAT-RFA-069 FA, Gas Suppression, Pre-Action
IKDC-BINKEI-FP-SAT-RFA-069 FA, Gas Suppression, Pre-Action
No: IKDC-BINKEI-FP-SAT-RFA-067
Indonesia Area : Revision: 04
DUBNIUM IKDC PROJECT
WORK COMPLETION
To be signed by the Commissioning Authority indicated below after this functional test procedure has been
witnessed. The Commissioning Authority certifies that the recorded results are accurate and determines that
the equipment and System is:
_______________________________________________________
Commissioning Authority Date
Commissioning Authority
T&C Leader
BMS Representative
Construction Manager
Owner’s Representative
TEST INFORMATION
1. GENERAL
Verify Functional Test of Fire Systems; Fire Alarm, Gas Suppression and PreAction Sprinkler
System. This test procedure is to record each of test results during the windows time of testing.
Refer to the updated Punchlist and future DCRs for status of open items.
1.3. Reference
k. SNI 03-3985-2000; Prosedur untuk Perencanaan, Instalasi, dan Pengetesan Sistem Deteksi
Fire Alarm untuk Mencegah Bahaya Kebakaran Saat Pembangunan.
l. KEPMEN PU No. 10 / KPTS / 2000 Part 2 Fire Detection and Fire Alarm System.
Status
Description
(If NO or YES)
Fire Detection System has been started up and the associated start up reports and
construction checklists, if applicable, are available on site for review, all indicating that the Y N
unit is ready for site acceptance testing
Gas Suppression System has been started up and the associated start up reports and
construction checklists, if applicable, are available on site for review, all indicating that the Y N
unit is ready for site acceptance testing
PreAction Sprinkler System has been started up and the associated start up reports and Y N
construction checklists, if applicable, are available on site for review, all indicating that the
These site acceptance test procedures, as revised, are assumed to have been reviewed by the
Y N
installing contractor and the Engineer of Record or their authorized representative.
It is declared that all sensors are calibrated, programming debugged, and loop tuning has
Y N
been completed.
Prior to Test, The Main Wet Pipe System is temporarily isolated off from feeding to
Y N
PreAction Sprinkler
Prior to Test, Gas Kits are temporarily disconnected off from the Manifold; Replace with
Y N
Lamp Indicator
The CxA has determined that the equipment is ready for testing and construction conditions
Y N
permit a safe and potentially successful execution of the procedure.
All present and/or vested parties are well informed and the planned testing is highly coordinated to
prevent the accidental deployment of any fire suppression or extinguishing system that may cause
disruption to a live data center or damage to any equipment. Methods of testing detectors,
suppression system, damper operations, and all associated alarms and notifications must be agreed
upon and authorized by facility owner representation. The following system set points, control
parameters, limits, delays, lockouts, schedules, etc. changed to accommodate testing. Check when
returned to normal values.
A. Test Equipment
Quantity
Item Responsibility
(sets)
Aerosol Smoke Sampler and Test Injector Fire System Contractor 10
Quantity
Item Responsibility
(sets)
Extending Test Stick applicator Fire System Contractor 2
Portable Electrical Toolset Fire System Contractor 2
Digital Multi-meter Fire System Contractor 2
Ladders, lifts, etc. Fire System Contractor 2
VS4 Panel Fire System Contractor 1
Camera Recorder Fire System Contractor 2
Stopwatch Fire System Contractor 2
Pipe Fitters toolset, etc. Fire System Contractor 1
Sound level dB Meter Fire System Contractor 2
Police Lines Fire System Contractor 20
Vacuum Cleaner Fire System Contractor 2
Cleaner Fire System Contractor 15
Safety glasses.
Safety shoes.
Safety vest.
Approved ShopDWG.
Certificates of Caliberation of Toolset used
Copies of Approved Work Method of Statement on how to test
Test Forms
Approved Level 3 Checklist
List of ManPower for Test & Commissioning & Assignment Mapping vs Roles
PIC Names/Numbers must be stationed to following sites;
Level 2 NOC
Level 1 FACC Room
Level 1 Testing Scene Venue
Level 1 Preaction Valve Room
Level 1 Gas Room
Level 1 Drain Discharge Test Assembly Point
UnderGround Fire Pump Room
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2.3. Main Fire Alarm Control Panel (MFACP)
Note: Application of canned test smoke is not a measureable or precise method. Therefore, every
effort to verify each level of detection should be made within reasonable environmental and testing
personnel limitations as determined by the CxA. It may not be possible to simulate every alarm at
every monitoring station.
