47 - Ugar DPR
47 - Ugar DPR
OF
FOR
PREPARED BY
1. INTRODUCTION 10 – 16
9. ANNEXURES
1 BAGASSE BALANCE 70
Executive Summary
Preamble
1.1 Numbers of new sugar factories have increased in the nearby area of The
Ugar Sugar Works ltd., and also existing sugar plant expansions are taking
place in the nearby area. Hence the total cane crushing capacity is
increasing in the same cane growing area, which in turn reduces the
duration of crushing days. To maintain the ultimate sugar production target
it is essential to increase the crushing capacity of USWL. At the same time
expansion of cogeneration and distillery is also essential to balance the by-
products. In this line of action management of ugar sugar have decided to
go for Sugar Plant expansion in phased manner. It is proposed to expand
sugar plant capacity to 20000 TCD, cogeneration 76 MW and distillery to
200 KLPD. Before going into details of the project, we can have a look on
manufacturing procedure of sugar in the following paragraphs.
1.2 Sugarcane will be harvested at field and clean cane will be loaded in the
vehicles at field and brought to the factory. The gross weight shall be taken
and cane unloaded on the feeder table with the help of electric crane
unloader. The tare weight of the vehicle will be taken to arrive at the weight
of the cane.
1.3 Cane will be fed to cane carrier from the feeder table. The cane
preparatory devices viz. Kicker, chopper, Leveler, fibrizer etc., are
installed on the carrier for the preparation of cane. The prepared cane will
be taken to Mills by second carrier where juice is extracted using
compound imbibition process and hot water is applied for maximum
extraction before last mill. Mixed juice is strained and sent for processing.
Water for imbibition and mixed juice both are weighed in automatic
weighing scale & by mass flow meter respectively. Bagasse (residue of
cane after juice extraction) is used as fuel in the boiler and surplus
bagasse saved in the form of bales.
1
UCL
2
UCL
Final molasses is weighed and stored in steel tanks (non duty paid). It is
then sold as bye product or used to distillery.
1.7 The sugar industry is the only industry blessed with captive regenerative
cellulosive matter to meet its own energy for processing sugar cane to
produce sugar. The optimal use of energy is the theme of the day. Cane
sugar industries having its own captive fuel till late were not very conscious
about the effective utilization of energy and to render surplus for other
utilization. In the present context newly developed technologies has proved
to be very effective in releasing energy (thermal & electrical) and
conservation of utilities.
1.8 The increasing concern about the effect of emissions from the power
industry, amongst others, on the environment is the driving force behind
the development of cogeneration and the utilization of renewable fuel
sources. The cane sugar industry is eminently suited, because it has been
in this field for 150 years or so as well as the fact that it uses a renewable
fuel that is C02 emission neutral.
1.9 Sugar factories, since inception are equipped with facilities for co-
generation of steam & power for captive use. However, in recent time the
meaning of the term “co-generation” has widened to denote the generation
of surplus power that can be supplied to the grid. The primary fuel in these
co-generation plants is bagasse, which is generated as a by-product of
cane crushing operations in the sugar manufacturing process. To extend
the operating days and to increase profitability, supplement fuel such as
coal can be used during off season.
1.10 India is one of the largest sugar producing nations in the world. There are
around 500 sugar factories in operation out of these two third are owned &
managed by cooperative sector & public sector. The estimated co-
generation potential from bagasse-based projects is 5000 MW, which
could be tapped by installing efficient co-generation plants.
3
UCL
1.11 Realizing the vast potential of cane production and power generation from
sugar plant co-generation a task force was constituted by Government of
India to address the constraints to commercially exploit the co-generation
potential. The task force had recommended the policy, fiscal incentives to
overcome constraints based on the recommendations Ministry of Non-
Conventional Renewable Energy Sources (MNRE) has announced
incentives like one time capital subsidy to set up co-generation projects in
the sugar factories.
2. USWL Background:
2.1 M/s. The Ugar Sugar Works Ltd. is one of the pioneers in sugar industry in
the state of Karnataka, having started its operations way back in 1939.
USWL has distillery, IML section and Co-generation plant. The company
has expanded its capacity from time to time and the present capacity is
10,000 TCD and 44 MW co-generation, out of which 28 – 30 MW is
exportable.
2.2 The factory started Distillery in the year 1963 & the present capacity of the
distillery is 75 KLPD (30 KLPD batch type & 45 KLPD continuous type).
Company has further installed 20 KLPD Ethanol Plant & 50 KLPD ENA
Plant with blending & bottling of 9 different IML varieties. The company has
provided fully fledged effluent treatment plant which includes Chemical
digesters, concentration & spray drying of spent wash and mixed lagoons
anaerobic & aerobic treatment of sugar factory effluent & evaporation &
drying system for distillery spent wash etc.
2.3 The company has also provided Methane gas generated by biodegradation
of filter cake is used for domestic fuel requirement. The gas is provided to
170 residential quarters. Filter cake is a by-product of sugar factory.
4
UCL
3. Production Scheme
3.1 The main activity of the company is to manufacture white crystal sugar,
Electrical power, ENA, ethanol & IML.
5
UCL
3.2 The daily Sugar cane crushing capacity of the plant after expansion will be
20000 TCD, which means the additional production as follows (maximum).
3.3 The raw material for manufacturing the above is Sugarcane i.e. 25 to 30
lakh MT which is sufficient for 120 to 150 days @ 20000 TCD. The
productivity of the sugar cane & yield depend on water supply & hence, the
cane can be grown in & around the Ugar. Which is on the bank of river
Krishna, has full & sufficient irrigation facility. It is expected that yield will
be 30 to 40 MT per Acre with recovery of sugar as 11% to 12%.
