HKU CSM RECO7079 L4 Risk Management
HKU CSM RECO7079 L4 Risk Management
Intolerable
Tolerable
Negligible
Acceptable and Tolerable Risk
Designer Constructor
Establish
- produces - reviews & Pass on info on
Generic / Non
construction updates log
Generic residual hazards
hazard log
Construction - implements to operator/
hazard - identifies & mitigation maintainer
Database resolves measures
hazards
Note:
• Focus is on identification and reduction of hazards by design during preliminary/detailed
design stages
• Contractors are already required to identify and rectify hazardous conditions under
F&IU (Safety Management) Regulations
What is RISK ASSESSMENT?
RISK ASSESSMENT is
• The process used to determine risk
management priorities by evaluating and
comparing the level of risk against predetermine
standards, target risk levels or other criteria
(AS/ZNS 4360)
• The overall process of estimating the magnitude
of risk and deciding whether or not the risk is
tolerable or acceptable (BS8800)
• A risk assessment is simply a careful
examination of what, in your work, could cause
harm to people, so that you can weigh up
whether you have taken enough precautions or
should do more to prevent harm. (HSE)
Reasons for implementing RA
• The results can be used to
– improve work method, job instruction
– better control on critical jobs.
– correct existing analysis
– protection of plant / equipment and personnel
– minimize occupational accidents caused by unsafe acts.
– prepare for safety legislation
– emergency procedures and provision of
information etc.
Legal Requirements
Risk Assessment
Identify risks
Communicate
and consult
Monitor
Review
and
Analysis risks
Evaluate risks
Treat risks
Risk Assessment
3 major process:
• Identification of risk
• Analysis of risk
• Evaluation of risk
Establishing the Context
Electrical Hazards
Mechanical Hazards
Ergonomic Hazards
Man Machine
Chemical &
Physical Hazards
Dust Hazards
Material Env
Biological Hazards
Chemical & Dust Hazards
Identify Risks
• What can happen
– to generate a comprehensive list of events
for further action
• How and why it can happen
– consider possible causes and scenarios
• Tools and techniques
– checklists
– judgements based on experience and
records,
– flow charts
– brainstorming…
Some typical Construction Hazards
Materials falling into deep shafts or excavations Slips, trips and falls
Vehicles falling into deep shafts or excavations Fire in tunnels/ hot works/ flammable materials
Frequency
consequences
• Analysis may be in the
form of qualitative or
quantitative Consequence
MTR Risk Matrix
Risk evaluation
Legend
E: extreme risk; immediate action required
H: high risk: senior management attention needed
M: moderate risk; management responsibility must be specified
L: low risk; manage by routine procedures
3 x 3 Risk Matrix
Risk Assessment
Risk Regions
Example based on ISO 14971, Fig E.1
Frequent
Intolerable
Probable
Likelihood
Occasional ALARP
As Low As Reasonably
Practicable
Remote
Broadly
Improbable Acceptable
Incredible
Negligible Marginal Critical Catastrophic 53
Severity
Proposed CLP Power Strategic Risks Matrix
PROBABILITY CATEGORY
Consequence A B C D E
Category Almost Likely Possible Unlikely Rare
Certain
I Loss of Conflict of interest
Scheme of Under SOC
Significant Control (Commercial)
(Regulatory) Wrong E-bill
amount to all
customers(IT)
IV
Minor
I Significant •Fatalities/Serious impact • Huge finanical loss •Significant regulatory •Large shortfalls Issue of •Massive information
on public • Significant claim change in SOC that of skilled International integrity loss,
•Significant disruption to from service outside CLP resources to run media’s interest •Damaging
large community/Full providers to expectation the business (repeated nformation
scale response (load coroporate level •Significant reduction •Widespread staff occurrence of disclosure,
loss > 200MVA or • Legal breach in business volume issue or morale major events) •loss of processing
affecting > 100k • > HK$ 10 M which may affect stock problem affecting BU's
customers over 1 hour) price and long term viability
•Severe and long-term borrowing capability •multiple sites with
damage of image or •Unable to meet supply broad network effect
reputation obligation
II Major •Serious Injury/Limited • Major finanical loss •Major regulatory •Some shortfalls Issue of •Affiliate or business
impact on public • Significant claim change in SOC that in skilled Government line database
•Significant disruption to from service outside CLP resources to run interest (repeated corrupted
small community (load providers to expectation the business occurrence of •tactical nformation
