Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

THE REPUBLIC OF UGANDA

IN THE HIGH COURT OF UGANDA AT KAMPALA

CIVIL SUIT NO. 423 OF 2014

SOUTHERN RANGE NYANZA LIMITED :::::::::::::::::::::::::::::::::::::::::::::::::::::::PLAINTIFF

VERSUS

UGANDA NATIONAL ROADS AUTHORITY:::::::::::::::::::::::::::::::::::::::::::DEFENDANT

VERSUS

COWI LIMITED::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::THIRD PARTY

JUDGMENT

The plaintiff filed this suit seeking for a declaration that the defendant owes the plaintiff

a sum of Uganda Shillings thirty billion four hundred seventy eight billion (UGX

30,478,000,000) arising out of a claim for injurious affection suffered by the plaintiff

owing to expropriation of its property, special damages, and general damages of

2,000,000,000/= interest and costs of the suit.

In 2010 the 1st defendant planned and sought to construct a new bridge across River

Nile at Jinja Uganda. Part of the Plaintiff’s land comprised LRV 403 Folio 3 Plot No. 22-

52 and 21-51 Yusuf Lule road, Njeru Town Council was identified as the most optimal

alignment for construction of the New Nile Bridge. Through the Chief Government

Valuer, the land was assessed a valuation report generated. In accordance with the

report, the 1st defendant made an offer of UGX 8,980,810,000/= being compensation

particularly for the administration block –UGX 1,150,000,000/=, bonded warehouse –

UGX 6,210,000,000/=, weighbridge – UGX 6,210,000/=, parking shed – UGX 13,800,000/=,

site works – UGX 296,700,000/=, residential block – UGX 92,000,000/=, land-Plot 22-52 &

21-51 – UGX 1,186,800,000/= and Plot M-35 – UGX 25,300,000/= plus 15% Disturbance

Allowance making a total of 8,053,260,000/=


At the point of effecting the said compensation to the plaintiff, it raised several fears of

some of its properties being injuriously affected by the construction works and it was

agreed between both parties that further consultations would be made at the design

stage to consider all effects identified in the Resettlement Action Plan and that it is at

that point that all issues raised by the plaintiff would be addressed. At the design stage

however, the plaintiff’s claims for further compensation were not considered.

At the time of filing this suit, the construction of the New Nile Bridge had since began

without the assessment of the plaintiff’s injurious claim. The construction was

completed and the 1st defendant contends that the construction works were carried out

up to the end without occasioning any damage (as earlier feared) to the plaintiff’s

factory. The plaintiff claims that the defendant breached its promise to compensate it.

The plaintiff further claims that when its certificate of title formerly pledged as security

to Bank of Baroda (plaintiff’s banker), was released to the defendant and not returned

within the agreed 90 days, it suffered business loss as it could no longer access credit

facilities. It was on that claim that the defendant joined the third party to this suit

claiming to be entitled to a contribution and/or indemnity from the Third Party for any

liability, loss, damages or costs which the plaintiff claimed from the defendant as a

result of the delay to return the title.

Representation
The plaintiff was represented by Mr. Mugabi Enoth while the defendant was presented
by Mr. Kamya Titus and Mr Pecos Mutatina while the Third Party was represented by
Mr. Mubangizi Absolom
During Scheduling, the following facts and issues were agreed upon by the parties.

Agreed Facts

• The plaintiff is the registered proprietor of land comprised in LRV 403 Folio 3,
Plot No. 22-52 and 21-51 Yusuf Lule Road, Njeru Town Council.
• The defendants expropriated part of the suit land for the New Bridge
Construction.
• The plaintiff was paid and acknowledged receipt of compensation of Ugx
8,980,810,000/=, which comprised payments in respect of expropriation of
Administration block, Bonded Ware house, Weigh bridge, site works, Residential
Block, Parking Shade, land and a 15%Disturbance Allowance.
• The suit land certificate of title at expropriation had been pledged as security to
Bank of Baroda for a Loan by the plaintiff, that was released by the Bank to 1 st
defendant for sub-division and transfer of the expropriated portion.
Agreed Issues

1. Whether the plaintiff suffered any compensable loss over and above the
compensation of UGX 8,890,810,000/= that was payable by the defendant as a
result of the acquisition of the suit land for which the defendant is liable.

2. Whether the dispute between the defendant and Third Party should be referred
to Arbitration.

3. Whether the Third Party is liable to indemnify the defendant as claimed.

4. What remedies are available to the parties?


The parties filed final written submissions that were considered by this court.

RESOLUTION OF ISSSUES

Issue 1: Whether the plaintiff suffered any compensable loss over and above the

compensation of UGX 8,890,810,000/= that was payable by the defendant as a result of

the acquisition of the suit land for which the defendant is liable.

