KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO
Project
The 3rd Party Civil Testing Lab & personnel’s shall be
Approval of 3rd Party Civil Testing Lab & Specification
1.2
its personnel’s
SAEP 383
RE-614005 RH RH approved to comply the requirements of SAEP-383 (Sec.
7.1, 8.1)
Rev. 0
Project
Approved Project Specifications, Project
Specification
1.3 Scope of Works and IFC Drawings/Shop Schedule Q
RE-614005 RH/H R
Drawings.
Rev. 0
Special
Approved Special Process Procedure for Process
1.4
Precast Works
Schedule Q
Procedure for RH RH
Precast Works
RECEIVING
2.0
INSPECTION
KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO
3.0 INSTALLATION
KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1 Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 I : 100% participation by Contractor QC Inspector for Inspection/Test
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not
4 present.
5 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
6 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection