Sanitary Engineering Lec.: November 2015
Sanitary Engineering Lec.: November 2015
net/publication/283463083
CITATION READS
1 12,531
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Waleed M. Sh. Alabdraba on 03 November 2015.
5. POPULATION FORECASTING
Design of water supply and sanitation scheme is based on the projected population of a
particular city, estimated for the design period. Any underestimated value will make system
inadequate for the purpose intended; similarly overestimated value will make it costly.
Changes in the population of the city over the years occur, and the system should be designed
taking into account of the population at the end of the design period.
The present and past population record for the city can be obtained from the census
population records. After collecting these population figures, the population at the end of
design period is predicted using various methods as suitable for that city considering the
growth pattern followed by the city.
This method is suitable for large and old city with considerable development. If it is used for
small, average or comparatively new cities, it will give lower population estimate than actual
value. In this method the average increase in population per decade is calculated from the
past census reports. This increase is added to the present population to find out the population
of the next decade. Thus, it is assumed that the population is increasing at constant rate.
Hence, dP/dt = C i.e., rate of change of population with respect to time is constant.
Example: 1
Predict the population for the year 2021, 2031, and 2041 from the following population data.
Year 1961 1971 1981 1991 2001 2011
Population 8,58,545 10,15,672 12,01,553 16,91,538 20,77,820 25,85,862
Solution
Population forecast for year 2021 is, P2021 = 2585862 + 345463 x 1 = 2931325
Similarly, P2031 = 2585862 + 345463 x 2 = 3276788
P2041 = 2585862 + 345463 x 3 = 3622251
In this method the percentage increase in population from decade to decade is assumed to
remain constant. Geometric mean increase is used to find out the future increment in
population. Since this method gives higher values and hence should be applied for a new
industrial town at the beginning of development for only few decades. The population at the
end of nth decade ‘Pn’ can be estimated as:
Pn = P (1+ IG/100) n (2)
Where, IG = geometric mean (%)
P = Present population
N = no. of decades.
Example: 2
Considering data given in example 1 predict the population for the year 2021, 2031, and 2041
using geometrical progression method.
Solution
Year Population Increment Geometrical increase
Rate of growth
1961 858545 -
1971 1015672 157127 (157127/858545)
= 0.18
1981 1201553 185881 (185881/1015672)
= 0.18
1991 1691538 489985 (489985/1201553)
= 0.40
2001 2077820 386282 (386282/1691538)
= 0.23
2011 2585862 508042 (508042/2077820)
= 0.24
Example: 3
Considering data given in example 1 predict the population for the year 2021, 2031, and 2041
using incremental increase method.
Solution
Year Population Increase (X) Incremental increase (Y)
1961 858545 - -
1971 1015672 157127 -
1981 1201553 185881 +28754
1991 1691538 489985 +304104
2001 2077820 386282 -103703
2011 2585862 508042 +121760
Total 1727317 350915
Average 345463 87729
Population in year 2021 is, P2021 = 2585862 + (345463 x 1) + {(1 (1+1))/2} x 87729
= 3019054
For year 2031 P2031 = 2585862 + (345463 x 2) + {(2 (2+1)/2)} x 87729
= 3539975
P2041 = 2585862 + (345463 x 3) + {(3 (3+1)/2)} x 87729
= 4148625
5.4 GRAPHICAL METHOD
In this method, the populations of last few decades are correctly plotted to a suitable scale on
graph (Figure 5.1). The population curve is smoothly extended for getting future population.
This extension should be done carefully and it requires proper experience and judgment. The
best way of applying this method is to extend the curve by comparing with population curve
of some other similar cities having the similar growth condition.
In this method the census populations of cities already developed under similar conditions are
plotted. The curve of past population of the city under consideration is plotted on the same
graph. The curve is extended carefully by comparing with the population curve of some
similar cities having the similar condition of growth. The advantage of this method is that the
future population can be predicted from the present population even in the absence of some
of the past census report. The use of this method is explained by a suitable example given
below.
Example: 4
The populations of a new city X given for decades 1970, 1980, 1990 and 2000 were 32,000;
38,000; 43,000 and 50,000, respectively. The cities A, B, C and D were developed in similar
conditions as that of city X. It is required to estimate the population of the city X in the years
2010 and 2020. The population of cities A, B, C and D of different decades were given
below:
(i) City A: 50,000; 62,000; 72,000 and 87,000 in 1960, 1972, 1980 and 1990,
respectively.
(ii) City B: 50,000; 58,000; 69,000 and 76,000 in 1962, 1970, 1981 and 1988,
respectively.
(iii) City C: 50,000; 56,500; 64,000 and 70,000 in 1964, 1970, 1980 and 1988,
respectively.
(iv) City D: 50,000; 54,000; 58,000 and 62,000 in 1961, 1973, 1982 and 1989,
respectively.
Population curves for the cities A, B, C, D and X are plotted (Figure 5.2). Then an average
mean curve is also plotted by dotted line as shown in the figure. The population curve X is
extended beyond 50,000 matching with the dotted mean curve. From the curve, the
populations obtained for city X are 58,000 and 68,000 in year 2010 and 2020.
100
A
Population in thousand
80 B
C
60 D
X
40
20
0
1960 1970 1980 1990 2000 2010 2020
Year
Population curve
The big and metropolitan cities are generally not developed in haphazard manner, but are
planned and regulated by local bodies according to master plan. The master plan is prepared
for next 25 to 30 years for the city. According to the master plan the city is divided into
various zones such as residence, commerce and industry. The population densities are fixed
for various zones in the master plan. From this population density total water demand and
wastewater generation for that zone can be worked out. By this method it is very easy to
access precisely the design population.
This method is used when the growth rate of population due to births, deaths and migrations
takes place under normal situation and it is not subjected to any extraordinary changes like
epidemic, war, earth quake or any natural disaster, etc., and the population follows the growth
Note: When a party wall has communicating openings protected by a single automatic or self-closing
Class A fire door, it qualifies as a division wall for reduction of area.
Note: Where communications are protected by a recognized water curtain, the value of P is 0.
- Aqueducts:
The term aqueduct usually refers to conduits constructed of masonry and built at
the hydraulic gradient.
Such structures are operated at atmospheric pressure, and unless the available
hydraulic gradient is very large, tend to be larger and more expensive than pipelines
operated under pressure.