According to the plaintiff, the compensation received was on condition that the

defendant first address the concerns raised at the design stage something that the

defendant did not do. The plaintiff had fundamental credible concerns to the operation

of the factory, possible interruption with production in the event of disabling the

functioning of the Effluent Treatment Plant, any changes to the plaintiff’s operation

flow and resultant operational changes, inconvenient use and access of staff canteen
and Archives Section Development as well as dust and heavy vibrations expected

during the construction phase of the bridge reaching equipment located close to the

highway.

The defendant on the other hand submitted that the plaintiff was promptly &

adequately compensated for the acquisition of its land and as such suffered no loss

attributable to the defendant’s actions. Counsel further submitted that the plaintiff’s

fear at the time it received the compensation was that if the issues raised then, remained

unattended to, its factory would be severely affected by effects of the construction

works however approximately 3 years since the New Nile Bridge project was

completed, the plaintiff is fully operational and functioning without any effects

registered.

Compulsory acquisition of private land for public use or interest is provided for under

the Constitution which also highlights the principle of adequacy of compensation. The

principle of adequacy of compensation is enshrined under Articles 26 (2) and 237 of our

Constitution. Article 26 (2) provides for the prompt payment of fair and adequate

compensation, prior to taking possession or acquisition of the property for public use

in the event of compulsory land acquisition especially in instances where the land is

required for public use or interest.

In this case the plaintiff contends that it was not adequately compensated. That it was

paid and acknowledged receipt of conditional compensation of UGX: 8,980,810,000

which comprised payments in respect of expropriation of; the Administration Block

(Modern & Executive Single Storied), Bonded Ware House, Weigh Bridge, Site Works

(2), Residential Block and land and a 15% disturbance allowance.

From the evidence on record, on the 9th July 2013, the plaintiff, the defendant and CGV

visited the suit land, to which it was thereafter agreed there were fundamental credible
concerns to the future operation of the plaintiff of possible interruption with production

in the event of disabling the functioning of the Effluent Treatment Plant (referred as the

“ETP”) literally disabling the factory from operation among others.

It was agreed, the CGV would nominate 2-3 names of consultants to carry out the

injurious affection claim for the plaintiff, the defendant would coordinate the

procurement of the consultants with the objective of enabling CGV receive the

independent consultants report within 40 days (by the end of August 2013) to guide the

settlement of the plaintiff’s injurious affection claim. The CGV recommended three

consultants from whom one was to be designated by the defendant to undertake the

assessment however no appointment was done of the three (3) consultants

recommended by the CGV and no assessment was done by the defendant during the

design stage and throughout the entire project construction period which prompted the

plaintiff to file this suit. It was the plaintiff’s submission that, the compensation paid to

the Plaintiff was conditional.

The plaintiff submitted that the defendant undertook to consider the concerns raised by

the Plaintiff at design stage. To-date the New Nile Bridge is completed and in use,

without the consideration raised by the Plaintiff being considered/assessed, contrary to

the “Principle of Equivalence”. The plaintiff’s counsel submitted that, at Page 18

Paragraph 6.8 of the GCALA it is noted Severance and Injurious Affection; assessments of

the value lost due to injurious affection and severance would have to be undertaken and included

in the compensation. Severance occurs when the land acquired contributes to the value of

the land which is retained, so that when severed from it, the retained land loses value

while injurious affection is the depreciation in value of the property as a result of the

proposed construction and use of the land acquired by the acquiring authority for the

scheme and its treatment should be as provided for in the Common Law.
The plaintiff submitted that the orphaned land measuring approximately three (3) acres

across the road, severed as a result of expropriation has been rendered cumbersome to

use-confirmed by DW2, which entitles the Plaintiff to a “severance damage”.

Furthermore, it was the plaintiff’s case that it has suffered indirect loss as expounded by

its’ testimony and elaborated by a self-help prepared Consequential Loss Quantification

Report - EXHIBIT P17. The loss as expounded in this report is non-physical entitling

the plaintiff to compensation for “Injurious Affection”

The defendant submitted that whilst the parties had agreed by minutes 9th July, 2013

that the CGV would nominate 2-3 consultants to be tasked to assess the injurious

affection claim from the plaintiff that was prepared by M/S SURVESIS, the plaintiff

later changed its claim as prepared by Survesis and instead procured D. Craven

Consulting to prepare the Consequential Loss Compensation Claim Report, contrary to

the consultants nominated by CGV and the Report referred to by the CGV. This in effect

altered that agreed terms resulting in each party relying on its own independent

consultants. The plaintiff is therefore estopped on making reference to the initial

arrangement or to insist on the assessment by the CGV in the circumstances. If the

plaintiff believes that the CGV should have assessed the alleged consequential loss, it

should have submitted its experts report to the CGV for his assessment which it failed

to do.

