Contract and Claim Dispute Management in The Infrastructure and Energy Sector
Contract and Claim Dispute Management in The Infrastructure and Energy Sector
dispute management
in the infrastructure
and energy sector
Contents
Be a future-ready leader 4
Role of digitalization 6
Managing claims 10
Be a future-ready leader
Importance of contract, claim and dispute management
Rapid urbanisation and growing demand mean that the construction industry is one of the largest industry
sectors in the world, consistently poised to outpace the world GDP1. However it is also one of the most
sluggish in terms of adapting to change to match its productivity growth as compared to demand.2
Global economy
$37/hour
Global construction
sector
$25/hour
Average value added by employees per hour worked1
1
2015 data in real 2005 dollars
This can be attributed to a variety of challenges affecting survey from 2019, the problems of cost and time
the industry productivity, profitability and sustainability. overruns continue to plague the industry with as many
We are witnessing that delivery of projects on time and as 6 out of 10 construction projects failing to meet the
within budget remains a major point of concern for cost and schedule projections.4
both the market players intent on retaining their profit
The global Covid-19 pandemic of 2020 exacerbated this
margins and the contracting parties which need timely
problem, with project suspensions and remobilisations,
delivery of the construction project. Looking at some
not to mention considerable supply-chain delays and
of the more global industry trends of the last 5 years,
reduced availability of on-site manpower, potentially
in 2016, a major survey concluded that large projects
leading to mega disputes. The sub-optimal construction
typically take 20% longer to finish than scheduled and
productivity levels are estimated to result in a loss to
are up to 80% over budget,3 and according to another
the global economy approximating around USD 1.63
trillion annually. A critique heard often is that there
exists a ‘perceived lack of urgency’ in adopting necessary
1 GCP Global/Oxford Economics, Global Construction 2030: A global forecast for changes required to arrest the spread of uncertainty in
the construction industry to 2030.
2 McKinsey, Reinvention Construction through a productivity revolution, February contract disputes.
2017, https://www.mckinsey.com/industries/capital-projects-and-infrastructure/
our-insights/reinventing-construction-through-a-productivity-revolution.
3 McKinsey, Imagining Constructions Digital Future, June 2016, https://www.
mckinsey.com/industries/capital-projects-and-infrastructure/our-insights/ 4 Compass International, Construction Project Cost Overruns, 25 July 2019, https://
imagining-constructions-digital-future. compassinternational.net/construction-project-cost-overruns-part-two/.
Contract and claim dispute management in the infrastructure and energy sector
disputes is USD 33 million and the 8 Arcadis, Report on Global Construction Disputes 2019, https://www.arcadis.com/
media/5/D/1/%7B5D16141D-B883-4398-BB35-218023E1F4F6%7DRP_GCDR_
global average length of disputes AL20190620_Final.pdf, and KPMG, Global Construction Survey 2019: The Future-Ready
Index: Leaders and followers in the engineering and construction industry, https://assets.
increased to 17 months.6 kpmg/content/dam/kpmg/xx/pdf/2019/04/global-construction-survey-2019.pdf.
6
Role of digitalization
A golden rule of disputes in major projects is to “cut In short, digital processes can be used to:
through the noise” and present the most compelling
• Create, assign, prioritize tasks
evidence in the simplest manner possible. This not only
makes for a more coherent claim, but also increases the • Immediate notifications
chances of a win! Thus, a key question before companies
• Check real time status of work progress,
now is how to organise their contract management
updates, revisions and plan changes
processes in the most cost efficient way.
• Monitor crew deployment
For instance, if we look at 2020, we can see that critical
infrastructure and construction were classified by most • Update and track compliance checklists
countries as a ‘critical activity’ during the COVID-19 • Maintain updated records, which are easily
pandemic and allowed to continue operations, albeit accessible, of all project related communications
with increased rules and unavoidable disruptions.