Possibility of construction with locally available materials, longer life than metal
conduits, and lower loss of hydraulic capacity with age.
Likelihood of interference with local drainage.
Pipelines:
Pipelines are commonly constructed of reinforced concrete, asbestos cement, ductile
iron, steel, or plastic ( PVC – polyvinyl chloride, UPVC- un-plasticized polyvinyl
chloride, GRP-glass reinforced plastic pipe), and are located below the ground surface
only so far as is necessary to protect them against freezing and surface loads and to
avoid other subsurface structures. In locations in which the ground ( and pipe )
elevations vary by very large amounts, high pressures at low points may be avoided by
breaking the hydraulic gradient with overflows or auxiliary reservoir or by installing
special pressure –reducing valves.
At low points in the system, valved blowoff branches or hydrants are provided to drain
the line and permit removal of sediment.
High points in the line should be kept below the hydraulic grade line, since negative
pressure at such locations will lead to accumulation of gases which eventually may
block the flow. High points should be provided with vacuum and air relief valves to
admit air when the line is being emptied and to release air from which is initially in the
line or which accumulates during use.
Figure show standard pipe bedding conditions
Various Types of Pipes :
The pipes are available in several types and sizes. They may be classified into three groups
according to the material used in their manufacturing.
Metallic pipes: the pipes such as Cast Iron - CI Pipes, Ductile pipes, Steel pipes and GI
Pipes.
Cement Pipes: the pipes such as Cement Pipes, Asbestos cement (AC) pipes, cement
concrete pipes.
·Plastic Pipes: the pipes such as PVC – polyvinyl chloride, polyethylene pipe, UPVC- un-
plasticized polyvinyl chloride, GRP-glass fiber reinforced thermosetting resin pipe,
Polythene Pipes (low density)
Strength of pipe
Water carrying capacity
Life and durability of pipe
Expenditure on transportation
Jointing process, maintenance and repairs.
Module 3 – Unit 2 Piping Components and Fittings
3
Module 3 – Unit 2 Piping Components and Fittings
11
Classification of Water Pumps
Water pumps can be divided into two types: Displacement and Dynamic.
Positive displacement pumps can be of reciprocating and rotary type. In either case liquid
is displaced from the low pressure suction side to the high pressure discharge side (the
term positive refers to the direction of flow displacement related to the pressure gradient).
The geometry of the pump is changed periodically and determines the flow in both supply
and delivery system. In a positive displacement pump there is no direct communication
between the suction and discharge circuit. As a rule, a positive displacement pump is self-
priming.
Piston Pumps
A reciprocating piston pump basically consists of a piston, two valves and suction and a
delivery pipe. In the traditional piston pump the upper valve is usually situated in the
piston and known as the piston valve; the lower valve is called the foot valve. If the upper
valve is not integrated in the piston, the pump is usually called a plunger pump.
Centrifugal (Roto Dynamic) pumps
These pumps are based on the principle of imparting kinetic energy to the water. In these
pumps water enters axially and is discharged by the rotor into a discharge pipe. They have
an impeller which rotates in a casing of a special shape. The impeller vanes accelerate the
water, which is thrown out by the centrifugal force. The shape of the casing is designed to
effectively build up a high pressure at the pump outlet. In Figure below, a single stage of a
centrifugal pump is shown. This type of pumps are typically driven by an electric motor or
combustion engine and installed above ground level.
Each impeller together with its casing is called a stage. If more pressure is needed than can
be created by a single stage, several stages can be mounted in series on a common shaft to
form a multi-stage pump , Pump operation may be modeled by a system of affinity laws
that show a relationship between rpm, flow rate, and power. Understanding these basic
relationships, shown below, is very important in considering the performance of a
pumping system.
Where Q= Water discharge, H =Total head, P= the power, D=the impeller diameter and
N=the speed of pump (rpm). , Htotal=hd+hfd+hs+hfs
The Water power can be determined as follow P= g.H.Q (kW) Where g= Gravity
Accelerator
Because the pump and motor cannot be work in 100% efficiency, the power needed to
operate can be calculated as =P/ (ep*et*em)
Where ep= Pump efficiency, et= Transportation efficiency and em= Motor efficiency
Ex1:- calculate the power needed to operate a centrifuge pump in kW if you know the
discharge is 0.25 m3/s and the total head is 30 m, overall efficiency of system is 0.7.
Ex2:- estimate the changes in pump performance for example 1 above resulting from a
change in
1- Pump speed from 1000 rpm to 1500 rpm.
2- Diameter of impeller from 0.3 m to 0.4 m.
Section Lift
Section Lift (hs) is the allowable deference between water level and the centerline
of the pump
hs = (10.33 *A.P/760)-(hf+hv+hvapor)
where:-
EX:- ------------------------------
Where:-
hf = f l Q2 /2 g d A2
hv = Q2 / 2gA2
the we draw the total head vs disgorge on normal scale paper then draw the pump
characteristics curve and fined the optimum Q and H.
Ex:----------------------------
Water Treatment Plants
General layout
Water Intake
Types of Intakes
1- Riever Intake
Direct Intake
In direct Intake
2- Cannel Intake
3- Reservoir Intake
Components of intake
1- Coerce screen
2- Cylindrical or bell mouth Strainer
3- Raw water gravity pipe
4- Sluice gate or Sluice valve
5- Intake well or Suction well
6- Foot valve
7- Suction pipe of law lift pump
8- Backwash pipe
Design Criteria of intake components
1- Strainers
Velocity through the openings (0.15-0.3 m/s)
Opening diameters (6-12 mm)
Total area = 2 * effective area where effective area= the sum of
total opening areas
2- Raw water gravity pipe
The velocity throw the pipe (0.6-1.5 m/s) (at low level of water
not less than 0.6 m/s and at high level of water not exceed 1.5
m/s)
3- Intake well
Two wells at lest
Detention time 20 min or it is enough for maintenance.
The bed of it 1.5 m below low water level or 1m below riverbed
4- Suction pipe of law lift pump
The velocity throws the pipe (0.6-1.5 m/s)
5- Backwash pipe
The velocity through the pipe not less than 3 m/s
Qbackwash=(1/3) Qin
Treated water should be used for washing.
b- intake well if you know that high water level 2 m below ground and low
water level 3 m below ground level , and c- backwash pipe.