4. Co-generation scheme
4.1 The co-gen plant is configured keeping in view that the sugar factory
operations & also to meet peak steam & power requirement. The
installed capacity of co-gen plant is 77.6 MW with 4 numbers of boilers
having 310 TPH capacities @ 62 bar 490 deg C temp, one boiler having
100 TPH capacity @ 110 bar 540 deg Temp and one 50 TPH capacity @
32 bar 490 deg c & two back pressure TG sets of 22 MW each, one back
pressure TG of 12 MW and one extraction cum condensing turbo
alternator. of 20 MW
4.2 The total average cane crushing is envisaged 25 to 30 lakh MT every year
in the crushing period of 120 to 150 days with crushing rate of 20000 TPD
This would be achieved by the sugar factory from its past performance
data of unit I.
6
UCL
4.3 The process steam consumption is assumed 41.5% on cane; this could
be easily achieved as the proposed modification in the boiling house is
proved one. The electricity consumption during season of sugar factory,
cogeneration, colony etc. is taken as 28 kwh / MT of cane crushed with
electric drives for mill.
4.4 The proposal for expansion is to add one new boiler of 100 TPH capacity
along with modification in the existing boiler. The modification Scheme
envisages the boiler with super heater outlet steam parameters of 32 bar
& 490 Deg. C. & turbo-alternator with the steam inlet parameters of 30 bar
& 480 Deg. C. New Boiler is of 110 bar with 540 deg C steam parameters
with suitable new TG set. All the necessary auxiliary plants & systems in
respect of boiler modification will be installed for the efficient operations of
the co-gen plant.
4.5 The power generation is at 11 KV voltage level from the co-gen plant.
The interconnection with the KPTCL grid is at 110 KV after stepping up
the voltage from 11 KV to 110 KV. The power evacuation feeder is
connected to 110 KV sub-station at ugar which is around 2 Kms from the
co-gen plant site.
4.6 It is envisaged that the co-gen plant would run on sugar factory Bagasse
for 120 to 150 days (normal crushing season) & on saved bagasse for
around 150 to 200 days in non-crushing season to optimize the utilization
of co-gen plant.
4.7 Other equipments remains same, which comprises high pressure boiler,
TG set. condensate system, DM water system, cooling water system, fire
fighting system, compressed air system, instrumentation & control
system, electrical system, LT / HT switchgears, distribution panels, step
down transformers, step up transformer, outdoor switchyard equipment,
data acquisition system etc. for efficient & trouble free operation of co gen
facility.
7
UCL
5.1 The total estimated capital cost of the sugar plant expansion is around
16626 lakhs. This includes land development, civil works, main plant
equipment, auxiliary plants, miscellaneous works, preliminary &
preoperative expenses, contingencies, interest during construction,
financing & other soft costs.
5.2 Project Cost Rs.16626 lakhs
Means of finance
Equity 25% : 4156.5
DEBT 75% : 12469.5
Total = : 16626
5.3 The financial analysis is based on the sugar plant operation. Other
benefits during crushing season as well as Bagasse saving.
8
UCL
9
UCL
CHAPTER 1
INTRODUCTION
1. Background
1.1 The Ugar Sugar Works Ltd. is one of the pioneers in sugar production in the
state of Karnataka; the Company was incorporated on 11th September 1939,
under the able guidance and kind patronage of his late highness The
Rajasahab of Sangli with a crushing capacity of 500 tons per day.
1.2 Vaidya and Company was the first Managing Agents. In the year 1940, M/s.
Shirgaokar Brothers were called to manage the affairs of the Company and
they were the Managing Agents till 31st December 1969. M/s. Shirgaokar
Brothers who had by then made the Kolhapur Sugar Mills outstanding and
notable success proved to be successful in bringing up the Ugar Sugar
Works Ltd., also.
1.3 Under the overall supervision and control of M/s. Shirgaokar Brothers the
crushing capacity of the factory has been increased from time to time as
detailed in Table No. 1.1. At present the cane crushing capacity 12,000 TCD.
Table 1.1 growth in crushing capacity of the plant
Sr. CRUSHING PERIOD
No. CAPACITY IN
TCD
1 800 1955-56
2 1200 1960-61
3 2000 1969-70
4 5000 1988-89
5 6500 1994-95
6 7500 1997-98
7 10000 2002-03
1.4 The company has introduced number of irrigation schemes for the
10
UCL
1.5 The company has started its own distillery during the year 1962-63 and liquor
section in the year 1967-68. New distillery plant unit with production capacity
of 45000 liters of rectified spirit has been commissioned in March 1995.
2. Cane availability
2.1 In Belgaum District where the plant is located, sugar cane is available from
the month of October to April even many times the season has to extend up
to the end of May. Typically, sugar cane availability is for a period of 7 to 8
months in a year. The registered area under sugar cane cultivation allocated
to Ugar Sugar Company is 60,000 acres. The important factor with regard to
the operation of USWL is that the cane arrival is fairly uniform and the plant
reaches the maximum crushing rate within a month of season
commencement. The total cane availability during a season is approximately
40 Lakh tones and most of it reaches the plant during the crushing season.
But now, due to new sugar plants installed in the nearby area, crushing
season days have reduced from 8 months to 5 to 6 months.
3.4 About 90% of the sugar plant's process steam requirement, which is at 2.5 kg
11
UCL
per cm2 abs., is met through exhaust of the backpressure turbines and the
balance requirement, which is at 9 kg per cm2, is met through extraction from
turbine.
Table 1.2 Details of existing Boilers at USWL I
Steam Generators Make Year Capacity Pressure Temp. °C
T/Hr. kg/cm2 (g)
Babcock & Wilcox * 1998 75 62 490
Babcock & Wilcox * 1998 75 62 490
Krupp I 2000 80 62 490
Krupp II 2002 80 62 490
Walchandnagar Industries** 1989 55 32 490
* Purchased old which are manufactured in 1959
** modification proposed to increase capacity by 5 TPH & temp from 380 to 490
deg C
4.3 The average own power generation is about 120.00 million units per year.
The major electrical load of the plant comprises boiler fans, feed pumps,
12
UCL
6.4 The quadruple effect evaporation system has three trains namely A, B & C
and two trains will be always on line. The disposition of the heat transfer
surfaces for the streams is as given in Table 1.4
13
UCL
6.5 The raw juice heating is done in two stages. In the first stage heating up to
50° C is carried out through Vapour Line Juice heater and the heating from
50° C to 75° C is achieved by Dynamic juice heater between 3rd & 4th Body..
