Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

[Project Name]

[Company Name]

Project Lead: John Doe


Today's Date: 6/27/2024 (Thu) (vertical red line)
[42] Start Date: 1/2/2012 (Mon) First Day of Week (Sun=1): ###
###
2###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

Days Remaining
Duration (Days)

Days Complete

07 - May - 12

14 - May - 12

21 - May - 12

28 - May - 12

06 - Aug - 12

13 - Aug - 12

20 - Aug - 12
Working Days

06 - Feb - 12

13 - Feb - 12

20 - Feb - 12

27 - Feb - 12

05 - Mar - 12

12 - Mar - 12

19 - Mar - 12

26 - Mar - 12
02 - Jan - 12

09 - Jan - 12

16 - Jan - 12

23 - Jan - 12

30 - Jan - 12

04 - Jun - 12

11 - Jun - 12

18 - Jun - 12

25 - Jun - 12
02 - Apr - 12

09 - Apr - 12

16 - Apr - 12

23 - Apr - 12

30 - Apr - 12

02 - Jul - 12

09 - Jul - 12

16 - Jul - 12

23 - Jul - 12

30 - Jul - 12
% Complete
WBS Tasks Task Lead Start End

1 Task Category 1 John 1/02/12 3/18/12 76 80% 55 60 16


1.1 Sub Task 1/02/12 1/20/12 18 100% 15 18 0
1.2 Sub Task 1/21/12 2/20/12 30 95% 21 28 2
1.3 Sub Task 1/22/12 2/10/12 19 95% 15 18 1
1.4 Sub Task 2/10/12 3/18/12 37 50% 26 18 19
2 Task Category 2 Jane 3/01/12 5/13/12 73 13% 52 9 64
2.1 Sub Task 3/01/12 3/18/12 17 50% 12 8 9
2.2 Sub Task 3/01/12 3/18/12 17 30% 12 5 12
2.3 Sub Task 3/18/12 4/26/12 39 0% 29 0 39
2.4 Sub Task 4/15/12 5/13/12 28 0% 20 0 28
3 Task Category 3 Bill 4/25/12 9/03/12 131 0% 94 0 131
3.1 Sub Task 4/25/12 5/12/12 17 0% 13 0 17
3.2 Sub Task 5/12/12 5/29/12 17 0% 12 0 17
3.3 Sub Task 5/29/12 7/05/12 37 0% 28 0 37
3.4 Sub Task 8/05/12 9/03/12 29 0% 21 0 29

HELP

- Modify the GREEN cells and the WBS, Tasks, and Task Lead columns. The rest of the columns are formulas.
- The number of weeks shown in the gantt chart is limited by the maximum number of columns available.
- The Start Date that you choose determines the first week in the gantt chart, starting on a Monday.
- Change the first day of the week via cell K8
- Use the slider to adjust the range of dates shown in the gantt chart.
- Only 34 weeks can be shown/printed at one time, because each week uses up 7 columns.

Q: How do I make Task 2 start the day after the end of Task 1?
Use the following formula for the start date of Task 2:
=EndDate+1
where EndDate is the reference to the cell containing the end date of task 1

Q: How do I add/insert tasks and subtasks?


Copy the entire ROW (or a group of rows) for the type of task(s) you want to add and then right-click on the row where you want to insert the new tasks, then select Insert Copied Cells.
Important Note: When inserting a new subtask after the last subtask or before the first subtask, you will need to update the formulas for calculating the Level 1 %Complete and Duration
(see below) to include the new subtask, because the ranges won't automatically expand to include the additional row.

Q: How do I calculate the %Complete for a Level 1 task based upon the %Complete of all of the associated subtasks?
Example: If Task 1 is on row 11 and the subtasks are on rows 12-15, use the following formula:
=SUMPRODUCT(F12:F15;G12:G15)/SUM(F12:F15)

Q: How do I calculate the Duration for a Level 1 task based upon the largest end date of a sub task?
Example: If the Level 1 task is on row 11 and the sub tasks are on rows 12-15, use the following formula
=MAX(E12:E15)-D11

Q: How can I include holidays in the calculation of the Working Days?


You can add a list of holidays to exclude in the NETWORKDAYS function. See the help on that function.

Q: How do I change the print settings?


Select the entire range of cells that you want to print and then define a Print Range in the Format menu. Then go to Format > Page and select the Sheet tab. Adjust the Scaling mode as
desired.

You might also like