Coagulation and Flocculation
All waters, especially surface waters, contain both dissolved and suspended
particles. Coagulation and flocculation processes are used to separate the
suspended solids portion from the water, The suspended particles vary
considerably in source, composition charge, particle size, shape, and density.
COAGULATION
The first step destabilizes the particle’s charges. Coagulants with charges
opposite those of the suspended solids are added to the water to neutralize the
negative charges on dispersed non-settable solids such as clay and color-
producing organic substances, A high-energy, rapid-mix to properly disperse
the coagulant and promote particle collisions is needed to achieve good
coagulation. Over-mixing does not affect coagulation, but insufficient mixing
will leave this step incomplete. Coagulants should be added where sufficient
mixing will occur. Proper contact time in the rapid-mix chamber is typically 30
sec to 2 minutes.
FLOCCULATION
Following the first step of coagulation, a second process called flocculation
occurs. Flocculation, a gentle mixing stage, increases the particle size from
submicroscopic microfloc to visible suspended particles. The microflocs are
brought into contact with each other through the process of slow mixing. Once
the floc has reached it optimum size and strength, the water is ready for the
sedimentation process. Design contact times for flocculation range from 15 or
20 minutes to about 1 hour or more.
CONVENTIONAL PLANTS
Conventional plant designs separate the coagulation, or rapid-mix, stage from
the flocculation, or slow-mix, stage. Normally this is followed by a
sedimentation stage
COMBINATION UNITS
Some designs incorporate coagulation, flocculation, and sedimentation within a
single unit
COAGULANT SELECTION
The choice of coagulant chemical depends upon the nature of the suspended
solid to be removed, the raw water conditions, the facility design, and the cost
of the amount of chemical necessary to produce the desired result.
Final selection of the coagulant (or coagulants) should be made following
thorough jar testing and plant scale evaluation. Considerations must be given to
required effluent quality,.
Inorganic Coagulants
Inorganic coagulants such as aluminum and iron salts are the most commonly
used. When added to the water, they furnish highly charged ions to neutralize
the suspended particles.
Inorganic Coagulant Reactions
Common coagulant chemicals used are alum, ferric sulfate, ferric chloride,
ferrous sulfate, and sodium aluminates. The first four will lower the alkalinity
and pH of the solution while the sodium aluminates will add alkalinity and raise
the pH. The reactions of each follow:
ALUM
A12(SO4)3 + 3 Ca(HCO3)2 ========= 2 Al(OH)3 + 3CaSO4 + 6 CO2
Aluminum + Calcium ========= Aluminum + Calcium + Carbon
Sulfate Bicarbonate Hydroxide Sulfate Dioxide
(Already in the water to treat)
FERRIC SULFATE
Fe2(SO4)3 + 3 Ca(HCO3)2 ========= 2 Fe(OH)3 + 3CaSO4 + 6 CO2
Ferric + Calcium ========= Ferric + Calcium + Carbon
Sulfate Bicarbonate Hydroxide Sulfate Dioxide
(present in the water to treat)
FERRIC CHLORIDE
2 Fe Cl3 + 3 Ca(HCO3)2 =========2 Fe(OH)3 + 3CaCl2 + 6CO2
Ferric + Calcium ========= Ferric + Calcium + Carbon
Chloride Bicarbonate Hydroxide Chloride Dioxide
(present in the water to treat)
FERROUS SULFATE
FeS04 + Ca(HCO3)2 ========= Fe(OH)2 + CaS04 + 2CO2
Ferrous + Calcium ========= Ferrous + Calcium + Carbon
Sulfate Bicarbonate Hydroxide Sulfate Dioxide
(present in the water to treat)
POLYMERS
Polymers--long-chained, high-molecular-weight, organic chemicals--are
becoming more widely used, especially as coagulant aids together with the
regular inorganic coagulants. Anionic (negatively charged) polymers are often
used with metal coagulants. Low-to-medium weight positively charged
(cationic) polymers may be used alone or in combination with the aluminum
and iron type coagulants to attract the suspended solids and neutralize their
surface charge.
Polymers are effective over a wider pH range than inorganic coagulants. They
can be applied at lower doses, and they do not consume alkalinity. They
produce smaller volumes of more concentrated, rapidly settling floc.
DESIGN OF RAPID MIXING (COAGULATION) UNITS
Rapid mixing unit provide
1- Complete mixing of the coagulant and raw water.
2- Destabilization of colloidal particle
3- Early stages of floc formation
Types of Rapid Mixing Units
1- Hydraulic mixing units
2- Mechanically mixing units
Design Criteria:
G for rapid mix = 700-1000 sec-1
t (detention time) for rapid mixing = 20-60 sec
P =μG2V , P= power(watt) , V= volume of tank (max 8 m3)
It may be single compartment or double compartment
→ Single compartment basins are usually circular or square in plan view
Liquid depth = 1-1.25 x (basin diameter or width)
→ Small baffles are desirable to minimize vortexing.
Impellers Type
EX:- A square rapid-mixing basin, with a depth of water equal to 1.25 times the
width, is to be designed for a flow of 7570 m3/d. The velocity gradient is to be
790 sec-1, the detention time is 40 seconds, dose of Alum is 35mg/l and dynamic
viscosity of water is 0.0013 N-s/m2, Determine:
1- The basin dimensions
2- The power required
3- Quantity of Alum used per day.
Flocculation
11
Flocculation
¾Complete flocculation depends on:
− The relative ease and rate of by which the small microfloc
aggregate into large floc particles
− Number of particle collisions
¾OR in other words, it depends on:
− Floc characteristics
− G (if G is too high, large floc will not be formed)
− GT (gives indication on the number of collisions)
¾Fragile flocs require low G values (<5/sec)
¾High-strength flocs require high G values
(≈10/sec)
12
Flocculation Basins
¾Designed to provide tapered flocculation
[decreasing G values (high 50 to low 20 to lower
10/sec)]
¾Horizontal and vertical shafts are used to mount
the paddle wheel
¾Flocculation basins are composed of minimum 3
compartments to:
− Minimize short circuiting
− Facilitate tapered flocculation
13
Flocculation Basins
14
Baffled Basins or
P = ρ*g*h/t = G2*μ
Where, t = detention time in sec, P= power in watt/m3
Ex:- flow throw baffled basin is 12 m3/min , the head losses throw the basin is 1
m and the detention time is 40 min
Estimate G and GT
Ex:- Estimate the power required to rotate the paddle at 5 rpm , G and GT for a
rectangular flocculater tank have 4 horizontal cross flow shafts each one carry
4 paddles 30 cm * 7.5 m if you know that ,Q= 60000 m3/day, Tank dimensions
are 6*8*25 m.