6.6 The second effect of evaporator supplies vapors to part of A and B pans and
1st effect vapor is utilized for the C pan. 3rd effect vapors to A continuous pan.
The temperature raise in different stages are as given in
Table 1.5
Raw Juice Heated by Rise in temperature
Stage I III body vapors 30 to 50 C
Stage II I body vapors 50 to 75 C
Sulphited
Juice
Stage I I body vapors 75 to 90 C
Stage II SKI vapors 90 to 100 C
14
UCL
6.8 There are eight cell induced draught cooling towers for removing the heat
absorbed by the re-circulating water from the process.
7. Water supply system
7.1 The complete raw water requirement of the plant is drawn from river
Krishna, which is very near from the plant. The pumping station has got six
pumps out of which two pumps are utilized for sugar plant operation and the
pump ratings are as under:
Pump 1: Capacity: 390 M3/Hour. Head: 36.6 meters.
Pump 2: Capacity: 170 M3/Hour Head: 36.6 meters.
7.2 The raw water, from the river is brought to the plant by a 600-mm
underground RCC pipe and finally discharged into a constant level water
pond.
8. Boiler Feed Water System.
8. The raw water is passed through the pre-water treatment plant comprises
1 solid contact clarifier and chemical dosing system. This clarified water is
passed through DM plants having the capacities of 30m3/hr, 60 and 72
m3/hr. (3 bed de-ionization plants). Exhaust condensate received from the
process and turbine condenser is used directly as Boiler feed water.
Softener water is being used as makeup water for power plant cooling tower
and drainage of this water is used as makeup water for sugar plant cooling
tower.
9. DISTILLERY
9.1 There are two distilleries available with the USWL. One is of very old with
the capacity of 30 KLPD and another one is of 45 KLPD. Total existing
capacity is 75 KLPD. Usw is having IML section also wherein bottling with
their own brand are being manufactured. There is a separate effluent
treatment plant ie evaporation and drying effluent to form a powder is
available with USW.
10 Fire Fighting System.
10. Sprinkler system is provided all through bagasse carriers. Hydrants and
1 portable fire extinguishers are available at other places.
15
UCL
16
UCL
CHAPTER 2
NEED FOR THE PROJECT
1.0
1.1 All the nearby plants are going for the expansion and the forecast is total
crushing days will be reduced. Previously it was only one sugar factory in
Athani taluka, now there are 6 – 7 sugar factories in the radius of 20 to 30
KM.
1.2 Athani Farmers is going for expansion to 5000 TCD
Krishna SSK is going for expansion to 5000 TCD
Renuka Sugar – Kokatnur is going for expansion to 15000 TCD
Renuka Sugar Raibag SSK is going for expansion to 5000 TCD
Mohanrao Shinde Arag is 2500 TCD.
New plant Shirguppi sugar is coming up with capacity – 5000 TCD
New plant Shivshakti sugar is coming up with capacity 2500 TCD.
1.3 To achieve maximum crushing in minimum crop days with maximum sugar
recovery it is essential to go for expansion. Present overheads at Ugar are
already high, which leads to face difficulties in arriving at competitive cane
price. Hence Ugar Sugar management is proposing to expand the sugar
plant capacity to 20000 TCD.
2 Ugar Sugar has already taken steps to overcome the bottlenecks faced to
crush 416.66 TCH (10000 TCD in 24 hrs) and during last season USWL
has crushed almost 416.66 TCH. One of the bottlenecks is still exists i.e.at
cane unloading station of 42 x 84 mill. Due to space constraint and lower
capacity cane un-loaders they are unable to maintain uniform cane feeding.
Bagasse moisture will be on higher side, which leads to fluctuations in boiler
steam working parameters and in turn affects the crushing. Along with cane
unloading station the other parameters, i.e. reduction in crop days in future,
higher overheads per ton of cane and competitive cane price, sugar plant
expansion seems to be essential. Hence USWL proposing to expand the
crushing capacity.
17
UCL
2.1 Alongwith the expansion of the sugar plant capacity to 20000 TCD it is also
proposed to expand cogen power plant capacity to 76 MW with distillery of
200 KLPD capacity.
2.2 The main areas covered under the sugar plant expansion is mill and Boiling
house..
2.3 Mill Expansion: it is proposed to reshuffle the cane unloading system and
enhancing the unloader capacity from 7.5 MT to 12.5 MT to overcome the
existing cane feeding bottle necks and addition of Zero Mill of size 50” X
100” and last mill of 50 X 100 with GRPF for existing 42 X 84 mill to crush
at the required capacity.
2.4 Boiling House capacity to be increased to 20000 TCD, for new additions
capacity shall be suitable for 909 TCH. One parallel boiling house set has
been proposed for the expansion.
2.5 The viability of the sugar factory is improved due to cogeneration, which is
also a need of the State to have more power to meet the growing power
demand in the State.
2.6 Alcohol plays one of the important role in the countries economy. Alcohol is
by product of sugar industry, which is linked to agriculture. There alcohol
produced from molasses deserves the preferential place as a substitute
feed stock for chemical industry and to bridge a gap in our every need. The
gap between the availability of alcohol and requirement by the industry has
been avoiding.
18
UCL
CHAPTER 3
PRODUCT SALE POLICY
1.0 Sugar Sale Policy
19
UCL
20
UCL
21
UCL
CHAPTER 4
22
UCL
2 nos batch type A centrifugal machines are prposed for the expanded
capacity
Four numbers of continuous centrifugal machines are proposed for B
and C massecuite for the expanded capacity
Modification is proposed in the sugar drying and sugar hoppers. There
is no change in sugar silo system
One additional sugar bagging and conveying system up to sugar go-
down is proposed
One additional cooling tower is proposed to take additional heat load
generated by condensers
For cogeneration 1 new Boiler of 100 TPH with working parameters of
110 ata and 540 deg C temperature. Alongwith new Boiler one old
Boiler of 32 bar 380 deg temp is proposed modify to get outlet
temperature 490 deg C.
