Chapter 2 – Software Processes

30/10/2014 Chapter 2 Software Processes 1


The software process

 A structured set of activities required to develop a software


system.
 Many different software processes but all involve:
 Specification – defining what the system should do;
 Design and implementation – defining the organization of the system and
implementing the system;
 Validation – checking that it does what the customer wants;
 Evolution – changing the system in response to changing customer
needs.
 A software process model is an abstract representation of a
process. It presents a description of a process from some
particular perspective.
30/10/2014 Chapter 2 Software Processes 2
Software process descriptions

 When we describe and discuss processes, we usually talk


about the activities in these processes such as specifying a
data model, designing a user interface, etc. and the ordering of
these activities.

 Process descriptions may also include:


 Products, which are the outcomes of a process activity;
 Roles, which reflect the responsibilities of the people involved in the
process;
 Pre- and post-conditions, which are statements that are true before and
after a process activity has been enacted or a product produced.

30/10/2014 Chapter 2 Software Processes 3


Plan-driven and agile processes

 Plan-driven processes are processes where all of the process


activities are planned in advance and progress is measured
against this plan.

 In agile processes, planning is incremental and it is easier to


change the process to reflect changing customer requirements.

 In practice, most practical processes include elements of both


plan-driven and agile approaches.

30/10/2014 Chapter 2 Software Processes 4


Software process models

 The waterfall model


 Plan-driven model. Separate and distinct phases of specification and
development.
 Incremental development
 Specification, development and validation are interleaved. May be plan-
driven or agile.
 Integration and configuration
 The system is assembled from existing configurable components. May
be plan-driven or agile.
In practice, most large systems are developed using a process
that incorporates elements from all of these models.

30/10/2014 Chapter 2 Software Processes 5


The waterfall model

30/10/2014 Chapter 2 Software Processes 6


Waterfall model phases

 There are separate identified phases in the waterfall model:


 Requirements analysis and definition
 System and software design
 Implementation and unit testing
 Integration and system testing
 Operation and maintenance

 The main drawback of the waterfall model is the difficulty of


accommodating change after the process is underway. In
principle, a phase has to be completed before moving onto the
next phase.

30/10/2014 Chapter 2 Software Processes 7


Waterfall model problems

 Inflexible partitioning of the project into distinct stages makes it


difficult to respond to changing customer requirements.
 Therefore, this model is only appropriate when the requirements are
well-understood and changes will be fairly limited during the design
process.
 Few business systems have stable requirements.

 The waterfall model is mostly used for large systems


engineering projects where a system is developed at several
sites.
 In those circumstances, the plan-driven nature of the waterfall model
helps coordinate the work.

30/10/2014 Chapter 2 Software Processes 8


Incremental development

30/10/2014 Chapter 2 Software Processes 9


Incremental development benefits

 The cost of accommodating changing customer requirements is


reduced.
 The amount of analysis and documentation that has to be redone is
much less than is required with the waterfall model.
 It is easier to get customer feedback on the development work
that has been done.
 Customers can comment on demonstrations of the software and see
how much has been implemented.
 More rapid delivery and deployment of useful software to the
customer is possible.
 Customers are able to use and gain value from the software earlier than
is possible with a waterfall process.
30/10/2014 Chapter 2 Software Processes 10
Incremental development problems

 The process is not visible.


 Managers need regular deliverables to measure progress. If systems are
developed quickly, it is not cost-effective to produce documents that
reflect every version of the system.

 System structure tends to degrade as new increments are


added.
 Unless time and money is spent on refactoring to improve the software,
regular change tends to corrupt its structure. Incorporating further
software changes becomes increasingly difficult and costly.

30/10/2014 Chapter 2 Software Processes 11


Integration and configuration

 Based on software reuse where systems are integrated from


existing components or application systems (sometimes called
COTS - Commercial-Off-The-Shelf) systems.

 Reused elements may be configured to adapt their behaviour


and functionality to a user’s requirements.