Counsel for the defendant further submitted that while the plaintiff seeks for costs of

replacement, relocation and re-alignment of various facilities, no evidence was led to

show that following the completion of construction of the New Nile Bridge, there was

need to replace, relocate and realign the said facilities. There was no technical expert or

engineer who testified on part of the plaintiff to prove the effect if any on the facilities

before, during and after construction of the bridge. The only expert report was prepared

by D. Craven Consulting (Chandi Jamwa) who did not appear in court to defend their
report. It is noteworthy that these were neither engineers nor valuers. Indeed the

defendant’s documents P.17 and Exhibit D4 being the Expert Valuers reports prepared

by Knight Frank (Judy Rugasira-MD) and UNRA Land Valuation Department Report

(Solomon Arinaitwe, accompanied by a Civil Engineers report Morris Odwoch)

respectively clearly show that the plaintiff’s said facilities/properties were not affected

following the completion of the bridge and there was no need for relocation, re-

alignment or replacement of the same.

The following were the concerns raised by the plaintiff prior to the construction of the

New Nile Bridge as discussed by the defendant in their submissions;

The staff canteen and archives section that would be cut off from the main factory

rendering its access and use impossible.

According to the plaintiff, the staff canteen and archives section development would

remain situate across the bridge following the bridge alignment hence use of these

facilities would be compromised. The plaintiff would not be able to use these facilities

conveniently as it would have wished.

The defendant submitted that during trial the plaintiff’s director Mr. Richard Mubiru

confirmed that the staff canteen and archives stores are still in place and can be accessed

from the Njeru part. PW2 testified that the plaintiff had incurred additional business

related costs because of hiring more space for storage and canteen services. Through

cross examination, the PW2 testified that the canteen is still there and that some staff

live there accessing it through an alternative route. The plaintiff rented space from

picfare a sister company of the plaintiff where the canteen is now situate.

The plaintiff also contended that it had to rent archives stores in Kampala upon the

expropriation of their land. PW 2 Sanjeev Sharma during cross examination testified

that the renting of office premises in Kampala, instead of Njeru was for the convenience
of the plaintiff and not the New Nile Bridge project. He testified that previous archives

and store are still accessible and they sit on a plot of land of about 3 acres which has

ample parking space.

The defendant submitted that since the archives section is accessible, the plaintiff

should not be paid for the cost of hiring stores and archives in Kampala for convenience

purposes. Since PW1 testified rightly so that the archive stores and staff canteen were

not among the buildings expropriated by the Defendant and where thereby not

affected, they remained accessible and senior management still uses the canteen for its

meals, counsel invited court to find that there is no justification for this claim for

payment of alternative stores and canteen as these were purely for the convenience of

the Plaintiff.

Permanent increase in the cost of production due to expropriation of the raw material

warehouses which shall permanently affect the vertical production process flow,

hence increased cost of production on account of transport cost for raw materials.

The plaintiff seeks for costs of relocation of the raw materials ware house. The plaintiff

claimed that it might suffer a permanent increase in the cost of production due to

expropriation of the raw materials ware house.

The defendant on the other hand submitted that the warehouses were compensated for

by the defendant with a 15% disturbance allowance, which fact is acknowledged by the

Plaintiff. Therefore, a claim for relocation of the same is superfluous, frivolous and

vexatious, because under compulsory land acquisition, one is already compensated to

relocate a structure from the expropriated land.

Costs of relocation of the Spinning Department

The plaintiff seeks for costs of relocation of the spinning unit stating that it might suffer

vibrations from the bridge affecting the spinning unit.


The defendant submitted that no evidence of vibrations affecting the spinning unit was

led or proved by the Plaintiff. On the contrary the defence Reports Exhibit P. 17 and

Exhibit D4 show that neither the spinning unit nor the rest of the plaintiff’s factory was

or is affected by vibration from the traffic on the New Nile Bridge. Both Plaintiff’s and

Defendant’s witnesses confirmed that the spinning unit was not affected by the

expropriation of part of the plaintiff’s land for construction of the New Nile Bridge. At

the time of receiving compensation, the plaintiff feared that during the construction

stage, there would be a possibility for vibrations and dust resulting in to impossibility

for the plaintiff to maintain the spinning department at its current location and

therefore it needed to have the same relocated to avoid such effects.

Counsel for the defendant further submitted that at the time this claim was raised it was

speculative because the construction works had not commenced and so it was

unreasonable for the plaintiff to demand its spinning department to be relocated.

Counsel concluded that this claim was overtaken by evets hence untenable under law.

Enhanced security at the present spinning department.

It was the defendant’s submission that from the evidence adduced, it is clear that the

spinning department was not affected by the construction of the bridge and there was

no need to relocate the same. Furthermore, increased security at the present spinning

department or elsewhere at the factory as a result of expropriation of land is a claim too

remote and this inconvenience if any, is catered for in the 15% disturbance allowance.