For above Boiler Two TG sets have been proposed, 1 no 12 MW back
pressure TG set suitable for 32 bar steam and one 20 MW double
extraction cum condensing TG set suitable for new Boiler steam.
Switch yard with transmission line is also to be expanded suitably.
Existing Distillery capacity is 75 KLPD, additional 125 KLPD distillery
to be added.
b) Bagasse saving for 135 days operation with 909 TCH increased
crushing & 90 PLF nearly 137696 MT of bagasse can be saved. Total
Bagasse saving in a season for 909 TCH will be about 137696 MT
c) During season as well as off season USW needs steam to distillery 25
TPH and for evaporator drier of ETP about 25 TPH. This requirement
will be fulfilled by operating cogeneration during season & off season.
d) When cogeneration is in operation distillery steam requirement can be
met through the turbine extraction. Hence it is essential to operate
cogeneration during off season with saved bagasse.
e) Accordingly during off season one of the Boilers will be operated on
saved bagasse for maximum possible days.
23
UCL
24
UCL
TECHNO-COMMERCIAL ANALYSIS
10 CONDENSATE RECOVERY
a FROM SUGAR PROCESS (2.5 ATA) % 90.00
QUANTITY TPH 327.27
b FROM SUGAR PROCESS (8 ATA) % 0.00
QUANTITY TPH 0.00
c CONDENSER % 95.00
QUANTITY TPH 14.25
d DEAERATOR TPH 22.57
f TOTAL CONDENSATE RECOVERY TPH 364.09
g BOILER STEAM GENERATION TPH 458.00
h BLOWDOWN WATER & STEAM LOSSES % 2.00
25
UCL
13 POWER BALANCE
1 POWER GENERATION 2 - SNM MW 43.33
2 POWER GENERATION DEC MW 17.55
3 POWER GENERATION FROM LP STEAM MW 12.00
4 TOTAL POWER GENERATION MW 72.89
5 TOTAL CAPTIVE POWER MW 25.45
6 EXPORTABLE POWER MW 47.43
26
UCL
27
UCL
CHAPTER 5
TECHNICAL SPECIFICATIONS OF EQUIPMENTS
The expansion proposal covers 4 main areas, 1 Mill section, 2. Boiling house,
3.Cogeneration and 4. Distillery. It is proposed to expand the crushing capacity from
10000 to 20000 TCD Co-gen capacity from 44 MW to 76 MW and distillery from 75
KLPD to 200 KLPD
A) MILL EXPANSION
1) All existing 9nos (5 nos for 42 X 84 mill and 4 nos for 33 x 66 mill) cane
unloaders with all its accessories to be replaced by 12.5 MT capacity unloaders.
2) One additional new complete cane unloader of 12.5 MT capacity with gantry,
support structure, feeder table with all accessories to be added to 42 X 84 Mill.
Minimum gantry height should be 12 mtrs.
3) All existing Gantry height to be increased to minimum 12 mtrs height with
necessary strengthening of gantry and columns.
4) Increase in CC No. 1 depth by 300 mm & Width to 2750 mm suitable for 682
TCH crush rate. (Size after increase will be 1400 mm straight & 2750 mm width)
5) One additional strand Chain, replacement of Slats, replacement of tail end shaft
and modification in drive shaft of CC 1. If modification is not possible it is to be
replaced by new one. Suitable motor gear box etc to be added.
6) Chopper to be installed at existing Kicker location with necessary modification
and increasing the RPM.
7) Kicker to be installed at existing chopper location with necessary Modification.
8) Leveler – new shaft with additional knives to be installed.
9) Fibrizor has to be designed to achieve 89 to 90 PI. Complete new assembly to
be installed, swing diameter to be considered as minimum 2130 mm.
10) New 2500Kw 750RPM HT motors – 2 Nos. to be added with starter and control
panel to Fibrizer.
11) New Cane Carrier No.2 suitable to 50”x100” Mill for 682 TCH capacity to be
added.
12 Rotary Strainer identical to existing to be added.
13 Inter Rake Carrier – Depth of carrier truff to be increased
14 Bagasse Elevator – Minor modification (depth of trough and height of rakes to
be increased.)
15 Zero mill and last mill of 50”x100” (2 Nos.) with TRPF & TUFR to be added. Mill
RPM shall be 4 rpm for ultimate capacity i.e. for 682 TCH crush rate. 1250 KW
DC motor removed from Fibrizer to be installed for zero mill. Planetary Gear
system with rope coupling suitable for 1250 KW power transmission.
28
UCL
¾ For operation of these motors, push button type panel shall be provided
and its location shall be in the cabin attached to the trolley.
29
UCL
3. Mill – 2 Nos.
¾ two nos. of Ø 1270 X 2540 mm nominal roller size five roller Integrated
30
UCL
type mills with Toothed roller pressure feeder to be installed. The mills
shall have toothed roller pressure feeder driven by top and feed roller
through chain sprocket to give surface speed of about 30% higher than
mill roller surface speed.
¾ All the mill rollers will have bearing journal of minimum 620 mm dia. and
770 mm length and central shaft dia 670 mm and running in gun metal
liner fitted in cast steel housing. The rollers will have circumferential 'v'
grooves. The headstock to headstock centre distance shall be @ 3850
mm.
¾ The roller will be of coarse grain cast iron having hardness 180-210 BHN.
The composition of the shell material will conform to IS 11201:1985 and
will be-
¾ The cast iron shell will be hot shrunk fitted on forged steel shaft of 45C8
quality conforming to IS:1570-1979 or equivalent having a minimum
tensile strength of 58 Kg/mm2. All the shafts will have square ends not
less than 500 x 500 mm. Top roller will have stationery collars duly hard
faced and fixed with head stock. The bottom roller will be provided with
juice rings and removable guards to prevent entry of juice into the
bearings. The cast steel crown pinions will have minimum, 750 mm face
width and conform to IS: 2708 Grade III with well dressed well ground and
matched and good profiled cast teeth and will use tangential key's on
roller shaft for pinion fitting and suitable mild steel guards and troughs will
be provided. The apex angle of mill will be limited to 750 max. approx.