Several other projects were suspended due to financial • Upload, create standardized documentation
issues and other woes, and were already, or may be • Claims Management
restarted. This situation only serves to highlight the
importance of going digital as the quantity and quality of It is now accepted that today, a digitalized and
documentation will play a key role in how the disputes efficient project management system is a key driver for
in these projects are resolved. It is imperative that a successful project execution. Use of electronic document
system is adopted which can segregate issues arising management software not only helps streamline the
directly from the pandemic and those not related. contract processes and maintain a chronology of
The broader learning however, is that for any company events, especially for claim management, it facilitates
to survive and compete long-term, adopting a system early review and filtering and analysis of documents
which enables good contract management should now to prepare the best possible narrative for a party for
be the standard, as opposed to an emergency measure. making or defending a claim. As the leading innovative
law firm in Europe and a standout for its expertise in
This is where the use of digital tools comes in, helping dispute resolution,9 Hogan Lovells offers complete
to create centralized structures which facilitate legal support to contract management and dispute
streamlining of not only the contract but also claim resolution through all of the stages of a project from
management. Used properly, digital tools can help inception to completion. This service is based on use of
with properly archiving project documents, monitoring digital project management tools integrated with legal
of contract provisions and deadlines, as well as functions to craft an effective way forward for contract
standardising project correspondence in line with and claims management in the construction industry.
contractual requirements.
9 Hogan Lovells once again named one of the most innovative law firms in Europe by the Financial times; 13 September 2019; https://www.hoganlovells.com/en/news/
hogan-lovells-once-again-named-one-of-the-most-innovative-law-firms-in-europe-by-the-financial-times.
8 Hogan Lovells
The execution phase of the project is a crucial phase for team, who may not always be familiar with the specific
contract management. As the work progresses, changes provisions and timelines of the project contract. This can
to the contract must be effected based on real-time lead to unclear demarcation of roles and responsibilities
situations and events during the project implementation. of key personnel and workers involved in the contract.
At this point, all contract documentation should be From a legal perspective, it is important that the project
kept up-to-date and consistent so all parties have a personnel have the legal know-how of the terms of the
common view of potential and agreed changes to avoid contract and any related consequences. We are aware that
the unnecessary errors which often give rise to disputes. in addition to use of current technology, enhancing the
It is common for disputes to arise on the field and technological capabilities of personnel and integrating
correspondence on the same must be duly preserved to innovative processes into the overall project culture have
avoid future complications. This is also the stage when a huge impact on the successful outcomes in any project.
typically, new members are introduced to the project
Managing claims
Claims management is an important part of contract management and involves logging of issues,
maintenance of records and claims from the beginning of the dispute itself. Over 2019-2020, it has
emerged, globally, that ‘poorly drafted, incomplete or unsubstantiated claims’ is the number one cause
of construction disputes.
Major challenges in claim management have been non- availability of key personnel involved with
identified as i) collection and retrieval of key information the claim or the project, claims being barred by
and documents ii) knowledge and adherence to contractual or statutory time limitations or generally
contractual and statutory time limits and conditions prolonged negotiations and loss of motivation.
iii) managing claims under foreign law iv) gathering
Proper claims management procedure which combines
key witnesses and experts v) presentation vi) deciding
the benefit of expert legal advice with technology can
whether to settle a claim or initiate formal procedures
help address the challenges outlined above.
such as arbitration or court litigation.
It is evident that claims management involves
To minimize errors, the following key considerations
inculcation of a better understanding of the key
should be kept in mind:
functions of project management at different contract
• Preparation for and seeking opportunities to avoid stages (as outlined earlier) and integrating them.
litigation even prior to the loss emergency response, With a deep rooted understanding of the industry
business resumption and disaster recovery. processes and the working environment, lawyers
especially are equipped with the necessary skills to act
• Gathering information related to the claim – this
as integrators and provide a system which will make
should be an ongoing process. Ensuring thorough,
project and claims management tasks simpler and
detailed and streamlined communication between
time efficient.
the necessary partners and teams and providing
continuous feedback, factoring in issues relating Claim management, at its core, is a legal exercise which
to applicability of foreign law in cross border spans the breadth of a project. Having legal oversight
transactions which often involve application of of claims management is useful in many instances.