Costs for relocation of the administration blocks and raw material ware houses.

PW3 Richard Mubiru during cross examination testified that the administration block

and warehouses were compensated. There is no need for this court to address this

concern.
Relocation of the Effluent Treatment Plant (ETP), without which the process house

cannot work.

PW3 testified that after construction of the bridge, the ETP was affected. He testified

that the channel that evacuates water from the effluent plant is underneath the bridge.

He further testified that channels of this nature once they are covered they can’t be

opened since they are susceptible to blockages which could then kill off the entire

facility. The witness also testified that they were experiencing leakages affecting the

operations of the plaintiff.

The defendant’s second witness testified that the defendant mitigated any damage to

the factory to ensure its continued operation which wasn’t interrupted. The ETP was

protected by site hooding. Exhibit D4 appendix 1 showed that the ETP and sewerage

system were protected which enhanced and improved the plant’s capacity extending its

functional life as per DW2.

Counsel for the defendant submitted that during trial the defendant led evidence (see

appendix 1 of Exhibit D 4) to show that the effluent line crossing the project site was

encased in high strength concrete which eliminates any possibility of future leakage

because even if the encased asbestos pipe is worn off, the hollow section equivalent to

the external diameter of the pipe would have formed the high strength concrete that

would successfully facilitate the flow of the effluent liquid. In addition, all effluent

manholes within the site area were improved under the project cost on the request of

the plaintiff. Furthermore, there is no structural loading on the encased pine running

from the effluent treatment plant across the project area to the downstream side that

will endanger or affect the functionality of the pipe as shown in the photos and notes on

page 1 of Appendix 1 to Exhibit D4. Consequently, there was no need for the

construction of a brand new Effluent Treatment Plant because the existing one was not

affected. Counsel further submitted that the plaintiff’s insistence on the second
assessment of the issues that remained unattended to is misconceived and of no effect

the construction works having ended without the feared damage taking place.

Relocation of other critical infrastructure like power, drainage channels underneath

the present factory for storm water, whose blockage at construction would mean

flooding of the entire place.

Counsel for the defendant submitted that the plaintiff reasoned that if infrastructure

like power and drainage channels were affected at the construction stage, it would be

difficult to avert any likely damage but adduced no evidence of damage caused to the

power lines and drainage channels during construction to warrant the compensation

claimed.

PW1 testified that there were no electricity lines in need of relocation within the right of

way.

Counsel further submitted that in any event from the evidence adduced in court, the

construction is now completed and there has not been any electricity, water or sewage

lines that were cut off or rendered nonfunctional by reason of the expropriation and

construction of the New Nile Bridge.

The super sensitivity to vibration and dust by hugely electronics based machinery in

the spinning department.

The plaintiff contended that the bridge alignment being too proximate to the spinning

department that has hyper dust and vibrations sensitivity machinery, there would be a

high likelihood that the equipment would be damaged.

Under Minute 2 following the meeting of 9th July 2013, it was noted by the plaintiff that

the large electronics driven machinery and equipment- spinning department located
close to the highway would obviously reach by dust and heavy vibrations expected

during the construction phase.

The defendant led evidence (see appendix 1 of Exhibit D4) during trial that best

construction methods were used by the contractor whereof a retaining wall of

approximately 4 meters high bordering the plaintiff’s premises and the right of way

before actual road works which effectively eliminated the impact of vibration on the

adjacent properties.

Analysis

The court shall now resolve the concerns raised by the plaintiff and claims of injurious

affection and severance.

The plaintiff claimed that it suffered injurious affection severance. As cited by counsel

for the plaintiff, Paragraph 6.8 of the Guidelines-for-Compensation-Assessment-

under-Land-Acquisition (GCALA) provides for severance and injurious affection;

assessments of the value lost due to injurious affection and severance would have to be

undertaken and included in the compensation.

Severance; occurs when the land acquired contributes to the value of the land which is

retained, so that when severed from it, the retained land loses value. For example, if a

new road is built across a field, it may no longer be possible to have access by vehicle to

part of the field, rendering it virtually useless and therefore less valuable.

Injurious Affection; injurious affection is the depreciation in value of the property as a

result of the proposed construction and use of the land acquired by the acquiring

authority for the scheme and its treatment should be as provided for in the Common

Law. Claims arising injurious affection under Common Law may include lack of access

to homes, amnesties, means and sources of livelihood, drainage, privacy, noise and

compatibility of existing land use among others. It is the impact of the whole of the
proposed scheme that is to be considered not just the effect on the area acquired from

the land owner.

In the case of Abbey Homesteadys Group Ltd v Secretary of State for Transport [1982] 2

EGLR 198 The land Tribunal found that compensation for land taken must be as a

matter of law be assessed separately from compensation for severance and injurious

affection to the land retained. In the present case, it appears both assessments for the

land and possible assessment of loss where done together and the practice is more

convenient, although the plaintiff had anticipated more loss which lead to the filing of

this suit which never happened.

