OWNER:

LOCATION:

ITEM NO DESCRIPTION MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER
DATE DATE DURATI WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17 WEEK 18 WEEK 19 WEEK 20 WEEK 21 WEEK 22 WEEK 23 WEEK 24 WEEK 25 WEEK 26 WEEK 27 WEEK 28 WEEK 29 WEEK 30 WEEK 31 WEEK 32 WEEK 33 WEEK 34 WEEK 35 WEEK 36
STARTED FINISHED ON ######
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
PART I- PLANNING, PERMITS, AND TEMPORARYPERMITS 6-Mar-24 16-Mar-24 10 1 1 1 1 1 1 1 1 1 1 1
A.1 Execution and Lay out of Shop Drawings 6-Mar-24 16-Mar-24 10 1 1 1 1 1 1 1 1 1 1 1
A.2 Processing of Permits 6-Mar-24 16-Mar-24 10 1 1 1 1 1 1 1 1 1 1 1
A.3 Methodology
A.3.1 Construction 17-Mar-24 5-Apr-24 19 11111111111111111111
A.3.2 Wet Stand Pipe 17-Mar-24 5-Apr-24 19 11111111111111111111
A.3.3 Smoke Extraction 17-Mar-24 5-Apr-24 19 11111111111111111111
A.3.4 FDAS 17-Mar-24 5-Apr-24 19 11111111111111111111
PART II -TEMPORARY FACILITY
B.1 Provision for Temporary Facility for Engineer, Admin and Clinic 29-Apr-24 14-May-24 15 1111111111111111
B.2 Fabrication Area 29-Apr-24 14-May-24 15 1111111111111111
B. 3 Mobilization 9-May-24 19-May-24 10 11111111111
PART III - FDAS
C.1 Mobilization 9-May-24 19-May-24 10 11111111111
C.2 - Fabrication of Support
C.2.1 Hanggering Support 13-May-24 28-May-24 15 1111111111111111
C.3 Installation of Control Panels 31-May-24 20-Jun-24 20 111111111111111111111
C.4 Installation of Pipes and Wires 31-May-24 25-Jun-24 25 11111111111111111111111111
C.5 Installation of Addressable Fire Alarm Control Panel (FACP) 31-May-24 20-Jun-24 20 111111111111111111111
C.6 Install and Test of Iniatiating and Notification Field Devices 16-May-24 10-Jun-24 25 11111111111111111111111111
C.7 Commissioning and Final Checks and Testing 17-Oct-24 6-Nov-24 20 111111111111111111111

PART IV - FIRE PROTECTION


D.1 Remove and Relocation of 15 000 Water Tank 1-Jul-24 16-Jul-24 15 1111111111111111
D.2 Relocation of Existing Fire Pump and Jockey Pump 16-Sep-24 16-Oct-24 30 1111111111111111111111111111111
D.3 Supply and Installation of 50 hp Engine Driven Diesel Fire Pump
D.4 Hydro Testing

PART V - WET STAND PIPE


Mobilization 9-May-24 19-May-24 10 11111111111
E.3 - Fabricatioon of Support
E.3.1 Hanggering Support 12-Jun-24 7-Jul-24 25 11111111111111111111111111
E.3.2 Fabrication of Brackets 12-Jun-24 7-Jul-24 25 11111111111111111111111111
E.4 Installation of Brackets and Pipings 18-Jun-24 13-Jul-24 25 11111111111111111111111111
E.5 Painting of Pipes 2-Jul-24 17-Jul-24 15 1111111111111111
E.6 Supply and Installation of Fire hose Cabinet and Accessories 2-Jul-24 22-Jul-24 20 111111111111111111111
E.7 Hydro testing 6-Oct-24 6-Nov-24 31 11111111111111111111111111111111

