Part D
Part D
Standard Costing
Standard costing
Standard costing
3
1. Introduction to standard costing
4
1. Introduction to standard costing
5
1. Introduction to standard costing
6
1. Introduction to standard costing
8
Recall: Fixed and flexible budgets
Fixed Flexible Actual Budget
budget budget results variance
(a) (b) (c) (b)-(c)
Sales (units) 2,000 3,000 3,000
$ $ $ $
Sales revenue 20,000 30,000 30,000 0
Variable costs
Direct materials 6,000 9,000 8,500 500 (F)
Direct labour 4,000 6,000 4,500 1,500 (F)
Maintenance 1,000 1,500 1,400 100 (F)
Semi-variable costs
Other costs 3,600 4,600 5,000 400 (A)
Fixed costs
Depreciation 2,000 2,000 2,200 200 (A)
Rent and rates 1,500 1,500 1,600 100 (A)
Total costs 18,100 24,600 23,200 1,400 (F)
Profit 1,900 5,400 6,800 1,400 (F)
9
1. Introduction to standard costing
10
1. Introduction to standard costing
11
2. Flexed budgets and variances
12
3. Direct material cost variance
材料成本为什么产生差异?
材料成本=产量*单位用量*单价
13
3. Direct material cost variance
Usage
Direct materials cost variance
Price
The direct material total variance is the difference between what the output
actually cost and what it should have cost, in terms of material.
The direct material usage variance is the difference between the standard
quantity of materials that should have been used for the number of units
actually produced, and the actual quantity of materials used, valued at the
standard cost per unit of material. It is the difference between how much
material should have been used and how much material was used, valued at
standard cost.
The direct material price variance is the difference between the standard
cost and the actual cost for the actual quantity of material used or purchased.
It is the difference between what the material did cost and what it should
have cost.
14
3. Direct material cost variance
15
3. Direct material cost variance
16
3. Direct material cost variance
17
3. Direct material cost variance
Summary:
Usage variance 17,000 (A)
Price variance 18,400 (F)
Total variance 1,400 (F)
18
3. Direct material cost variance
直接人工成本为什么产生差异?
人工成本=产量*单位工时*工资率
19
3. Direct material cost variance
Efficiency
Direct labour cost variance
Rate
The direct labour total variance is the difference between what the output should have
cost and what it did cost, in terms of labour.
The direct labour efficiency variance is the difference between the hours that should
have been worked, valued at the standard rate per hour. It is the difference between
how many hours should have been worked and how many hours were worked, valued
at the standard rate per hour.
The direct labour rate variance is the difference between the standard cost and the
actual cost for the actual number of hours paid for. It is the difference between what
the labour did cost and what it should have cost.
20
3. Direct material cost variance
21
3. Direct material cost variance
22
3. Direct material cost variance
23
3. Direct material cost variance
Summary $
Efficiency variance 1,500 (A)
Rate variance 2,600 (F)
Total variance 1,100 (F)
24
5. Variance production OH variances
变动制造费用为什么产生差异?
变动制造费用=产量*单位工时*单位工时变动成本
25
5. Variance production OH variances
Efficiency
Variable production overhead variance
Expenditure
The variable production OH total variance is the difference between what the
output should have cost and what it did cost, in terms of variable production
OH.
The variable production OH efficiency variance is exactly the same in hours
as direct labour efficiency variance (only actively hours), but priced at the
standard variable production overhead rate per hour.
The variable production OH expenditure variance is the difference between
the amount of variable production overhead that should have been incurred in
the actual hours actively worked (not idle time), and the actual amount of
variable production overhead incurred.
26
5. Variance production OH variances
27
5. Variance production OH variances
28
5. Variance production OH variances
29
5. Variance production OH variances
30
Specimen exam: A12
A company has calculated a $10,000 adverse direct material variance
by subtracting its flexed budget direct material cost from its actual
direct material cost for the period.
C
31
2. Flexed budgets and variances
Usage
a) Direct materials cost variance
Price
Efficiency
b) Direct labour cost variance
Rate
Efficiency
c) Variable production overhead variance
Expenditure
32
Overview
33
Cost variances
Cost variances
Ø Fixed production OH variances
Ø Significance of cost variances
35
1. Fixed production OH variances
Fixed overhead total variance is the difference between fixed overhead incurred
and fixed overhead absorbed.
In other words, it is the under- or over-absorbed fixed overhead.
36
1. Fixed production OH variances
Expenditure variance
Volume variance @OAR
37
1. Fixed production OH variances
38
1. Fixed production OH variances
Fixed overhead volume variance
Ø Fixed overhead volume efficiency variance is the difference between the
number of hours that actual production should have taken, and the number of hours
actually taken (that is, worked) multiplied by the standard absorption rate per hour.
Ø Fixed overhead volume capacity variance is the difference between budgeted
(planned) hours of work and the actual hours worked, multiplied by the standard
absorption rate per hour.
39
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit OAR/unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
(a) The fixed overhead total variance
$
Fixed overhead incurred 20,450
Fixed overhead absorbed (1,100 units × $20 per unit) 22,000
Fixed overhead total variance (= under-/over-absorbed overhead) 1,550 (F)
40
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
(b) The fixed overhead expenditure variance
$
Budgeted fixed overhead expenditure 20,000
Actual fixed overhead expenditure 20,450
Fixed overhead expenditure variance 450 (A)
41
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
(c) The fixed overhead volume variance
$
Actual production at standard rate (1,100 × $20 per unit) 22,000
Budgeted production at standard rate (1,000 × $20 per unit) 20,000
Fixed overhead volume variance 2,000 (F)
42
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
(d) The fixed overhead volume efficiency variance
43
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
(e) The fixed overhead volume capacity variance
44
1. Fixed production OH variances
Suppose that a company plans to produce 1,000 units of product E during August 20X3. The
expected time to produce a unit of E is five hours, and the budgeted fixed overhead is $20,000.