Compensation for severance and injurious affection therefore represents the difference

between the value of the retained land ‘with or ‘without’ the project. In the case of

Melwood Units Pty Ltd v Commissioner of Roads [1979] 1 All ER 161; The Privy

council noted that it is permissible to apply the Pointe Gourde principle to the

assessment of compensation for severance and injurious affection as well as for

compensation for land taken. Therefore any increase or diminution in the value of

retained land due to matters having developed in a different way because of the scheme

should be left out of the account.

The valuation of compensation for the land acquired and compensation for injurious

affection for the retained land must be made on a consistent basis as noted in the case of

Horn v Sunderland Corporation [1941] 2 KB 26.

A claim for depreciation in the existing use value of retained land should be resisted to

the extent that such depreciation would have been an inevitable consequence of

dividing the land for the purpose of realising a price for development purposes for the

land taken. The main objective should be to ensure that- within what the law allows-
the claimant receives in total compensation no less, but more, than the claimant’s real

loss.

With those guidelines and principles in mind, court ought to determine whether the

plaintiff’s circumstances fall within the stipulation above.

All the witnesses called by the parties testified that the alleged orphaned land can still

be accessed by the plaintiff. PW1 testified that the staff canteen remained accessible and

senior management still uses the canteen for its meals whereas the archives are used as

residences for some of the staff. Indeed, the plaintiff witness confirmed that the archives

were transferred to Kampala for their convenience and not necessarily due to

inaccessibility.

The plaintiff’s land was therefore not rendered virtually useless as a result of the project

however PW2 testified that it was disturbance for the senior management to move a

longer route than they usually used to stating that the distance from the factory to the

canteen was now longer than it was before. PW3 also testified that the old structures

were still in place but accessing the old canteen was inconveniencing hence the plaintiff

had to rent other premises leaving the original canteen to accommodate some of its

employees. PW3 further testified that like for the canteen, accessing the old archive

stores was possible but with difficulty. When asked by court why the archive stores

were then transferred to Kampala, PW3 testified that it was because of strategic

considerations.

From this evidence the court is comfortable to conclude that the plaintiff did not suffer

injurious affection and/or severance when it came to the orphaned land. The plaintiff

made a conscious decision to move their archive stores to Kampala alive to the fact that

the old stores were still accessible and available for use. It was not a decision that was

caused by the New Nile Bridge project. The same applies to the canteen, severance and
injurious affection cannot be claimed owing to the fact that the canteen is still accessible

and available on foot and by vehicle, is in use by senior staff and accommodates other

employees of the plaintiff. The inconvenience experienced by the plaintiff with regard

to a longer route is part of the general upheaval as a result of the expropriation was

provided for in the compensation awarded as part of the 15% disturbance allowance.

There is no stated basis upon which compensation for severance and injurious affection

should be assessed. The measure of compensation should be value to the owner and not

open market value. The damage due to severance mainly arises when the land acquired

reduces the value of the land retained. The measure of compensation in respect of

severance is depreciation in the value of the claimant’s retained interest arising from

severing of land acquired from the original whole. It is not known by evidence whether

the land in issue indeed reduced in value and on the contrary it could have increased in

value due to its accessibility on the main road. Compensation for severance and

injurious affection should relate to the depreciation in the market value of the

claimant’s retained interest. See Budgen v Secretary of State for Wales [1985] 2 EGLR

203; R A Vine (Engineering) v Havant BC [1982] 2 EGLR 15

The permanent increase in the cost of production due to expropriation of the raw

material warehouses which shall permanently affect the vertical production process

flow, hence increased cost of production on account of transport cost for raw materials.

The raw material warehouses were expropriated and compensated for as confirmed by

PW2. The consequences of their relocation were catered for under the 15% disturbance

allowance hence the plaintiff cannot credibly raise this is a concern to seek more

payment from the defendant.

Costs of relocation of the Spinning Department; the plaintiff’s witnesses did not lead

evidence to show that the plaintiff suffered was or is affected by vibration from the

traffic on the New Nile Bridge. It was therefore unreasonable for the plaintiff to relocate
the spinning department with no evidence of suffering dust or vibrations from the New

Nile Bridge to warrant its relocation.

The effect of compulsory acquisition may be to increase substantially the costs of using

the retained land. The cost of working on the land will however be reflected in its open

market value. It is therefore not the increased cost of using the land retained that can be

claimed but the depreciation in the open market value of that land following the

acquisition compensation for the liability of a claimant for the increased costs of

working the land comprises injurious affection and not disturbance.

Enhanced security at the present spinning department. There was no evidence from the

plaintiff’s witnesses to prove that the plaintiff has to pay above and beyond for

enhanced security as a result of expropriation. The court can therefore not make an

award in absence of evidence to back up this claim.