loss > 50MVA or business level •Major reduction in • Business group moderate events) disclosure
affecting 20k to 100 • Major legal breach business volume staff issue or •loss of processing
customers over 1 hour) • > HK$ 1 - 10 M •Short term inability to morale problem affecting many
•Short term damage of meet supply obligation business cycles with
image or reputation major losses
•remote site work
group network
failures
III Moderate • < 5 serious injuries or • High finanical loss •Moderate regulatory •Lack of some Issue of Public •Workgroup
medical treatment • Moderate claim change in SOC internal resources concern / local information corrupted
required from service •Moderate reduction in which can be media interest •internal working
• Minor disruption (Load providers to business volume outsourced nformation disclosure
loss of > 10MVA or business level •Inability to meet • Business unit •loss of processing
affecting 5k to 20k • Legal non- supply obligation staff issue or affecting one or more
customers over 1 hour) compliance temporarily morale problem business cycles with
• Limited response of • HK$50k to $1M no major losses
short duration •remote site work
group network
IV Minor •Medical treatment • Small finanical loss •Minor regulatory •Lack of internal Issue not of •Individual
required • No claim from change in SOC resources for low concern / local information corrupted
• Power disruption < service providers to •Minor reduction in priority works media interest •Unclassified or
10MVA or affecting 800 business level business volume undamaging
to 5k customers • Legal non- •Inability to meet • individual staff information
• Minor / no response compliance supply obligation in issue or morale disclosure
• < HK$ 50k one odd case problem •loss of processing
PROBABILITY CATEGORY
LII and LIII Operational Risks Matrix (existing) A B C D E
Operational
Generation Safety / Health
Operational Safety / Public Environmental Asset Once per Once per Once in Once in Once in
Effects
Disruption Disruption Health Disruption Impact Loss Month Year Several Every 10 Every 50
(HK$) Years Years Years
A B C D E
I Loss of
of 3load Fatalities / Multiple Large Major / > 10 M I High High High Medium Medium
Loss or Loss of load
Catastrophic Fatalities / Community Extended
200MVA
more > 200MVA
Power duration/full
generating
Serious disruption Scale
units with
Public response
total capacity
Impact
>1500MW (>100k
customerso
ver 1hr)
II
Loss of load Serious Injuries Single Fat. / Small Serious / > 1M II High High Medium Medium Low
Loss of 2 or more Loss of load Multiple community significant
Serious 50MVA
generating units Serious
> 50MVA power resource
with total capacity injuries
800 MW<x<1500 disruption commitment
MW Limited (>20k
Public customerso
impact ver 1hr)
III Loss of load Minor injuries / Minor
Minor
Moderate / > 50k III Medium Medium Low Low
High
Moderate Loss10MVA
of any 1 injuries / Limited
Loss of load Power
generating unit Response /
> 10MVA disruption
Little Short
Public duration
Impact (>5k
customers
over 1hr)
IV Loss of load < Minor injuries / Minor Minimal Power Minor / Little < 50k IV Low Low Low Low Low
None injuries Disruption Or no
Minor 10MVA Loss of load (> 800
< 10MVA No public customers response
No public impact over 1hr)
impact
Risk Treatment
• Risk Avoidance for the risks of high-frequency high-
consequence
• Risk Retention for the risks of low-frequency low-
consequence
• Risk Transfer for the risks of low-frequency high-
consequence (and also high-frequency high-
consequence)
• Risk Reduction for the risks of high-frequency low-
consequence
Treatment of Risk
• Identify Treatment options
– Avoid
– Transfer
– Reduce consequence
– Reduce likelihood
• Evaluate options
• Prepare treatment plans
• Implement treatment plans
Risk Control Priorities
❑ Avoidance of Exposure
❑Method
❑Material
❑ Substitution
SUPERVISION
❑ Engineering Control
❑Separation by time & space
❑Provide local control
❑ Administrative Control
❑Written rules & procedures
❑Shifting
❑Time restriction
❑ PPE as a last resort
Avoid Risk
(cont’d)
• Action to reduce or control LIKELIHOOD
– Quality assurance, management and standards
– Research and development, technological
development
– Structured training and other programs
– Supervision
– Testing
– Organizational arrangement and
– Technical control
Risk Treatment (AN/NZS 4360:2004)
(cont’d)
• Action to reduce or control CONSEQUENCE
– Portfolio planning
– Pricing policy and control
– Separation or relocation of an activity and resources
– Public relations and
– Ex gratia payments
Reduce Risk
Step 3 Step 4