PART VI - SMOKE EXTRACTION


F.1 Mobilization 9-May-24 19-May-24 10 11111111111
F.2 - Fabrication of Support
F.2.1 Hanggering Support 14-May-24 29-May-24 15 1111111111111111
F.2.2 Fabrication of Brackets 14-May-24 29-May-24 15 1111111111111111
F.3 Installation of Brackets 21-May-24 10-Jun-24 20 111111111111111111111
F.4 Creation of ingress for the Smoke Extraction fans 21-May-24 5-Jun-24 15 1111111111111111
F.5 Installation of Smoke Extraction Fans 27-May-24 11-Jun-24 15 1111111111111111
F.6 Installation of Maintenance Ladders 31-May-24 20-Jun-24 20 111111111111111111111
F.7 Installation of Smoke Extraction Control Panel 7-Jun-24 22-Jun-24 15 1111111111111111
F.8 Commissioning and Final Checks and Testing 17-Oct-24 6-Nov-24 20 111111111111111111111

PART VII - CIVIL WORKS FIRE PUMP ROOM


PART A. EARTHWORKS WATER TANK
G.1.1 Removal of Structures and Obstruction 14-May-24 29-May-24 15 1111111111111111
G.1.2 Structural Excavation (Common Soil) 29-May-24 13-Jun-24 15 1111111111111111
G.1.3 Embankment From Structure Excavation 24-Jun-24 14-Jul-24 20 111111111111111111111
PART. B - PLAIN AND REINFORCED CONCRETE WORK
G.2.1 Structural Concrete ( Footings and Sub on Fill, Class A) 13-Jun-24 28-Jun-24 15 1111111111111111
G.2.3 Structural Concrete (Columns, Class A) 19-Jun-24 4-Jul-24 15 1111111111111111
G.2.5 Stractural Concrete (Beams/ Girder, Class A) 25-Jun-24 10-Jul-24 15 1111111111111111
G.2.6 Reinforcing Steel, Grade 40 15-May-24 9-Jun-24 25 11111111111111111111111111
G.2.7 Forms and False works 11-Jun-24 26-Jun-24 15 1111111111111111
PART C. EARTHWORKS PUMP ROOM
G.3.1 Removal of Structures and Obstruction 16-Jul-24 26-Jul-24 10 11111111111
G.3.2 Structural Excavation (Common Soil) 19-Jul-24 3-Aug-24 15 1111111111111111
G.3.3 Embankment From Structure Excavation 5-Aug-24 15-Aug-24 10 11111111111
PART. D - PLAIN AND REINFORCED CONCRETE WORK
G.4.1 Structural Concrete ( Footings and Sub on Fill, Class A) 30-Jul-24 14-Aug-24 15 1111111111111111
G.4.2 Structural Concrete (Footing Tie Beams, Class A) 13-Aug-24 23-Aug-24 10 11111111111
G.4.3 Structural Concrete (Columns, Class A) 6-Aug-24 21-Aug-24 15 1111111111111111
G.4.4 Structural Concrete (Suspended Slab, Class A) 20-Aug-24 4-Sep-24 15 1111111111111111
G.4.5 Stractural Concrete (Beams/ Girder, Class A) 13-Aug-24 28-Aug-24 15 1111111111111111
G.4.6 Reinforcing Steel, Grade 40 15-May-24 9-Jun-24 25 11111111111111111111111111
G.4.7 Forms and False works 29-Jul-24 13-Aug-24 15 1111111111111111
PART. E - FINISHING
C.5.1 - Masonry Works
G.5.1.1 CHB(Including Reinforcing Steel), 10 mm 13-Aug-24 2-Sep-24 20 111111111111111111111
G.5.2 - Fabricated Materials & Hardware
G.5.2.1 Door, Flush 16-Sep-24 26-Sep-24 10 11111111111
G.5.2.2 Finishing Hardware (Knobs) 16-Sep-24 26-Sep-24 10 11111111111
G.5.2.3 Finishing Hardware (Hinges) 16-Sep-24 26-Sep-24 10 11111111111
G.5.2.4 Louvers Vent 13-Aug-24 2-Sep-24 20 111111111111111111111
G.5.3 - Finishing Works
G.5.3.1 Cement Floor Finish 2-Sep-24 17-Sep-24 15 1111111111111111
G.5.3.2 Cement Plaster Finish 13-Sep-24 3-Oct-24 20 111111111111111111111
G.5.3.3 Interior Skim Coat 20-Sep-24 10-Oct-24 20 111111111111111111111
G.5.3.4 Epoxy Floor Coating 1-Oct-24 11-Oct-24 10 11111111111
G.5.3.5 Fascia Board 15-Sep-24 25-Sep-24 10 11111111111
G.5.3.6 Fiber Cement Board Ceiling on Metal Frame 26-Sep-24 16-Oct-24 20 111111111111111111111
G.5.4 - Roofing and Roof Framing
G.5.4.1 Structural Steel, Purlin Rafters 15-Sep-24 30-Sep-24 15 1111111111111111
G.5.4.2 Structural Steel, Purlins 15-Sep-24 30-Sep-24 15 1111111111111111
G.5.4.3 Prepainted Metal Sheet (4mm Rib Type, Long Span) 15-Sep-24 30-Sep-24 15 1111111111111111
G.5.5 - Painting Works
G.5.5.1 Painting Works (Masonry Concrete) 1-Oct-24 11-Oct-24 10 11111111111
G.5.5.2 Painting Works (Steel) 15-May-24 9-Jun-24 25 11111111111111111111111111
PART. F - ELECTRICAL WORKS
G.5.1 Conduits, Boxes and Fittings 16-Sep-24 1-Oct-24 15 1111111111111111
G.5.2 Wires and Wiring Devices 16-Sep-24 1-Oct-24 15 1111111111111111
G.5.3 Lightning Fixtures 16-Sep-24 1-Oct-24 15 1111111111111111