different laws from different jurisdictions and For example, companies have to observe more caution
different judicial practices. while communicating with the other party, as all
emails, documents, meetings and exchanges between
• Acting quickly – One of the many reasons why
the parties are open to examination during the dispute
claims fail is because they are not raised at quickly
procedure. There have been countless instances wherein
or at the appropriate time. Once a claim is delayed,
the different teams send separate communications to
it becomes more onerous to pursue and/ or defend
the other party without having consulted with each
the same. This can be attributed to factors such
other, or without knowledge that a dispute has arisen,
as factual distortion over a period of time, oral or
which can have the unintended effect of weakening a
verbal agreements made in urgency on the field,
parties position in a dispute.
Contract and claim dispute management in the infrastructure and energy sector 11
A typical ‘work-out phase’ of a project cycle is all about management’s briefing as well as for subsequent briefings
assessment of deliverables, checking whether all if new findings necessitate changes to the chances and
loose- ends are tied-up and getting a final evaluation of risk assessment.
the project. Thus, once the project nears completion, in
this phase the parties often raise claims from disputed
variation orders, time extensions, or open punch list Decision tree analysis diagram:
items. It is also not rare for parties to raise inflated
claims to get leverage in settlement negotiations and to
avoid any potential limitation issues. The downside to
this of course is that a higher gap between the mutual
claims makes it more difficult it is to reach a settlement. Was claim addressed within
Escalation of disputes leads to retention of payments, due time?
and invocation of guarantees which potentially trigger Contractual deadline exceeded
emergency court proceedings. Again, a key driver of this Deadline invalid under German law?
is the improper contract management by the project
parties, disabling them to fully assess the substance of
their claims.
Timeliness is the need of the hour. To be able to
conduct settlement discussion on reliable grounds and
to weight the alternatives to proceed with the dispute,
it is imperative for the project parties to get quickly an
overview on its rights and obligation. To this end, we offer
an Early Case Assessment analysing the legal issues of Deadline validly agreed
highest relevance and give recommendations on how to
proceed. Early Case Assessment is typically conducted Claim €40m
within a few weeks and at modest costs.
A typical Early Case Assessment process commences
Deadline invalid
with identifying and defining the legal hypothesis for
actual and potential claims vis-a- vis the contractual
terms and conditions and available facts. A set of core
documents are selected and examined at this stage to
assess the chances and risks of the case. If required,
initial interviews of key members of the project team
are conducted to assess the facts further. Tools such as
process charts and decision trees may be used to simplify
and visualize the findings, which will be beneficial for the
Contract and claim dispute management in the infrastructure and energy sector 13
33.33%
€40m
€40,000,000
70.0% 33.33%
Obstruction by employer €20m
0 €20,000,000
33.33%
50.0% €0
€0
0
30.0%
No obstruction by employer
0
50.0%
0
Summary
Claim €40,000,000
Fictional expected value
Expected litigation costs €2,500,000
Fictional award
Fictional portion of expected litigation costs
Zone of agreement
14 Hogan Lovells
Disputes, whether minor or substantial, can arise at any stage of the project once the contract has been
executed and may relate to i) pre-contractual issues such as bid clauses ii) provisions pertaining to
contract which include disputes regarding payments made under the contract, problems encountered in
execution such as change in ground conditions, unforeseeable events etc., risk allocation provisions and
time extension claims iii) breach of warranty, misrepresentation or negligence claims.
Good project management entails that such disputes Moreover, as the outcome of the dispute tends to turn
are resolved as quickly as possible to limit exposure; on facts, construction disputes are also generally very
however, it is often observed that disputes are evidence heavy and involve scrutiny of vast quantities
postponed for resolution at a later date – this could be of documents ranging from communications, technical
due to lack of understanding of procedure and follow reports, records of plans and schedules etc. For large and
up on claims, or other extraneous issues like change in complicated projects, this can run into tens of thousands
management. The tendency to avoid dispute resolution of pages and renders document review a complicated,
can result in a collective bunch of claims, which end inefficient and exhausting process.
