Professional Documents
Culture Documents
Gant T Chart Template
Gant T Chart Template
[Company Name]
Days Remaining
Duration (Days)
Days Complete
07 - May - 12
14 - May - 12
21 - May - 12
28 - May - 12
06 - Aug - 12
13 - Aug - 12
20 - Aug - 12
Working Days
06 - Feb - 12
13 - Feb - 12
20 - Feb - 12
27 - Feb - 12
05 - Mar - 12
12 - Mar - 12
19 - Mar - 12
26 - Mar - 12
02 - Jan - 12
09 - Jan - 12
16 - Jan - 12
23 - Jan - 12
30 - Jan - 12
04 - Jun - 12
11 - Jun - 12
18 - Jun - 12
25 - Jun - 12
02 - Apr - 12
09 - Apr - 12
16 - Apr - 12
23 - Apr - 12
30 - Apr - 12
02 - Jul - 12
09 - Jul - 12
16 - Jul - 12
23 - Jul - 12
30 - Jul - 12
% Complete
WBS Tasks Task Lead Start End
HELP
- Modify the GREEN cells and the WBS, Tasks, and Task Lead columns. The rest of the columns are formulas.
- The number of weeks shown in the gantt chart is limited by the maximum number of columns available.
- The Start Date that you choose determines the first week in the gantt chart, starting on a Monday.
- Change the first day of the week via cell K8
- Use the slider to adjust the range of dates shown in the gantt chart.
- Only 34 weeks can be shown/printed at one time, because each week uses up 7 columns.
Q: How do I make Task 2 start the day after the end of Task 1?
Use the following formula for the start date of Task 2:
=EndDate+1
where EndDate is the reference to the cell containing the end date of task 1
Q: How do I calculate the %Complete for a Level 1 task based upon the %Complete of all of the associated subtasks?
Example: If Task 1 is on row 11 and the subtasks are on rows 12-15, use the following formula:
=SUMPRODUCT(F12:F15;G12:G15)/SUM(F12:F15)
Q: How do I calculate the Duration for a Level 1 task based upon the largest end date of a sub task?
Example: If the Level 1 task is on row 11 and the sub tasks are on rows 12-15, use the following formula
=MAX(E12:E15)-D11