1. Introduce a ground condition to at least one “Trouble” alarm on local FACP,
Y N
circuit Bldg MFACP, and Fire Network
“Trouble” alarm sent to BMS Y N
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2.4. Ionization & Photoelectric Smoke Detector Operation
Note: Application of canned test smoke is not a measureable or precise method. Therefore, it is
preferred that the testifier pole system is the preferred method of testing of automatic fire
detectors, if this cannot be accomplished, every effort to verify each level of detection should be
made within reasonable environmental and testing personnel limitations as determined by the CxA. It
may not be possible to simulate every alarm at every monitoring station.
“Trouble” alarm on local FACP,
1. Remove detector from base Y N
Bldg MFACP, and Fire Network
2. Return head to base Alarm clears. Y N
3. Spray the smoke tester into the detector to “Trouble” alarm on local FACP,
Y N
activate the alarm. Follow smoke Bldg MFACP, and Fire Network
manufacturer’s recommended distance from Zone Address is correct Y N
detector and duration of blast.
“Trouble” alarm sent to BMS
Y N
A/V Indicator Alert 1 activate
Y N
4. Verify that alarm clears All alarms clear Y N
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2.7. Gas Suppression Test with Battery Panel (Supply Power Fail)
Before testing the Suppression system, make sure all have PPE and the area is
1. Y N
protected.
Before starting the Suppression System testing, the contractor must invite a
2. Y N
construction management representative.
3. Prepare tools for testing. Y N
Unplug one of the power battery cables, to find out whether the battery is active or
4. Y N
not.
5. Turn off MCP power supply and FACP panel. Y N
6. Check the condition of the battery using a multitester. Y N
7. Check the status of the FACP panel when running using the Battery panel. Y N
After the FACP is in good or normal condition, do the suppression system test
8. Y N
using the battery for approximately 1 hour maximum and using smoke tester.
Triggered only one Smoke Detector by used aerosol smoke tester : INERGEN
9. FACP will indicate the signal as first level alarm. Bell, and Warning Lamp Y N
Evacuate active. Solenoid Actuator is not active.
Triggered the second Smoke Detector by used aerosol smoke tester : INERGEN
FACP will indicate the signal as second level alarm and count down for 30
seconds before activate the solenoid actuator. Horn/Strobe, Bell, and Warning
10. Y N
Lamp active. Horn/Strobe, Bell, and Warning Lamp active. Solenoid actuator
active after 30 seconds since second level alarm active and count the time using
the stopwatch. Notification in BMS system, buzzer active.
Press and hold the “Abort Switch” button when the second level alarm is active :
Abort switch only functioned before 30s count down time is over. Horn/Strobe,
11. Y N
Bell, and Warning Lamp is continue active. The countdown time is stop at 10
second and solenoid Actuator is not active.
Remove the pressed from the “Abort Switch” button : Horn/Strobe, Bell, and
12. Warning Lamp is continue active. INERGEN FACP will continue the countdown Y N
timer at 10 seconds before activating the actuator solenoid.
Remove smoke from detector, clean detector, Acknowledge Status at FACP:
13. Y N
Smoke detector is normalized
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2.7 Gas Suppression Test with Battery Panel (Supply Power Fail)
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
14. Reset the solenoid actuator: Solenoid actuator is standby (normal). Y N
Reset panel: System will be standby and normal and BMS system normal
15. Y N
condition
16. Before leaving the room, clean all areas as before. Y N
After everything is finished, immediately make a test report signed by the Sub-
17. Y N
contractor, Contractor and Construction Management.
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2. 9 Pre-action Sprinkler System Operation
3. Slowly open the dry pipe drain line to The “Low Pressure Trouble” alarm
reduce the pressure in the pipe enough to for the correct zone comes up on
Y N
activate the first stage low pressure alarm the local FACP and other building
and energize the automatic air compressor. FACP’s
Record the pressure. Pressure psi ( bar) Y N
The air compressor starts and the
Y N
pipe pressure increases
4. Close the drain line. Record the pressure The air compressor stops when the
Y N
when the air compressor stops. system pressure limit is satisfied
Pressure psi ( bar) Y N
5. Clear the alarm on the FACP The alarm clears Y N
6. Verify autoStart fire pump The fire pump allows water
fulfilled into the wet-sprinkler Y N
system piping
7. Fill the pilot sprinkler pipe line with MCV (Main Control Valve Double
pressurize air. interlock) and ACV (Alarm Check
Valve) shall on “NC” position after Y N
pilot line fully fill with pressurize
air.