¾ The headstocks will be of cast steel as per IS: 1030 - 1974 grade 260/520
W. The head stock supplied shall be suitable to integral type Five Roller
Mill of our patented design.
31
UCL
¾ These will be of pin type head stock. Removable gun metal wear plates
on feed side as well as at discharge side of top roller bearing with
lubricating arrangement between bearings and wearing plates will be
provided. The top and side caps will be of cast steel as per IS: 1030-1974
grade 260/520 W and will be securely locked in position for quick
assembly. Stainless steel strip of 8 mm thick will be provided on the side
roller bearing face of the headstock. The eccentricity between top roller
bearing center and hydraulic top cap center will be minimum 45 mm
towards the feed side of the head stock.
¾ All rollers will be coated with surface roughening electrode material and
its bearing will be of cast steel housing with renewable gun metal liner
with water cooling arrangement. The top and side roller bearing will be of
cast steel housing with renewable gun metal liner as IS: 318-1981. The
housing will have water cooling arrangement. All top roller bearings will
be interchangeable. Similarly all feed side and discharge side roller
bearings will be interchangeable by their respective bearings.
¾ Mill to be provided with cast steel trash beam as per IS 1030 grade
260/520 W and supported on heavy steel brackets with pivoted journals
fitted in the headstocks and adjustable by means of tie rods and fitted with
renewable CS trash plate as per IS: 1030 grade 22/45, bolted by high
tensile bolts and nuts. Meschaert groove scrapers will be of spring steel
secured on square shaft and supported on cast steel blocks and provided
with lever or other suitable adjusting device. Scrappers for top and
discharge roller shall have renewable tips.
32
UCL
¾ Juice trough under the mill will be made of 6 mm thick S. S. 409M plates.
The trough will be welded to the headstocks. Joints will be suitably sealed
to prevent any juice leakage. The trough will have 900 included angle. Mill
will be high set, so that no part of the juice tank and pumps are situated
below floor level. All the mills will have common gangway on both sides
having width not less than 1000 mm with gratings and minimum 3 Nos of
stair cases, two for crusher side, and one from mill drive platform along
with the cross connection between each mill. Access from mill platform to
cane carrier drive platform, and rake elevator drive platform with suitable
cat ladders shall be provided. All gangways and staircases will have hand
railings.
6. Planetary Gear Box with fls (lubrication system) for Mill drive
¾ The planetary gear box shall be of foot mounted design, ratio 1000: 4.0,
suitable for 900 KW continuous rating with 2.0 minimum service factor.
The shafts of the planetary gear box shall run in antifriction bearings. The
gear box shall be complete with forced oil lubrication system, geared type
input coupling and rope type output coupling, base plate etc.
33
UCL
welding the roller shell all over by hard facing electrodes. TRPF top roller
is driven by mill top roller by 3” pitch duplex chain and sprocket similarly
bottom roller is driven by mill feed roller by 3” pitch duplex chain and
sprocket.
¾ Closed feed hopper fabricated out of 6 mm thick SS409 M plate duly M.S.
reinforced to be provided for each mill. It will have arrangements to adjust
the blanket thickness from adjustable front plate. The feeding height in
each hopper will not be less than 2.5 meters and its inclination will be 900
with the horizontal. The closed feed hopper will have electronic/electro-
mechanical suitable level sensing device to control the cane feeding.
Suitable indicators may be provided to indicate level of bagasse in
donnelley chute.
34
UCL
horizontal. The head shaft will be on 45C8 quality, dia 200 at centre and
dia 175 at journal running in G.M. bearing. The tail shaft will be of forged
steel having MS drum running in dia 150 mm G.M. liner. The size of
chain 229 mm pitch block forges type with 80 ton breaking load.
¾ Mill shall be provided with conical bottom cylindrical whirler tank having
1250 mm dia. made of 5 mm thick SS 409M material connected to mill
juice trough through 3.2 mm thik SS gutters.
¾ The juice pumps all running at 1000 RPM shall be following capacities
and heads shall be supplied along with all its suction, delivery piping
valves, along with TEFC motors etc.
¾ All pumps in mill house shall be of choke-less type with stainless steel
body and stainless steel impeller with full bore discharge and capable of
pumping mill juice with min 20% solids, at head specified above. The juice
from 1st mill shall be separately pumped through choke-less pump with
SS metal body and impeller with full bore discharge and capable of
pumping 600 m3/hr net juice plus min. 20% solids and 20 M head through
piping to rotary juice screen. The speed of the motors driving these
pumps shall not be more than 1000 RPM.
35
UCL
¾ New B Crystallizer
¾ New C Crystallizer
¾ Centrifugal machines
¾ Vibro screens
¾ Cooling Tower
¾ Condenser Automation
¾ Structural supports
¾ Miscellaneous equipments
36
UCL
In order to operate the distillery throughout the year say about 300 days/
annum, it is proposed that the Distillery shall have separate boiler in off season
of suitable capacity with T.G. set.
They shall have its own arrangement for steam & electricity. The Power
generated will full for operating the distillery as well as for lightening the roads
& buildings.
Distillery will discharge spent wash effluent at the rate of 10 to 12 liters
per liter of Alcohol produced. Daily production of spent wash shall be 2000 m3
to 2400 m3. The spent wash has high B.O.D. to the extent of 80,000 to 90,000
mg/l. As per the standard laid down by the Government the BOD should be
brought down to 100 to 30 mg /l. Before it is charged over land or water
respectively. There is no suitable and economical method to achieve these
standards. The method of concentration and drying of spent wash besides
being very costly, pose number of problems, as regards it maintenance and
repairs due to high temperature and corrosive nature of spent wash.
The alcohol produced in the distillery shall be sold as per the
Government’s directives to the parties getting allotment. The distillery shall
make good profits, besides getting better price for its molasses. It provides
good opportunity for the further diversification. The distillery project is very
attractive as the demand for alcohol will be increasing for manufacturing
chemicals.
