PURPOSE:
APPLICABILITY:
The IGC Code, as amended applies to ships regardless of their size, including those of less
than 500 gross tonnage, engaged in the carriage of liquefied gases having a vapor pressure
exceeding 0.28 MPa absolute at a temperature of 37.8°C and other products, as shown in chapter
19, when carried in bulk.
1.0 REQUIREMENTS:
1.1 Regulation 18.2 of the IGC Code, as amended, requires every liquified gas carrier subject
to this Code to be provided with copies of suitably detailed cargo system operation manuals
such that trained personnel can safely operate the ship with due regard to the hazards and
properties of the cargoes that are permitted to be carried.
1.2 Additionally, in accordance with the IGC Code, as amended, the ship’s cargo operations
manual shall be approved by the Administration and updated copies of the same shall be
also kept on board. The cargo operations manual shall include the following but not limited
to:
a) Overall operation of the ship from dry-dock to dry-dock, including procedures for cargo tank
cooldown and warm-up, transfer (including ship-to-ship transfer), cargo sampling, gas-
freeing, ballasting, tank cleaning and changing cargoes;
1 of 3
Inquiries concerning the subject of this Notice should be directed to the Office of the Deputy Commissioner, Republic of
Liberia, the Liberian International S hip & Corporate Registry, LLC, 22980 Indian Creek drive, S uite 200, Dulles, VA
20166, US A
c) Cargo system limitations, including minimum temperatures (cargo system and inner hull),
maximum pressures, transfer rates, filling limits and sloshing limitations;
f) Special equipment needed for the safe handling of the particular cargo;
j) Procedures to change cargo tank pressure relief valve set pressures in accordance with 8.2.8
and 4.13.2.3 of the IGC Code, as amended; and
k) Emergency procedures, including cargo tank relief valve isolation, single tank gas-freeing and
entry and emergency ship-to-ship transfer operations
1.3 The cargo operations manual shall be submitted to the Administration for review and
approval in accordance with Section 3 of this Notice.
2.1 The manual shall be prepared taking into consideration the technical provisions in
regulation 18.2 of the IGC Code, as amended.
2.2 A model format for the cargo operations manual is provided as Appendix I to this Marine
Notice.
2.3 The manual shall be written and available in English and a working language understood
by the master and officers, if the working language is not English.
2.4 Each manual must identify the ship to which it applies, using the ship's name and IMO
number.
3.1 All manuals required under regulation 18.2 of the IGC Code, as amended, must be
approved by the Administration or an authorized RO.
3.2 The manual that is submitted to the Administration for approval shall be in English.
3.4 If the manual is submitted to the Administration for review, the following documents are
also required to be provided, as applicable:
3.5 To facilitate the review and plan approval process, it is recommended to complete the
checklist in Appendix II to this notice which will be used by the Administration for plan
approval and attach it to the submitted plan. The checklist identifies the applicable sections
of the manual.
Questions regarding this instruction, IGC Code, as amended requirements, and fees for the manual
review and approval should be referred to [email protected] or you may call +1-703-
790-3434.
* * * * *
Cover Page
Table of Contents
Record of Changes
Illustrations
Illustrations
Illustrations
Illustrations
Illustrations
Illustrations
Appendices
APPENDIX II
Approval of Liquified Gas Carrier Cargo Operations Manual Basic Requirements from MSC Resolution 370(93)
Liquified Gas Carriers Cargo Operations Manual Questionnaire
Preamble
Introduction. An introductory paragraph summing up the intent of the plan.
Ship Particulars:
Ship specific information:
✓ Name;
✓ Flag;
✓ Port of Registry;
✓ Gross Tonnage;
✓ IMO Number;
✓ LOA
✓ Length between BP,
✓ Beam,
✓ Call Sign,
✓ Class notation;
Index. An index of sections to be included to reference the contents of the manual.
Purpose: A brief introduction for the ship’s crew, explaining the need for the Liquified Cargo Operations Manual and
the importance of accurate record keeping.
General arrangement Plan
Tanks and Capacity Plan
Particulars of Cargo Equipment and Machinery
Applicable Rules and Regulations
Hazardous Areas and Gas Dangerous Zone Plan
Illustrations of the different hazardous areas on board
Properties of LNG
General information containing the following:
✓ Definitions;
✓ Physical Properties;
✓ Source of Ignitions;
✓ Chemical Properties;
✓ Principles of Refrigeration
Integrated Automation System (IAS)
General information containing the following:
✓ Control Room Arrangement;
✓ Integrated Automation System (IAS);
✓ Custody Transfer System;
✓ Illustrations
Cargo and Ballast System
General information containing the following:
✓ Cargo Containment System;
✓ Deterioration or Failure of Containment
✓ Cargo Piping System;
✓ Cargo Pumps;
✓ Cargo Compressors;
✓ Boil-Off/Warm-Up Heater;
✓ LNG Vaporiser;
✓ Forcing Vaporiser;
✓ Nitrogen Generator;
✓ Inert Gas and Dry-Air Generator;
✓ Fixed Gas Detection System;
✓ Valve Remote Control and Emergency Shutdown System;
✓ Ship-shore Link and Mooring Load Monitoring System;
✓ Relief Systems;
✓ Ballast System;
✓ Illustrations
Cargo Auxiliary and Deck system
General information containing the following:
✓ Technical specifications;
✓ Temperature Monitoring System;
✓ Primary and Secondary Insulation Space Nitrogen Pressurizing and Control System;
✓ Cofferdam Heating System;
✓ Fire Fighting Systems;
✓ Cargo Machinery Fresh Water-Cooling System Illustrations
Cargo Operations
General information containing the following:
✓ Technical specifications;
✓ Insulation Space Pressurising;
✓ Post Dry Dock Operation;
✓ Ballast Passage;
✓ Loading;
✓ Loaded Voyage with Boil-Off Gas Burning;
✓ Discharging with Vapour Return from Shore;
✓ Pre-Dry Dock Operations;
✓ One Tank Operation Illustrations
Emergency Procedures
General information containing the following:
✓ LNG Vapour Leakage to Barrier;
✓ LNG Liquid Leakage to Barrier;
✓ Water Leakage to Barrier;
✓ Failure of Cargo Pumps - Emergency Cargo Pump Installation;
✓ Fire and Emergency Breakaway;
✓ Ship to Ship Transfer;
✓ LNG Jettison