The distance between shaft and paddle center is 2.8 m., Cd= 1.8
Viscosity of water 1.002*10-2 N.s/m2, and velocity of paddle equal to 63% from
final velocity.
SEDIMENTATION
Some basic definitions will aid in understanding the basic concept and aim
of sedimentation.
Sedimentation , also known as settling, may be defined as the removal of
solid particles from a suspension by settling under gravity.
Clarification is a similar term, which usually refers specifically to the
function of a sedimentation tank in removing suspended matter from the
water to give a clarified effluent. In a broader sense, clarification could
include flotation and filtration.
Thickening in sedimentation tanks is the process whereby the settled
impurities are concentrated and compacted on the floor of the tank and in the
sludge-collecting hoppers.
Concentrated impurities withdrawn from the bottom of sedimentation tanks
are called sludge, while material that floats to the top of the tank is called
scum.
In water treatment, sedimentation is commonly used to remove impurities
that have been rendered settleable by coagulation and flocculation, as when
removing turbidity and color. Precipitates formed in processes such as water
softening by chemical precipitation are also removed by sedimentation.
Classification of settling behavior
Several cases of settling behavior may be distinguished on the basis of the
nature of the particles to be removed and their concentration.
Common classifications of settling behavior are:
Class I - Unlimited settling of discrete particles
Class II - Settling of dilute suspensions of flocculent particles
Class III - Hindered settling and zone settling
Class IV - Compression settling (compaction).
The general conclusion, that Vs depends on a particular diameter, particle
density and, under some conditions, also on fluid viscosity and hence on
temperature, is important in understanding sedimentation behavior.
Furthermore, in practical sedimentation tanks, the terminal settling velocity
is quickly reached, so, for non-flocculent particles and uniform fluid flow
the settling velocity is constant throughout the settling time. This fact can be
usefully applied to a study of settling in an ideal sedimentation tank to
provide an important design principle for sedimentation processes.
Idealized representations of three common types of sedimentation tanks are
shown in Fig 2.5: (a) rectangular horizontal flow, (b) circular radial flow.
The ideal rectangular horizontal flow sedimentation tank is considered
divided into four zones (Fig 2.5a)
a Inlet zone - in which momentum is dissipated and flow is established in
a uniform forward direction
b Settling zone - where quiescent settling is assumed to occur as the
water flows towards the outlet
c Outlet zone - in which the flow converges upwards to the decanting
weirs or launders
d Sludge zone - where settled material collects and is moved towards
sludge hoppers for withdrawal. It is assumed that once a particle
reaches the sludge zone it is effectively removed from the flow.
The critical particle in the settling zone of an ideal rectangular sedimentation
tank, for design purposes, will be one that enters at the top of the settling
zone, at point A, and settles with a velocity just sufficient to reach the sludge
zone at the outlet end of the tank, at point B. The velocity components of
such a particle are Vh in the horizontal direction and Vs, the terminal settling
velocity, in the vertical direction.
From the geometry of the tank it is apparent that the time required for the
particle to settle, to, is given by
H
to = = L/vs
Vp
but, since Vs = Q/WH, then Vs = Q/WL, where Q is the rate of flow, and L,
W and H are the length, width and depth of the tank, respectively. Since the
surface area of the tank, A, is WL, then
Vs = Q/A
Example 2
Design a coagulation sedimentation tank with a continuous flow for treating
water for a population of 45,000 persons with an average daily consumption
of 135 L/person. Assume a surface loading rate of 0.9 m3m-2h-1 and that the
weir loading rate is within acceptable limits.
Solution
Average consumption = 135 x 45,000 = 6,075,000 L/d.
Allow 1.8 times for maximum daily consumption:
Maximum daily consumption = 1.8 x 6,075,000 = 10,935m3/d.
Therefore, required surface area of the tank = (10,935/24)/0.9 = 506 m2.
Assume minimum depth of tank = 3.5 m.
Therefore, (settling) volume of the tank = 506 x 3.5 = 1772 m3.
Assume a length to width ratio of the tank of 3.5:1. Therefore the width
would be
= 506/3.5w2 m = 12m
Therefore, length of tank = 3.5 x 12 = 42 m.
Assuming a bottom slope of 1 in 60.
Depth of the deep end (at the influent end) = 3.5 + (1/60) x 42 = 4.2 m.
A floc chamber should be provided, at the entry to the tank, the capacity of
which is assumed to be 1/16 of the settling chamber, i.e. = 1772/16
= 110.8 m3.
If the depth of floc chamber is 2.5 m, then
the area of the floc chamber = 110.8/2.5 = 44.3 m2.
The flocculation chamber also has a width equal to the sedimentation
chamber, ie 12m. Therefore, length of floc chamber = 45.562/12 3.8m.
It should be considered to add this length to the settling tank as it would
otherwise reduce the settling volume by 3.8/42 = 9%. However, considering
that we have already provided amply for maximum flow conditions, we
could still fit the flocculation unit within the tank.
The overall removal of particles from a discrete suspension in a
horizontal flow sedimentation basin can be estimated from the suspension
settling velocity distribution curve, as illustrated in Fig 4.2. In addition to
The enclosure tank is usually smaller in size and is therefore placed under a
roof. The tank is generally rectangular in plan,constructed either in masonary or of
concrete,coated with water proof material.The depth of tank may vary between2.5 to
3.5m.Each unit may have a surface area of 20 to 50 m2 .They are arranged in series.The
length to width ratio is normally kept between 1.25 to 1.35.In addition to the underdrainage
system, the tanks also have C.I or R.C.C troughs spanning across the length or width of the
walls for the distribution of water to be filtered during normal operation, and for collection of
water during cleaning operation.During normal filtration operation the trough remain
submerged. figure(i) shows the details.
f. Back wash
Time 3-10 min ( 5 min)
Q 25-37 m3/m2.h
Air pressure 1-1.5 bar
Water pressure 1-2 bar
g. Free board 0.6 m
h. Total depth (sand and gravel) 1-1.2 m
Figure(i)
2
ESTIMATION OF SAND DEPTH
The depth of sand bed should be such that the flocs do not break through the
sand bed .Normally the depth of sand varies from 60 to 90 cm .figure (ii) shows
sand layer and gravel layer in a filter
Base material:
The filter sand media is supported on base material consisting of graded gravel
layers. The gravel should be free from clay, dire, vegetables and organic matter
and should be hard, durable and round. Its total depth varies from 45 to 60 cm
and is normally laid in the following layers:
LAYER DEPTH GRADE SIZE
Top most layer 15 cm 2mm to 6mm
Intermediate layer 15 cm 6mm to 12mm
Intermediate layer 15 cm 12mm to 20mm
Bottom layer 15 cm 20mm to 50mm
Design of underdrainage system :
12
WASH WATER TROUGHS:
Wash water troughs are provided at the top of filter to collect back wash water after it
emerges from the sand bed and to conduct it to the wash water gullet or drain.They are C.I. or
R.C.C troughs spanning across the width or length of the tanks. The bottom of the trough is
kept above the top of the expanded sand to prevent possibility of loss of sand during
backwashing .At the same time the upper edge of the trough should be placed sufficiently
near to the surface of sand so that a large quantity of dirty water is not left in the filter after
completion of washing .The trough should be large enough to carry all the water delivered to
it with F.B. of 6 to 8 cm. Any submergence of the gutter will reduce the efficiency of the
wash. The bottom of the trough is kept at least 5cm above the top level of sand .The spacing
of wash water troughs is kept between 1.5 to 2 cm.figure(iii) shows the arrangement of wash
water trough in rapid filters.
Q= 1.376*b*y3/2
10
Public Water Supply 469
chloramines are respectively 51.5, 85.9, and 120.4. Therefore, the chlo-
ramines contain 1.38, 1.65, and 1.85 g of available chlorine per gram of
chloramine, respectively.
The pH of the water is the most important factor on the formation of
chloramine species. In general, monochloramine is formed at pH above
7. The optimum pH for producing monochloramine is approximately 8.4.
DISTRIBUTION SYSTEMS
Reservoir
Sub-main
Sub-main
Branches
Advantages:
It is a very simple method of water distribution. Calculations are easy and simple to do.
The required dimensions of the pipes are economical.
This method requires comparatively less number of cut-off valves.
However, it is not usually favored in modern water works practice for the following
disadvantages.
Disadvantages:
The area receiving water from a pipe under repair is without water until the work is
completed.
In this system, there are large number of dead ends where water does not circulate but
remains static. Sediments accumulate due to stagnation of the dead end and bacterial
growth may occur at these points. To overcome this problem drain valves are provided
at dead ends and stagnant water is drained out by periodically opening these valves but
a large amount of water is wasted.
It is difficult to maintain chlorine residual at the dead ends of the pipe.
Water available for fire-fighting will be limited since it is being supplied by only one
water main.
The pressure at the end of the line may become undesirably low as additional areas are
connected to the water supply system. This problem is common in many less-developed
countries.
B. Grid Pattern
Reservoir
Main line
In grid pattern, all the pipes are interconnected with no dead-ends. In such a system,
water can reach any point from more than one direction.
Advantages:
Since water in the supply system is free to flow in more than one direction, stagnation
does not occur as readily as in the branching pattern.
In case of repair or break down in a pipe, the area connected to that pipe will continue to
receive water, as water will flow to that area from the other side.
Water reaches all points with minimum head loss.
At the time of fires, by manipulating the cut-off valves, plenty of water supply may be
diverted and concentrated for fire-fighting.
Disadvantages:
Cost of pipe laying is more because relatively more length of pipes is required.
More number of valves are required.
The calculation of pipe sizes are more complicated.
Loops are provided in a grid pattern to improve water pressure in portions of a city
(industrial, business and commercial areas).
Loops should be strategically located so that as the city develops the water pressure should
be sustained.
The advantages and disadvantages of this pattern are the same as those of the grid pattern.
DESIGN CONSIDERATIONS
Diameter ≥ 80 mm.
If velocity < 0.6 m/sec (due to minimum diameter limit) then drain valve is used on
that pipe.
Minimum pressure at the top of the highest floor of a building is about 5m.
2. The algebraic sum of the head loss in a loop must be equal to zero:
where
8fi Li
Ki ¼ , (3:15)
p2 gD5i
In general, it is not possible to satisfy Eq. (3.14) with the initially assumed pipe dis-
charges satisfying nodal continuity equation. The discharges are modified so that
Eq. (3.14) becomes closer to zero in comparison with initially assumed discharges.
The modified pipe discharges are determined by applying a correction DQk to the
initially assumed pipe flows. Thus,
X
Ki (Qi þ DQk )j(Qi þ DQk )j ¼ 0: (3:16)
loop k
Expanding Eq. (3.16) and neglecting second power of DQk and simplifying Eq. (3.16),
the following equation is obtained:
P
Ki Qi jQi j
loop k
D Qk ¼ P : (3:17)
2 Ki jQi j
loop k
The overall procedure for the looped network analysis can be summarized in the follow-
ing steps:
1. Number all the nodes and pipe links. Also number the loops. For clarity, pipe
numbers are circled and the loop numbers are put in square brackets.
2. Adopt a sign convention that a pipe discharge is positive if it flows from a lower
node number to a higher node number, otherwise negative.
3. Apply nodal continuity equation at all the nodes to obtain pipe discharges.
Starting from nodes having two pipes with unknown discharges, assume an arbi-
trary discharge (say 0.1 m3/s) in one of the pipes and apply continuity equation
(3.13) to obtain discharge in the other pipe. Repeat the procedure until all the
pipe flows are known. If there exist more than two pipes having unknown dis-
charges, assume arbitrary discharges in all the pipes except one and apply con-
tinuity equation to get discharge in the other pipe. The total number of pipes
having arbitrary discharges should be equal to the total number of primary
loops in the network.
54 PIPE NETWORK ANALYSIS
4. Assume friction factors fi ¼ 0.02 in all pipe links and compute corresponding Ki
using Eq. (3.15). However, fi can be calculated iteratively using Eq. (2.6a).
5. Assume loop pipe flow sign convention to apply loop discharge corrections;
generally, clockwise flows positive and counterclockwise flows negative are
considered.