 Reuse is now the standard approach for building many types of


business system.

30/10/2014 Chapter 2 Software Processes 12


Types of reusable software

 Stand-alone application systems (sometimes called COTS) that


are configured for use in a particular environment.

 Collections of objects that are developed as a package to be


integrated with a component framework such as .NET or J2EE.

 Web services that are developed according to service


standards and which are available for remote invocation.

30/10/2014 Chapter 2 Software Processes 13


Key process stages

 Requirements specification

 Software discovery and evaluation

 Requirements refinement

 Application system configuration

 Component adaptation and integration


30/10/2014 Chapter 2 Software Processes 14
Advantages and Disadvantages

 Reduced costs and risks as less software is developed from


scratch

 Faster delivery and deployment of system

 But requirements compromises are inevitable so system may


not meet real needs of users

 Loss of control over evolution of reused system elements


30/10/2014 Chapter 2 Software Processes 15
Process activities

 Real software processes are inter-leaved sequences of


technical, collaborative and managerial activities with the
overall goal of specifying, designing, implementing and testing
a software system.
 The four basic process activities of specification, development,
validation and evolution are organized differently in different
development processes.
 For example, in the waterfall model, they are organized in
sequence, whereas in incremental development they are
interleaved.

30/10/2014 Chapter 2 Software Processes 16


The requirements engineering process

30/10/2014 Chapter 2 Software Processes 17


Software specification

 The process of establishing what services are required and


the constraints on the system’s operation and development.

 Requirements engineering process


 Requirements elicitation and analysis
• What do the system stakeholders require or expect from the system?
 Requirements specification
• Defining the requirements in detail
 Requirements validation
• Checking the validity of the requirements

30/10/2014 Chapter 2 Software Processes 18


Software design and implementation

 The process of converting the system specification into an


executable system.

 Software design
 Design a software structure that realises the specification;

 Implementation
 Translate this structure into an executable program;

 The activities of design and implementation are closely related


and may be inter-leaved.
30/10/2014 Chapter 2 Software Processes 19
A general model of the design process

30/10/2014 Chapter 2 Software Processes 20


Design activities

 Architectural design, where you identify the overall structure of


the system, the principal components (subsystems or
modules), their relationships and how they are distributed.
 Database design, where you design the system data
structures and how these are to be represented in a database.
 Interface design, where you define the interfaces between
system components.
 Component selection and design, where you search for
reusable components. If unavailable, you design how it will
operate.

30/10/2014 Chapter 2 Software Processes 21


System implementation

 The software is implemented either by developing a program


or programs or by configuring an application system.

 Design and implementation are interleaved activities for most


types of software system.

 Programming is an individual activity with no standard process.

 Debugging is the activity of finding program faults and


correcting these faults.
30/10/2014 Chapter 2 Software Processes 22
Software validation

 Verification and Validation (V & V) is intended to show that a


system conforms to its specification and meets the
requirements of the system customer.
 Involves checking and review processes and system testing.
 System testing involves executing the system with test cases
that are derived from the specification of the real data to be
processed by the system.
 Testing is the most commonly used V & V activity.

30/10/2014 Chapter 2 Software Processes 23


Stages of testing

30/10/2014 Chapter 2 Software Processes 24


Stages of Testing

 Component testing
 Individual components are tested independently;
 Components may be functions or objects or coherent groupings of these
entities.

 System testing
 Testing of the system as a whole. Testing of emergent properties is
particularly important.

 Customer testing
 Testing with customer data to check that the system meets the
customer’s needs.
30/10/2014 Chapter 2 Software Processes 25
Software evolution

 Software is inherently flexible and can change.

 As requirements change through changing business


circumstances, the software that supports the business must
also evolve and change.

 Although there has been a demarcation between development


and evolution (maintenance) this is increasingly irrelevant as
fewer and fewer systems are completely new.