Relocation of the Effluent Treatment Plant (ETP), without which the process house

cannot work. PW3 when asked by defence counsel whether the ETP suffered any

damage attributed to construction of the bridge, he evaded the question however

testified that the plaintiff was experiencing leakages but did not reliably inform this

court whether the leakages were attributed to the construction of the bridge. The court

cannot engage in speculation to assign responsibility of the leakages to the defendant

for the leakages at the plaintiff’s factory.

Relocation of other critical infrastructure like power, drainage channels underneath the

present factory for storm water, whose blockage at construction would mean flooding

of the entire place. The plaintiff did not lead any evidence to prove that there was

relocation of any critical infrastructure as a result of construction of the New Nile

Bridge. With no evidence the court cannot reliably believe that there was any relocation

then or now after construction of the bridge.


The super sensitivity to vibration and dust by hugely electronics based machinery in the

spinning department. There was no evidence by the plaintiff to show that the hugely

electronics based machinery closely situate to the bridge was affected by vibration and

dust from the bridge. The defendant led evidence Exhibit D4 during trial that best

construction methods were used by the contractor whereof a retaining wall of

approximately 4 meters high bordering the plaintiff’s premises and the right of way

before actual road works which effectively eliminated the impact of vibration on the

adjacent properties. The court found this evidence reliable.

On that note, I find all the concerns raised by the plaintiff incredible. However the

defendant acted improperly and besides their agreement with the plaintiff, had they

honored their promise to assess these concerns before construction of the bridge these

concerns would have been ruled out earlier and the plaintiff’s fears laid to rest.

However, it was also a blessing in disguise since the court was able to assess the entire

project after its completion rather than making assumptions of the anticipated losses

arising out of the construction of the project.

In addition to the above, the plaintiff contends that they suffered loss as a result of the

defendant and 3rd party staying in possession of their certificate of title longer than the

agreed 90 days.

The Suit Land Certificate of title at expropriation had been pledged as security to Bank

of Baroda for a loan by the plaintiff that was released by the Bank to 1st Defendant for

sub-division and transfer of the expropriated portion. The Defendant returned the

residue Certificate of Title to Bank of Baroda on 11th May 2015. Counsel for the plaintiff

submitted that the defendant ought to have returned the Title to the Bank on 31st

September 2010 however the defendant contended that this period was extended. PW3

testified that the plaintiff took on best endeavours to seek for the return of the

Certificate of Title as borrowers. PW3 in cross-examination testified that the 90 days


were entered upon the clear background that the plaintiff had one certificate of title,

which was pledged to Baroda so the possibility of extension was not there because this

title was the only security for the business.

Counsel further submitted that because of the delay in return of the Title the Bank could

not enhance the Plaintiff’s borrowing limits, this curtailed growth. PW3 noted the

Plaintiff’s turnover increased on return of the title to 62.3 Billion in 2015, 74.6 Billion in

2016, 83.8 Billion in 2017, 88.7 Billion in 2018 and 108 Billion at end of 2019 from 56

Billion at end of 2014; which is a demonstration that the plaintiff had capacity to have

Bank of Baroda enhance access to working capital so as to cause business growth. This

explains clearly why the plaintiff’s turn-over that was UGX 41. 2 Billion in 2010 only

grew to UGX 62.3 Billion by end of 2015 in five years yet in the subsequent 4 years from

2015, turn-over grew to UGX 108 Billion. Clearly, the less than optimal business

performance as herein explained is directly linked to the less than optimal

borrowing/credit facilities up-take dictated by conditions visited on plaintiff by

defendant’s failure to return the title in 90 days.

The defendant on the other hand submitted although the parties had initially agreed to

ensure subdivision and return of the residue title is completed within 90days, there

were circumstances beyond the control of the defendant that necessitated the further

extension of time to complete the exercise and return of title. The parties having agreed

to waive the time, the same ceased to be of essence especially given the fact that the

parties collaborated to ensure that the plaintiff mortgages/credit facilities were

registered on the title while it was still in the custody of the land office.

Counsel further submitted that save for the allegations made by the Plaintiff that it

suffered such losses, no scintilla of evidence was produced in court of any credit

applications made by the plaintiff and rejected on grounds of non-availability of its title

whereas the defendant led evidence to show that even with the absence of the said title
from the plaintiff’s custody, it enabled the plaintiff to have all its facilities registered on

title. A perusal of the certificate of title particularly on the encumbrance page, it is

evident that all mortgages executed between the plaintiff and its bankers during the

period when the title was with the defendant’s agent COWI (June, 2010 – May, 2015),

the said mortgages were effectually registered on the title. This fact was not denied by

the plaintiff, in fact during cross examination both Sanjeev Sapkota Sharma-the

plaintiff’s Finance Manager and Mr. Richard Mubiru-one of the plaintiff’s directors

confirmed to court that the plaintiff obtained credit facilities from Bank of Baroda, its

banker between 2011 and 2015 (the period when the title was with the defendant’s

agents).