6. Calculate DQk for the existing pipe flows and apply pipe corrections
algebraically.
7. Apply the similar procedure in all the loops of a pipe network.
Repeat steps 6 and 7 until the discharge corrections in all the loops are relatively very
small.
Example 3.3. A single looped network as shown in Fig. 3.10 has to be analyzed by the
Hardy Cross method for given inflow and outflow discharges. The pipe diameters D and
lengths L are shown in the figure. Use Darcy – Weisbach head loss – discharge relation-
ship assuming a constant friction factor f ¼ 0.02.
Solution
Step 1: The pipes, nodes, and loop are numbered as shown in Fig. 3.10.
Step 2: Adopt the following sign conventions:
A positive pipe discharge flows from a lower node to a higher node.
Inflow into a node is positive withdrawal negative.
In the summation process of Eq. (3.13), a positive sign is used if the discharge in
the pipe is out of the node under consideration. Otherwise, a negative sign will be
attached to the discharge. For example in Fig. 3.10 at node 2, the flow in pipe 1 is
toward node 2, thus the Q1 at node 2 will be negative while applying Eq. (3.13).
Step 3: Apply continuity equation to obtain pipe discharges. Scanning the figure
for node 1, the discharges in pipes 1 and 4 are unknown. The nodal inflow
q1 is 0.6 m3/s and nodal outflow q3 ¼ 20.6 m3/s. The q2 and q3 are zero.
Assume an arbitrary flow of 0.1 m3/s in pipe 1 (Q1 ¼ 0.1 m3/s), meaning
thereby that the flow in pipe 1 is from node 1 to node 2. The discharge in
pipe Q4 can be calculated by applying continuity equation at node 1 as
The discharge in pipe 4 is positive meaning thereby that the flow will be from
node 1 to node 4 (toward higher numbering node).
Also applying continuity equation at node 2:
Iteration 1
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.10 6528.93 65.29 1305.79 0.30
2 0.10 4352.62 43.53 870.52 0.30
3 20.50 6528.93 21632.23 6528.93 20.30
4 20.50 4352.62 21088.15 4352.62 20.30
Total 22611.57 13,057.85
DQ 2(22611.57/13,057) ¼ 0.20 m3/s
56 PIPE NETWORK ANALYSIS
Repeat the process again for the revised pipe discharges as the discharge correction
is quite large in comparison to pipe flows:
Iteration 2
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.30 6528.93 587.60 3917.36 0.30
2 0.30 4352.62 391.74 2611.57 0.30
3 20.30 6528.93 2587.60 3917.36 20.30
4 20.30 4352.62 2391.74 2611.57 20.30
Total 0.00 13,057.85
DQ ¼2 (0/13,057) ¼ 0.00 m3/s
Q1 ¼ 0.3 m3/s
Q2 ¼ 0.3 m3/s
Q3 ¼ 0.3 m3/s
Q4 ¼ 0.3 m3/s.
Example 3.4. The pipe network of two loops as shown in Fig. 3.11 has to be analyzed
by the Hardy Cross method for pipe flows for given pipe lengths L and pipe diameters D.
The nodal inflow at node 1 and nodal outflow at node 3 are shown in the figure. Assume
a constant friction factor f ¼ 0.02.
Solution. Applying steps 1 – 7, the looped network analysis can be conducted as illus-
trated in this example. The K values for Darcy – Weisbach head loss – discharge relation-
ship are also given in Fig. 3.11.
To obtain initial pipe discharges applying nodal continuity equation, the arbitrary
pipe discharges equal to the total number of loops are assumed. The total number of
The discharge correction DQ is applied in one loop at a time until the DQ is very
small in all the loops. DQ in Loop 1 (loop pipes 3, 4, and 5) and corrected pipe
discharges are given in the following table:
Loop 1: Iteration 1
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
3 20.40 49,576.12 27932.18 39,660.89 20.25
4 20.40 4352.36 2696.38 3481.89 20.25
5 0.10 59,491.34 594.91 11,898.27 0.25
Total 28033.64 55,041.05
DQ 0.15 m3/s
Thus the discharge correction DQ in loop 1 is 0.15 m3/s. The discharges in loop
pipes are corrected as shown in the above table. Applying the same methodology for
calculating DQ for Loop 2:
Loop 2: Iteration 1
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.10 6528.54 65.29 1305.71 0.19
2 0.10 33,050.74 330.51 6610.15 0.19
5 20.25 59,491.34 23598.93 29,264.66 20.16
Total 23203.14 37,180.52
DQ 0.09 m3/s
58 PIPE NETWORK ANALYSIS
The process of discharge correction is in repeated until the DQ value is very small as
shown in the following tables:
Loop 1: Iteration 2
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
3 20.25 49,576.12 23098.51 24,788.06 20.21
4 20.25 4352.36 2272.02 2176.18 20.21
5 0.16 59,491.34 1522.98 19,037.23 0.20
Total 21847.55 46,001.47
DQ 0.04 m3/s
Loop 2: Iteration 2
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.19 6528.54 226.23 2430.59 0.21
2 0.19 33,050.74 1145.28 12,304.85 0.21
5 20.20 59,491.34 22383.53 23,815.92 20.17
Total 21012.02 38,551.36
DQ 0.03 m3/s
Loop 1: Iteration 3
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
3 20.210 49,576.12 22182.92 20,805.82 20.197
4 20.210 4352.36 2191.64 1826.57 20.197
5 0.174 59,491.34 1799.33 20,692.47 0.187
Total 2575.23 43,324.86
DQ 0.01 m3/s
Loop 2: Iteration 3
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.212 6528.54 294.53 2773.35 0.220
2 0.212 33,050.74 1491.07 14,040.10 0.220
5 20.187 59,491.34 22084.55 22,272.21 20.180
Total 2298.95 39,085.67
DQ 0.008 m3/s
3.7. ANALYSIS OF LOOPED NETWORKS 59