37
UCL
produced which can be used as a fuel in boiler. The quantity of gas produced is
almost sufficient to generate the steam required for generation. It requires
secondary treatment for the Distilleries are as under:
38
UCL
One no. 36’ dia with 5 Nos. compartments of 1525 mm height. Clarifier shall
have separate juice & mud outlet from each compartment.
The flocculating compartment complete with skimmer & feed well shall be
installed separately. The clarifier shall be made of mild steel plates having
following minimum thickness:
Particulars
Type : 555
Quantity : 1 No
Capacity : 36 Feet Dia
Accessories : Flash tank
PLATE THICKNESS : Carbon Steel as per IS 2062
1. Bottom : 12 mm
2. Shell : 10 mm with stiffeners
3. Tray (intermediate) : 12 mm
4. Tray (top) : 10 mm
5. Top cover : 10 mm
6. Flocculating compartment : 10 mm
Mud Liquidation Pump
Quantity : 1 No
Capacity : 50 m3/hr & 20 m head
Drive : Suitable
Flocculating dosing system
Tank : Adequate Capacity
Dosing pump with drive : One set
Juice liquidation pump
Quantity : 1 No
Capacity : 50 m3/hr & 20 m head
Drive : Suitable
39
UCL
The continuous clarifier shall be complete with mild steel flash tank &
withdrawal boxes 2 Nos. for clear juice & 1 No. for mud with sleeves,
telescope pipes & O rings, hinge type squeezers, driving mechanism with
variable speed drive head with motor consisting of sprocket, chain & drive
guards, all inside & outside clear juice piping & mud piping, all valves & pipe
fittings etc. & complete with peripheral walkway, angle iron bracket supporting
angles, piping for railing, rail support etc. 5 manholes one for each
compartment, each manhole to have platform, railing & access ladder. Each
pump with receiving tank & support. Insulation material of mineral wool 50 mm
thick with PP etc to be included in the scope of vendor. Mud liquidating and
juice liquidating pump of CI construction with bronze fittings.
Mud boot sealing arrangement to be done from topside of mud boot bottom
plate.
The bodies shall have a vapour space height (between the top tube plate and
the bottom of the catch all or cylindrical portion of the vapour space) shall not
be less than 1.5 times the calendria height. Suitable arrangement for light and
heavy noxious gas removal shall be provided. Boxes shall be provided for
easy removal of condensate from calendria. Manhole shall be provided in
bottom saucer and vapour space & catch all. Suitable connection for soda
washing and draining for juice shall be provided. Suitable relief valve spring
loaded or dead weight lever type shall be provided on calendria and in the
vapour space of evaporator to ensure the pressure in the body does not
exceed working pressure.
Condensate outlet pipe shall have sight glasses at eye level in addition to
sight glasses in extraction columns. The cock shall be provided at all units
individually for testing condensate for sugar traces and suitable drain
connection shall be provided to drain the condensate.
Evaporators shall be complete in all respect with fittings for satisfactory
operation.
40
UCL
SS-304 Poly baffle type suitable to pass all the vapours generated and 100%
guaranteed design against entrainment, Following connections to be provided
on Catchall of minimum 18 mm thk.
1 100 NB for water washing nipple with coil 1 No
3 Vapour outlet suitable for 120 T/hr. Vapour at 25 mtrs/sec. 1 No
velocity.
5 400 mm manhole hinge type 1 No
6 Other balance connections required.
BODY SHELL
Cylindrical vapour space 600 mm dia more than the Calendria dia with
minimum height 1.5 times more than tube length, shell thickness 18 mm thick.
The cylindrical portion should be with required stiffeners rings.
1 200 mm dia sight glass first assembly and first glass at 200 2 Nos
mm from top tube plate.
An inverted umbrella type vapour deflector placed at 2 m. height from top tube
plate of 16mm thick.
2 200 mm dia light glass assembly 1 No
3 500 mm dia manholes 2 Nos
4 100 mm connections for soda connection 1 No
5 150 N.B water connection 1 No
6 150 NB Temperature gauge connections 1 No
7 Pressure gauge connection 1 No
CALENDRIA
1 Shell plate 18 mm thick
2 Tube Plate 32 mm thick
3 Ligament 15 mm (min)
4 Pitch 60 mm
Peripheral down take with 2 Nos. Juice outlets 4 Nos. stools
Bolted/welded connection with bottom cone.
4 Steam entry 1200mm dia with flange & nipple. 1 No
5 150 N B water connection with flange & nipple 1 No
6 150 N B Condensate connections with flange & nipple 4 Nos
80 N B Noxious gas connections each for light & heavy gas complete with
interconnecting piping of SS 304. Moreover removal of noxious gases from
centre of Calendria of 80 N B 6 Nos minimum. OR as per your design so that
100% noxious gases shall be removed to get the required evaporation rate.
7 Pressure gauge connection 1 No
8 Temperature gauge connection 1 No
41
UCL
BOTTOM CONE
Bottom /Welded connections with Calendria shell cone thickness 25 mm thick
consisting of Juice coil and Juice deflector etc.
1 250 N B Juice inlet connections 1 No
2 250 N B Juice outlet connections 2 Nos
3 150 N B drain connections 1 No
4 500 mm hinged manholes 2 Nos
5 150 NB wash out connections 1 No
Standard fittings as per requirement
Condensate receiver and pumps with motor including all valve and fittings.
Supply & application of 50 mm thick LRB mineral wool with PP
Right angle valve for the steam inlet
42
UCL
BODY SHELL
Cylindrical one with suitable stiffener rings cylindrical portion 18 mm thick,
minimum height 2 times the height of the tubes.
1 200mm dia sight glass first one at 200mm from top tube plate. 3 Nos
2 200mm dia light glass assembly 1 No
3 500mm dia manhole(to be fixed as per the site requirement) with 4 Nos
hinge type cover having 3 to 4 bolts
4 150mm soda connection 1 No
5 150mm water connection 1 No
6 150 NB relief valve connections 2 Nos
7 Pressure gauge connection 1 No
8 200 N B peripheral juice outlets 4 Nos
CALENDRIA
1 Shell plate 18mm thick
2 Tube Plate 32mm thick
3 Ligament 15 mm (min)
Central sealed down take 12 mm thick 4 Nos. stools
Bolted/welded connection with bottom cone.
