Walker-Site Remediation Using Soil Mixing Techniques On A Hazardous Waste Site-A Case History
Walker-Site Remediation Using Soil Mixing Techniques On A Hazardous Waste Site-A Case History
ANDREW D. WALKER
Geo-Con, Inc.
P.O. Box 17380
Pittsburgh, PA 15235
INTRODUCTION
At 2,400 beds, the $112.5 million Allegheny County Jail in Pittsburgh, PA, will be
one of the nation’s largest county jails.
This case history presents the evolution of these remediation measures, with the
main emphasis on the insitu treatment of the contaminated soils adjacent to the
Parkway structures.
SITE DESCRIPTION
Petroleum hydrocarbons had affected site soils at three separate locations over
the estimated area of approximately 32,000 sq. ft. The depth of contamination
varied from 3 feet in two areas to over 20 ft. in the area next to the retaining wall.
Total Petroleum Hydrocarbon (TPH) concentrations ranged from less than 50
ppm up to 11,000 ppm with levels varying from the surface to the groundwater
table which was located at 25 ft. below existing grade.
A typical soil description for the excavation area was sandy silt to silty clay with
cinders, rocks, and brick pieces. Standard penetration tests ranged from 2 to 13
blows per foot.
The higher loaded sections of the retaining wall were founded on piles which
apparently transferred load to the underlying bedrock. The present condition of
these timber piles was unknown. In other sections, loads decreased as the
Interstate ramped down, with the wall on spread footings only.
This immediately raised the question of the stability of the retaining wall and
hence the Parkway if the proposed excavations were made.
Therefore, emphasis was placed on the use of a microfine cement grout for
improved permeation, injected using the end of casing method, in order to
optimize filling of soil pores to fixate the hydrocarbons and densify the material.
Although Ordinary Portland Cement would have been adequate in the coarser
general fill and debris, microfine cement was selected for use since portions of
the subsurface contained fine granular soils which required fixation to prevent
water infiltration. The strength requirement was secondary and was specified as
an unconfined compressive strength of 500 psi in order that the zone would be
capable of supporting its own structure on near-vertical slopes.
PADER and Penn DOT both concurred with this approach and the project was
placed out for bid in the Spring of 1991.
The Specialist Geotechnical Contractor who was low bid on the Remediation
Contract offered a Value Engineering alternate to the microfine cement grouting
specified, namely the use of Shallow Soil Mixing (SSM) in conjunction with
single-phase Jet Grouting. This alternate was attractive both technically and
commercially and was reviewed, accepted and the contract awarded. The
remainder of the cleanup work was implemented as planned.
SHALLOW SOIL MIXING
Although the process of soil mixing originated in the United /states in the 1950's,
its major development has occurred over the last twenty years in Japan. To
date, there have been thousands of projects performed in Japan using some
form of soil mixing, however, the first use for Environmental cleanups was in the
United States. In North America, it has been used for foundation elements, block
stabilization, gravity walls, and fixation/solidification of contaminated soils. the
first geotechnical construction application was completed in 1990 in Canada [1].
The mixing head can also be enclosed in a bottom-open cylinder to allow for
closed system mixing of waste and powdered reagents. The dry treatment
chemicals are then transferred pneumatically.
The advantages of the system on the Pittsburgh site were numerous and were
key in the client’s decision to sanction its use.
While microfine cement grouting was feasible to treat the areas of low-level
contamination, it had some limitations, in contrast to the advantages of SSM,
namely:
• The soil profile was extremely heterogenous with material varying from rock
and brick fragments to cinder, sandy silts, and silty clays. While the former
may be injected by a cementitious grout, the latter will not be permeated by a
particulate grout [2]. Hydrofracture may well occur if not closely monitored
which, rather than strengthening the soil mass, may create weak sliding
planes with the body. Uniformly consistent treatment throughout the zone is
impossible to achieve since the microfine cement will extend into only
“groutable” soils and voids.
• The use of the end-of-casing method, in which grout is pumped from the
bottom of an open pipe, is often employed with success in loose formations
but has numerous disadvantages. With the method, it is impossible to know
positively at which elevations the grout ahs been accepted into the ground. It
is quite possible for grout to pass up the side of the injection pipe and enter
the soil at a higher elevation than that of the pipe tip. In extreme cases, the
grout may daylight at the surface. Therefore, monitoring of grout takes by
elevation, an important QA/QC control on grouting work, may be difficult and
in some cases, misleading.
• With specified method, it was not possible to inject different grout or grout
mixes successively in the same hole. For instance, highly permeable rubble
which may be present on site would probably accept a more economical
ordinary Portland grout rather than the high-cost microfine cement.
• The extent of ground treatment required cannot be ascertained in advance of
commencing grout injection on site. Work would proceed in a Primary,
Secondary, Tertiary split-spacing manner with grout acceptance monitored
until acceptable reductions in take had been achieved, at which time work
would cease. This increases the risk of schedule overrun on a method which,
in addition, is intrinsically slower than the alternate proposed. This was
significant on a contract let on a very tight schedule, where all risks of time
extensions must be mitigated.