Loop 1: Iteration 4
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
3 20.197 49,576.12 21915.41 19,489.36 20.193
4 20.197 4352.36 2168.16 1711.00 20.193
5 0.180 59,491.34 1917.68 21,362.18 0.183
Total 2165.89 42,562.54
DQ 0.004 m3/s
Loop 2: Iteration 4
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.220 6528.54 316.13 2873.22 0.222
2 0.220 33,050.74 1600.39 14,545.68 0.222
5 20.183 59,491.34 22001.85 21,825.91 20.181
Total 285.33 39,244.81
DQ 0.002 m3/s
Loop 1: Iteration 5
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
3 20.193 49,576.12 21840.21 19,102.92 20.192
4 20.193 4352.36 2161.55 1677.07 20.192
5 0.181 59,491.34 1954.67 21,567.21 0.182
Total 247.09 42,347.21
DQ 0.001 m3/s
Loop 2: Iteration 5
Corrected Flow
Flow in Pipe Q K KQjQj 2KjQj Q ¼ Q þ DQ
Pipe (m3/s) (s2/m5) (m) (s/m2) (m3/s)
1 0.222 6528.54 322.40 2901.61 0.223
2 0.222 33,050.74 1632.17 14,689.40 0.223
5 -0.182 59,491.34 21978.73 21,699.52 20.182
Total 224.15 39,290.53
DQ 0.001 m3/s
60 PIPE NETWORK ANALYSIS
The discharge corrections in the loops are very small after five
iterations, thus the final pipe discharges in the looped pipe network in
Fig. 3.11 are
Q1 = 0.223 m3/s
Q2 = 0.223 m3/s
Q3 = 0.192 m3/s
Q4 = 0.192 m3/s
Q5 = 0.182 m3/s
Wastewater Treatment Facilities
576 Chapter 6
v2 V2
h1 1 5 h2 1 (6.28)
2g 2g
1 ⌬h
and
V 2 2 v2
h 5 h1 2 h2 5 (6.29)
2gC 2
1 V 2 2 v2 (6.30)
h5 a b
0.7 2g
w 4/3 v2
H 5 Ba b sin u (6.31)
b 2g
where H ⫽ headloss, m
w ⫽ maximum width of the bar facing the flow, m
b ⫽ minimum clear spacing of bars, m
v ⫽ velocity of flow approaching the rack, m/s
Wastewater Engineering 583
Bar type B
Example 1: Compute the velocity through a rack when the approach veloc-
ity is 0.60 m/s (2 ft/s) and the measured headloss is 38 mm (0.15 in)
solution: Using Eq. (6.30)
V 2 2 v2
h5
0.7s2gd
V 2 2 s0.6 m/sd2
0.038 m 5
0.7s2 3 9.81 m/sd2
V 2 5 0.882
V 5 0.94 m/s
5 3.08 ft/s
Example 2: Design a coarse screen and calculate the headloss through the
rack, using the following information:
solution:
Figure 6.11 BOD5, removal in primary settling tank (source: Illinois EPA 1998).
Inlet zone
Outlet
Settling zone zone
12
1
Figure 6.12 Typical circular basin design-plan view and cross section.
Peripheral weirs shall be placed at least 300 cm (1 ft) from the well (Ten
States Standards, GLUMRB, 1996).
Example 1: Design circular clarifiers using English system units with the
same given information as in the example for rectangular clarifiers design.
solution:
Example 2: If the surface overflow rate is 40 m3/(m2 ⭈ d) [982 gal/(d ⭈ ft2)] and
the weir overflow rate is 360 m3/(d ⭈ m) [29,000 gal/(d ⭈ ft)], determine the max-
imum radius for a circular primary clarifier with a single peripheral weir.
solution
or
Q ⫽ 720pr m /(d ⭈ m)
3
u ⫽ V/Q (6.69)
Figure 6.15 Schematic chart of complete-mix activated sludge reactor: (a) sludging wast-
ing from the aeration tank; (b) sludge wasting from return sludge line.
Referring to Fig. 6.15a, the mean cell residence time uc (or sludge age
or SRT) in the system is defined as the mass of organisms in the aeration
tank divided by the mass of organisms removed from the system per day,
and is expressed as
X
uc 5 (6.70)
s⌬X/⌬td
For system-drawn waste sludge from the return sludge line (Fig. 6.15b),
the mean cell residence time would be
VX
uc 5 (6.72)
Qwr X r 1 Qe Xe
where Qwr ⫽ flow of waste sludge from return sludge line, m3/d
Xr ⫽ microorganism concentration in return sludge line, mg/L
dX
V 5 QX0 1 Vsrrgd 2 sQwaX 1 Qe X ed (6.73)
dt
Substituting Eq. (6.74) into Eq. (6.73), and assuming the cell con-
centration in the influent is zero and steady-state conditions, this
yields
(6.75)
QwaX 1 QeXe r
5 2Y su 2 kd
VX X
The left-hand side of Eq. (6.75) is the inverse of the mean cell residence
time uc as defined in Eq. (6.71); thus
1 r
5 2Y su 2 kd (6.76)
uc X
Q S 2S
rsu 5 sS 2 Sd 5 0 (6.77)
V 0 u
ucYsS0 2 Sd m sS 2 Sd
X5 5 m 0 (6.78)
us1 1 kducd ks1 2 kducd
Substituting for u from Eq. (6.69) for (6.78) and solving for the reactor
(aeration tank) volume yields
ucQYsS0 2 Sd
V5 (6.79)
Xs1 1 kducd
Wastewater Engineering 631
The term U is substituted for the term (–rsu/X) in Eq. (6.76). The result-
ing equation becomes
1
5 YU 2 kd (6.84)
uc
The term 1/uc is the net specific growth rate and is directly related
to U, the specific substrate utilization rate.
In order to determine the specific substrate utilization rate, the sub-
strate utilized and the biomass effective in the utilization must be given.
The substrate utilized can be computed from the difference between
the influent and the effluent BOD5 or COD.
In the complete-mix activated-sludge process with recycle, waste
sludge (cells) can be withdrawn from the tank or from the recycling
line. If waste sludge is withdrawn from the tank and the VSS in the
effluent Xe is negligible (QeXe ⬇ 0), Eq. (6.71) will (if Xe is very small)
be approximately rewritten as
VX
uc < (6.85)
QwaX
or
V
Qwa < (6.86)
uc
The flow rate of waste sludge from the sludge return line will be
approximately
VX
Qwr 5 (6.87)
ucXr
where Xr is the concentration (in mg/L) of sludge in the sludge return line.
