VAL 010 Revalidation Procedure Sample
VAL 010 Revalidation Procedure Sample
VAL 010 Revalidation Procedure Sample
Procedure
1. Revalidation Categories
1.1. Process Revalidation
With the exception of sterile/aseptic processes, process revalidation is NOT frequent as
validated status is maintained via a change control process. The need for any revalidation
outside of the change control process will be considered in response to repeated or
unexplained batch failures or any adverse analytical trends.
1.2. Cleaning Revalidation
There is NO need to revalidate the process unless it is clear that the effectiveness of the
cleaning procedures is inadequate or where significant changes in the manufacturing
equipment or process have occurred.
1.3. Analytical Methods Revalidation
The routine revalidation of analytical methods is NOT necessary. Revalidation will therefore
normally result from the recurrence of analytical problems or excessive out of specification
results associated with the analytical method.
1.4. Revalidation of Pharmacopeial methods is NOT necessary, but need to verify when such
methods are updated
2. Initiation
2.1. It is the responsibility of the Validation Committee to provide an overall plan describing and
defining the subject for revalidation based on the initial Validation of the
equipment/process/system. The criticality of the equipment/process/system, plus a
knowledge of its inherent tendency to change, are considered when establishing the
equipment/process/system revalidation programme. The revalidation requirements are
documented as part of the Validation report at the time of initial validation but may be
modified over time when further knowledge of the equipment/process/system is gained.
2.2. Revalidation is required by the cGMP to be carried out on annual basis on all critical
processes or when significant changes have been made to the equipment/process/system.
Revalidation activities are usually preceded by a major preventative maintenance/calibration
programme conducted by the Maintenance Department.
6. Revalidation Protocols
Revalidation Protocols are used to highlight the Test Objective, Acceptance Criteria, Test Method,
and the results obtained.
7. Revalidation Timing
Revalidation schedule should be prepared taking into account the current production activities, which
will determine the availability of the equipment/process/system. Therefore, studies are to be
conducted in the time frame of plus or minus one month of the most recent past revalidation, (i.e.
11-13months). If an extension beyond that date occurs without revalidation being conducted, the
equipment/process/system cannot be used for production activities without the specific
documented approval of the Quality Assurance Manager.
8. Equipment Checklist
An Equipment Checklist is used to ensure that all parameters are set correctly after any
maintenance/adjustments have been made. The principle is to ensure that the
equipment/process/system has not altered from the original, validated parameters. Checklists are
developed during the Operation & Performance Qualification by the Project Team for new
equipment/processes/systems.
The checklist is stored with the Validation Department to ensure that current versions are maintained
and issued by the validation staff to the Maintenance team prior to the revalidation activities.
The Equipment Checklists are approved by the Maintenance Department.
A summary list of all the registered forms from the Change to Control System and an outline
of the Revalidation Programme are prepared by the validation staff.