The plaintiff also contended that that it was charged interest of 3% following its excess

drawing beyond sanctioned limits of UGX 2.5 Billion and USD 3.75 Million. The

plaintiff relied on Exhibit P 11- a letter from Bank of Baroda wherein it was stated that

due to the plaintiff’s failure to prevail over the defendant to return its title, constrained

the bank’s capabilities to continue enhancing the plaintiff’s credit due to breach of

lending terms which thereby triggered penalties. Counsel for the defendant submitted

that the document ought to be studied cautiously owing to the fact that the letter was

written to the defendant by Bank of Baroda upon request from the plaintiff to provide

the defendant with information in respect of financing terms, particularly; regarding the

delay by the defendant to return the certificate of title. Counsel wondered why in the

first place this information (on penalties levied against the plaintiff as a result of non-

availability of title) was not available to the plaintiff itself.

Counsel for the defendant further submitted apart from the said letter, there is nothing

that was adduced in court showing the exact interest that was levied. The plaintiff

neither produced original sanction letters from the bank addressed to it detailing the

percentages and amounts that were to be levied for its alleged breaches of lending
terms, nor was there evidence of the bank accounts from which the alleged drawings

over the permitted limits were made and bank statements showing that interest levied

as a result of the said breaches.

The plaintiff also alleged to have missed a business opportunity to supply textiles to

South Sudan attributed to the defendant’s failure to return the title within the agreed 90

days. The defence counsel submitted that exhibit PE.19 (Annexture 10 reading contract

award from South Sudan; letter dated 8th December, 2014) presented showed a different

company (Ms. Southern Nytil Garments Ltd) from the plaintiff that was addressed. The

exhibit was not signed by the issuing authority. It fell short of a contract between the

plaintiff and the Government of South Sudan as alleged or an offer/bid. Furthermore

that plaintiff was at all times able to register credit facilities with on the title during the

period is issue. Therefore the claim that it missed a business opportunity on account of

the missing title is unfounded.

It has been clear from the evidence adduced before this court, the title not being in

physical possession of the plaintiff’s bankers did not stop the plaintiff from acquiring

credit facilities from the bank. This was confirmed by all three of the plaintiff’s

witnesses. The court concurs with counsel for the plaintiff that the title was returned out

of the time agreed by the parties however the plaintiff did not prove to this court what

loss was suffered as a result of this delay. Counsel’s submission that because of the

delay in return of the Title the Bank could not enhance the plaintiff’s borrowing limits,

this curtailed growth is not tenable since there was no evidence led by the plaintiff

showing that they were ever denied credit facilities by the bank as a result of not having

physical possession of the title. All evidence on the encumbrance page of the title shows

that the plaintiff continued to access credit facilities as usual despite the title being in

the possession of the defendant and/or third party. Secondly, the third party witness

also testified that the leases expired and they had to make applications for renewal.
The plaintiff contention that it was charged interest of 3% following its excess drawing

beyond sanctioned limits of UGX 2.5 Billion and USD 3.75 Million was also not reliably

proved before this court. The plaintiff relied on Exhibit P 11- a letter from Bank of

Baroda wherein it was stated that due to the plaintiff’s failure to prevail over the

defendant to return its title, constrained the bank’s capabilities to continue enhancing

the plaintiff’s credit due to breach of lending terms which thereby triggered penalties.

However evidence showed that even before the title was submitted to the defendant

there was still a clause saying 5% additional interest will be charged. PW2 in his cross

examination while explaining the bank’s sanctions and penalties testified that whether

the bank’s client has the title or not, it is standard of norms that the bank will penalize

this money. PW2 testified that these are standard norms of the bank whenever they

sanction any letters they always add that clause.

Furthermore PW2 did not reliably inform this court if the plaintiff had drawn beyond

the permitted limit.

The plaintiff also alleged to have missed a business opportunity to supply textiles to

South Sudan attributed to the defendant’s failure to return the title within the agreed 90

days. PW3 stated there was award for the contract but rather an invitation to quote for

the business. The plaintiff failed to prove correlation between the absence of the title

and the failure to be awarded the contract.

Therefore everything considered, I do not find that the plaintiff suffered any

compensable loss over and above the compensation that was paid by the defendant that

included 15% disturbance allowance. On that note, issue 1 fails.

Issue 2: Whether the dispute between the defendant and third party should be

referred to arbitration.
The involvement of the third party in this case is only limited to indemnification of the

defendant in the event court finds it liable to the plaintiff.

From my determination of issue 1, the court has found the plaintiff’s claim devoid of

any merit therefore the defendant is not liable in any way to the plaintiff. It would be

redundant for the court to delve further into the determination of this issue however

regardless of that it is worthy to note that had the defendant been found liable to the

plaintiff, the question of indemnity between the defendant and the third party would

have been referred to arbitration.

Although judicial power is an essential prerogative of any country, the parties may if

they express the wish to do so, give jurisdiction to arbitrators to settle their disputes.

However, a country retains the power to prohibit settlement of certain types of disputes

outside its courts.

The contract between the defendant and third party clearly stipulated that disputes

arising would be referred to arbitration. Despite this court being clothed with inherent

unlimited original jurisdiction under Article 139, it has also pronounced itself several

times that when it comes to arbitration this court it has limited jurisdiction in arbitration

matters as per section 5 of the Arbitration and Conciliation Act. It provides as follows:

“5. Stay of legal proceedings.

(1) A judge or magistrate before whom proceedings are being brought in a matter which is the

subject of an arbitration agreement shall, if a party so applies after the filing of a statement of

defence and both parties having been given a hearing, refer the matter back to the arbitration

unless he or she finds—

(a) that the arbitration agreement is null and void, inoperative or incapable of being performed;

or
(b) that there is not in fact any dispute between the parties with regard to the matters agreed to

be referred to arbitration.

(2) Notwithstanding that an application has been brought under subsection (1) and the matter is

pending before the court, arbitral proceedings may be commenced or continued and an arbitral

award may be made.”

The arbitration clause in the contract is very clear about referring any dispute between

the defendant and 3rd party to arbitration which both parties validly entered into and

there were no grounds in these circumstances warranting refusal of this dispute to

arbitration. Arbitration is ultimately a matter of consent. Parties’ intentions and

expectations and arbitrators’ discretion should be given priority.

The underlying basis of arbitration is that it is a consensual process in which parties

refer disputes to a neutral third party to make a binding decision. Therefore the

consensual nature and the principle of freedom to contract give the right to arbitrate

mutuality right to arbitrate which is so sacrosanct that negating it would be contrary to

public policy.

The court in British American Tobacco Uganda Limited vs Lira Tobacco Stores M.A

No. 924 of 2013 extensively discussed the jurisdiction of this court when it comes to

arbitration matters. Justice Christopher Madrama Izama held; “Before taking leave of this

issue, the Respondents Counsel referred to section 14 of the Judicature Act which provides for

the unlimited original jurisdiction of the High Court. However under section 14 (2) (a) of the

Judicature Act, the jurisdiction of the High Court shall be exercised in conformity with the

written law. Particularly under section 14 (2) (b) of the Judicature Act provides that subject to

any written law, the High Court may apply any established and current custom or usage. In

other words, any customs or usage is subject to the written law. The court therefore has no
jurisdiction or discretionary powers to try any customs or usages which are in conflict or not in

conformity with section 5 of the Arbitration and Conciliation Act.”

Where a valid arbitration agreement exists between the parties to a dispute, they will be

discouraged by the courts from commencing any court action until the terms of

arbitration agreement are satisfied. The provisions of the Arbitration and Conciliation

Act are quite instructive on this matter and the net effect of those provisions is that once

the parties have agreed to settle their disputes by arbitration and one party, attempts to

side-step this procedure by commencing legal proceedings, such proceedings will not

be allowed to proceed until the arbitral process has been completed. The law makes it

obligatory for the judicial authority not only to make an order for staying the

proceedings on an application from the party, but also refer the parties to arbitration.

The defendant brought third party proceedings in breach of an existing arbitration

agreement and it may seem that this was due to the suit filed against it and they were

forced to have the third party explain the delay in processing the land title for the

plaintiff. It was out of fear of being condemned for actions of the third party and the

court would have apportioned responsibility and liability to that extent.

In the premise therefore, the defendant was wrong to take out third party proceedings

against the Third Party and any proceedings against it ought to have been determined

through an arbitral process. It is moot to determine issue 3 as the resolution of the

preceding issues disposed of it.

Issue 4: What remedies are available to the parties?

Since it was determined that the plaintiff’s claims were devoid of merit, there are no

available remedies to the parties.


The suit is dismissed with no order as to costs between the plaintiff and defendant. The

defendant is ordered to pay costs to Third party for erroneously dragging them to court

instead of initiating arbitral proceedings.

I so order.

Obiter dictum

There is need for clarity and precision in the law of compensation in order to help ensure both
that a land owner obtains fully the compensation the law intended and that the land owner is not
paid twice for what is essentially the same loss.

The court has a duty to balance between doing justice to individuals and equitably preserving
tax payers’ funds for greater priorities and this is the most pervasive considerations. In pursuit
of that balance it is inevitable that the distinctions will be drawn in order to avoid any arbitrary
awards or inconsistent awards which may be influenced through corrupt tendencies.

SSEKAANA MUSA
JUDGE
19th/04/2021

You might also like