Cost-Benefit Analysis in Project Management
Cost-Benefit Analysis in Project Management
Today we will discuss cost-benefit analysis in project management. This technique is also known as benefit-cost analysis, cost-benefit ratio, project cost
analysis, etc.
It is rare for an organization to have unlimited resources, so they routinely must choose the best option from all the opportunities available. One of the
ways organizations make these decisions is by using cost-benefit analysis.
This technique is also very helpful when deciding on a new course of action.
Cost-benefit analysis has a vast scope, and explaining it in one blog post is not easy, so I will provide a preliminary outline of this project’s cost analysis
technique.
Cost-Benefit Analysis
Cost-benefit analysis is a benefit measurement method usually performed by top management.
This technique is useful during the feasibility study to determine if the project is worth taking.
Also, cost-benefit analysis helps management select the right project from multiple options during the project selection analysis. They gather data,
analyze all the projects, and then try to discover which project is more profitable.
Expected Profit
Time value of the profit
The basis for comparing the projects
Expected Profit
The cost-benefit analysis finds and converts the benefits into monetary values. Then, the investment costs are subtracted from the benefits to get the
result.
You can proceed if the result is positive; if not, abandon the idea.
For instance, suppose your company is involved with manual bookbinding, and you propose that management buy equipment to improve efficiency.
Before submitting the proposal, you will perform a cost-benefit analysis. You will list the costs of the investment.
For example:
Machine cost
Maintenance cost
Cost of electricity used by these machines
Then you will identify the benefits, such as
You will figure out the investment cost and the monetary value of the benefits.
You will then perform the cost-benefit analysis by subtracting investment cost from the benefits. Use this figure with management to justify your
proposal.
For example, assume a 5% inflation yearly. What you can buy for 100 USD today will cost 105 USD after one year.
Considering yearly inflation of 5%, what will the current value be?
FV = CV(1+r/100)^n
Here,
FV = Future Value
CV = Current Value
r = Inflation
n = time
Given values,
FV = 10,000 USD
r=5
n =1
10,000 = CV(1+0.05)^1
CV = 10,000/1.05
CV = 9,523.80
There is no specific cost-benefit analysis formula; however, simple equations can provide accurate information.
If it is a multi-year project, you will not realize a profit in today’s value. You may hope you will profit from it; however, a Net Present Value (NPV) analysis
could be eye-opening and worth doing.
It is useful for small projects with shorter durations. As the duration increases, this technique gets more complex and unwieldy. Bigger projects are more
difficult; converting intangible costs is not easy, so this technique is no longer useful.
As the project grows more complex, intangible costs and benefits rise. Converting these costs and benefits into monetary form is not an easy task.
Inflation plays an important role in longer projects. Also, the greater the project duration, the greater the risks.
Summary
The cost-benefit technique is a systematic approach to calculate the investment cost and received benefits. It is a simple technique that lets you know if
you should proceed with the project or which project you should select among many.
Cost-benefit analysis is an important concept from a PMP exam point of view. Make sure you fully understand it.
How do you use cost-benefit analysis in your organization? Please share your thoughts in the comments section.
I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date,
thousands of professionals have passed the PMP exam using my resources.
PMP Question Bank PMP Training Program
This is the most popular Question Bank for the PMP Exam. This is a PMI-approved 35 contact hours training program
To date, this PMP Question Bank has helped over 10,000 and it is based on the latest exam content outline
PMP aspirants pass the PMP exam. applicable from Jan 2nd, 2021.
Similar Posts
Stakeholders in Project Management: Definition, Types & Examples Kick-Off Meeting: A Guide on Conducting Project Kickoff Meeting
By Fahad Usmani, PMP September 28, 2022 By Fahad Usmani, PMP October 11, 2022
22 Comments
Please permit me to ask few questions here. Before I get confused. Shortly before I came across your blog, I have learnt that Cost benefit analysis also known as
Return on Investment (ROI) can be calculated using this formula: (G-C)/C=ROI.