The standard fixed overhead cost per unit of product E will therefore be as follows.
5 hours at $4 per hour = $20 per unit
Actual fixed overhead expenditure in August 20X3 turns out to be $20,450. The labour force
manages to produce 1,100 units of product E in 5,400 hours of work.
The variances may be summarized as follows.
$
Expenditure variance 450 (A)
Efficiency variance 400 (F)
Capacity variance 1,600 (F)
Over-absorbed overhead (total variance) 1,550 (F)
45
Specimen exam: A22
A manufacturing company operates a standard absorption costing system. Last month
25,000 production hours were budgeted and the budgeted fixed production cost was
$125,000. last month the actual hours worked were 24,000 and standard hour for actual
production were 27,000.
What was the fixed production overhead capacity variance for last month?
A. $5,000 Adverse
B. $5,000 Favourable
C. $10,000 Adverse
D. $10,000 Favourable
46
3. The significance of cost variances
Four general causes of variances
a) Inappropriate standard.
b) Inaccurate recording of actual costs.
c) Random events.
d) Operating inefficiency.
48
3. The significance of cost variances
Ø Materiality, controllability, the type of standard being used, the
interdependence of variances and the cost of an investigation should be
taken into account when deciding whether to investigate reported variances.
Ø When two variances are interdependent (interrelated) one will usually be
adverse and the other one favourable: materials price and usage variances, labour
rate and efficiency variances.
49
Overview
Fixed production OH variances:
Ø Total
Ø Expenditure
Ø Volume (efficiency and capacity)
50
Sales variances and operating statements
Sales variances and operating statements
Ø Sales variances
Ø Operating statements
Ø Variances in a standard MC system
Ø Deriving actual data from standard details and variances
Ø Control action
52
1. Sales variances
53
1. Sales variances
54
1. Sales variances
$
Sales revenue from 2,000 units should have been (@ $15) 30,000
But was (@ $15.30) 30,600
Selling price variance 600 (F)
55
1. Sales variances
56
1. Sales variances
57
2. Operating statements
$
Budgeted profit 30,600
Sales volume profit variance 1,500 (A)
Standard profit from actual sales 29,100
(F) (A)
Variance $ $
Sales price 1,400
Material price 600
Material usage 500
Labour rate 200
Labour efficiency 3,400
Labour idle time 1,000
Variable overhead expenditure 200
Variable overhead efficiency 510
Fixed overhead expenditure 4,560
Fixed overhead volume efficiency 6,290
Fixed overhead volume capacity 8,140
10,900 15,900 5,000 (A)
58
2. Operating statements
A company uses a standard absorption costing system. The following
figures are available for the last accounting period in which actual profit
was $270,000.
$
Sales volume profit variance 15,000 A
Sales price variance 12,500 F
Total variable cost variance 17,500 A
Fixed cost expenditure variance 7,500 F
Fixed cost volume variance 5,000 A
What was the standard profit for actual sales in the last accounting
period?
A. $252,500 B. $267,500 C. $272,500 D. $287,500
59
Specimen exam: A13
A company has recorded the following variances for a period:
Sales volume variance $10,000 adverse
Sales price variance $5,000 favourable
Total cost variance $12,000 adverse
60
3. Variances in a standard MC costing system
61
3. Variances in a standard MC costing system
$ $ $
Budgeted contribution 68,340
Sales volume contribution variance 3,350 (A)
Standard contribution from actual sales 64,990
(F) (A)
Sales price 1,400
Material price 600
Material usage 500
Labour rate 200
Labour efficiency 3,400
Labour idle time 1,000
Variable overhead expenditure 200
Variable overhead efficiency 510
4,610 3,200
1,410 (F)
Actual contribution 66,400
Budgeted fixed production overhead 37,740
Expenditure variance 4,560 (A)
Actual fixed production overhead 42,300
Actual profit 24,100
62
December 2011 exam paper
63
3. Variances in a standard MC costing system
A company uses standard marginal costing. Last month the standard contribution on
actual sales was $10,000 and the following variances arose.
$
Total variable costs variance 2,000 A
Sales price variance 500 F
Sales volume contribution variance 1,000 A
Total fixed costs variance 1,000 F
64
4. Deriving actual data
65
4. Deriving actual data
XYZ uses standard costing. The following data relates to labour grade 11.
Actual hours worked 10,400 hours
Standard allowance for actual production 8,320 hours
Standard rate per hour $5
Rate variance (adverse) $416
What was the actual rate of pay per hour?
Rate variance = 10,400 * X – 10,400 * 5 = 416
X = 5.04
66
4. Deriving actual data
The standard material content of one unit of product A is 10kg of
material X which should cost $10 per kg. In June 20X4, 5,750 units of
product A were produced and there was an adverse material usage
variance of $1,500.
Required
Calculate the quantity of material X used in June 20X4.
Let the quantity of material X used = Y
5,750 units should have used (@ 10kg) 57,500 kg
But did use Y kg
Usage variance in kg (Y – 57,500) kg
@ standard price per kg × $10
Usage variance in $ $1,500
10 (Y – 57,500) = 1,500
Y = 57,650 KG
67
Overview
68