8. Activate or trigger the detector FACP will activate the solenoid
To construct Cross-Zoned Fire Alarm mode valve and through the water to the Y N
ACV.
Alarm system will active. Y N
Event is recorded in the FACP Y N
9. Record pressure on dry pipe pressure gauge. Pressure psi ( bar) Y N
Test Status
No. Test Procedure Expected (and Actual) Response Y=Pass
N=Fail
2. 9 Pre-action Sprinkler System Operation
10. Open the drain valve. Drain valve will clear the water
from pilot line and open the Deluge Y N
Valve.
Water alarm gong will ringing to
Y N
announce the active location.
11. Flow water through the test connection to LED on monitoring module
water flow pressure switch. activates; and the “Water Flow”
alarm for the correct zone comes up Y N
on the local FACP and other
building FACP’s.
12. Stop water flow Closing the test drain valve will
silent the alarm and normalize the Y N
system.
13. Reset FACP Resetting the panel after test will
Y N
normalize the alarm system.
14. Test all panels and record results in Table 4 Complete
Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Table 2. Smoke Detectors, Manual Call Point, Pull Station, Abort Switch,
A/V Indicator Stage 1, A/V Indicator Stage 2, Illuminated Signs
Address on Status to
Unit Status to
FACP Status Alarm Fire Status to Comments
ID/Address FACP
Correct Network BMS
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Y N Y N Y N Y N
Contractor
No. Check Point Initials CxA
Approval
A. Disconnect Fire Alarm Wire
1. Verify response at status of valve, A/V indicator,
Y N Y N
MCFA, fire network, system status at BMS.
2. Check other interface: access control, lighting, CRAH,
Y N Y N
power, fan (if any), fire damper (if any)
3. Check status preaction Y N Y N
4. Normalise Y N Y N
B. Simulate Single Zoned Alarm
Contractor
No. Check Point Initials CxA
Approval
C. Simulate Cross-Zoned Alarm
1. Verify response at status of gas valve, A/V indicator,
Y N Y N
MCFA, Fire network, system status BMS.
2. Check other interface: access control, lighting, CRAH,
Y N Y N
power, fan (if any), fire damper (if any).
3. Check status pre-action. Y N Y N
C.1 Simulate Abort Pressed Down
1. Verify response at status of gas valve, A/V indicator,
Y N Y N
MCFA, Fire network, system status BMS.
2. Check other interface: access control, lighting, CRAH,
Y N Y N
power, fan (if any), fire damper (if any).
3. Check status pre-action. Y N Y N
C.2 Release Abort
Contractor
No. Check Point Initials CxA
Approval
E. Simulate Manual Release (By Alarm as Electrinically)
Contractor
No. Check Point Initials CxA
Approval
G. Simulate Pressure Loss at Pressurised Cylinder
Contractor
No. Check Point Initials CxA
Approval
A. Disconnect Fire Alarm Wire
1. Verify response at status of pre-action valve, A/V
indicator, MCFA, fire network, system status at Y N Y N
BMS.
2. Check other interface: access control, lighting,
Y N Y N
CRAH, power, fan (if any), fire damper (if any)
3. Check gas suppression kit Y N Y N
4. Check pump status Y N Y N
5. Normalise Y N Y N
B. Simulate Single Zoned Alarm
1. Verify response at status of pre-action valve, A/V
indicator, MCFA, fire network, system status at Y N Y N
BMS.
2. Check other interface: access control, lighting,
Y N Y N
CRAH, power, fan (if any), fire damper (if any)
3. Check gas suppression kit Y N Y N
4. Check pump status Y N Y N
5. Normalise Y N Y N
C. Simulate Cross-Zoned Alarm
1. Verify response at status of pre-action valve, A/V
indicator, MCFA, fire network, system status at Y N Y N
BMS.
2. Check other interface: access control, lighting,
Y N Y N
CRAH, power, fan (if any), fire damper (if any)
3. Check gas suppression kit Y N Y N
4. Check pump status Y N Y N
5. Normalise Y N Y N
Contractor
No. Check Point Initials CxA
Approval
Contractor
No. Check Point Initials CxA
Approval
6. NOTES
Step Description
**Refer to Cx Running Punchlist for status/resolution of deficiencies**
Test sections that have a grey background could not be performed as indicated in this test procedure, see the
Daily Commissioning Reports and Running Punch List for details.
See the Daily Commissioning Reports and Running Punch List for the status of all test items that failed or did
not meet specification, and any additional tests performed.
7. REVISION HISTORY