30/10/2014 Chapter 2 Software Processes 26


System evolution

30/10/2014 Chapter 2 Software Processes 27


Coping with change

 Change is inevitable in all large software projects.


 Business changes lead to new and changed system requirements
 New technologies open up new possibilities for improving
implementations
 Changing platforms require application changes

 Change leads to rework so the costs of change include both


rework (e.g. re-analyzing requirements) as well as the costs of
implementing new functionality

30/10/2014 Chapter 2 Software Processes 28


Reducing the costs of rework

 Change anticipation, where the software process includes


activities that can anticipate possible changes before
significant rework is required.
 For example, a prototype system may be developed to show some key
features of the system to customers.
 Change tolerance, where the process is designed so that
changes can be accommodated at relatively low cost.
 This normally involves some form of incremental development.
Proposed changes may be implemented in increments that have not yet
been developed. If this is impossible, then only a single increment (a
small part of the system) may have be altered to incorporate the
change.

30/10/2014 Chapter 2 Software Processes 29


Coping with changing requirements

 System prototyping, where a version of the system or part of


the system is developed quickly to check the customer’s
requirements and the feasibility of design decisions. This
approach supports change anticipation.

 Incremental delivery, where system increments are delivered to


the customer for comment and experimentation. This supports
both change avoidance and change tolerance.

30/10/2014 Chapter 2 Software Processes 30


Software prototyping

 A prototype is an initial version of a system used to


demonstrate concepts and try out design options.

A prototype can be used in:


 The requirements engineering process to help with
requirements elicitation and validation;
 In design processes to explore options and develop a UI
design;
 In the testing process to run back-to-back tests.

30/10/2014 Chapter 2 Software Processes 31


Benefits of prototyping

 Improved system usability.

 A closer match to users’ real needs.

 Improved design quality.

 Improved maintainability.

 Reduced development effort.


30/10/2014 Chapter 2 Software Processes 32
The process of prototype development

30/10/2014 Chapter 2 Software Processes 33


Prototype development

 May be based on rapid prototyping languages or tools

 May involve leaving out functionality


 Prototype should focus on areas of the product that are not well-
understood;
 Error checking and recovery may not be included in the prototype;
 Focus on functional rather than non-functional requirements such as
reliability and security

30/10/2014 Chapter 2 Software Processes 34


Incremental delivery

 Rather than deliver the system as a single delivery, the


development and delivery is broken down into increments with
each increment delivering part of the required functionality.

 User requirements are prioritised and the highest priority


requirements are included in early increments.

 Once the development of an increment is started, the


requirements are frozen though requirements for later
increments can continue to evolve.

30/10/2014 Chapter 2 Software Processes 35


Incremental development and delivery

 Incremental development
 Develop the system in increments and evaluate each increment before
proceeding to the development of the next increment;
 Normal approach used in agile methods;
 Evaluation done by user/customer proxy.

 Incremental delivery
 Deploy an increment for use by end-users;
 More realistic evaluation about practical use of software;
 Difficult to implement for replacement systems as increments have less
functionality than the system being replaced.

30/10/2014 Chapter 2 Software Processes 36


Incremental delivery

30/10/2014 Chapter 2 Software Processes 37


Incremental delivery advantages

 Customer value can be delivered with each increment so


system functionality is available earlier.

 Early increments act as a prototype to help elicit requirements


for later increments.

 Lower risk of overall project failure.

 The highest priority system services tend to receive the most


testing.
30/10/2014 Chapter 2 Software Processes 38
Incremental delivery problems

 Most systems require a set of basic facilities that are used by


different parts of the system.
 As requirements are not defined in detail until an increment is to be
implemented, it can be hard to identify common facilities that are needed
by all increments.

 The essence of iterative processes is that the specification is


developed in conjunction with the software.
 However, this conflicts with the procurement model of many
organizations, where the complete system specification is part of the
system development contract.

30/10/2014 Chapter 2 Software Processes 39