PART VIII - CIVIL WORKS FUEL TANK & BOILER AREA


PART. A - DEMOLITION
H.1 Demolition and dismantling of existing and affected steel doors 19-Aug-24 8-Sep-24 20 111111111111111111111
PART . B - PLAIN AND REINFORCED CONCRETE WORK
H.2.1 Structural Concrete (Columns, Class A) 7-Sep-24 2-Oct-24 25 11111111111111111111111111
H.2.2 Stractural Concrete (Beams/ Girder, Class A) 7-Sep-24 2-Oct-24 25 11111111111111111111111111
H.2.3 Reinforcing Steel, Grade 40 7-Sep-24 2-Oct-24 25 11111111111111111111111111
H.2.4 Forms and False works 7-Sep-24 2-Oct-24 25 11111111111111111111111111
PART. C - FINISHING
H.3.1 - Masonry Works
H.3.1.1 CHB(Including Reinforcing Steel), 10 mm 14-Sep-24 4-Oct-24 20 111111111111111111111
H.3.2 - Fabricated Materials & Hardware
H.3.2.1 Door 1-Oct-24 11-Oct-24 10 11111111111
H.3.2.2 Finishing Hardware (Knobs) 1-Oct-24 11-Oct-24 10 11111111111
H.3.2.3 Finishing Hardware (Hinges) 1-Oct-24 11-Oct-24 10 11111111111
H.3.3 - Finishing Works
H.3.3.2 Cement Plaster Finish 3-Oct-24 23-Oct-24 20 111111111111111111111
H.3.5 - Painting Works
H.3.5.1 Painting Works (Masonry Concrete) 15-Oct-24 30-Oct-24 15 1111111111111111
H.3.6 - Testing
H.3.6.1 Compressive Strength Test 13-Jul-24 2-Oct-24 81 1111111111111111111111111111111111111111111111111111111111111111111111111111111111
H.3.6.2 Tensile Strength Test 0