up get escalated to formal dispute resolution processes
For complex cases involving vast quantities of
costing time and effort.
documentation and evidence, digital tools for document
Another aspect to keep in mind is to formulate and recovery are being increasingly utilized to help minimize
figure out the right mechanism for resolution. One time and cost of dispute resolution. Such technology-
can approach the courts; however, the nature of assisted review (TAR) software utilizes machine learning
construction disputes, especially in large and complex algorithms to assess the relevance of a document.
projects, is often very technical and involves application This algorithm is based upon review and ranking of a
of several contractual provisions at the same time. small sample of documents by a lawyer which is analyzed
Thus, in major energy and infrastructure projects, and incorporated by the software. Research on the
disputes usually escalate in stages: parties can choose subject has also revealed that a lawyer only needs to
between a myriad of options such as mediation, review 1.9% of the documents to get better results than
expert determination, adjudication boards and finally, a full manual review.10 As a result important documents
arbitration. It is important to ensure that the forum are reviewed first and are less likely to be missed and
chosen fits the needs of the parties and is appropriate irrelevant documents can be excluded from manual
with regard to the nature and size of the claim to curtail review. Such technology is gaining wider acceptance
prolongation and expenses. even within court of laws as a credible method of
document review.
Power Plant
#28
16
Broadly, it can be summarized that preventing we advise on and implement advanced technology
inefficiencies in project management and occurrence solutions for the management of information in
of disputes is a three-step process. disputes and investigations. We use our market
knowledge and strong relationships with external
• Adequate contractual framework that envisages
providers to find the best technology option for our
potential events
clients and help control costs.
• Timely risk assessment and allocation
Adopting an innovative technology driven model
• Fostering a more transparent and agile project has multiple benefits such as enhanced productivity,
culture with defined project goals resolution of disputes in a collaborative or timely
manner and lower costs. By combining our industry
Hogan Lovells is a leader in providing support solutions
knowledge and experience with digitalization potential,
on highest professional level with state of the art legal
we can help you address challenges throughout
tools. We have a specialist in-house resource, part of
the life- cycle of a project through project support,
a global firm wide team that can offer cross-border
compliance analysis risk assessment and effective
solutions. Applying our expertise and experience,
dispute management and resolution processes.
Contacts
Lead legal adviser for the Umm One of the most innovative law
al-Hayman Wastewater Project. firms in Europe (ranked 2nd) by
Middle East PPP Deal of the Year the Financial Times, 2020
Alicante Milan
Amsterdam Minneapolis
Baltimore Monterrey
Beijing Moscow
Birmingham Munich
Boston New York
Brussels Northern Virginia
Budapest* Paris
Colorado Springs Perth
Denver Philadelphia
Dubai Riyadh*
Dusseldorf Rome
Frankfurt San Francisco
Hamburg Sao Paulo
Hanoi Shanghai
Ho Chi Minh City Shanghai FTZ*
Hong Kong
Houston
Silicon Valley
Singapore
www.hoganlovells.com
Jakarta* Sydney
Johannesburg Tokyo “Hogan Lovells” or the “firm” is an international legal practice that includes Hogan Lovells
International LLP, Hogan Lovells US LLP and their affiliated businesses.
London Ulaanbaatar*
The word “partner” is used to describe a partner or member of Hogan Lovells
Los Angeles Warsaw International LLP, Hogan Lovells US LLP or any of their affiliated entities or any employee
or consultant with equivalent standing. Certain individuals, who are designated as
Louisville Washington, D.C. partners, but who are not members of Hogan Lovells International LLP, do not hold
qualifications equivalent to members.
Luxembourg Zagreb* For more information about Hogan Lovells, the partners and their qualifications,
see www.hoganlovells.com.
Madrid Where case studies are included, results achieved do not guarantee similar outcomes
Mexico City *Our associated offices for other clients. Attorney advertising. Images of people may feature current or former
lawyers and employees at Hogan Lovells or models not connected with the firm.
Miami Legal Services Centre: Berlin © Hogan Lovells 2021. All rights reserved. 1163050_0121