JET GROUTING
Jet grouting is a soil improvement technique which is now beginning to gain wide
acceptance in the United States as the recent conference in New Orleans clearly
demonstrated [3].
There are at present three general forms of jet grouting involving the injection of
a single fluid (grout), two fluids (grout/air), or three fluids (air/water/grout). The
single-phase system (CCP) was used on the Pittsburgh site in which the grout
both excavates and cements the soil. This is in contrast to the two-phase system
in which an air shroud is used to improve cutting efficiency and the three-phase
in which the excavation and cementing operations are separated. In this respect,
the single-phase system can be regarded as more of a jet mixing method rather
than pure replacement.
Whatever, the form, the method relies on the use of ultra-high pressures
(typically 4,000 psi to 6,999 psi) to impart energy to a fluid which is injected at
about 800-1000 ft.sec. the high speed fluid cuts and mixes the native soil
usually, as in the case here, with a neat cement grout. The high velocity is
developed by using 350 HP triplex piston pumps which inject the grout through
small nozzles set in a monitor mounted on the tip of a drill string. Figure 2 shows
the monitor above ground. By varying the rotation speed and the rate that the
drill string is lifted from the bottom of the treatment zone, soilcrete columns of
different sizes may be formed. the type of soil being mixed has a significant
effect on the final properties of the column.
As shown in Figure 3, three rows of 8 ft. diameter columns on a 6 ft. x 6, 7 ft. grid
were installed. They were formed on a primary and secondary sequence within
each row, with the installation of the secondary columns timed to occur before
the adjacent primary columns reached full strength. In this manner, block of
ground over the full width were completed as the soil mixing progressed along
the wall. In order to stabilize/fixate areas that could not be accessed safety with
the 150-ton crane jet grouting was necessary. These zones were limited to
adjacent to the timber piles and under Liberty Bridge. In these areas 3 ft.
diameter jet grout columns were formed, either contiguous or on a 2.5 ft.
triangular grid.
For both techniques, the stabilizing reagent was a Portland Cement slurry.
It was the intention to produce similar strengths for the SSM columns at an
earlier date in order for excavation to proceed quickly after column construction,
thus ensuring compliance with the very tight overall project schedule of 60 days.
Grout control was performed by frequent checks on the grout mix unit weight by
use of a mud balance. The test location was at the batching plant prior to
pumping grout to the SSM and jet grout rigs.
CONSTRUCTION
The SSM rig consisted of a high torque turntable mounted on a 150-ton crane
which powered the 8 ft. diameter auger. Figure 4 illustrates the rig in operation.
Grout was supplied by a high-speed, continuous-mix, colloidal grout plant. This
consisted of a storage silo, 1,000-gallon colloidal mixer and a progressive cavity
pump. this same setup was used for the jet grouting with the exception of the
use of a 350 HP pressure, triplex piton jet pump. This pump was rated at
pressures up to 20,000 psi and flow rates up to 170 gpm. While plant was being
assembled, initial shallow excavation of contaminated material away from the
retaining wall took place, along with concrete removal operations and waste
characterization profile soil sampling. Test pits were also dug along the line of
the wall to confirm the location of the piles.
All grouting work was completed within twenty days with initial excavation of a
vertical face against the stabilized block taking place only four days after column
construction, thanks to the excellent early soilcrete strengths obtained. Figure 6
gives a good indication of the columns produced.
Air monitoring started as soon as work commenced using the HNU, LEL, and
PDM3. At no time did ratings exceed background levels. On this basis, Level D
personal protective equipment (PPE) was stipulated for the SSM work. This was
modified to include a two-piece chemical-resistant splash suit (PE or PVC Tyvek)
and outer inner gloves for the jet grouting work where there was a possibility of
splashing.
Figure 6. Trial SSM Column with Completed Wall to Left
STRENGTH RESULTS
Wet samples were retrieved from columns for testing from each day’s work.
these samples were taken by a special sampling tool below the surface of the
column immediately following installation. The tool, mounted on a beam and
deployed by the crane, consisted of a cylinder with a bottom flap that could be
activated from the surface.
Compressive strength tests were performed in accordance with ASTM C39, the
results of which are shown in Figures 7 and 8.
1. Higher soilcrete strengths are produced by SSM than by jet grouting for
both short and longer term curing periods.
2. A much quicker early strength gain for the SSM compared with jet grouting
and better strength gain with age.
Even though more cement is used per unit volume of treated soil in jetting, these
results demonstrate that SSM is a more effective tool, producing a technically
superior final material at a lower cost. This is partly the result of the cement
wastage inherent in jet grouting.
Figure 7. Soilcrete Strengths, Short Term
These comments only apply to the particular soil conditions on this site, and
results may be radically different for other soils.
CONCLUSIONS
This case history clearly demonstrates the role that the soil mixing technologies,
initially developed for General Civil Engineering work, can and are now playing in
the Environmental market, to provide cost-effective proven solutions in
hazardous site remediation.
With this method, much greater depths up to 100 ft. may be reached.
REFERENCES