Wastewater Engineering 633
S0 QS0 mg BOD5/d
F/M 5 (6.88)
VX mg MLVSS
5 5
uX
U 5 (6.89)
sF/MdE
100
S0 2 S
E 5 3 100 (6.90)
S0
water and the amount of microorganisms wasted per day from the
634 Chapter 6
QsS0 2 Sd
kg O2/d 5 2 1.42Px (SI units) (6.94a)
s1000 g/kgd f
QsS0 2 Sd 1
kg O2/d 5 a 2 1.42Yobs b (6.94b)
1000 g/kg f
1
lb O2/d 5 QsS0 2 Sd 3 8.34a 2 1.42Yobsb (US customary units) (6.95)
f
Given:
Equation (6.48) is valid for Reynolds numbers less than 0.2, which is gen-
erally the situation in hindered settling.
A typical curve of interface height versus time for activated sludge is
shown in Fig. 6.10. From A to B, there is a hindered settling of the par-
ticles and this is called liquid interface. From B to C there is a deceler-
ation marking the transition from hindered settling into the compression
Qtu
A5 (6.50)
H0
C 0 H0
Hu 5 (6.51)
Cu
5 180 mm
Step 2. Determine tu
Step 3. Calculate the area required for the thickening, using Eq. (6.50)
5 12.02 m2
5 129 ft2
696 Chapter 6
Note: This is the power required for mixing and is commonly the control
factor in sizing the aerators for domestic wastewater treatment. For indus-
trial wastewater treatment, the control factor is usually reversed.
22 Trickling Filter
A trickling filter is actually a unit process for introducing primary efflu-
ent into contact with biological growth and is a biological oxidation bed.
The word “filter” does not mean any filtering or straining action; nev-
ertheless, it is popularly and universally used.
22.3 Recirculation
Recirculation of a portion of the effluent to flow back through the filter
is generally practised in modern trickling filter plants. The ratio of the
return flow Qr, to the influent flow Q is called the recirculation ratio r.
Techniques of recirculation vary widely, with a variety of configura-
tions. The recirculation ratios range from 0 to 4 (Table 6.14) with usual
ratios being 0.5 to 3.0.
The advantages of recirculation include an increase in biological solids
in the system with continuous seeding of active biological material; elim-
ination of shock load by diluting strong influent; maintenance of more
uniform hydraulic and organic loads; an increase in the DO level of the
influent; thinning of the biological slime layer; an improvement of treat-
ment efficiency; reduction of filter clogging; and less nuisance problems.
100
(6.129)
1 1 0.532 2W/VF sSI unitsd
E1 5
100
(6.130)
1 1 0.561 2W/VF sUS customary unitsd
E1 5
11r
F5 (6.131)
s1 1 0.1rd2
Example 1: Estimate the BOD removal efficiency and effluent BOD5 of a two-
stage trickling filter using the NRC formula with the following given conditions.
solution:
Step 1. Estimate BOD loading at the first stage
Influent BOD C1 ⫽ 300 mg/L (1 – 0.35) ⫽ 195 mg/L
W ⫽ QC1 ⫽ 2 Mgal/d ⫻195 mg/L ⫻ 8.34 lb/(Mgal ⭈ mg/L)
⫽ 3252 lb/d
Water Pollution
• Pollutant
– Any substance that does not belong in the natural system and disrupts the
natural balance
• Water Pollution
– Degradation of water quality in a manner that disrupts/prevents its intended or
original use.
Water pollution contaminant types
Infectious agents
Oxygen-demanding Wastes
Plant nutrients and cultural eutrophication
Toxic tides
Inorganic Pollutants ( Metals, nonmetallic salts, acids and bases )
Organic Chemicals
Sediment
Thermal Pollution and thermal shocks
MCL and secondary MCL
MCL=Maximum Contaminant Level
– The highest concentration of a pollutant allowed in drinking water by
law
– Concentration above which adverse health effects are believed to occur
Secondary MCL
– Concentration of a pollutant above which the water is unpleasant in
odor or taste
– May not be hazardous to your health at that level
Dissolved Oxygen – DO
– Amount of oxygen available in the water. – Oxygen in water maintained by
• exchange with the atmosphere
• Production of oxygen by photosynthetic organisms (vegetation)
• Circulation of water (essential to maintain oxygen levels in deeper portions)
– Oxygen consumed by decaying organic matter and oxygen breathing
organism.
BOD
• Biochemical Oxygen Demand
–Measure of the amount of oxygen required for the aerobic degradation of
organic and non-organic compounds in the water.
–Highly polluted waters have very high BOD implying that oxygen is
consumed rapidly.
Third Lecture Sources of water pollution
Page 1 of 6
Third Lecture Sources of water pollution
Page 2 of 6
Third Lecture Sources of water pollution
Page 3 of 6
Third Lecture Sources of water pollution
Page 4 of 6
Seventh Lecture Water resources and their characterization- river 4
Oxygen Sag Curve
Where:
kd= the de-oxygenation rate constant (d-1)
Lt= the BOD remaining t (days) after the wastes enter the river, (mg/L).
where Lo is the BOD of the mixture of stream water and wastewater at the point of
discharge.
Page 1 of 4
Seventh Lecture Water resources and their characterization- river 4
Oxygen Sag Curve
Where:
kr= re-aeration constant (d-1).
D= dissolved oxygen deficit = (DOs – DO)
DOs= saturated value of dissolved oxygen.
DO= actual dissolved oxygen at a given location downstream.
Where:
kr= re-aeration coefficient at 20 °C (d -1)
u = average stream velocity (m/s)
H = average stream depth (m)
D0 = DOs -
Where :
D0 = initial oxygen deficit of the mixture of
the river and WW
DOs = saturated value of DO in water at
the temperature of the river
Page 2 of 4
Seventh Lecture Water resources and their characterization- river 4
Oxygen Sag Curve
The combined the two equations, Rate of deoxygenation= kdL0e-kdt and Rate of
reaeration = krD, yields the following expression for the rate of increase of the
oxygen deficit:
Rate of increase of the oxygen deficit = Rd - Rr
( )
Since the deficit D is the difference between the saturation value of dissolved
oxygen DOs and the actual value DO, we write the equation for the DO as:
( )
This equation is called the " classic streeter-phelps oxygen sag curve"
( )
( )
Page 3 of 4
Seventh Lecture Water resources and their characterization- river 4
Oxygen Sag Curve
( )
Page 4 of 4