4 Vapour entry to Calendria 2 Nos
5 150 N B water connection 1 No
6 150 N B Condensate connections 4 Nos
7 80 N B Noxious gas SS 304 12 nos
Connection each for light & heavy gas complete interconnecting piping and 2
Nos. 100 N B outlet with valves. of SS 304.
7 Pressure gauge connection 1 No
8 Temperature gauge connection 1 No
BOTTOM CONE
Bottom /Welded connections with Calendria shell cone thickness 25 mm thick
consisting of Juice distribution coil.
1 250 N B Juice inlet connections 1 No
2 250 N B Juice outlet connections 1 No
3 200 N B drain connections 1 No
4 500 mm hinged manholes 2 Nos
5 150 NB wash out connection 1 No
STANDARD FITTINGS
43
UCL
44
UCL
10 Body thickness 18 mm
12 Calendria thickness 18 mm
14 Catchall Internals 12 mm
45
UCL
34 Steam Conn. To 25 mm NB
compartment. Drains
39 Pump for seed drive and PSP pump with VFD drive
gearbox capacity 15 T/Hr @
40 m head-1x
46
UCL
Valve
47
UCL
10 Body thickness 18 mm
12 Calendria thickness 18 mm
14 Catchall Internals 12 mm
48
UCL
49
UCL
Functional Requirements -
The system as a minimum, shall meet the following requirements without
the supervisory computer:
1) Control
2) Data acquisition & monitoring
3) Alarming
4) Logging & report generation
5) Historical data storage
6) Trending
7) System shall have free memory space available for the user and CPU
shall have the additional capability to perform advance control functions,
process optimization programs or generate management reports. The
availability of process control language shall be preferred.
50
UCL
Control System –
Control system for PAN automation shall be PLC based with latest
technology available. The system shall be designed with redundant
controller. Controller make & model to be informed before finalizing. No.
of IO shall be as per the requirement of the PAN control. Additional 20%
IO’s to be considered in the system for future use. The communication
between PLC controller & Operator station shall be Ethernet only.
PLC Make : Honeywell HC-900, GE
Software –
SCADA -
Printer –
One no. of LaserJet printer shall be supplied with system for report &
trend printings.
Control Valves –
All required control valves for feed control (masscuite & water) should be
of Butterfly type only with double acting rotary actuator. The actuator
should have smart positioner with position feedback output. All other
valve required for steam/vapour shall be of globe type with pneumatic
actuator & smart positioner. All required air filter regulators to be
considered in scope of supply.
Feed Valve Mark : El-O-Matic
Valve Positioner: YTC
Air Filter Regulator: Janatics
51
UCL
Transmitters –
Conductivity Sensors –
Flow Meters –
All required flow meters should supply with required accessories along
with meeting Flanges. Remote type Flow Transmitter with display and
programmable to be supplied with min. 10 mtr. cable from flow tube.
Electromagnetic Flow meter sizing calculation should inform to us before
finalizing. Make: Krohne, Emerson, Yokogawa
Temperature Sensors –
52
UCL
SYSTEM FURNITURE -
Online UPS system with required capacity with minimum 2 Hrs. battery
backup to be considered in the scope of supply. The batteries to be shall
be Tubular type and industrial grade only with min. 5 years warranty.
The input cable for UPS system shall be in supplier’s scope. Minimum
10 mtr.cable to be considered for input supply of UPS system. The cable
between batteries & UPS shall be also in supplier’s scope. Minimum 5
mtr. Cable to be considered from UPS to battery bank.
Horizontal type water cooled crystallizer 2 nos for B massecuite shall be driven
by planetary drive, suitable for continuous working, complete with suitable
reduction gear unit, suitable design to give a stirrer speed of not more than 60
RPH, The cooling surface (m2) to volume (m3) ratios shall be minimum 2.
The shell of the horizontal crystallizer shall be made of minimum 12 mm and end
plates 18mm thick MS plate.
53
UCL
4 Quantity 1 No
The difference between height of inlet massecuite in the shell and overflow
gutter will be 2 mtrs. and the vertical crystallizer shall have sufficient cooling
surface so as to cool the massecuite from 65 deg C to 40 deg C, in 20 hrs,
when supplied with cooling water at 30 deg. C provision in the design will be
made for a maturing period of 4 – 5 hrs.
7 Tentative Dimensions
8 Plate Thickness
b) Bottom plate 20 mm
c) Trough Shell 8 mm
d) Hollow Shaft 12 mm
54
UCL
10 Drive
12 Accessories
Twin type Vertical type water cooled crystallizer for 'C' massecuite shall be
driven by electric motor for 250 T capacity suitable for continuous working,
complete with suitable reduction gear unit, suitable design to give a stirrer
speed of not more than 0.26 RPM, with Planetary gear box.
Necessary cooling surface shall be provided so that the temperature of the
massecuite is cooled from 65 deg C to 40 deg C in 20 hours, when supplied
with cooling water at 30 deg C. Provision in the design shall also be made for a
maturing period of 4-5 hrs in case of low grade continuous crystallizers. The
cooling surface (m2) to volume (m3) ratio shall be minimum 2. The heat
exchange elements shall be tested at pressure of 6 – Kg/cm2 g. suitable for
continuous working.
12 CO-GENERATION
Existing boiler modification to enhance the generation capacity from 50 TPH to
55 TPH and temp up-gradation from 380 to 500 deg C. One no new 12 MW bk
pr TG set suitable for these working parameters is proposed
In order to meet the process steam demand it is also proposed to add one new
55
UCL
boiler of 100 TPH capacity with working parameter of 110 bar pr and 540 deg
C temp. one 20 MW Double extraction cum condensing turbine suitable for
new Bloiler steam working parameter is also considered.
56
UCL
CHAPTER 6
2) Land Availability:
a) The layout of the sugar complex is studied in detail & land required for
addition of zero mill is available between fibrizer and first mill. Last mill
addition is replacement of 42 X 84 mill. There is no need of any
additional space for modifications to be carried out in the milling section.
b) Area required for Clarifier is near existing clarifier on north side.