However, you gave FV=CV(1+r/100)^n as the formula for calculating the Future value of a project/current worth.
The question is looking at the two formulae above, one tends to measure ROI in percentage while the other, the current worth.
Thank you
Reply
Awhe says:
September 15, 2023 at 2:10 PM
Cost/Benefit analysis is conducted in steps. Step one is the calculate the cost and benefits in today or current prices. That is,
the incremental gains G (or benefits) minus the incremental costs C divided by the costs C {(G-C)/C} to estimate the Return on Investment (ROI) The rule of
thumb is that a project that gives a positive ROI is acceptable. +ROI means that for every unit of currency expended, you are receiving a higher sum in return.
However the formula {(G-C)/C} is a simplified statement of the true picture of project inflows and outflows, which come at different times in the life of the
project. There is need to account for the time value of money. A unit of inflow or outflow today is rated more than the flows a year or more from now. Future
flows or values (FV) are discounted at a given discount rate (r) to give a their current values (CV) to arrive at a Net Present Value (NPV). A project with a
positive NPV is acceptable. The discount rate (r) at which the NPV=0 is called the Internal Rate of Return (IRR). A project is acceptable if the IRR is more than
the ongoing savings interest rate. What that means is that, all things being equal, it is better to invest your money in a project than put it in the bank, and vice
versa.
Simply, use the (G-C)/C formula to illustrate project cost/benefit analysis without consideration of the time value of money.
Reply
Mousham says:
May 21, 2023 at 7:29 AM
Thank you, it was very helpful to learn how intangible costs and inflation impact the overall CBA.
Reply
There is actually! The ‘Engineering Economics’ provides pre-defined different types of solutions on how to calculate net value, whether it is present to annual,
future to present, etc. The equations and calculations are pretty simple to follow and implement. I recommend everyone reading this to watch some videos on
Youtube about this interesting discipline.
Reply
Thank you. It was well put out, which encouraged ease in assimilation for me.
Reply
Reply
How do you quantify intangible benefits? are there standard procedures to do that?
Reply
Thank you for the valuable information, you’ve done great job by helping people, this our Mission as a human.
Thank you again
.
Reply
This blog has taught me so much. I am a newbie learning project management to hone my skills.
Reply
Reply
Thakur says:
June 12, 2022 at 3:17 PM
Reply
fredrick says:
June 7, 2022 at 3:35 AM
Reply
Dineo says:
December 14, 2021 at 3:04 PM
I am an newbee in the field… still studying. How I do appreciate that analyzing the budget for a project prior to beginning it is an important part of the
foundation we call project initiation.
Reply
Abdelbaky says:
April 26, 2021 at 12:03 AM
Analyzing the expected cost and profits is a good strategy in all cases, provided that it is undertaken before the start of the implementation of the project to
determine the extent of its economic feasibility for the company in addition to anticipating the general economic situation and making an account for the
economic, technological and political market grades
Reply
SD says:
June 20, 2017 at 3:54 PM
Does this technique is performed outside of the project boundaries by senior management to determine if they should proceed with the project or terminate??
How can we say that benefit/cost analysis is done in initiation phase??? Because in initiation phase, we already get the selected project for which charter is
developed.
Reply
This analysis is performed by the project sponser to see if it fulfills his objective.
Initiation phase and Initiation process groups are different. What you are talking is, initiation process group, not initiation phase.
Reply
How we can convert Benefit Cost Analysis into Monetary value or funds or money before submitting our proposal or project to the management?
Reply
https://pmstudycircle.com/2014/03/project-selection-methods/
Reply
Cost benefit analysis is performed during Initiating process group. I believe it falls under project integration management knowledge area.
Reply
Thanks
Reply
Reply
Reply
Leave a Reply
Your email address will not be published. Required fields are marked *
Comment *
Name *
Email *
Website
Post Comment