57
UCL
58
UCL
59
UCL
f) Liquid wastes from the milling plant and boiling house, This water will
be diluted and discharged into circulating water pit after checking for
dissolved solids and pit.
60
UCL
CHAPTER 7
RISK ANALYSIS & MANAGEMENT
1) USWL Performance:
ii) USWL has a vast pool of technically qualified staff, which has
gained ample training & experience. Steady management control
mitigates the risks of management instability.
iii) State support for the sugar industry as a whole mitigates the risk of
unfavorable political environment.
61
UCL
ii) Area of operation consists large no. of villages from athani, taluka,
on river bank Krishna. At present cane area is covered by river
irrigation & as well as well irrigation.
62
UCL
ii) The relative profitability per hectare of different crops in India as per
the draft report of World Bank is the highest for sugar cane.
3) Fuel Risk:
a) Risk of non-availability of bagasse will not arise as bagasse generated
from the own mill will be more than sufficient.
4) Technology Risk:
Technology adopted for the expansion plant is an established technology & in
operation in the same plant for the past 75 years.
5) Construction Time:
i) Total expansion work requires hardly 6 to 7 months. Hence there is no
risk of work completion before start of the coming crushing season.
6) Environment Risks:
i) The compliance with the Indian environmental standards will be ensured
from the time of project design. It is proposed that factory will undertake
rapid Environmental Impact Assessment (EIA) & Disaster Management
Plan through a reputed agency.
ii) Procuring the plant & machinery from proven & established equipment
manufacturers.
63
UCL
iii) Engaging experienced staff for the operation & maintenance of the
cogen plant.
iii) Individual components of the project will be executed under EPC with
fixed price EPC contract thereby minimizing the risk of cost overrun.
64
UCL
65
UCL
CHAPTER 8
PROJECT COST ESTIMATION
1) Cost Structure:
a) General
i) This section of the report gives the estimation of the total cost of the
new equipments like boiler, turbine, boiling house equipments,
distillery along with the modifications in the existing set up is estimated
on the basis of the prevailing prices & rates as in Dec 2011 & the
estimation is for the installation of power generation & service
facilities. The estimate is based on the in house cost data compiled
from the other similar jobs executed in the recent past No provision
has been made for any escalation in these estimates & the project is
expected to be implemented shortly. However the estimates include a
contingency provision of 2% on the estimated cost.
ii) The cost of the conversion cost of the plant, presented in this report,
covers all the costs associated with the construction cost, cost of plant
& includes the civil construction cost, cost of equipment, cost of
auxiliaries & utilities. The total project is arrived at by adding to this
cost, the pre-operative expenses inclusive of project design &
engineering, interest during construction.
The detail of the estimate of the total project cost which includes the
contingency & pre-operative expenses, IDC & the working capital is
given in a separate table at the end of this chapter.
66
UCL
ii) The civil work quantities & the cost of civil worked out are only
estimates & will have to be suitably modified & firmed up after the
equipment supply is finalized & adequate data regarding the loading
& dimensions of the equipment are available from the manufactures
& suppliers during the engineering stage & also on the actual soil
conditions encountered at different stages of construction. The
estimates given here are based on the expected soil bearing capacity
of 25 tones / sq. m.
iii) The total cost of civil works including equipment foundations,
buildings, cost of land development, roads, miscellaneous foundation
etc. is considered.
ii) The cost estimate includes the cost of Pipelines, Ash handling
system, bagasse feeding system.
iii) The cost estimate also includes the modification cost of the bagasse
handling system. This includes all the conveyors, their supports,
67
UCL
electrical interlocks cost of from end loaders & tractors. The cost also
covers the complete ash handling system for the plant.
iv) Cost towards the plant erection, testing & commissioning have been
included in the equipment cost indicated. Also the cost estimates
given in the report are inclusive of the taxes & duties, freight &
insurance.
e) Contingency Provision
A provision of about 2% of the cost of civil & structural work, mechanical &
electrical equipment & other costs has been provided towards
contingencies, during the construction of the project.
f) Preliminary & Preoperative Expenses
A provision is made towards the preliminary expenses to cover project
management expenses, travel, startup, training etc.
68
UCL
No Equipments Rs Lakhs
1) Mill Section 1800
2) Boiler 2500
3) Boiling House 2500
4) Fuel & Ash handling 500
5) TG Set 2000
6) Distillery 2500
7) Molasses tank 200
8) Sugar Bag handling & sugar go-down 400
9) Switchyard 400
10) Civil 1200
11) Miscellaneous 300
12) Total 14300
13) Taxes Duties & transport (@ 14.%) 2000
14) Contingency @ 2% 326
Total = 16626
69
UCL
909 TPH
Bagasse Production
(At 29%) 263.6 TPH
263.6 TPH
254.5 TPH
46.36 TPH
70
UCL
46.36 TPH
Bagasse Production Bagasse Saving
254.55 TPH 46.36 TPH
22.72 TPH 185.46 TPH
PRDS
80 TPH
130 TPH 130
92.5 TPH
22.8 MW SNM 22.8 MW SNM
1Turbine 1Turbine
New DEC 20 MW TG
12 MW Turbine 15 TPH
7.4 TPH 15 TPH Condenser 15 TPH
15 TPH
distillery
8 ata 37.4 TPH
71
UCL
POWER GENERATION
From SNM TG Set – 43.33 MW
From New TG Set – 12 MW
From Siemens TG Set – 17.55 MW
Total Power Gen. – 72.89 MW
72.89 MW
POWER CONSUMPTION
Captive for Sugar Plant –20 MW
Captive for Cogen Plant –5.45 MW
Total Captive Power = 25.45 MW
47.43 MW
EXPORTABLE POWER to
KSEDCL Grid – 47.43 MW
72
UCL
110 ata
500 Degree C
1 X 100 TPH
86 TPH
73
UCL
11.94 MW
10.02 MW
Exportable Power to
Grid 10.02 MW
74